W9127N25BA013_AMD3.pdf

PDF 718 KB Posted

Attached to
BON Navlock Upstream Stoplogs
Solicitation number
W9127N25BA013
Issued by

About this file

This is a U.S. Army Corps of Engineers solicitation for the Bonneville Navigation Lock Upstream Stoplogs project located in Cascade Locks, Oregon. The contract (W9127N25BA013) involves dredging the navigation lock site, fabricating and installing twelve concrete stoplogs, and placing excavated sediment in designated placement sites. The project will require specialized marine equipment including a 1200 horsepower twin-screw tugboat, a floating clamshell dredge, and bottom dump or split hull scows.

Key contract requirements include precise dredging to specific depths (34.6-40 feet NGVD29), high-resolution underwater imaging, pre- and post-dredge surveys, and careful material placement. The sediment is predominantly sand (72%) with some silt, gravel, and clay. Contractors must follow strict environmental and safety guidelines, including handling potential lamprey larvae and coordinating with marine traffic. The contract includes multiple contract line item numbers (CLINs) for mobilization, dredging, stoplog fabrication and installation, with payment based on cubic yard quantities and specific job tasks. Bid submissions are electronic-only, with a telephonic bid opening scheduled.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.

If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Bonneville Navigation Lock Upstream StoplogsBlock 5 (Project Number):

Section 00 21 13 - Instructions to Bidders

Miscellaneous text in this section has been deleted:

BID SUBMISSION INSTRUCTIONS

HARD COPY SUBMISSIONS WILL NOT BE CONSIDERED

Bids are due no later than the time and date specified in Block 13 of Standard Form 1442, or SF 30 if applicable. Bids received at the Government Point of Entry after the date and time in block 13.A. of the solicitation will be considered late and will not be considered for award.

Submit your bid package via email to Ian Lutjens, at ian.k.lutjens@usace.army.mil and Brandon Lasich at brandon.m.lasich@usace.army.mil Bidders should enter a description for every file submitted. For files over 20 megabytes (MB) the bidder shall break the file into smaller files sent via separate emails, each marked to identify which number the email is relative to the total number of emails submitted (i.e.

"one of four"). Once the emails submitted have been received, the Government will confirm receipt via return email. If a bidder submits multiple bids, the Government will only consider the last bid submitted prior to the bid due date and time. The electronic Bid shall be in Portable Document Format, filename extension: ".pdf" and suitable for viewing in Adobe Reader. Bidders shall bookmark and label each electronic PDF to afford easy identification from the Bid table of contents.

Do not assume submission will be instantaneous. File size and number of files submitted shall be considered. Bidder/Teammate/Subcontractors should allow adequate time for submission completion because the entire Bid package (bid, bid guarantee, and small business subcontracting plan if applicable) must be received by the time and date specified in Block 13 of Standard Form 1442, or SF 30 if applicable.

To avoid bid rejection, the bidder must make every effort to ensure its electronic submission is virus-free.

Bids, or portions thereof, submitted with the presence of a virus or which are otherwise unreadable will be treated as unreadable pursuant to FAR 14.406.

The requirement that an original and copy(ies) be submitted as found in block 13A of the SF1442 is satisfied through the electronic submission. Additionally, electronic submission of the bid guarantee, is due with the bid submission (mailing a bid guarantee is not allowed).

BID OPENING

No hard copy documents are allowed to be submitted at the bid opening. Due to the requirement that bids be submitted electronically only, the bid opening is scheduled for one hour following the bid due date and time to allow the Contracting Office time to download all bid documents.

The bid opening will be held telephonically at 3:00 pm Pacific Time on the date bids are due.

Bidders wishing to participate in the telephonic bid opening shall email a list of their participants to both Ian Lutjens, and Brandon Lasich 24 hours prior to the bid opening. In the email subject line use title, "W9127N25BA013 BON Navlock Stoplogs". The telephone number and security passcode for bidders to

W9127N25BA0130003

utilize will be provided to the bidder's initial email including the list of its participants. There will be no physical bid opening held at the Portland District, therefore, bidders are advised that they shall not plan to attend a bid opening in person on the day of bid opening.

