This is a Purchase Description document for a U.S. Army Corps of Engineers (USACE) procurement for The Dalles Lock & Dam project located in Oregon. The contractor shall supply three customized Straval brand products consisting of two check valves (CLIN 0001) rated at 6000 psi with a flow coefficient of 6.188 and set pressure of 2 psig, two relief valves (CLIN 0002) rated at 3000 psi with a flow coefficient of 7.95 to be set in the field, and two strainers (CLIN 0003) rated at 3000 psi with a flow coefficient of 42 and perforation size of 0.062 inches.
The contractor is responsible for shipment and delivery to The Dalles Lock and Dam facility in The Dalles, Oregon within four weeks of contract award. All deliveries must arrive during normal business hours of Monday through Thursday, 7:00 a.m. to 4:00 p.m. Pacific Time, excluding federal holidays. Products must be properly packed to ensure undamaged arrival. All items are covered by the manufacturer's standard one-year minimum warranty on parts, labor, and workmanship. Invoices must be submitted electronically to the USACE Finance Center at CEFC-G2invoices@usace.army.mil with copies to delivery point of contact Heather Pyles at Heather.L.Pyles@usace.army.mil and David A. Hovde at David.A.Hovde@usace.army.mil.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Purchase Description: Straval Check Valve, Relief Valve, and Strainer
Project: U.S. Army Corps of Engineers (USACE), Northwestern Division Portland District (NWP), The Dalles Lock & Dam
1. Scope of Work The Contractor shall provide the following Brand Name Straval products to the below specifications.
Contract Line Item (CLIN)
Supply Description QTY
CLIN 0001
Customized Product: Check Valve Rated Pressure 6000 psi psi ~414 bar rating Estimated Flow Cv: 6.188 Options selected: Spring Range: 2 - 2 psig / 0.138
- 0.138 barg Set Pressure: 2 pcs. @ 2 psig (0.138 barg)
CLIN 0002 Customized Product: Relief Valve High Pressure Group 3000 psi (207 bar) Rating Estimated Flow Cv: 7.95 Options selected: Spring Range: 250 - 2000 psig /
17.2 – 138 barg Set Pressure: 2 pcs. @ None (Valve will be set in the field)
CLIN 0003 Customized Product: Strainer Strainers with Perf Baskets: Body 3000# psi Rating (207 bar) Estimated Flow Cv: 42 Options selected: Perf Size: 0.062 - 0.062 in /
1.575 mm
1.1 Warranty:
All items shall be covered by the manufacturer’s standard warranty on all parts, labor, and workmanship from factory defects. Warranty period shall be a minimum of one year.
1.2 Shipment and Delivery:
Contractor is responsible for shipment and delivery of procured products (Destination) to the address listed below within four (4) weeks after contract award. The contractor shall be responsible for packing and shipping the components in a manner that will ensure undamaged and complete arrival at the powerhouse. All shipments must be scheduled to arrive during The Dalles normal business hours of Monday-Thursday 7:00 a.m. to 4:00 p.m. Pacific Time, excluding federal holidays. Please note, if a federal holiday occurs on a Sunday, it is observed the Monday after.
1.3 Delivery POC:
Heather Pyles Email: Heather.L.Pyles@usace.army.mil Phone: (541) 506-8532
Delivery Location:
US Army Corps of Engineers The Dalles Lock and Dam I-84 EXIT 88 Interstate 84 Exit 40 The Dalles, OR 97058
1.4 Invoice Information.
Invoice(s) shall be prepared in accordance with FAR clause 52.212-4(g) and submitted electronically via email to USACE Finance Center:
CEFC-G2invoices@usace.army.mil
Electronic Copy to: The Dalles POCs Heather.L.Pyles@usace.army.mil and David.A.Hovde@usace.army.mil.
For Invoice receipt verification or for a vendor's Payment problem, the vendor may contact the USACE Finance Center at Phone Number (901) 873-9077.
USACE FINANCE CENTER
5722 INTEGRITY DRIVE
WILMINGTON, TN 38054-5005
mailto:Heather.L.Pyles@usace.army.mil mailto:CEFC-G2invoices@usace.army.mil mailto:Heather.L.Pyles@usace.army.mil mailto:David.A.Hovde@usace.army.mil
| Purchase Description: Straval Check Valve, Relief Valve, and Strainer |
| 1. Scope of Work |
File details come from the government source that posted it. Updated .