A.02 PWS Green Peter SEED.pdf
PDF 2 MB Posted
- Attached to
- Vegetation Management IDIQ Federal contract opportunity
- Solicitation number
- W9127N25QA030
About this file
This Performance Work Statement (PWS) details vegetation management services for the Green Peter Dam located in Foster, Oregon, under the US Army Corps of Engineers – Portland District. The project requires removing vegetation within 30-50 feet of the dam toe and edge of abutments to maintain a "Vegetation Free Zone" that prevents structural damage and allows proper dam monitoring.
The work involves specific tree removal in two designated zones, with optional tasks for log material disposal. Contractors must fell trees, dispose of them in a designated stockpile area, treat tree stumps with herbicide, and restore the site grade. The project has strict requirements for safety, environmental protection, herbicide application, and personnel qualifications. All onsite work must be completed by September 30, 2026, with optional tasks to be executed within specific timeframes prior to contract completion. Contractors must submit detailed plans including work plans, safety plans, environmental protection plans, and daily quality control reports.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Combination Synopsis Solicitation - W9127N25QA030 Amendment 1 - 21 Aug 25.pdf | ||
| SCA WD 2015-5569 Lane-23Dec24.pdf | ||
| Combination Synopsis Solicitation - W9127N25QA030.pdf | ||
| SCA WD 2015-5571 Jackson-23Dec24.pdf | ||
| SCA WD 2015-5573 Marion_Polk-23Dec24.pdf | ||
| SCA WD 2015-5587 Linn-23Dec24.pdf | ||
| PWS - W9127N25QA030.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Work Statement (PWS) for the
Green Peter Vegetation Management, Linn County, Oregon
1 INTRODUCTION
The US Army Corps of Engineers – Portland District has a requirement to solicit services to manage vegetation at the Green Peter Dam in Foster, OR as identified in this Performance Work Statement (PWS).
This is a non-personal services requirement. Perform these services in accordance with the terms of the Base
Contract and this Task Order. Comply with all local, state, and federal regulations.
2 LOCATION
Project is located at Green Peter Dam, Route 20, Foster, OR 97345. Refer to Attachment A for map to site location.
3 PERIOD OF PERFORMANCE
All onsite work under this Task Order must be completed by 30 September 2026.
4 EXISTING CONDITIONS
4.1 General
Green Peter Dam has a required “Vegetation Free Zone” which must be maintained to prevent structural damage to the dam and to allow maintenance staff proper visibility to monitor the dam. Currently, the
Vegetation Free Zones have prohibited vegetation which must be removed. The vegetation requiring removal consists primarily of evergreen and deciduous trees.
4.2 Attachment List
The attachments listed below are provided to help illustrate the existing conditions of the project site and are for reference only:
Attachment A – Site Location
Attachment B – Work Area
Attachment C – Spill Response Form
Attachment D – NWP Pesticide Use Annual Reporting
Attachment E – Herbicide Post Application Report
4.3 Site Access
Site access is via Quartzville Drive. Top of dam is a public roadway, South Bank Road. Partial and full closures of the road need coordination with USACE, public notice and state certified flaggers.
5 DEFINITIONS
5.1 Contracting Officer (KO)
The Government employee who is authorized to enter into, administer, and/or terminate Contracts and make related determinations and findings.
5.2 Contracting Officer’s Representative (COR)
The Government employee who has been authorized in writing as the Contracting Officer’s Representative, acting within the limits of their authority.
6 REFERENCES
Comply with applicable federal, state, local, and USACE standards, including:
a. EM-385-1-1 (Latest)
b. 29 CFR 1926
c. Environmental Protection Agency (EPA)
d. Occupational Safety and Health Administration (OSHA)
e. American Society for Testing and Materials (ASTM)
f. Oregon Department of Environmental Quality (ODEQ)
g. Oregon Administrative Regulation (OAR)
7 PERFORMANCE OBJECTIVES SUMMARY (POS)
Provide all personnel labor, equipment, tools, materials, vehicles, testing, supervision, and incidental services necessary to perform the work as defined by the tasks listed herein including mobilizations and demobilizations from the site.