SPECIAL CONTRACT REQUIREMENTS

FAR provision 52.229-11 and FAR clause 52.229-12

FAR provision 52.229-11 and FAR clause 52.229-12 are included in this solicitation. This provision and clause concern the imposition of a 2 percent Federal excise tax withholding on any resultant contract award or payment request. This rule applies to Federal Government contracts for goods or services that are awarded to foreign persons - such as foreign contractors. It implements the Department of the Treasury's final regulations published in the Federal Register at 81 FR 55133 on August 18, 2016, under section 5000C of the Internal Revenue Code relating to the 2 percent tax on payments made by the U.S.

Government to foreign persons pursuant to certain contracts.

Pursuant to the FAR 52.229-3 Federal, State, and Local Taxes, taxes imposed under 26 U.S.C. 5000 C may not be included in the contract price or reimbursed.

Exemptions from this excise tax must be claimed by an Offeror when it submits, with its offer, a U.S.

Department of Treasury Internal Revenue Service (IRS) Form W-14, Certificate of Foreign Contracting Party Receiving Federal Procurement Payments, available via the internet at www.irs.gov/W14. If not submitted with the offer, exemptions will not be applied to any resulting contract and the Government will withhold a full 2 percent on each contract payment. Failure to submit an IRS Form W-14 with each payment request will also result in an automatic withholding of 2 percent from the payment request.

When filling out the IRS Form W-14 the following information may be used to complete Part I, Lines 6 and 7.

Line 6 Contract/reference number: W9127N25BA013 Line 7 "Name and address of the acquiring agency": Portland District, 333 SW 1st Avenue, STE 10, Portland, OR, 97204

Any exemption claimed and self-certified is subject to audit by the IRS. Any disputes concerning this tax are adjudicated by the IRS because the Section 5000C tax is a tax matter not a contract issue.

Offerors are encouraged to seek guidance from their own tax professionals for advice concerning the provision, clause, and exclusions exclusion/submission of IRS Form W-14. Additional information is also available at:

Notwithstanding the above, the USACE does not have a means of withholding this excise tax at this time.

As a result, contractors are expected to comply with the instructions above and to properly complete and return the W-14 at proposal submission, and with each pay application. The amount due for each withholding will be confirmed by USACE, BUT WILL NOT BE WITHHELD. It is the contractor's responsibility to set aside, or remit to the IRS, the amount confirmed by USACE. Whether the contractor sets the money aside for future payment to the IRS, or makes payment to the IRS, is the contractor's discretion, based on its analysis of the regulations regarding the excise tax. In the event that USACE is able to withhold during contract performance, it will notify the contractor and make such a withholding (including any catch up withholdings); no advance notice is required to the contractor prior to the withholding. Under no circumstances is USACE liable for any tax not paid by the contractor. The contractor is liable for the tax, to the extent required by law, regardless of whether USACE makes a withholding.

FAR 29.204 expressly states that "[a]gencies merely withhold the tax (section 5000C tax) for the Internal Revenue Service (IRS). All substantive issues regarding the underlying section 5000C tax, e.g., the imposition of, and exemption from the tax, are matters under the jurisdiction of the IRS." Therefore, we cannot help you determine how the tax law applies to you. We strongly recommend that you contact the IRS and/or a tax professional should you have any questions of this nature. To be clear, this information does not constitute tax advice or a representation of your tax liability. Furnishing this information does not create liability for the USACE for any Federal, state, or local taxes applicable to the above-referenced contract or any other contract.

For submission requirements and basis of evaluation:

Executed FAR Provision 52.229-11.

Completed IRS Form W-14, Certificate of Foreign Contracting Party Receiving Federal Procurement Payments, if applicable. If not submitted with the offer, exemptions will not be applied to any resulting contract and the Government will withhold a full 2 percent on each payment.

