Attachment_E_-_Installation_Facility_Standards_&_Plans.pdf

PDF 7 MB Posted

Attached to
Tyndall AFB Temporary Modular Medical Facility Federal contract opportunity
Solicitation number
W9127S19Q6039
Issued by
Department of the Army Corps of Engineers Engineering District Little Rock

About this file

Attachment E

View the file

Other files for this federal contract opportunity

Other files attached to Tyndall AFB Temporary Modular Medical Facility, newest first.
File Type Posted
1-V1.04_SURVEY_PLAN.pdf PDF
49_25__TPFV4.0_STANDARD_RAMP_AND_STAIR_DETAILS_STAMPED.pdf PDF
55_TQ3.11C_-_FFE_PLAN_-_TPF_PHASE_1,_AREA_C.pdf PDF
55_TQ3.11_-_FFE_PLAN_-_TPF_PHASE_1.pdf PDF
55_TQ4.11C_-_FFE_PLAN_-_TPF_PHASE_2,_AREA_C.pdf PDF
49_24__TPF3.0_Full_Luminary_Plan.pdf PDF
49_23__TCP1.2_Combined_Clinic_TPF_RCP.pdf PDF
49_23__TCP1.0_Combined_Clinic_TPF_RCP.pdf PDF
55_TQ3.11B_-_FFE_PLAN_-_TPF_PHASE_1,_AREA_B.pdf PDF
49_24__TPF7.0_Overall_Plumbing_Plan_-_D.W.V.pdf PDF
49_25__TPFV3.0_STANDARD_RAMP_AND_STAIR_DETAILS_STAMPED.pdf PDF
49_25__TPFV5.0_STANDARD_CANOPY_DETAILS_STAMPED.pdf PDF
49_24__TPF2.1-P2_Full_Building_Plan_Phase_2.pdf PDF
55_TQ4.11D_-_FFE_PLAN_-_TPF_PHASE_2,_AREA_D.pdf PDF
49_23__TCP1.5_Combined_Clinic_TPF_RCP.pdf PDF
49_25__TPFV2.0_STANDARD_RAMP_AND_STAIR_DETAILS_STAMPED.pdf PDF
49_24__TPF2.0-PI_Full_Building_Plan-Phase_1.pdf PDF
29_06_TNX1.0_Building_Cross_Section.pdf PDF
43_16_TCCA1.0_Exterior_Elevations.pdf PDF
36_10_TSP3.0-PII_Plumbing_Plan_-_Supply_Phase_2.pdf PDF
07_E0-02_-_SYMBOL_LEGEND_AND_GENERAL_NOTES.pdf PDF
36_09_TSA2.0_Floor_Plan.pdf PDF
36_11_TSE3.0_Task_Lighting_Illumination_Plan.pdf PDF
29_02_TNA4.0_Egress_Plan.pdf PDF
36_09_TSA3.0_Reflective_Ceiling_Plan.pdf PDF
29_03_TNP2.0_Plumbing_Schematics.pdf PDF
43_16_TCCA4.0_Egress_Plan.pdf PDF
43_17_TCCE1.0_Elec_Plan.pdf PDF
29_04_TNE3.0_Task_Lighting_Illumination_Plan.pdf PDF
29_05_TNM1.0_Mechanical_HVAC_Plan.pdf PDF
36_10_TSP4.0-PII_Plumbing_Plan_-_DWV_Phase_2.pdf PDF
36_10_TSP1.0_Plumbing_Schematics.pdf PDF
36_09_TSA1.0_Exterior_Elevations.pdf PDF
W9127S19Q6039_Tyndall_TMMF_Response_to_Questions_19Aug19.pdf PDF
29_04_TNE4.0_MDP_-_One_Line_Diagram.pdf PDF
05_1-CU1.02_UTILITY_PLAN_-_PHASE_2_AND_3.pdf PDF
29_03_TNP3.0_Plumbing_Plan.pdf PDF
36_10_TSP2.0_Plumbing_Schematics.pdf PDF
29_02_TNA3.0_Reflective_Ceiling_Plan.pdf PDF
36_14_TSFD1.0_Foundation_Plan_and_Details.pdf PDF
36_11_TSE4.0_MDP_-_One_Line_Diagram.pdf PDF
36_09_TSA3.0-PII_Reflective_Ceiling_Plan.pdf PDF
29_04_TNE1.0_Elec_Plan.pdf PDF
W9127S19Q6039_Tyndall_TMMF_Combined_Synopsis_Solicitation_13Aug19.pdf PDF
Attachment_C_-_AFMSA_Design_Guidance.pdf PDF
Attachment_B_-_Utility_Plans.pdf PDF
W9127S19Q6039_Tyndall_TMMF_Combined_Synopsis_Solicitation.pdf PDF
Attachment_G_-_PFD_TYNDALL_TPF_v2_20190702.pdf PDF
Attachment_F_-_Codes_&_Criteria.pdf PDF
Attachment_D_-_DHA_LAN_WLAN_Guides.pdf PDF
Show all 50

Tyndall AFB Temporary Modular Medical Facility has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tyndall AFB IFS

5 NOVEMBER 2018

PRE-FINAL

TYNDALL AIR FORCE BASE

INSTALLATION FACILITIES STANDARDS (IFS)

Installation Elements

Size image to:

170 pixels width x 170 pixels height

Click here to insert image

Site Development

Facilities Exteriors

Facilities Interiors

Installation Elements Site Development Facilities Exteriors Facilities Interiors

APPROVED FOR PUBLIC RELEASE; DISTRIBUTION UNLIMITED

Signature Field LIERLY.RANDALL.L.1230871775 Digitally signed by LIERLY.RANDALL.L.1230871775 Date: 2018.11.03 18:04:16 -05'00'

AIR FORCE

INSTALLATION

FACILITIES

STANDARDS

Tyndall Air Force Base IFS

Table of Contents

A. OVERVIEW

A01. Facility Hierarchy

A02. Facility Quality

A03. Facility Districts

B. INSTALLATION ELEMENTS

B01. Comprehensive Planning

B01.1. Installation Development Plan (IDP) B01.1.1. IFS Component Plan of IDP B01.1.2. Brief History of Base B01.1.3. Future Development

B02. Street Envelope Standards

B02.1. Hierarchy of Streets B02.1.1. Arterial Streets B02.1.2. Collector Streets B02.1.3. Local Streets B02.1.4. Special Routes

B02.2. Hierarchy of Intersections B02.2.1. Arterials B02.2.2. Arterial/Collector B02.2.3. Collectors B02.2.4. Special Intersections B02.2.5. Street Frontage Requirements B02.2.6. Sight Lines

B02.3. Street Elements B02.3.1. Paving B02.3.2. Curb and Gutter B02.3.3. Utility Service Elements B02.3.4. Traffic Signs B02.3.5. Street Lighting B02.3.6. Other