7.1 Task 1 – Specific Tree Removal – Zone #1, CLIN 0001
Provide all pre-work submittals as listed in section 8.6 of this Task Order for Government review and approval prior to the start of any work. The Contractor shall fell all trees within 30 feet of the dam toe and edge of abutments in the designated work area as shown in Attachment B. Dispose of felled trees in log stockpile area as shown in Attachment B. Trees will vary in size and variety. Designated work area may contain uneven terrain, road rights-of-way, infrastructure, and confined environments. Confirm designated work area boundaries with COR prior to the start of work. Treat tree stumps with herbicide injection as required in PWS section 8.5. Backfill any voids created during removal operations to match the grade of the adjacent land. Payment will be made for the site preparations, felling, chipping, piling in the designated stockpile area, herbicide application, and completion of site restoration tasks. Amount will be measured by job and based on COR visual inspection of the completion of requirements in PWS Sections 8.5, 8.6, 8.7, and 8.8.
7.2 Task 2 – Log Material Disposal – Zone #1, CLIN 0002 (OPTIONAL)
Remove and dispose of all piled log material from Task 1 off Government Property. Payment will be made for the disposal of stockpiled log material off Government Property. Amount will be measured by job and based on Contractor submission of load tickets and COR visual inspection of removed material. Optional
CLIN to be executed no later than 60 calendar days prior to Contract Completion.
7.3 Task 3 – Specific Tree Removal – Zone #2, CLIN 0003 (OPTIONAL)
The Contractor shall fell all trees from 30 feet off the dam toe and edge of abutments to 50 feet off the dam toe and edge of abutments in the designated work area as shown in Attachment B. Dispose of felled trees in log stockpile area as shown in Attachment B. Trees will vary in size and variety. Designated work area may contain uneven terrain, road rights-of-way, infrastructure, and confined environments. . Confirm designated work area boundaries with COR prior to the start of work. Remove tree stumps and dispose in log stockpile area as shown in Attachment B. Backfill any voids created during removal operations to match the grade of the adjacent land. Payment will be made for the site preparations, felling, chipping, piling in the designated stockpile area, stump removal, and completion of site restoration tasks. Amount will be measured by job and based on COR visual inspection of the completion of requirements in PWS Sections 8.5, 8.6, 8.7, and 8.8.
Optional CLIN to be executed no later than 180 calendar days prior to Contract Completion.
7.4 Task 4 – Log Material Disposal – Zone #2, CLIN 0004 (OPTIONAL)
Remove and dispose of all piled log and stump material from Task 3 off Government Property. Payment will be made for the disposal of stockpiled log and stump material off Government Property. Amount will be measured by job and based on Contractor submission of load tickets and COR visual inspection of removed material. Optional CLIN to be executed no later than 60 calendar days prior to Contract Completion.
8 PERFORMANCE REQUIREMENTS SUMMARY (PRS)
The Task Order service requirements are summarized in performance objectives that relate directly to requirements. The performance threshold briefly describes the minimally acceptable levels of service required for each requirement. The PRS and the Contractor’s Quality Control Plan provide information on
Contract requirements, the expected level of Contractor performance and the expected method of
Government validation and confirmation of services provided. These thresholds are critical to mission success
8.1 Performance Requirement Summary Table
Below are the criteria against which the performance will be evaluated. Work shall be considered deficient if any one of the following conditions are not in accordance with the following requirements.
PERFORMANCE
OBJECTIVE
PWS
PARA.
PERFORMANCE
THRESHOLD
METHODS OF
VERIFICATION
Task 1: Specific Tree
Removal – Zone #1
7.1 No more than one
(1) valid defect per task order.
Periodic Validation, Planned Inspection, and Customer/Public
Complaint
Task 2: Log Material
Disposal –
Zone #1 (OPTIONAL)
7.2 No more than one
(1) valid defect per task order.
Periodic Validation, Planned Inspection, and Customer/Public
Complaint
Task 3: Specific Tree
Removal – Zone #2
(OPTIONAL)
7.3 No more than one
(1) valid defect per task order.
Periodic Validation, Planned Inspection, and Customer/Public
Complaint
Task 4: Log Material
Disposal – Zone #2
(OPTIONAL)
7.4 No more than one
(1) valid defect per task order.