In accordance with 52.102(c), the following provisions and clauses, available at www.

acquisition.gov, require your review and action:

52.204-8

52.219-1

52.219-28

52.222-5

52.223-3

52.229-11

52.236-13 Alt. I

252.204-7007

PROPOSAL INQUIRIES

All inquiries regarding this solicitation are to be submitted via ProjNet-Bid at https://www.projnet.org Telephone and email inquiries will not be accepted. ProjNet-Bid is a web-based program that /projnet/.

allows offerors to post questions regarding the solicitation, and to view all questions by other offerors, and answers by the U.S.

Army Corps of Engineers.

No response will be posted to inquiries after the Close of Business on the seventh business day preceding the solicitation due date. All offerors will be held to have reviewed the questions and responses in ProjNet -Bid prior to offer submission. Nothing in the solicitation is changed unless an amendment is issued via Contract Opportunities at SAM.gov.

The Bidder Inquiry Key for this solicitation is: 6DMMG3-GNTIPS

To access the ProjNet-Bid website the first time:

1) Register.

2) Click Quick Add Key. (The Agency is USACE.)

3) Enter the following information for access: The Bidder Inquiry Key for this solicitation & Valid business contact information

W9127N25BA0130003

https://www.projnet.org/projnet/.

https://www.projnet.org/projnet/.

Submit questions or review questions and answers. When an answer is posted to a question, the question and answer is then available for all other bidders to review.

For questions about the ProjNet-Bid, access the help tab on the ProjNet website.

Section 00 73 00 - Supplementary Conditions

Miscellaneous text in this section has been deleted:

CONTRACT ADMINISTRATION

SECTION DESCRIPTION

A. CONTRACT ADMINISTRATION

B. UNAUTHORIZED INSTRUCTIONS FROM GOVERNMENT OR

OTHER PERSONNEL

C. IDENTIFICATION OF EMPLOYEES

D. OTHER WORK

E. SUBMITTING PAY ESTIMATES AND PAYMENTS TO THE

CONTRACTOR

F. IMPLEMENTING EQUIPMENT GUARANTEES

G. SAFEGUARDING OF INFORMATION

H. PUBLIC RELEASE OF INFORMATION

I. CONTRACTOR PERFORMANCE EVALUATIONS

J. INSURANCE - WORK ON A GOVERNMENT INSTALLATION

A. CONTRACTADMINISTRATION

This contract will be administered by:

U.S. Army Corps of Engineers, Portland District Bonneville Resident Office Bonneville Dam Cascade Locks, OR 97014

(End of Requirement)

B. UNAUTHORIZED INSTRUCTIONS FROM GOVERNMENT OR OTHER PERSONNEL

The Contractor shall not accept instruction issued by any person employed by the U.S. Government or otherwise, other than the Contracting Officer or the authorized representative of the Contracting Officer acting within the limits of his authority. Only a warranted Contracting Officer (either a Procuring

Contracting Officer (PCO) or an Administrative Contracting Officer (ACO)), acting within their appointed limits, has the authority to issue modifications or otherwise change the terms and conditions of a contract. If an individual other than the Contracting Officer attempts to make changes to the terms and conditions of this contract, you shall not proceed with the change and shall immediately notify the Contracting Officer. Proceeding with any work not authorized by the Contracting Officer will be at the Contractor's own risk.

(End of Requirement)

C. IDENTIFICATION OF EMPLOYEES

The Contractor is responsible for furnishing to each employee engaged on the work to display such identification as may be approved and directed by the Contracting Officer. All prescribed identification shall immediately be delivered to the Contracting Officer for cancellation upon the release of any employee. When required by the Contracting Officer, the Contractor shall obtain and submit fingerprints of all persons employed or to be employed on the project.

(End of Requirement)

D. OTHER WORK

The Contractor shall fully cooperate with other Contractors, utility companies, and Government employees engaged in other work on and/or adjacent to the work to be performed under this contract. The Contractor shall coordinate the work herein and the use of haul roads, aggregate sources, and utilities that become a joint responsibility. Any damage resulting from the use of facilities of other Contractors shall immediately be repaired to the satisfaction of, or as directed by the Contracting Officer.

