6/24/2016

US Army Corps of Engineers

BUILDING STRONG®

MKARNS Station Dredging Little Rock District

Jonathan J. Sawrie

Chief, Operations & Civil Works Branch

Contracting Division

15 June 2016

BUILDING STRONG®

Overview

Invitation for Bid – W9127S-16-B-0001

Provide station dredging on the McClellan- Kerr Arkansas River Navigation System (MKARNS), Arkansas & Oklahoma, navigation miles 0.0 to 444.8.

BUILDING STRONG®

Three Generalized Dredging Cases:

1. White River Entrance Channel

2. Lock Approaches

3. Mainstem

BUILDING STRONG®

Overview

Unrestricted Procurement

Magnitude of Construction

– Over $10 Million

BUILDING STRONG®

Overview

Performance Period:

- Base period, 12 months

- Two, 12-Month Option Periods

Public Bid Opening:

– 06 July 2016, 1:00 P.M., CDST

BUILDING STRONG®

Approximately $70 Million backlog of critical infrastructure repairs needed

BUILDING STRONG®

Dredging Trends (2005 – 2014)

2005 2006 2007 2008 2009 2010 2011 2012 2013 2014

Locations

200,000

400,000

600,000

800,000

1,000,000

1,200,000

2005 2006 2007 2008 2009 2010 2011 2012 2013 2014

Quantity (CY)

BUILDING STRONG®

Dredging Trends Contract Cost: Avg. $3.0 Million/yr (2005 to 2014)

Avg. $2.1 Million/yr (2010 to 2014)

Contract Cost / CY: $ 4.22 Million (2005)

$ 4.41 Million (2010)

$15.56 Million (2014)

Standby Percentage of Time: Avg. 61% (2005 to 2014)

Avg. 72% (2010 to 2014)

BUILDING STRONG®

New Dredging Approach:

Page 59 of the solicitation:

- 1.1.1 Work Season 01 May – 30 Nov

- 1.1.2 Work for Others

01 Dec – 30 Apr

BUILDING STRONG®

Notes:

Page 6 of the solicitation:

- Submit a hard copy and a

CD ROM copy of your bid

Page 81 of the solicitation:

- Anti-terrorism/Operations Security Requirements, Level I Requirement

BUILDING STRONG®

Notes:

Pages 57-58 of the solicitation

-1.6 Pre-Award Survey

1.6.1 Offeror’s Qualifications

1.6.2 Inspection of Plant

1.6.3 Unbalanced Bids

BUILDING STRONG®

Notes:

ALL QUESTIONS MUST BE SUBMITTED

IN PROJNET !

Bidder Inquiry Key: 7ZMVF2-AGP2RK

ProjNet closes for RFIs on 20 June 16