Periodic Validation, Planned Inspection, and Customer/Public
Complaint
8.2 Performance Assessment and Remediation
If any work does not conform to the Base Contract or Task Order requirements, the Government may require the Contractor to perform the work again in conformity with the Base Contract or Task Order requirements, at no increase in Task Order amount. Deficiencies shall be corrected within 24 hours of notification of non-conformance. When the defect(s) cannot be corrected by re-performance, the Government may require the
Contractor to take necessary action to ensure future performance to contract requirements OR reduce the contract price to reflect the reduced value of the work performed. When performance is deemed unacceptable, as defined in the PRS, the COR will inform the Contractor’s on-site representative that performance is unacceptable and written documentation shall be provided. The Contractor shall respond to the written notice within 10 calendar days of receipt. Disputes in surveillance should be referred to the KO.
8.3 Methods of Verification
Contract performance will be assessed through periodic validation, planned inspection, and customer or public feedback. The KO or COR shall inspect by validating actual work performance, physically checking an attribute of the completed task, checking management information reports, investigating customer or public complaints, conferring with Project Staff, or otherwise inspecting the task or its results to determine whether performance meets the standards contained in this Task Order and in the Base Contract. Method of
Verification for each Performance Objective are specified below:
a) Periodic Validations: The COR may employ a “spot check” inspection and evaluation of services performed. Periodic validations will be conducted on a scheduled basis (daily, weekly, or monthly) and may be adjusted, based on quality trends.
b) Planned Inspections: This method of inspection surveillance is used by the COR when individual activities of importance or cost are performed, where the Contractor has a record of poor performance, or where services to be monitored are at several sites and can be scheduled to conserve inspection travel time.
c) Customer or Public Complaints: The COR shall perform inspections as necessary to address customer or public complaints.
8.4 Project Coordination
Coordinate project activities and resolve critical issues in a timely manner with COR. Outside approved schedule as specified in paragraph 8.7.4, notify the COR at least 5 workdays, excluding weekends, prior to start of work under each task and within 5 workdays of completion of work of each task.
8.5 Contractor Required Personnel
The Contractor Quality Control Manager (CQCM), Site Safety and Health Officer (SSHO), and Project
Superintendent may all be the same individual. If any qualification requirements conflict, the most stringent requirement applies.
8.5.1 Site Safety and Health Officer (SSHO)
The SSHO must meet the requirements of EM 385-1-1 chapter 2 and ensure that the requirements of 29 CFR
1926.16 are met for the project. The SSHO or an equally qualified Designated Representative/alternate must be at the work site at all times to implement and administer the Contractor's safety program and Government-accepted Accident Prevention Plan. The SSHO's training, experience, and qualifications must be as required by EM 385-1-1 paragraph 2-2(3), entitled Level 3 SSHO.
Provide a Competent Person on-site at all times when the work that presents the hazards associated with their professional expertise is being performed for all of the hazards identified in the Contractor's Safety and
Health Program in accordance with the accepted Accident Prevention Plan. Provide the credentials of the
Competent Person(s) to the COR.
Site Safety and Health Officer (SSHO) must be employed by the Prime Contractor. Provide a SSHO meeting the following requirements:
a. A minimum of 3 years safety work on similar project.
b. 30-hour OSHA construction safety class or equivalent within last 5 years.
c. Competent person training as needed including designation and qualification to be a "competent person" in accordance with 29 CFR 1926.
8.5.2 Contractor Quality Control Manager (CQCM)
Identify an individual at the site of the work who is responsible for overall management of the Contractor’s
Quality Control (CQC). Authorize the individual to act in all CQC matters for the Contractor, including stoppage of work and removal of noncomplying work. The CQC Manager must be on the site at all times during tree removal, including during the work of any Subcontractors.
8.5.3 Project Superintendent
Identify an individual at the site of the work who is the full-time onsite supervisor. The superintendent must have a minimum of two years’ experience with tree removal.
8.6 Herbicide Application
For the use of herbicide to treat tree stumps, supply and apply specified herbicides to tree stumps of removed trees in the work area (Attachment B). Perform herbicide application using the application technique injection. Perform herbicide application services in accordance with all local, state, and federal laws, EPA approved label instructions, and in accordance with specifications contained herein.
8.6.1 Approved Herbicides
Use only approved herbicides that are effective against the target species and safe for the environment. Do not use any herbicides that contain ingredients found in Oregon’s Listing of Restricted Use Pesticides or found in OAR 603-057-0205.
8.6.2 Application
Mix and apply all herbicides according to the EPA approved label instructions in designated work areas. The
Contractor shall be liable for any damages resulting from improper use of herbicides.