(End of Requirement)

E. SUBMITTING PAY ESTIMATES AND PAYMENTS TO THE CONTRACTOR

The Contractor shall use the Resident Management System- Contractor Module (RMS-CM) to prepare Engineer Form 93 (ENG 93), Payment Estimate - Contract Performance, as request for payment. The Contracting Officer's Representative or Administrative Contracting Officer is responsible for ensuring acceptance and approval for payment. The Contractor must submit the certification at FAR Clause 52.232- 5, paragraph (c) along with each request for progress payments.

(End of Requirement)

F. IMPLEMENTING EQUIPMENT GUARANTEES

When the completed facility or part of a facility is accepted by the Contracting Officer, and the work includes equipment covered by a guarantee which exceeds the warranty of construction period as specified, the Contractor shall furnish the following information to the Contracting Officer:

a. A list of all items with make and model numbers.

b. A copy of manufacturer's or vendor's guarantee documents which extend beyond the warranty of construction period.

c. The date during which the Contractor's guarantee is in effect under the properly identified individual section and paragraph of the Technical Provisions each item of equipment on the list, indicating for each item the date of acceptance for the beginning of the guarantee period, either for beneficial use or final acceptance, whichever is earlier, and the expiration date of the guarantee period.

d. Name of an authorized representative of the Prime Contractor with complete address and telephone number, and the names, addresses, and telephone numbers of all subcontractors and/or equipment suppliers or manufacturers specifically designated in writing by the Prime Contractor for direct contact by the United States Army Corps of Engineers for implementing the guarantee after transfer of the equipment.

(End of Requirement)

G. SAFEGUARDING OF INFORMATION

The personnel employed on this contract may, in the performance of their assigned duties, have access to data and information pertaining to location of goods, supplies, parts, equipment, and vehicles.

Knowledge of this nature is considered restricted security information. This information shall be protected and safeguarded against disclosure to any unauthorized person or party and shall be furnished or used on an official "need to know" basis only. Safeguarding of information is extended to dependents and guests of employees who may, in any manner, obtain any of the above-specified knowledge.

(End of Requirement)

H. PUBLIC RELEASE OF INFORMATION

The contractor shall coordinate with the Portland District of the U.S. Army Corps of Engineers for release of information to the public concerning this contract or any program related to this contract. This clause covers Media Relations and Printed Materials.

1. Media Relations

The contractor is permitted to speak to news media representatives in accordance with their firm's public relations policies and in conjunction with applicable U.S. government or Army Corps of Engineers' guidelines on release of information related to the specific program for which the contract was awarded. The contractor is required to inform the Portland District of significant media contacts. The contractor is encouraged to coordinate directly with Portland District's Public Affairs Officer, as necessary, when the media call is being responded to; however, this shall not preclude the contractor from responding to media requests in a timely manner. The contractor shall respond to inquiries that directly fall within their domain; and shall not speak for the Army or the Corps.

2. Printed Materials

a. The contractor shall not release to anyone outside the contractor's organization any unclassified information, regardless of medium, pertaining to this contract, unless:

i. The Portland District has given written approval, either by the Public Affairs Officer or by the Contracting Officer;

ii. Or the information is otherwise in the public domain before the date of release.

b. The contractor shall obtain approval from the Portland District prior to the dissemination of any briefings or speeches, news releases, articles, fact sheets, advertisements, or any other informational materials intended for public release that are the result of work performed or to be performed under this contract. This review is intended to ensure that public release of material does not violate government policy.

c. Requests for approval shall identify the specific information to be released, the medium to be used, and the purpose for release. This material shall be submitted to the Public Affairs Officer and to the Contracting Officer at the Portland District. The contractor shall strive to provide five working days for such approvals. Materials to be released within a shorter period of time will require special handling procedures, and the contractor shall request special consideration directly to the Public Affairs Officer or to the Contracting Officer.

d. The Contractor agrees to include a similar requirement in each subcontract under this contract.