B03. Open Space / Public Space

B03.1. Plazas, Monuments and Static Displays

B03.1.1. Paved Plazas B03.1.2. Sculptures, Markers and Statuary B03.1.3. Static Display of Aircraft

B03.2. Grounds and Perimeters

B03.2.1. Parade Grounds B03.2.2. Parks

B03.2.3. Preserves B03.2.4. Perimeter Fence

C. SITE DEVELOPMENT

C01. Site Design

C01.1. Site Design Considerations

C01.2. Building Orientation

C02. Utilities

C02.1. Utility Components

C03. Parking Areas

C03.1. Configurations and Design C03.1.1. Paving and Striping C03.1.2. Curbing C03.1.3. Internal Islands and Medians

C03.2. Parking Structures

C03.3. Connectivity

C04. Stormwater Management

C04.1. Stormwater Requirements

C05. Sidewalks, Bikeways and Trails

C05.1. Circulation and Paving C05.1.1. Ramps and Stairs C05.1.2. Lighting

C06. Landscape

C06.1. Climate-based Materials C06.1.1. Landscape Design Concept C06.1.2. Xeriscape Design Principles C06.1.3. Minimizing Water Requirements C06.1.4. Plant Material Selection C06.1.5. Water Budgeting (Hydrozones) C06.1.6. Base Entrance Landscaping C06.1.7. Streetscape Landscaping C06.1.8. Pedestrian Circulation Landscaping C06.1.9. Parking Lot Landscaping C06.1.10. Screen/Accent Landscaping C06.1.11. Other

C07. Site Furnishings

C07.1. Furnishings and Elements

Table of contents continued on next page

Table of contents continued

C07.2. Site Furnishings Products, Materials / Color .. 55

C07.2.1. Barbeque Grills C07.2.2. Benches C07.2.3. Bike Racks C07.2.4. Bike Lockers C07.2.5. Bollards C07.2.6. Bus Shelters C07.2.7. Drinking Fountains C07.2.8. Dumpster Enclosures / Gates C07.2.9. Fencing C07.2.10. Flagpoles C07.2.11. Lighting – Landscape / Accent C07.2.12. Litter and Ash Receptacles C07.2.13. Picnic Tables C07.2.14. Planters – Free Standing C07.2.15. Play Equipment C07.2.16. Screen Walls C07.2.17. Tree Grates C07.2.18. Other

C08. Exterior Signs

C08.1. Colors and Types C08.1.1. Materials and Color Specifications C08.1.2. Installation and Gate Identification Signs C08.1.3. Building Identification Signs C08.1.4. Traffic Control Devices (Street Signs) C08.1.5. Directional and Wayfinding Signs C08.1.6. Informational Signs C08.1.7. Motivational Signs C08.1.8. Parking Lot Signs C08.1.9. Regulatory Signs C08.1.10. Other

C09. Lighting

C09.1. Fixtures and Lamping

C09.2. Light Fixture Types

C09.2.1. Street Lighting C09.2.2. Parking Lot Lighting C09.2.3. Lighted Bollards C09.2.4. Sidewalk Lighting C09.2.5. Walls / Stairs Lighting C09.2.6. Other

D. FACILITIES EXTERIORS

D01. Supporting the Mission

D02. Sustainability

D03. Architectural Features

D03.1. Orientation, Massing and Scale

D03.2. Architectural Character

D03.3. Details and Color D03.3.1. Climate-based Data D03.3.2. Natural Ventilation System D03.3.3. Thermal Mass

D03.3.4. Thermal Shading D03.3.5. Renewable Heating/Cooling D03.3.6. Solar Photovoltaic System D03.3.7. Solar Thermal System

D04. Building Entrances

D04.1. Primary Entrances

D04.2. Secondary Entrances

D05. Wall Systems

D05.1. Hierarchy of Materials

D05.2. Layout, Organization and Durability

D05.3. Equipment, Vents and Devices

D05.4 Wall Systems Materials

D05.4.1. Flat Metal Panels D05.4.2. Brick Veneer D05.4.3. Architectural Precast D05.4.4. Stucco Over Sheathing D05.4.5. Curtain Wall D05.4.6. Cast-in Place Concrete D05.4.7. Tilt-up Concrete D05.4.8. Ribbed Metal Sheeting

D05.4.9. EFIS

D05.4.10.GRFC

D05.4.11.Concrete Block D05.4.12. Fiber Cement Siding D05.4.13. Other

D06. Doors and Windows

D06.1. Types

D06.2. Layout and Geometry

D06.3. Glazing and Shading

D06.4. Hardware

D06.5. Doors and Windows Materials D06.5.1. Anodized Aluminum D06.5.2. Hollow Metal D06.5.3. Aluminum-clad Wood D06.5.4. Other

D07. Roof Systems

D07.1. Roof Type and Form

D07.2. Roof Slope

D07.3. Parapets and Copings

D07.4. Color and Reflectivity

D07.5. Gutters, Downspouts, Scuppers, Drains

D07.6. Roof Vents and Elements

D07.7. Clerestories and Skylights

D07.8. Vegetated Roof

Table of contents continued on next page

Table of contents continued

D07.9. Roof Systems Materials D07.9.1. Standing Seam Metal D07.9.2. Membrane Single-ply D07.9.3. Built-up Multi-ply D07.9.4. Concrete Tile D07.9.5. Clay Tile D07.9.6. Slate Shingles D07.9.7. Vegetated System D07.9.8. Ribbed Metal Sheeting D07.9.9. Composite Shingles D07.9.10. Other

D08. Structural Systems

D08.1. Systems and Layouts

D08.2. Structural Systems Materials D08.2.1. Concrete D08.2.2. Insulated Concrete Forming (ICF) D08.2.3. Steel D08.2.4. Pre-Engineered Steel D08.2.5. Masonry D08.2.6. Heavy Timber D08.2.7. Light-gauge Steel D08.2.8. Lumber Framing D08.2.9. Other

D09. Mechanical, Electrical and Plumbing

D09.1. Passive and Active Systems

D09.2. Functionality and Efficiency

E. FACILITIES INTERIORS

E01. Building Configurations

E01.1. Layout and Common Areas

E01.1.1. Interior Design Process E01.1.2. Codes and Regulations

E01.2. Quality and Comfort

E02. Floors

E02.1. Floor Materials

E02.1.1. Prepared Slabs E02.1.2. Natural Stone and Terrazzo E02.1.3. Quarry Tile E02.1.4. Ceramic Tile E02.1.5. Resilient Floor E02.1.6. Carpet E02.1.7. Rapidly-Renewable Products E02.1.8. Other