8.6.3 Weather
Identify weather conditions before beginning any pesticide application and continue to monitor weather conditions throughout the course of the application. Manufacturer's label directions and warnings relative to temperature, wind, or other weather conditions must be strictly adhered to. Immediately stop applying pesticide if weather conditions begin to adversely impact the application. Herbicide applications must not take place before or when precipitation is expected. Area must be retreated if it rains within the specified dry period stated on the herbicide label.
8.6.4 Training
Personnel must be trained and have a current Oregon Department of Agriculture (ODA) pesticide applicators license. Submit certifications with Environmental Protection Plan (EPP).
8.6.5 Records, Applications, and Submittals
Provide accurate records of all herbicides used on public lands. Submit a completed post-use pesticide application report (Attachment E) for all herbicides applied. This form must be completed and submitted no more than 48 hours after completion of the application. Complete the NWP Pesticide Use Annual Reporting
(Attachment D) for the pesticide(s) used on the project site to be submitted during Task Order close out.
8.7 Submittals
Submit the following submittals via email to the COR for approval within 30 calendar days of Task Order
Award. Submittals a. through h. must be approved prior to on-site work beginning. The Government review period will be 14 calendar days.
a. Work Plan
b. Accident Prevention Plan (APP)
c. Environmental Protection Plan (EPP)
d. Project Schedule
e. Disposal Receipts
f. Contractor’s Quality Control Plan (CQCP)
g. QC Reports: 24 hours after completion of each workday
h. Qualifications of Competent and Qualified Persons, as pertinent
8.7.1 Work Plan
Submit a work plan for Government approval. At minimum, include the following:
a. Equipment list that includes make and model of equipment to be used for the work,
b. List of all employees who will be working on site to include prime and Subcontractors,
c. Map of area and planned equipment staging and access,
d. Organization chart including Subcontractors, number of workers onsite,
e. References to the CQCP, and APP as appropriate. Break down work plan per performance objective task.
8.7.2 Accident Prevention Plan
a. Submit an APP in accordance with the requirements of EM 385-1-1 2-7.b. Follow the mandatory ENG
Form 6293 (Accident Prevention Plan Worksheet) to ensure all required elements are captured. A copy of ENG Form 6293 can be found at:
https://www.publications.usace.army.mil/LinkClick.aspx?fileticket=LmW_eJDoLpI%3d&tabid=164
38&portalid=76&mid=43543
b. If an item on ENG Form 6293 is not applicable because of the nature of the work to be performed, state this exception and provide a justification.
c. The APP must be job-specific and must address any unusual or unique aspects of the project or activity for which it is written. General corporate-level safety and health programs are not considered job or work-site specific.
d. Green Peter Dam and Foster, Oregon have previously experienced significant wildfires in the area.
Include in the Accident Prevention Plan the processes and procedures that employees will implement in the event of a wildfire in the area.
e. Work cannot proceed without a Government-accepted APP.
f. Once accepted, the APP and appendices will be enforced as part of the Task Order. Disregarding the provisions of this Task Order or the Government-accepted APP will be cause for stoppage of work, until the matter has been rectified.
g. Once work begins, changes to the APP must be made with the knowledge and concurrence of the
COR, Project Superintendent, SSHO, and Contractor’s Quality Control Manager. Should any severe hazard exposure, become evident, stop work in the area, secure the area, and develop a plan to remove the exposure and control the hazard. Notify the COR both verbally and in writing, within 24 hours of discovery. In the interim all necessary action must be taken by the Contractor to restore and maintain safe working conditions in order to safeguard on-site personnel, visitors, the public (as defined by
ASSE/SAFE A10.34), and the environment.
h. Copies of the APP must be maintained at the work site. Continuously review and amend the APP, as necessary, throughout the life of the Task Order. Incorporate unusual or high-hazard activities not identified in the original APP in the plan as they are discovered.
8.7.3 Environmental Protection Plan (EPP)
a. Submit an Environmental Protection Plan (EPP) for approval by the COR prior to initiation of the work tasks, that includes the following:
1) Name(s), phone number(s), and qualification(s) of individual(s) responsible for ensuring adherence to the Environmental Protection Plan.