Subcontractors shall submit requests for authorization to release through the prime contractor to the government (the Public Affairs Officer and the Contracting Officer), assuring the government that the prime contractor is knowledgeable of the action and concurs.

Nothing in the foregoing section on public release of information shall affect compliance with the clause of the contract entitled, "Security Requirements."

(End of Requirement)

I. CONTRACTOR PERFORMANCE EVALUATIONS

In accordance with Engineering Regulation 415-1-17, Construction Contractor Performance Evaluations, dated 24 January 2012, it is USACE policy that the Procuring Contracting Officer (PCO), or designated representative of the construction office responsible for monitoring contractor performance, will evaluate construction contractor's performance and prepare a performance evaluation report in the Contractor Performance Assessment Reporting System (CPARS). The Contractor shall be briefed of the CPARS process at the time of the Preconstruction Conference.

(End of Requirement)

J. INSURANCE - WORK ON A GOVERNMENT INSTALLATION

a. The Contractor shall, at its own expense, provide and maintain during the entire performance period of this contract, at least the kinds and minimum amounts of insurance required by this Clause as follows:

TYPE

AMOUNT

1) Workman's Compensation and Employer's Liability (including Federal Longshoremen. and Harbor Worker's Insurance) As legally required by the State wherein the work is being performed.

2) Comprehensive General Liability Insurance Personal Injury Liability:

$1 million per person

$1 million per occurrence

Property Damage (may be included in general aggregate limits or combined single unit coverage): $1 million per occurrence

3) Automobile Liability Personal Injury Liability:

$1 million per person

$1 million per occurrence

Property Damage (may be included in general aggregate limits or combined single unit coverage): $1 million per occurrence

4) If single general aggregate limits or combined single unit coverage is obtained for General Liability and/or Automobile Liability coverage, minimum amounts shall be the sum of the personal injury and property damage coverage required above. Umbrella Form Excess Liability insurance coverage shall be added to general liability and automobile liability coverage to determine if minimum insurance limits are met.

b. Before commencing work under this contract, the Contractor shall certify to the Contracting Officer in writing that the required insurance has been obtained. The policies evidencing required insurance shall contain an endorsement to the effect that any cancellation or any material change adversely affecting the Government's interest shall not be effective

(1) for such period as the laws of the State(s) in which this contract is to be performed prescribe, or (2) until 30 days after the insurer or the Contractor gives written notice to the Contracting Officer, whichever period is longer.

c. The Contractor shall insert the substance of this clause, including this paragraph (c), in subcontracts under this contract that require work on a Government installation and shall require subcontractors to provide and maintain the insurance required in the Schedule or elsewhere in the contract. The Contractor shall maintain a copy of all subcontractors' proofs of required insurance and shall make copies available to the Contracting Officer upon request.

d. "Government Installation" for this clause includes government vessels.

(End of Requirement)

CONFLICTING WAGE RATES

The Contractor will be responsible for complying with the applicable wage decision, tax laws, and any unique laws and regulations of the state in which work is being performed. Wage determinations for both Oregon and Washington are incorporated into this contract. Some work under this contract may require members of the contractor's work force to perform work in both states. The contractor shall segregate the work performed in each state and under each wage determination on its payrolls. In the event that it is impracticable to segregate an employee's work, or in the event of a conflict as to the place of performance of that work, the wage classification (and rate) resulting in the highest rate of pay /fringe benefits to that employee will apply.

