SOW_JDN D-S Gate Trackwheel.pdf
PDF 331 KB Posted
- Attached to
- USACE NWP, John Day Track Wheels Purchase Federal contract opportunity
- Solicitation number
- W9127N26QA001
About this file
This Statement of Work (SOW) details the purchase of replacement trackwheel assemblies for the John Day Dam navigation lock downstream lift gate. The U.S. Army Corps of Engineers requires six stainless steel trackwheel assemblies with specific material specifications, including ASTM A564 Type 630 Condition H1150 Stainless Steel components, self-lubricated Nickel Aluminum Bronze bushings, and associated hardware. The procurement includes an option to purchase two additional assemblies, with all components to be delivered by February 16, 2026, to the John Day Dam located at I84 Exit 109 in Rufus, Oregon. Delivery is restricted to Monday through Thursday between 0800-1600 PST, with two point of contact representatives provided: Adrian Mariscal-Arellano and Travis O'Brien, both from the U.S. Army Corps of Engineers.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment W9127N26QA0010001 SF 30.pdf | ||
| Questions Answered_11.07.2025.pdf | ||
| Solicitation Amendment - W9127N26QA0010001.pdf | ||
| Contracting Officers Decision FAR Part 13.501 JDA Trackwheel amended_Redacted.pdf | ||
| Questions Answered_11.04.2025.pdf | ||
| Questions answered_31Oct2025.pdf | ||
| JDGTRE26_SPECS_ADV.pdf | ||
| Contracting Officers Decision FAR Part 13.501 JDA Trackwheel_Redacted.pdf | ||
| Solicitation - W9127N26QA001.pdf | ||
| Final_Drawings_with_Cover_Sheet_signed_20251008.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Purchase of a Replacement Trackwheel Assemblies for the John Day Navigation Lock Downstream Gate
Scope:
This scope of work (SOW) covers the purchase and shipment of the components listed below.
a. Background:
The John Day Dam navigation lock downstream lift gate requires replacement trackwheels as the current trackwheels are at the end of their service life. The trackwheels stabilize the gate as it translates vertically to open and close the lock.
Requirements:
Purchase components listed below for delivery by 16 February 2026.
Purchase of:
a. Description: Stainless steel trackwheel assembly with self-lubricated bushings
i. ASTM A564 Type 630 Condition H1150 Stainless Steel Trackwheel
ii. ASTM A564 Type 630 Condition H1150 Stainless Steel Trackwheel Shaft
iii. ASTM A564 Type 630 Condition H1150 Stainless Steel Keeper Plate
iv. ASTM A240 Type 304 Stainless Steel Retainer plate
v. Self-lubricated Nickel Aluminum Bronze backed lined collar
vi. Self-lubricated Nickel Aluminum Bronze backed lined bushing
vii. Nickel Aluminum Bronze Mid Eccentric Bushing
viii. Nickel Aluminum Bronze End Eccentric Bushing
ix. ASTM A240 Type 304 Stainless Steel Clamp plate
x. Containment Exclusion seals
xi. Bolts, washers, and nuts as indicated on drawings
xii. ASTM A403 Type 304 Stainless Steel Grease port plug
b. Manufacturer Part Number: N/A
c. Manufacture: N/A
d. Quantity: Six Trackwheel assemblies (6) with the option for two (2) additional assemblies. Spare hardware as indicated in the drawings.
Shipping:
Supplies shall be delivered to John Day Dam, I84 Exit 109, Rufus, OR 97050 Mon-Thur
0800-1600 PST,
POC: Adrian Mariscal-Arellano, email: Adrian.MariscalArellano@usace.army.mil, phone:
(509) 733-2535
Travis O’Brien, email: Travis.C.Obrien@usace.army.mil, phone (541) 739-1090