2) Site-Specific Spill Prevention and Response Plan (Attachment C)
3) Plan for debris and disposal management
4) Protection of Water Resources
5) Provisions to assure that dust, debris, materials, trash, etc., do not become air borne and travel off the project site.
6) If applicable, Erosion Control Plan (ECP) detailing procedures on implementation of site-specific Best Management Practices (BMPs) during onsite activities. ECP measures must be maintained and monitored daily for proper functionality ensuring erosion does not leave the work site.
7) If using herbicide, certifications of personnel applying herbicide
b. Observe and comply with all local fire restrictions regarding road closure, equipment use and fire suppression equipment. If operations extend into fire season, submit a fire prevention plan for review and approval.
c. If at any point during work, measures are found ineffective at protecting and/or preventing visible erosion or other environmental pollution, the project must stop to evaluate environmental protection measures and reestablish control. Repairs, replacements, or the installation of additional measures must be completed prior to resuming work.
8.7.4 Project Schedule
a. Submit a Project Schedule that includes at a minimum:
1) Anticipated site mobilization and demobilization dates.
2) Submission of all submittals listed in section 8.6 for approval by the COR.
3) Preparatory meeting and initial demonstration of performance.
4) Anticipated start and end dates for work under each task.
5) Government inspection of completed work.
8.7.5 Disposal Receipts
The Contractor shall provide copies of all disposal receipts identifying (at a minimum):
a. Material(s) disposed of.
b. Location of disposal (including company name and address).
c. Cost
d. Volume or weight in tons.
e. Date
f. Disposal type (recycle, compost, landfill, converted/reuse, etc.).
8.7.6 Contractor’s Quality Control Plan (CQCP)
Submit the Contractor’s Quality Control Plan (CQCP) for Government acceptance. Identify the Contractor
Quality Control Manager (CQCM) in the plan. On site work cannot begin until the CQC Plan has been accepted. The Contractor, not the Government is responsible for quality control actions necessary to meet the quality standards set forth by this Task Order.
8.7.7 Daily QC Reports
Document work progress with daily QC Reports. Provide CQCM reviewed and signed daily operations reports to the COR, showing daily and cumulative progress. Reports will include personnel onsite, hours worked, area of work, type of work, the amount of debris removed from the work site and location of material disposal. Include in reports photographs of daily progress. Submit daily QC reports via email in PDF format within 24 hours for Government acceptance.
8.7.8 Qualifications of Competent and Qualified Persons
EM 385-1-1 requires as a minimum, designate Competent Persons and submit qualifications for each of the following major areas: mob and de-mob operations; fall protection; hazardous energy; confined space; health hazard recognition, evaluation and control of chemical, physical and biological agents; personal protective equipment and clothing to include selection, use and maintenance.
8.8 Safety
8.8.1 Reference
Conform to all safety standards of the most recent edition of the Corps Safety and Health Requirements
Manual EM-385-1-1 (Latest).
8.8.2 Activity Hazard Analysis
Prepare a Job Safety Analysis, also known as Activity Hazard Analysis (AHA), in accordance with EM-385-
1-1 and submit as part of the Accident Prevention Plan for approval by the COR prior to initiation of the work tasks.
8.8.3 Tools and Equipment
All tools and equipment shall have manufacturer's recommended safety protective devices to ensure worker safety at all times. Inspect tools and equipment daily by the Contractor and maintained in good working condition. Ensure all workers are properly trained to operate tools and equipment using safe practices.
8.8.4 Accident or Mishap Reports
a. All accidents involving property damage, fires, personal equipment, and all injuries to the public, regardless of degree, must be reported to the KO and on ENG Form 3394 and according to the schedule which follows:
b. Investigation and Reporting
1) Conduct a mishap investigation for recordable injuries and illnesses, for Medical Treatment, property damage accidents resulting in at least $2,000 in damages, and near misses as defined in EM 385-1-1, to establish the root cause(s) of the accident. Complete the accident or mishap reports form, ENG Form 3394, and provide the report to the COR within two calendar days of the accident.
2) Conduct an accident investigation for any of the following High Visibility Mishap: Load
Handling Equipment and Rigging, Fall-from-Height. Make the initial report within four hours and provide a completed ENG Form 3394 to the COR within five calendar days of the accident.
Do not proceed with further operations until cause is determined, and corrective actions have been implemented to the satisfaction of the COR.