Bonneville Navlock One Upstream Stoplogs

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00.00 25

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 GENERAL INFORMATION

1.4 UNIT PRICE PAYMENT ITEMS

1.5 JOB PAYMENT ITEMS

1.6 MEASUREMENT AND PAYMENT

1.6.1 Fabrication of Concrete Stoplogs, CLIN 0001

1.6.2 Delivery of Concrete Stoplogs, CLIN 0002

1.6.3 Mobilization and Demobilization for Dredging, CLIN 0003

1.6.4 Dredging and Placement of Materials, Bonneville Dam Navlock 1, Pre/Post, CLIN 0004

1.6.5 Mobilization and Demobilization for Stoplog Installation, CLIN

1.6.6 Installation of Concrete Stoplogs, CLIN 0006

PART 2 PRODUCTS

PART 3 EXECUTION

3.1 SUBMISSION OF INVOICES FOR PAYMENT

3.2 ACCEPTANCE

3.2.1 Dredging - Navlock 1

3.3 HIGH RESOLUTION UNDERWATER IMAGING

3.4 MEASUREMENT - PRE/POST SURVEYS

3.4.1 Survey Timing

3.4.2 Pre/Post Dredge Surveys

3.4.3 Dredging Quantity Computations

-- End of Section Table of Contents --

AMD #0003 SECTION 01 22 00.00 25 Page 1

SECTION 01 22 00.00 25

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 REFERENCES

The publication listed below forms a part of this specification to the extent referenced. The publication is referred to in the text by basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM-1110-2-1003 (November 2013 Edition) Hydrographic Surveying

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Navlock 1 Dredging Acceptance Plan

1.3 GENERAL INFORMATION

In each instance, the Contract price for an item will constitute full compensation in accordance with FAR 252.236-7008, CONTRACT PRICES - BIDDING SCHEDULES as herein specified, as shown, or as otherwise approved. The Contract price and payment will also constitute full compensation for all work incidental to completion of the item, unless such work is otherwise specifically mentioned for separate payment under another line item. In the event any work is required by the specifications Sections or by the Drawings and not specifically mentioned in the Paragraphs MEASUREMENT AND PAYMENT, separate or direct payment will not be made and all costs thereof are incidental to the work and included in the Contract prices and payments for all Contract Line Item Numbers (CLIN) listed in the price schedule.

1.4 UNIT PRICE PAYMENT ITEMS

Payment items for the work of this Contract on which the Contract unit price payments will be made are listed in Section 00 10 00, PRICE SCHEDULE, and described below. The unit price and payment made for each item listed will constitute full compensation for furnishing all plant, labor, materials, and equipment; performing all associated Contractor quality control, environmental protection, commissioning, preparation of working as-built drawing redlines, O&M manuals, tests and reports, meeting safety requirements; and for performing all work required for each of the unit price items.

AMD #0003 SECTION 01 22 00.00 25 Page 2

1.5 JOB PAYMENT ITEMS

Payment items for the work of this Contract for which Contract job payments will be made are listed in Section 00 10 00, PRICE SCHEDULE, and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job item, must be included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed will constitute full compensation for furnishing all plant, labor, materials, and equipment; performing all associated Contractor quality control, environmental protection, commissioning, preparation of working as-built drawing redlines, O&M manuals, tests and reports, meeting safety requirements; and for performing all work required for which separate payment is not otherwise provided.

Provide a schedule of values for job items prior to the first pay request.

Update with each subsequent payment request.

MANDATORY ITEMS

1.6 MEASUREMENT AND PAYMENT

1.6.1 Fabrication of Concrete Stoplogs, CLIN 0001

a. Measurement: Measurement will be made as a job for all costs associated with fabrication of twelve concrete stoplogs.

b. Payment: Payment will be made at the Contract amount under CLIN 0001.

1.6.2 Delivery of Concrete Stoplogs, CLIN 0002

a. Measurement: Measurement will be made as a job for all costs associated with the delivery of twelve concrete stoplogs.

b. Payment: Payment will be made at the Contract amount under CLIN 0002.