E03. Walls

E03.1. Wall Materials E03.1.1. Concrete E03.1.2. Masonry E03.1.3. Ceramic Tile E03.1.4. Gypsum Board E03.1.5. Metal Panels E03.1.6. Wood Paneling E03.1.7. Rapidly-Renewable Products E03.1.8. Other

E04. Ceilings

E04.1. Ceiling Materials

E04.1.1. Exposed Framing (Roof / Floor Structure Above) E04.1.2. Exposed Concrete E04.1.3. Grid and Acoustical Tile E04.1.4. Gypsum Board E04.1.5. Metal Panels E04.1.6. Wood E04.1.7. Rapidly-Renewable Products E04.1.8. Other

E05. Doors and Windows

E05.1. Doors and Windows and Frames Materials E05.1.1. Aluminum E05.1.2. Hollow Metal E05.1.3. Wood E05.1.4. Other

E06. Casework Systems

E06.1. Casework Materials E06.1.1. Plastic Laminate E06.1.2. Solid Polymer Surface E06.1.3. Rapidly-Renewable Products E06.1.4. Metal E06.1.5 Other

E06.2. Countertop Materials

E06.2.1. Plastic Laminate E06.2.2. Solid Polymer Surface E06.2.3. Natural Stone E06.2.4. Cast Stone E06.2.5. Metal E06.2.6 Other

E07. Furnishings

E07.1. Durability and Serviceability

E07.2. Accessories

E08. Interior Signs

E08.1 Types and Color

E08.2. Interior Signs Materials

E09. Lighting, Power and Communication

E09.1. Functionality and Efficiency

E09.2. Types and Color

F. Appendices

G. Appendices

Version 02.00.07

Page 5 of 144Tyndall Air Force Base IFS

A. OVERVIEW

Comply with Air Force Corporate Standards for Overview:

http://afcfs.wbdg.org/index.html

This Installation Facilities Standards (IFS) document is part of the Air Force Corporate Facilities Standards (AFCFS) program to assist bases in implementing and maintaining facilities standards as appropriate for efficient operations within the respective climate region. IFS fully replaces, consolidates and simplifies existing facilities standards documents, such as the Architectural Compatibility Plan (ACP) or ACGs, FEPs, etc., and organizes information using the same structure, or Table of Contents, as the AFCFS website.

IFS reflects the AFCFS’ concepts of "Facility Hierarchy" (categorizing facilities into group numbers) and “Facility Quality” (assigning an appropriate level of quality to each group number) and applies these principles at the base level. Applicable DoD and Air Force criteria such as UFCs, AFIs, Memoranda, and UFGSs (Guide Specs) are referenced and linked within IFS to ensure the document is always current.

Navigating within this IFS is efficient and straightforward. Please use the interactive Table of Contents to locate subject matter, and click on the title of a section to access it. From any page, click on the “Back to Table of Contents” footer to return. Content is organized into 4 major sections: Installation Elements, Site Development, Facilities Exteriors and Facilities Interiors.

This IFS document begins as a fill-in PDF form, which is fully editable, and becomes a "living document" that can be regularly updated by base-level personnel following a format that is consistent across the Air Force. While the format is standardized, IFS content is customized for base operations and the local climate to ensure mission success while emphasizing reduced maintenance and reduced initial costs, life-cycle costs, energy use, and water use.

1. Conformance to Air Force Corporate Facilities Standards (AFCFS) and Installation Facilities Standards (IFS) are required by Air Force Instruction (AFI) 32-1023 and Air Force Memorandum. Please refer to the AFCFS website for links to documentation on current policy.

2. Requests to deviate from any installation facilities standards, that are Unified Facilities Criteria (UFC) requirements, will follow the process outlined in the AFCFS for UFC waivers and exemptions.

3. The IFS is a component plan of the Installation Development Plan (IDP) per Air Force Instruction (AFI) 32-7062 (replacing the Architectural Compatibility Plan). All military construction projects and Non-Appropriated Funds (NAF) facilities are required to comply with the IDP and its IFS component plan by AFI 32-1023. The Base Civil Engineer (BCE) maintains and implements the IDP and its component plans, to include the IFS.

4. Please refer to the AFCFS website as a portal to reference materials and requirements documents for design and construction projects (via links). Specific references to current DoD memoranda and Air Force criteria are updated periodically to provide the most current guidance and requirements. Programming, design and contract documents should list “current edition” for all reference and requirements documents. The documents in force at the date of execution of the design and/or construction contract shall be the governing version.

5. Advanced Modeling Requirements:

For all Air Force projects requiring advanced modeling, to include 3D visualization, Building Information Modeling (BIM), facility data, quantity take-off, geospatial, etc., follow the Army standards. Refer to USACE Minimum Model Matrix (M3) and Project Execution Plan (PxP) which outline required model uses. Refer to CAD BIM Technology Center (Contract Requirements) for more information on M3 and PxP.

6. Joint Bases shall implement IFS under their Joint-Base designation with volume numbers for individual installations following the IFS Development Tool template. For example, for Joint Base Langley-Eustis, provide: Vol. 1 Langley AFB and Vol. 2 Fort Eustis.

7. References and Supplementary Documents listed in Appendix G are included in these Installation Facilities Standards by reference and are fully part of this document. Please refer to Appendix G for a listing of documents, which are available via hyperlink for viewing and downloading.

Page 6 of 144Tyndall Air Force Base IFS

Large graphicsApplicable N/A

Applicable N/A Small graphics

OPTIONAL: Insert Overview graphic that represents the region, locale or base

800 pixels width x 440 pixels in height

(jpg or png format)

Tyndall Air Force Base Coastal Setting

OPTIONAL: Insert Overview graphic that represents

250 pixels width x 188 pixels height

Main Gate Entrance Corridor

OPTIONAL: Insert Overview

Static Display Park

OPTIONAL: Insert Overview

Coastal Materials and Colors

A01. FACILITY HIERARCHY

Comply with AF Corporate Standards for Facility Hierarchy (and subsections):

http://afcfs.wbdg.org/facility-hierarchy/index.html

A02. FACILITY QUALITY

Comply with AF Corporate Standards for Facility Quality (and subsections):

http://afcfs.wbdg.org/facility-quality/index.html

A03. FACILITY DISTRICTS

Comply with AF Corporate Standards for Facility Districts (and subsections):

http://afcfs.wbdg.org/facility-districts/index.html

Page 7 of 144Tyndall Air Force Base IFS

Note: Apply the base-wide standards in this IFS for Installation Elements, Site Development, Facilities Exteriors and Facilities Interiors (products, materials, color, etc.). Following application of the base-wide standards, refer to the Appendix and apply any additional requirements specifically related to the Facility District.

Insert Base Map with districts indicated.