3) The COR must be notified by the most expeditious means available of all fatal and permanent total disability injuries, three or more persons hospitalized, all property damage of $500,000 or more, and structural damage involving a question of structural adequacy. All incidents involving disabling injury or an injury which may result in an employee's lost time, or property damage of $2,000 or more must be reported to the COR by telephone as soon as possible and in all cases within four hours.
4) In all accidents enumerated in sub-item (3), investigate the circumstances before the scene of the accident is changed, take corrective action, and within 48 hours forward to the COR four copies of ENG Form 3394.
5) In the event of an accident involving a fatality, permanent total disability, hospitalization of one or more persons, or property damage of $500,000 or more, the Contractor must promptly suspend all operations at the scene of the accident and notify the COR of the occurrence.
Immediately provide for the rescue and/or care of the injured. Restrict access to the area except in situations where safety may be compromised. Leave the scene undisturbed until investigated by a Government appointed board of investigation and until the Contractor is authorized to resume operations.
6) If property damage and injury result from the same accident, the consequence may be noted on the same ENG Form 3394. If more than one person is injured in a single accident, ENG
Form 3394 must be submitted for each person injured.
c. Types of Accidents and Reports. For each accident that results in a consequence or combination of the consequences listed below, a complete report on ENG Form 3394 must be furnished to the KO.
Please note that these reports cannot be used for any purpose other than accident reporting.
1) Disabling injury (including death) is an injury that renders a person unable to perform a regularly established job on the day following the injury or on any subsequent day. Known suicide or deaths from natural causes are not reportable.
2) Damage of $2,000 or more to the Contractor's property or equipment, including motor vehicles and fire and/or damage to other property caused by the Contractor while executing the Task
Order.
3) Accidents occasioned by flood, hurricane, tornado, fire, navigation, wind, ice, etc., and structural failure in excess of $2,000.
8.9 Environmental Protection
8.9.1 Erosion Control
Do not allow soil erosion or sediments caused by work activities to leave the site. Employ erosion control measures in accordance with state and local laws and regulations and as identified in the approved
Environmental Protection Plan.
8.9.2 Equipment and other Materials
Clean all construction equipment prior to bringing it onto the project site. Ensure the equipment is free from soil residuals, egg deposits from plant pests, noxious weeds, and plant seeds. Upon completion of work, remove from the site all equipment, unused materials, and any waste materials and rubbish resulting from the operation performed herein.
8.9.3 Environmental Protection Plan (EPP)
Comply with Government approved EPP in accordance with paragraph 8.5.3.
8.9.4 Protection of Historical, Archaeological, and Cultural Resources
The Contractor shall take necessary precautions to protect and preserve all cultural resources and historic properties within the work areas as specified in Base Contract. This Task Order does not include environmentally sensitive exclusion areas.
8.10 Project Security
8.10.1 Green Peter Site Access
a. South Bank Road is open to the public. Full and partial closures of the road will be coordinated through COR at least 7 days in advance.
b. The Green Peter Dam Site is not open to the public. The access gate is closed and requires key access.
Coordinate with the COR to obtain access to site. Ensure any gate is locked when not onsite.
Reference Attachment B Work Area for location of access gate.
c. Arrangement and scheduling of working hours and crews is limited to one shift, weekday operations and must be coordinated through the COR. Working hours that extend past 5:00 p.m. weekdays or on weekends and holidays must be coordinated ahead of time through the COR. Submit the intended working hours of staff on site and identify any employees working in any capacity.
d. Security of the Contractor's property and items furnished under this Task Order are the Contractor's responsibility.
8.10.2 Access and General Protection/Security Policy and Procedures
All Contractor and all associated Subcontractor employees must comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by
Government Representative*). Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by
DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this Task Order, should the Force Protection Condition (FPCON) at any installation or facility change, the
Government may require changes in Contractor security matters or processes. Unless otherwise stated, costs associated with the following execution of training, vetting, and verification requirements must be at the expense of the Contractor.
8.10.3 Pre-screen candidates using E-Verify Program
The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the
Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial Task Order award." *When Contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility
Verification, with the designated Government representative. This Form will be provided to the
Contracting Officer and shall become part of the official Task Order file.