1.6.3 Mobilization and Demobilization for Dredging, CLIN 0003

a. Measurement: Measurement will be made as a job for mobilizing and demobilizing all plant, equipment, fuel, supplies, materials, and personnel to and from the job site. Plant subject to pre-work safety inspection requirements will not be considered "mobilized" until such equipment is determined to be in compliance as determined by the floating plant inspection and verified during the joint equipment walk-through. This Contract Line Item Number (CLIN) applies to the Prime Contractor and all subcontractor mobilization and demobilization for the dredging scope.

b. Payment: Payment will be made at the Contract amount under CLIN 0003 as stated in FAR 252.236-7004, PAYMENT FOR MOBILIZATION AND DEMOBILIZATION (Dec 1991). Submit a schedule of mobilization and demobilization costs prior to submitting the first request for payment.

1.6.4 Dredging and Placement of Materials, Bonneville Dam Navlock 1, Pre/Post, CLIN 0004

a. Measurement and payment for this bid item will be considered complete and full compensation for the effort and cost to excavate the entire dredging pay areas to not less than the required dredging depths in accordance with Section 35 20 23.00 82, DREDGING AND CHANNEL CLEARING, including water quality monitoring and placement of all dredged

AMD #0003 SECTION 01 22 00.00 25 Page 3 material within the Government furnished placement site(s), and will be paid at the Contract unit price (cubic yards of dredged material) for this item.

b. The Government will determine cubic yard quantities for payment by taking pre-dredge and post-dredge surveys utilizing electronic depth sounding and horizontal positioning equipment. See Paragraph MEASUREMENT - PRE/POST SURVEYS of this Section for measurement description.

1.6.5 Mobilization and Demobilization for Stoplog Installation, CLIN 0005

a. a. Measurement: Measurement will be made as a job for mobilizing and demobilizing all plant, equipment, fuel, supplies, materials, and personnel to and from the job site. This Contract Line Item Number (CLIN) applies to the Prime Contractor and all subcontractor mobilization and demobilization for the stoplog installation.

b. b. Payment: Payment will be made at the Contract amount under CLIN 0005 as stated in FAR 252.236-7004, PAYMENT FOR MOBILIZATION AND DEMOBILIZATION (Dec 1991). Submit a schedule of mobilization and demobilization costs prior to submitting the first request for payment.

1.6.6 Installation of Concrete Stoplogs, CLIN 0006

a. Measurement: Measurement will be made as a job for providing all labor, equipment, materials, parts, and incidentals for the installation of concrete stoplogs.

b. Payment: Payment will be made at the Contract amount under CLIN 0006.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

3.1 SUBMISSION OF INVOICES FOR PAYMENT

Submit invoices for payment as required in Section 00 73 00, Special Contract Clause INVOICE SUBMITTAL. Progress payments for work accomplished will be made monthly.

3.2 ACCEPTANCE

3.2.1 Dredging - Navlock 1

a. Acceptance of Navlock 1 dredging will be via Contractor diver directed or remote operated vehicle (ROV) video streaming as referenced in Section 01 35 27.00 82, DIVING (DREDGING).

b. Criteria for acceptance will be:

(1) STA 8+04 to STA 7+80 - Clearance to a maximum of 3 inches sediment atop the concrete sill.

(2) STA 8+33 to STA 8+04 and STA 7+80 to 7+36 - Clearance to a maximum of 6 inches sediment atop the concrete sill.

AMD #0003 SECTION 01 22 00.00 25 Page 4

(3) STA 8+33 to STA 7+36 - No debris greater than 3 inches present.

c. Submit a Navlock 1 Dredging Acceptance Plan for Government approval for diver directed or ROV video grid of the entire dredge area. The plan must include method of measurement (EXAMPLE: measuring tape, ruler) as the diver or ROV scans the area. Video will be required of the full dredge area. The plan must be accepted by the Government prior to beginning dredging work tasks.

d. Notify the Government 24 hours prior to each dive for acceptance.

Government personnel must be on site during the acceptance dive or ROV operation. Government acceptance will be completed on-site immediately following diving operation.