800 pixels width x 800 pixels height

Overview Map:Tyndall Air Force Base IFS

Page 8 of 144Tyndall Air Force Base IFS

B. INSTALLATION ELEMENTS

Comply with Air Force Corporate Standards for Installation Elements:

http://afcfs.wbdg.org/installation-elements/index.html

B01. COMPREHENSIVE PLANNING

Comply with Air Force Corporate Standards for Comprehensive Planning:

http://afcfs.wbdg.org/installation-elements/comprehensive-planning/index.html

B01.1. Installation Development Plan (IDP)

Applicable N/A Large graphics

Applicable N/A Small graphics

Insert IDP graphic

Department of Defense, Department of the Air Force and Air Force Base Criteria

1. The Base Civil Engineer is responsible for developing, maintaining and implementing the installation’s Comprehensive Planning documents and to ensure that the Installation Development Plan (IDP) is prepared, maintained, and implemented following AFI 32-7062.

B01.1.1. IFS Component Plan of IDP

Applicable N/A Large graphics

1. Maintain this Installation Facilities Standards (IFS) as a Component Plan of the base's Installation Development Plan (IDP).

Page 9 of 144Tyndall Air Force Base IFS

B01.1.2. Brief History of Base

Applicable N/A Large graphics

Insert History of Base graphic

Tyndall Field WWII

Tyndall Field 1944

QF-100 Super Sabers 1990

Tyndall Field was opened on 13 January 1941 as a gunnery range. The airfield was named in honor of 1st Lt Frank Benjamin Tyndall (1894 -1930). With the establishment of the United States Air Force in 1947, the facility was renamed "Tyndall Air Force Base" on 13 January 1948.

September 1950, Tyndall became an Air Training Command (ATC) installation, designated as the USAF Pilot Instructor School. The base also trained Ground Controlled Intercept (GCI) operators as well as interceptor pilots & flight crews for the Air Defense Command. The base served as a stopover and refueling point for ADC aircraft deployed to Florida during the Cuban Missile Crisis, to be redeployed to other bases in the southeast shortly thereafter.

In 1991, Tyndall underwent a reorganization in response to the Department of Defense efforts to streamline defense management. With the disestablishment of Tactical Air Command (TAC) in 1992, Tyndall was temporarily transferred to the Air Combat Command (ACC) and then to the Air Education and Training Command (AETC) in July 1993.

The 21st century proved to be momentous for Tyndall AFB. The base was selected as the first home of the Air Force's newest aircraft, the F-22 Raptor. 2002 brought more change as the Chief of Staff of the Air Force changed the organizational structure of the 325th Fighter Wing, from an objective type wing to a combat organization. Today, Tyndall is the home of the 325th Fighter Wing, providing training for all F-22A Raptor pilots. In 2012, with the gaining of a combat-coded F-22 squadron, Tyndall AFB returned to Air Combat Command, after a 19-year tenure in AETC. In April of 2015 the 95th Fighter Squadron completed Tyndall's and F-22 Raptors first combat deployment. In November of 2017 Tyndall AFB was selected as the home to a MQ-9 Reaper wing, with airmen projected to arrive by 2020 and the first aircraft to arrive in 2022. The wing remains committed to its goal to "Train and Project Unrivaled Combat Power."

Page 10 of 144Tyndall Air Force Base IFS

B01.1.3. Future Development

Applicable N/A Large graphics

Insert Future Development graphic

MQ-9 Facility Layout

Page 11 of 144Tyndall Air Force Base IFS

Insert Future Development graphic

Future MQ-9 Locations

1. Follow AFI 32-7062 for Air Force Comprehensive Planning, the Comprehensive Planning Process, Comprehensive Planning Requirements, and Geospatial Mapping.

2. Address all future development under the Installation Development Plan (IDP).

3. Tyndall AFB has been selected as a future home of the MQ-9. Fully operational by 2025, project in excess of 275M.

Page 12 of 144Tyndall Air Force Base IFS

B02. STREET ENVELOPE STANDARDS

Comply with Air Force Corporate Standards for Installation Elements:

http://afcfs.wbdg.org/installation-elements/index.html

Comply with AF Corporate Standards for Street Envelope Standards:

http://afcfs.wbdg.org/installation-elements/street-envelope-standards/index.html

B02.1. Hierarchy of Streets

Applicable N/A Large graphics

Insert Hierarchy of Streets graphic

Airey Avenue

Hierarchy of Streets

Street Envelope Section

Alabama Ave

Page 13 of 144Tyndall Air Force Base IFS

Beacon Beach Rd

Typical Local Street

Fighter Drive

1. Develop and evolve a hierarchical transportation network of arterial, collector and local streets following UFC 3-201-01, Civil Engineering, and its industry references.

2. Provide consistent functionality throughout the installation and a level of visual quality relating to the adjacent Facility Group number.

3. Routes along facilities in Group 1 may have materials, finishes and features with a higher visual quality than Groups 2, 3 and 4.

Reduce maintenance requirements by installing highly durable materials and finishes in routes along Group 3 industrial facilities.

4. Special routes may have a visual quality comparable to those along facilities in Group 1.

5. Create and maintain arterials with two lanes of traffic in each direction with landscaped or paved medians as applicable to the local climate and adjacent facility group designation / land use.

6. Minimize stops and turns along arterials. Eliminate on-street parking along arterials and collector streets.

7. Connect arterials to local streets with appropriately scaled collector streets.

8. Provide appropriate landscape setbacks and pedestrian buffers along all streets.

9. Minimize and consolidate curb cuts along streets.

10. Ensure access for emergency and service vehicles.

11. Provide illustrations in the Installation Facilities Standards (IFS) to include street cross-sections and plans for every type of street specified on the installation. At a minimum provide dimensions for vehicular traffic-lanes, curb radii, medians, bike lanes, pedestrian buffers, sidewalks, crosswalks, tree planting areas, and on-street parking configurations.

12. Define appropriate force protection features, site furnishings, signs, lighting, utilities, and paving in the IFS.

13. Use consistent landscape treatment at all base entrances. Plant material massing, spacing, and height are characteristics that should visually reinforce the type of street.

14. Sidewalks, plazas, and covered walkways should be an important element in any new construction project. Sidewalks should be separated from vehicular traffic whenever possible. Walkways to building entrances should be 8 feet wide. Sidewalks should typically be 6 feet wide.

15. Define bicycle traffic routes in the Installation Development Plan or its applicable component plans. Bicycle traffic may be routed to adjacent pedestrian paths if the path is of adequate width to support both functions.

16. Fire Access Lanes: All ground level portions of structures must be within 150 feet of a drivable surface. Fire access lanes shall have a clear width of 20 feet, set back from facilities by 10 feet with a minimum vertical clearance of 13.5 feet and set 15 feet from fire hydrants and standpipe connections.