8.10.4 Non-US Citizens
Submit photocopies of the green card work permits and/or passports to the KO of all Contractor employees who are foreign born and have non-citizen status. Submit photocopies at least one month in advance of the start of work by the employees. This allows the USACE District Security Office sufficient time to run a security check on these affected personnel. Contractor personnel who fit the above description of non-citizenship shall not be permitted to work until they pass the security check in addition to other requirements of this Task Order.
8.11 Invoicing
Payment will be made for completed and accepted work. Provide invoicing that includes signed invoice, all related trip tickets, waste manifests, daily logs and summary sheets. Coordinate with COR prior to submission of invoice. Submit PDF invoice via email to the COR.
8.12 Unacceptable Performance
If any of the services do not conform to Task Order requirements, the Government may require the Contractor to perform the services again in conformity with Task Order requirements, at no increase in Task Order amount.
8.13 Damages Caused by the Contractor
Contractor shall be held accountable and liable to the Government for any damages to Government facilities, fixtures, furnishings, property, equipment, plantings (except those impacted by the intended work), or grounds (including roads) caused by the Contractors or their employees.
8.14 Interference with Government Operations
The Government may undertake or award other Task Orders for additional work during the performance of work. Do not commit or permit any act which interfere with the performance of work by any other Contractor or by Government employees.
9 CONTRACT ADMINISTRATION
9.1 Post Award Orientation
A Post Award Orientation will be coordinated between COR and Contractor within 30 calendar days after
Task Order Award to discuss prework submittals, personnel, scheduling, and review Task Order requirements.
9.2 Contract Changes
Changes in scope, time, or deliverables can only be authorized by the Contracting Officer. Contractor shall notify the Contracting Officer immediately if they have received direction to perform work outside the scope of the Task Order. Changes in scope will be negotiated and a written modification issued, before proceeding with the work.
9.3 Government Holidays
The Contractor is not required to perform services on the following recognized Federal holidays: New Year’s
Day, Birthday of Martin Luther King, Jr., Washington’s Birthday, Memorial Day, Juneteenth, Independence
Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, and Christmas Day.
9.4 Veterans Employment Emphasis for U.S. Army Corps of Engineers Contracts
In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR
Clause 52.222-35, FAR Clause 52.222-37, DFARS 222.13 and Department of Labor regulations, U.S. Army
Corps of Engineers (USACE) Contractors and Subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE Task Order. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant Task Order, USACE Contractors are encouraged to seek out highly qualified veterans to perform services under this Task
Order. The following resources are available to assist USACE Contractors in their outreach efforts:
Federal Veteran employment information at http://www.fedshirevets.gov/index.aspx
Department of Labor Veterans Employment Assistance at http://www.dol.gov/vets/
Department of Veterans Affairs-VOW to Hire Heroes Act at http://benefits.va.gov/vow
Army Recovery Care Program at http://wct.army.mil/modules/employers/index.html
U.S. Chamber of Commerce Foundation – Hiring Our Heroes at http://www.hiringourheroes.org/
Guide to Hiring Veterans – https://www.dol.gov/veterans/hireaveteran/pdf/Employer-Guide-to-Hire-
Veterans-June-2019.pdf http://www.fedshirevets.gov/index.aspx http://www.dol.gov/vets/ http://benefits.va.gov/vow http://wct.army.mil/modules/employers/index.html http://www.hiringourheroes.org/
Green Peter Dam
ATTACHMENT A SITE LOCATION
A-1
A-2
A-3
ATTACHMENT B WORK AREA
B-1
Legend
Zone #1 – Approx. 0.25 acres
Zone #2 – Approx. 0.20 acres
Contractor Laydown Area
Log Stockpile Area
Access Gate
SPILL EMERGENCY - INITIAL REPORT FORM
1. Reporting Name: _____________________ Responsible Party: ____________________
2. Location of Spill (include County, Nearest Town, County, Township, Range, Rivermile)
3. Spill Description (time & date spilled, material involved, quantity)
4. Environmental Impacts: Air? Surface Water? Groundwater? Fish? Wildlife?
5. Reporting Tracking No. Date/Time POC
National Response Center: ______________________________________________
Oregon Emergency Response System: ______________________________________________
Washington Emergency Management: ______________________________________________
6. Incident Action Plan: Strategic Goals (what to do) and Tactical Objectives (who & how)
Strategic Goals Tactical Objectives
a. Perform Hazard Assessment ____________________________________________
b. Establish Site Security ____________________________________________
c. Establish Incident Command ____________________________________________
d. Evacuate Injured or Exposed ____________________________________________
e. Contain the Spill ____________________________________________
f. Control the Spill ____________________________________________
g. Initiate Cleanup ____________________________________________
SPILL RESPONSE FORM
C-1
Project (OD-V, etc.) or Outgrant
Pesticide Trade Name Active Ingredient(s) EPA Class EPA Reg. # Target Species Treatment Location Description
Outgrant? (Y/N) Estimated Acres Estimated Quntity (oz, gal, or lb)
Example Aquaneat Glyphosate 9 228-365 Water Primrose BONN WA Operations PMA No Spot treatment over
2.5 acres 0.5 Gal (64 ozs)
NWP Pesticide Use Annual Reporting
Anticipated Use, Section 1: General Info (Due 15 DEC before application) Anticipated Use, Section 2: Proposed Use (Due 15 DEC before application)
Actual Acres or Linear Miles/Feet Treated
Actual Quantity Used (oz, gal, lb) - ANNUAL
SUM TOTAL
Actual Location of Application
Actual Target Species Date and Time of Application
Application Method (Broadcast or Spot Spray)
State Applied (WA or
OR)
If WA, applied directly to Water or at/below OHWM? (Y/N) If answer is YES, complete Section 5
If OR, applied directly to water or within 3 feet of US water? (Y/N) If answer is yes, complete section 5
Spot treatment over
2.5 acres 0.25 gal (32 ozs) 8/11/2020, 1300 Poison Hemlock 8/11/2020, 1300 Spot Spray WA Yes N/A
*Note 1: Separate any aquatic application from the terrestial application of the same product. E.g. If you treated 100 acres with Aquaneat, but only treated 20 linear feet below OHWM, create 2 entries. One for the 100 acres, with column R/S marked NO (terrestrial), and one for the 20 linear feet with column R/S marked YES (Aquatic).
Section 3: Actual Use (Due 15 JAN after application)
**Note 2: If applications occurred in both states, enter a seperate line for each state
Name License # Employer Street Address Phone Number
First and Last WA- xxxxx or OR-xxxxx Agency/ Company Street, City, State with Area code
Section 4: Applicator's Info (Due 15 JAN after application)
Surveillance: method, date, findings
Explanation for need of pest control
Action Threshold met Mgmt measures implemented prior to pesticide
Identification of waters pesticide was discharged to
Quantity used (Application rate, dilutants, dilution)
Concentration (%) of active ingredient in formulation
The effective concentration of active ingredient required for control
Any unusual or unexpected effects identified to non-target organisms
Visual assessment conducted? Y/N-- If yes, during application or post application, and if no, explain why not
Assessment of environmental conditions relating to proper pesticide use
Visual, 8/1, presence of Water Primrose
State listed, objective to strategical manage the spread
Infestation that jeopardizes ecological objectives
Prevention Columbia River
0.25 gallon for Spot treatment, 0.75% solution with 2 quarts of nonionic surfactant
0.75% (Should not exceed percentage in next column)
0.75% No adverse effects detected Yes, post application No adverse effects detected
Section 5: Additional Record Keeping Requirement for in/near water applications (Only permissible with direct coordination with Project Natural Resource Manager)
HERBICIDE POST-APPLICATION REPORT
WILLAMETTE VALLEY VEGETATION MANAGEMENT MATOC
Base Contract No.: W9127N25___________
Task Order Contract No.: W9127N___________
1. Herbicide Application Location: (e.g. Zone 1 of Task Order specified Work Area)
2. Date of Application: (e.g. August 10, 2025)
3. Weather at Time of Application: (e.g. 75 deg F with light wind)
4. Herbicide Supplier: (Company Name and Address)
5. Name(s) of Herbicides Used: (Common Name and EPA No.)
6. Total Amount of Herbicide Concentrate: (Ounces of Herbicide in Gallons of Water)
7. Target Species: (List of Vegetation Species Identified in Task Order and Present Onsite)
8. Applicator Name and License No.: (Company Name, Company License No., and Individual Performing Application)
| A.01.30 PWS.pdf |
| Attachment A Site Location.pdf |
| Slide Number 1 |
| Slide Number 2 |
| Slide Number 3 |
| Attachment B Work Area.pdf |
| Slide 1 |
| Attachment C Spill Response Form.pdf |