Page 14 of 144Tyndall Air Force Base IFS

17. Service Drives: Service drives are used to access service areas of facilities in the cantonment area. Service drives shall be combined with parking drives to serve multiple facilities and provide with access control point meeting minimum antiterrorism setback standards and signage that clearly identifies the service drive and restricted access. Service drives shall be shall have a clear width of 20 feet, set back from facilities by 10 feet.

18. Patrol Roads: Patrol roads are remote roads used for security patrols and monitoring of launch sites. Patrol roads shall be 16 feet wide. Shoulders should be stabilized and turnouts provided every quarter mile. Patrol roads may be paved with a stone/clay mix suitable for traffic. Patrol roads area to be used only by authorized GOV's.

B02.1.1. Arterial Streets

Applicable N/A Large graphics

Insert Arterial Streets graphic

Travel Lane (a): 12’ Median (b): 12’ Curb and Gutter (c): 2’ Sidewalk / Landscape (d): 12’) Setback (f): Min. 30' or per ATFP

Insert Arterial Streets graphic

Paved Median

Page 15 of 144Tyndall Air Force Base IFS

1. These specific requirements shall be incorporated into all arterial projects including roadway modifications/upgrades and associated building sites adjacent to the street. Increase landscape setbacks along evacuation routes.

2. Limit curb cuts on arterial streets to entries into major facilities, building groups and major parking areas.

3. Signs, plantings and street lighting should be added to reinforce the importance of arterial streets.

4. Continue to maintain the streets currently designated as aerial streets in future development.

B02.1.2. Collector Streets

Applicable N/A Large graphics

Insert Collector Streets graphic

Travel Lane (a): 12’ Median (b): N/A Curb and Gutter (c): 2’ Landscape (d): 10’ Sidewalk (e): 6’ Setback (f): Min. 15' or per ATFP

1. Design collector streets to be less prominent than arterials.

2. Match the level of quality of street elements to the adjacent Facility Group number.

3. On street parking may be allowed on one side where secondary roads are over 28 feet wide but not less than 34 feet wide.

Parking shall not interfere with intersections or traffic flow.

4. Provide sidewalks on at least one side of collector streets. Buffers are preferred but not required on collector streets.

Page 16 of 144Tyndall Air Force Base IFS

B02.1.3. Local Streets

Applicable N/A Large graphics

Insert Local Streets graphic

Travel Lane (a): 11’ Median (b): N/A Curb and Gutter (c): 1.5’ Landscape (d): 15’ Sidewalk (e): 6’ Setback (f): 15' or per ATFP requirements

1. Design and maintain local streets in due proportion to the amount of traffic.

2. Maintain consistent local streetscapes for visual and functional continuity.

3. Generally encourage the development of street frontage of adjacent sites to positively contribute features such as landscaping.

4. On street parking may be allowed on one side where secondary roads are over 28 feet wide but not less than 34 feet wide.

Parking shall not interfere with intersections or traffic flow.

B02.1.4. Special Routes

1. Develop all special routes consistently with those adjacent to Group 1 facilities.

Page 17 of 144Tyndall Air Force Base IFS

B02.2. Hierarchy of Intersections

Applicable N/A Large graphics

Insert Hierarchy of Intersections graphic

Intersection at Airey Avenue and Suwannee Avenue

1. Provide a hierarchy of intersections to include arterial, arterial-collector, collector, collector-local and local following UFC 3-201-01, Civil Engineering, and its industry references.

2. Passive systems such as traffic circles are preferred to active systems such as signalized intersections. Aggressively pursue passive systems to lower maintenance requirements and reduce energy use.

3. Use a level of visual quality for an intersection equal to the quality found in the related streetscape, which corresponds to the adjacent Facility Group number.

4. Streets should intersect at right angles and offset intersections should be avoided.

Page 18 of 144Tyndall Air Force Base IFS

B02.2.1. Arterials

Applicable N/A Large graphics

Insert Arterials graphic

Landscape Island at Turn Lane

Insert Arterials graphic

Signalized Intersection

1. Develop arterial intersections consistently with the adjacent facility group designation.

2. Maintain appropriate sight lines at all intersections.

3. Refer to UFC 2-100-01 Installation Master Planning for guidance on arterial streetscape design.

B02.2.2. Arterial/Collector

Insert Arterial/Collector graphic

Roadway and Parking Alignment

Insert Arterial/Collector graphic

Striped Turn Lanes

1. Develop arterial/collector intersections consistently with the adjacent facility group designation.

3. Refer to UFC 2-100-01 Installation Master Planning for guidance on streetscape design.

Page 19 of 144Tyndall Air Force Base IFS

B02.2.3. Collectors

Applicable N/A Large graphics

Insert Collectors graphic

Crosswalk and Curb Cuts

Insert Collectors graphic

Typical Intersection with Traffic Signs

1. Develop collector intersections consistently with the adjacent facility group designation.

B02.2.4. Special Intersections

1. Develop all special intersections consistently with those adjacent to Group 1 facilities.

B02.2.5. Street Frontage Requirements

1. Consistently maintain open space buffers following B03.2.3. Preserves.

2. Refer to C06.1.7. Streetscape Landscaping for planting and screen wall requirements along street frontage.

3. Refer to UFC 4-010-01 DoD Minimum Antiterrorism Standards for Buildings, with Change 1 and UFC 4-010-02 DoD Minimum Antiterrorism Standoff Distances for Buildings (FOUO) for street frontage requirements.

Page 20 of 144Tyndall Air Force Base IFS

B02.2.6. Sight Lines

Applicable N/A Large graphics

Applicable N/A Small graphics

1. Provide adequate sight lines for an effective and safe traffic operation per American Association of State Highway and Transportation Officials (AASHTO) standards and local municipality guidelines.

2. Sight lines will vary based on the speed and classification of the roadway or intersection. Plants and any related signage within the sight triangle should follow these rules:

• Shrubs may not exceed thirty inches (30") growing height within sight triangles.

• Trees may not be located in the sight line triangle unless there is a minimum clear understory of 6' in height. Evergreen trees will not be allowed in any sight triangles.

• Signs may not be placed in these triangles unless regulatory in nature and approved by the base traffic engineer.

B02.3. Street Elements

Insert Street Elements graphic

Street Elements Adjacent to Group 3 Facilities

1. Emulate the streetscape area's pre-development hydrology using passive and active design features to help sustain the adjacent regionally appropriate landscape. Coordinate with the base Stormwater Management Plan.

2. Employ systems, materials and techniques to maximize streetscape sustainability. Consider pervious paving and reflectivity of surfaces appropriate for the local climate.

Page 21 of 144Tyndall Air Force Base IFS

3. Install at-grade curbing and/or raised-profile curb and gutter as applicable to direct stormwater to bioswales and rain gardens as source water for vegetation. Do not paint concrete curbing.

4. Provide all on-site utility service lines and equipment below grade when adjacent to Facility Group 1. In routes along Group 2, 3 and 4, when mounting elements such as utility cabinets, communications equipment and water valves above grade is unavoidable, paint these consistently and provide visual screening following Installation Facilities Standards (IFS).

5. Provide traffic control devices including access control point/entry control facility signs, speed limit signs and street name signs following the current edition of the Manual on Uniform Traffic Control Devices (MUTCD) per UFC 3-120-01.

6. Follow UFC 3-120-01 for directional and wayfinding signs and address both vehicular and pedestrian traffic.

7. Reduce energy consumption and reduce maintenance requirements by providing street lighting only when functionally required to ensure safety and to address antiterrorism following UFC 4-010-01. Ensure the quality and quantities of lighting and fixtures are appropriate for the adjacent Facility Group number.

8. Integrate the style of traffic signal systems with other related streetscape items such as signage, lighting, and site furnishings. Avoid visual clutter at street intersections.

9. Crosswalk markings shall follow the MUTCD for Streets and Highways, current edition. Provide white markings that define the edges of the crosswalk or a tone of lines defining the area of the crosswalk consistent with common practices found in the adjacent municipality.

B02.3.1. Paving

Applicable N/A Small graphics

1. Pavement design shall comply with UFC 3-250-01, Pavement Design for Roads and Parking Areas. Ensure appropriate analysis and design of subgrade conditions to support low maintenance high performance pavements.

2. Materials for pavements shall be specified in accordance with UFC 3-250-01 and shall conform to requirements defined in the Unified Facility Guide Specifications for concrete and asphaltic concrete.

3. Avoid utility or other cuts in pavement. Whenever possible use tunneling technologies to go under pavement with conduits or piping.

Page 22 of 144Tyndall Air Force Base IFS

B02.3.2. Curb and Gutter

Applicable N/A Large graphics

Insert Curb and Gutter graphic

Barrier

Mountable

Header

1. A minimum standard curb height of 6 inches shall be consistently maintained. "Rolled" mountable curbs are allowed in Facility Group 4

2. Curb all parking, access roads and streets (except remote/isolated).

3. All streets should have integral concrete curbs and gutters. Painted curbs are prohibited because they are very difficult to maintain.

4. Use concrete for sidewalks and curbs. Do no use asphalt curbs.

5. Provide dimensions following the illustrations for Standard Mountable Curb, Standard Barrier Curb and Standard Header Curb.

6. Continuous concrete curbs and gutters shall be provided at street edges areas of the installation to:

• Help control drainage.

• Deter vehicles from leaving the pavement.

• Protect pedestrians.

• Delineate the pavement edge.

• Present a more finished general appearance.

• Assist in orderly and disciplined development of the street system.

B02.3.3. Utility Service Elements

Applicable N/A Small graphics

1. Provide all utility service lines below grade when streets are adjacent to Facility Group 1; when mounting elements (such as utility cabinets, communications equipment and water valves) above grade is unavoidable, paint these consistently and provide visual screening following Site Development, Landscaping.

2. Overhead service lines along streets adjacent to Facility Groups 2, 3 and 4 are discouraged.

Page 23 of 144Tyndall Air Force Base IFS

B02.3.4. Traffic Signs

Applicable N/A Large graphics

Insert Traffic Signs graphic

Typical Speed Limit Sign

Typical Pedestrian Crosswalk Sign

Typical Yield and Street Signs

1. Refer to Exterior Signs, Colors and Types for Traffic Control Devices, which includes signs.

2. For Regulatory and Warning type signage and roadway markings, signals, crosswalks, temporary traffic control, etc., comply with US Department of Transportation Federal Highway Administration Manual of Uniform Traffic Control Devices (MUTCD) and the DoD Supplement to the MUTCD. Guide Sign faces and other sign faces (such as handicap and reserved parking signs, etc.) shall be as required by UFC 3-120-01, Paragraph 2.18.2 Standard Brown paint (ISCC-NBS, Color Designation 56 String Brown, National Park Service Brown, Ink: PMS 469).

B02.3.5. Street Lighting

Applicable N/A Small graphics

1. Refer to the Lighting section for appropriate applications along streets.

B02.3.6. Other

Page 24 of 144Tyndall Air Force Base IFS

B03. OPEN SPACE / PUBLIC SPACE

Comply with Air Force Corporate Standards for Installation Elements:

http://afcfs.wbdg.org/installation-elements/index.html

Comply with AF Corporate Standards for Open Space / Public Space:

http://afcfs.wbdg.org/installation-elements/open-space-public-space/index.html

B03.1. Plazas, Monuments and Static Displays

Applicable N/A Large graphics

Insert Plazas, Monuments and Static Displays graphic

Insert Plazas, Monuments and Static Displays graphic

Plaza with Concrete Paving

Typical Monument

Ground-Mounted Display

Page 25 of 144Tyndall Air Force Base IFS

1. Natural features and culturally or historically significant features or events may be recognized and acknowledged with physical elements such as plazas, monuments and static displays. However, limit these elements on the base to ensure judicious use of resources and to reduce ongoing maintenance requirements.

2. Design highly durable plazas, monuments and static displays with a level of quality comparable to Facility Group 1.

3. Link plazas, monuments and static displays to the pedestrian circulation system. Install landscaping, site furnishings and lighting appropriate for the application and local climate following Installation Facilities Standards (IFS).

4. Select systems, products and materials for paving, walls, and structures following IFS.

B03.1.1. Paved Plazas

Insert Paved Plazas graphic

Concrete Paving at Flag Array

1. Mitigate heat island by providing high-albedo, shaded plazas. Pervious pavers shall be used on all plazas and courtyards in Facility Groups 1 and 2; use pervious concrete in Groups 3 and 4. The designer shall incorporate appropriate expansion and construction joints.

2. Pavers shall match the color of pavers used on adjacent sidewalks using base standard range of beiges, tans, browns, or terra cotta. Bricks used on plazas shall typically be 4” x 8” size.

Page 26 of 144Tyndall Air Force Base IFS

B03.1.2. Sculptures, Markers and Statuary

Applicable N/A Large graphics

Applicable N/A Small graphics

Insert Sculptures, Markers and Statuary graphic

Bronze Marker

1. Relate new sculpture, markers and statuary to the base's architectural design theme. Generally limit these elements to frequently used locations adjacent to Facility Group 1 and highly traveled community pedestrian spaces.

2. Consider entry gates as possible sites for new displays.

3. All proposed memorials shall follow AFI 36-3108 and be limited to highly deserving individuals or groups as deemed appropriate by the installation leadership. Living memorials (tree plantings / etc.) are discouraged due to added maintenance requirements.

4. When sculpture requires a base, match the materials and / or color palette of adjacent buildings.

5. Use LED direct or indirect lighting to accentuate features or enhance an intended effect.

6. Ensure that all sculpture, markers and statuary are honorable and inspiring, provide a sense of place, positively contribute to the base's visual quality, and encourage pride for the community and the US Air Force.

Page 27 of 144Tyndall Air Force Base IFS

B03.1.3. Static Display of Aircraft

Applicable N/A Large graphics

Applicable N/A Small graphics

Insert Static Display of Aircraft graphic

Typical Static Display

Insert Static Display of Aircraft

Ground Mounted Display

1. Follow IFS base-wide standards for all elements of the display area with specific attention to traffic sight lines, pedestrian circulation, site furnishings, signs, and lighting. Address requirements for the Facility District as well.

2. Generally locate concrete base/foundation structures for static displays below grade.

3. At static displays where pedestrian paths are provided, a minimum of one trash receptacle and one bench shall be provided. Receptacle and bench design must conform to IFS requirements.

Page 28 of 144Tyndall Air Force Base IFS

B03.2. Grounds and Perimeters

Applicable N/A Large graphics

Insert Grounds and Perimeters graphic

Water Feature at Marina

Insert Grounds and Perimeters

Open Space at Aircraft Park

Open Space Buffer

Open Space along Perimeter Fence

1. Provide formal spaces for parade and review functions, recreational areas and parks following the base's Installation Development Plan (IDP) and Installation Facilities Standards (IFS). Refer to the Site Furnishings topic for additional information.

2. Maintain preservation areas following the IDP and IFS.

3. Comply with UFC 4-010-01 DoD Minimum Antiterrorism Standards for Buildings and UFC 4-022-03 Security Fences and

Gates for all elements associated with the base's gates and perimeter fence.

Page 29 of 144Tyndall Air Force Base IFS

4. Identify and describe base-wide utility corridors in the IDP.

5. Base-wide utility infrastructure shall be inconspicuous. Bury utility service lines below grade when adjacent to Facility Group 1 and when economically feasible for Facility Groups 2, 3 and 4. When service lines are located above grade, create an ordered, coordinated appearance.

6. Follow the requirements of this IFS regarding all utility structures and service lines located above grade that visually impact the installation.

7. Where screening of utility equipment and structures is provided, allow adequate and proper clearance for safety and maintenance.

8. Reduce visual clutter and visual impact of the following items through a combination of careful placement, screen walls, landscaping and painting:

• Electrical switch-stations.

• Sewage lift stations.

• Water well pumps, storage tanks and/or related structures.

• Gas piping, meters and similar incidental items.

• Above ground fuel storage tanks.

• Any ground-mounted freestanding utility item exposed to view.

9. Larger structures such as electrical switch-stations, sewage lift stations, fuel storage tanks and mechanical/electrical equipment shall be screened from view, using materials, forms, and colors in the screen walls which match those respective design elements present at adjacent buildings.

10. Paint above-ground equipment and associated components such as electrical piping or exposed plumbing lines dark bronze.

11. Maintain currently buried utility service lines as a visual asset.

12. Bury the following exposed above-grade items in future projects when economically feasible:

• Electrical power grid and service lines.

• Telephone lines.

• Cable TV lines.

• Communications lines.

• Exterior lighting service lines.

• Any similar system of above-ground lines serving the base.

13. Consolidate and enclose service utility lines in underground utility corridors when feasible. Create routes along the inside edge of parking lot islands.

B03.2.1. Parade Grounds

1. Follow UFC 3-201-02, Appendix B for the planning and design process and criteria for parade grounds.

2. Establish and maintain parade grounds only where there is a confirmed need and provide landscape materials appropriate for the locale following IFS.

3. Bleachers may be installed only when there is a documented requirement at parade grounds. Nonferrous metals that do not require painting or going maintenance are preferred. The Base Civil Engineer shall determine quantities, sizes, and products on a case basis.

Page 30 of 144Tyndall Air Force Base IFS

B03.2.2. Parks

Applicable N/A Large graphics

Insert Parks graphic

Green Space near Lodging

Insert Parks graphic

Green Space at Housing Area

1. Bleachers may be installed only when there is a documented requirement at parks and fields for recreational events.

Follow guidance under Parade Grounds.

2. Picnic pavilions may be provided in parks where there is a documented need.

3. Prohibited picnic pavilion materials include wood, concrete masonry units (CMU) or metal pre-manufactured storage sheds. Use only materials and detailing that is low maintenance and endures with minimal weathering.

4. When picnic pavilions are permitted near facilities, generally match the architecture of the adjacent facility and provide a level of quality of the adjacent facility group number.

B03.2.3. Preserves

Insert Preserves graphic

Boardwalk

Beacon Beach Marina

Beacon Beach Marina

1. Preserve areas adjacent to runways, taxiways, aprons, golf course roughs, storage areas, antenna facilities, and ammunition storage areas, as open space.

Page 31 of 144Tyndall Air Force Base IFS

2. Provide minimal maintenance with mowing as needed for controlling bird behavior for airfield safety, or eliminating fire hazards.

3. Open areas and preserves identified in the IDP shall remain natural in state with minimal maintenance except for clearing brush and grass from the road side and/or removing trees, brush and grass under existing overhead utility lines.

B03.2.4. Perimeter Fence

Insert Perimeter Fence graphic

Fence with Integrated Planter

Insert Perimeter Fence graphic

CMU Posts with Steel Fencing

1. Design, install and maintain the base's perimeter fence following UFC 4-022-03.

2. Stringently comply with AT / FP requirements following UFC 04-010-01 for all spaces adjacent to the base's perimeter fence and all gates.

3. Fencing, gates and other elements that are associated with the main gates shall be a level of quality equivalent to Facility Group 1.

4. Maintain a positive visual quality along the traffic corridor on both sides of the main gates. Specifically address pedestrian access, circulation and common areas.

Page 32 of 144Tyndall Air Force Base IFS

C. SITE DEVELOPMENT

Comply with Air Force Corporate Standards for Site Development:

http://afcfs.wbdg.org/site-development/index.html

C01. SITE DESIGN

Comply with Air Force Corporate Standards for Site Development:

http://afcfs.wbdg.org/site-development/index.html

Comply with AF Corporate Standards for Site Design / NEPA:

http://afcfs.wbdg.org/site-development/site-design-nepa/index.html

C01.1. Site Design Considerations

Applicable N/A Large graphics

Applicable N/A Small graphics

Insert Site Design Considerations

Gathering Space

Shaded and Partially Enclosed Area

Plaza and Bench Near Entrance

1. Collect documentation to validate approvals and completion of the NEPA process.

2. Ensure site design compliance with the Installation Development Plan (IDP) and its component plans and Installation Facilities Standards (IFS).

3. Promote integrated design with on-site solutions such as engineered small-scale hydrologic controls verses base-wide infrastructure; consider open space, natural features, bioswales, building roofs, streets, and paved surfaces.

4. Limit the impact of development on land and water resources. All site elements and infrastructure shall reinforce an image of sustainability, with reduced energy demand, renewable-energy usage, and water conservation.

5. Consider energy conservation during site design for the following categories: building and site lighting, auxiliary systems and equipment (refrigerators, elevators, etc.), building envelope, electric power and distribution, HVAC systems and equipment, service hot water, energy management (metering, EMCS).

6. Coordinate on-site renewable-energy systems and components to minimize area requirements and maximize efficiencies.

Appropriately buffer and screen these and other mechanical systems and equipment.

7. New building projects should preserve open space and protect natural habitat.

8. Conform to existing topography to the greatest extent possible and use slopes to increase site and building efficiencies.

Design sites to minimize irrigation and impacts to stormwater runoff.

9. Carefully study new project sites to identify the character of adjacent buildings, streets, landscaping, and site design elements. Reinforce the existing character in new site design.

Page 33 of 144Tyndall Air Force Base IFS

10. Consider relationships to adjacent facilities and district / centralized heating and cooling infrastructure and cost effectively connect building systems to harvest heat, grey water or other beneficial byproducts.

11. Minimize existing and planned obstructions from landscaping, structures, topography, and adjacent developments to preserve solar access and natural ventilation.

12. Purposefully integrate service access, receiving and storage areas to eliminate the need for visual screening.

13. Appropriately connect to the base network of streets, sidewalks and trails using drive aisles, parking areas, walkways, paths, and bicycle routes addressing both vehicles and pedestrians.

14. Applicably coordinate heat island mitigation in paving and roof designs when implementing an integrated approach to stormwater management.

15. Consider the location of “Designated Tobacco Areas.”

C01.2. Building Orientation

Insert Building Orientation graphic

Conceptual Site Analysis and Site Design Diagram

Page 34 of 144Tyndall Air Force Base IFS

Local Solar Data

Local Climate Data

Site Data

East-West Axis

Optimum Solar Control

Maximized Shading

1. Ensure the site will accommodate optimum requirements for building orientation, which is with the long axis parallel to the east/west direction for rectilinear CONUS buildings.

2. Meet Installation Facilities Standards (IFS) requirements for the locations of the building's passive and renewable-energy systems --including geothermal and solar systems --and exterior shading systems.

3. Locate the building(s) and permitted ancillary structures to promote solar gain, solar shading, natural ventilation, rainwater harvesting, wind buffering and other beneficial passive systems. Consider natural ventilation during the design of HVAC systems.

4. Consider relationships to adjacent sites and their facilities and infrastructure, and cost effectively integrate building systems to harvest heat, grey water or other beneficial byproducts.

5. Consider the “public side” of the building, its views and the location of the main entrance.

6. Limit the use of courtyards and restrict their use to Group 1 and 2 facilities. When provided, conform to the geometry of rectilinear narrow buildings developed along an east-west axis. Define space with a building's exterior wall and with supplementary screen walls matching facility materials and detailing. Locate these near the main entrance, align with view corridors, and provide appropriate landscaping, site furnishings and lighting.

7. At a minimum, a courtyard must have one trash receptacle, one bench, and one (1) picnic table with seating. Generally use concrete or brick paving at all courtyards following standards for plazas.

C02. UTILITIES

Comply with AF Corporate Standards for Site Development:

http://afcfs.wbdg.org/site-development/index.html

Comply with AF Corporate Standards for Utilities:

http://afcfs.wbdg.org/site-development/utilities/index.html

Page 35 of 144Tyndall Air Force Base IFS

C02.1. Utility Components

Applicable N/A Large graphics

Insert Utility Components graphic

Screened Utility Yard at Group 1

Utility Enclosure and Adjacent Transformer

Fire Hydrant

Site Located Gear

Screen Walls at Group 2

Equipment in Need of Screening

1. Provide all on-site utility service lines below grade for Facility Group 1; Locate new electrical power lines and utilities in Groups 2, 3 and 4 underground whenever possible. Provide landscape setbacks along all buried utility routes.

2. When mounting elements (such as utility cabinets, communications equipment and water valves) above grade is unavoidable, paint these consistently and provide visual screening following Installation Facilities Standards (IFS).

3. Provide installation of utility infrastructure to support near term and future electric vehicle charging stations.

4. Define all service entry points into the building and route distribution below grade into an interior space within the facility;

exposed conduits, cables and wires on exterior walls are not permitted for Facility Group 1.

5. Include consideration of appropriate placement of meters in support of Automated Revenue Management Services

(ARMS).

6. Limit exterior mechanical distribution systems such as exterior steam, chilled water, and hot water distribution to Group 3 facilities; when required for Group 1 and 2 facilities integrate with the architecture and provide visual screens following

IFS.

7. Direct roof drainage to underground collection when feasible or provide splash blocks / paved channels to intercept roof drainage at grade.

Page 36 of 144Tyndall Air Force Base IFS

C03. PARKING AREAS

Comply with AF Corporate Standards for Site Development:

http://afcfs.wbdg.org/site-development/index.html

Comply with AF Corporate Standards for Parking Areas:

http://afcfs.wbdg.org/site-development/parking-areas/index.html

C03.1. Configurations and Design

Applicable N/A Large graphics

Applicable N/A Small graphics

Insert Configurations and Design

Small Lot Configuration

Large Lot Configuration

Facility Group 1 Configuration

90 Degree Configuration

Accessible Spaces Near Entrance

Landscape Island

1. Evaluate adjacent sites and cost-effectively consolidate parking areas to maximize efficient use; ensure that all areas meet accessibility guidelines.

2. Generally envision on-site parking as a series of small connected singular areas selectively placed around the facility served, rather than a single large area; buffer parking areas from the facility main entrance with a transition space and provide drop-offs to decrease close-in parking. Comply with IFS standards while meeting ATFP requirements.

3. Parking lots shall be designed to minimize the visual impact of parking areas by creating smaller, well-screened, landscape parking areas located behind the facilities they serve. Reduce the visual impact of oversized parking areas with landscaped medians and islands.

4. Parking areas shall be located within 500 feet of the facilities they serve but no closer than the minimum allowed by ATFP standard or as directed by the AT office or its representatives.

5. Parking lots must accommodate all vehicles that will serve the facility. Provide access for fire apparatus according to NFPA.

Page 37 of 144Tyndall Air Force Base IFS

6. Consider locations and requirements of near term and future electric vehicle charging stations.

7. Provide parking spaces for disabled use…