3.3 HIGH RESOLUTION UNDERWATER IMAGING

a. For the dredging of the Bonneville Navlock 1, Furnish all equipment, supplies, facilities, and experienced personnel to provide an underwater visualization of the work sites as specified in this Section.

b. Provide a high resolution underwater imaging system with real time imagery suitable for use in murky water.

c. Mount from a work platform or other suitable location in order to monitor work evolutions i.e. location of debris piles, relative location of equipment used for debris removal, and divers or in water objects.

d. The system and associated equipment must be capable of scanning the underwater work areas to create high resolution imagery.

e. The underwater imaging instrumentation and associated equipment used must be outlined in the Navlock 1 Dredging Acceptance Plan with a discussion on how the system will be used during on site work, and how it functions overall.

f. Imagery equipment must be in place and utilized during all active debris removal phases with personnel sufficiently knowledgeable to operate and adjust the system to achieve imagery suitable for the monitoring purposes.

g. All data must be available to the Government upon request.

3.4 MEASUREMENT - PRE/POST SURVEYS

3.4.1 Survey Timing

a. Request pre- and post- dredge Government hydrosurveys in accordance with this Section.

b. All requests for Government surveys must be made by submission of Attachment A6 Hydrographic Survey Request Form. The Request Form must be submitted a minimum of seven calendar days prior to the date on which the survey is required, or immediately upon receiving the layout drawing if the survey is needed in less than seven calendar days.

c. The Government will perform all surveys within five calendar days of the requested date. The complete layout or post dredge package (i.e.

electronic survey data, layout chart, quantity computations) will be

AMD #0003 SECTION 01 22 00.00 25 Page 5 available two calendar days thereafter.

d. All Contractor owned equipment including all attendant plant and anchor lines must be removed from the acceptance area prior to the initiation of a Government survey. If equipment remains in the acceptance area at the time of survey; the survey will be cancelled and the full daily rate for a Government survey crew of $5,800 will be charged.

e. In the event it becomes necessary to reschedule a request for survey, notify the Government at least one calendar day prior to the first day of the scheduled survey period. Failure to provide such notification will result in a charge of one-half the daily rate for a Government survey crew. If the survey party mobilizes to the site before the survey is cancelled, the full daily rate for a Government survey crew identified in Paragraph SURVEY TIMING (d) will be charged.

3.4.2 Pre/Post Dredge Surveys

a. In pre/post-dredge survey areas, the maximum pay depth is Elevation

34.6 Feet (NGVD29) from STA 8+33 to STA 8+04 and 40 Feet (NGVD29) from STA 8+04 to STA 7+36, as indicated on the Contract Drawings.

b. The following Government survey equipment (or comparable) will be used by the Government Survey Crew during the collection of survey data, and will be considered the standard for which data is obtained:

(1) Hydrographic:

(2) Positioning: Applanix POS MV WaveMaster

(3) Single-beam: ODOM CV100 Echosounder and three degree 200khz transducer

(4) Multi-beam Echosounder: Norbit iWMBS

(5) AML Sound Velocity Profiler

c. Accuracies will be in accordance with stated quality control values in

EM-1110-2-1003.

d. In addition to pre- and post-dredge surveys, the Government may conduct periodic progress surveys at all work locations. Government progress surveys will not impact Contractor's operations.

e. Survey control points can be found at https://usmart.sec.usace.army.mil/w/map?filters=%5B%5D&lat=45.64& lon=-121.94&zoom=14

f. Submit in writing a request for additional information from each Government survey, to include:

(1) Daily Report of Survey Operations

(2) Metadata

(3) Type of Survey

(4) Bar Check Calibration (when applicable)

AMD #0003 SECTION 01 22 00.00 25 Page 6

(5) Sound Velocity Profile Report (when applicable)

(6) Survey Tide File Log (when applicable)

(7) Lead Line Report (when applicable)

(8) Copy of Field Book

(9) Computation Report: The computation report will indicate the surveys used (identified by location and date) and the program and computation method used.

3.4.3 Dredging Quantity Computations

a. As prescribed in paragraph Pre/Post Dredge Survey of this Subpart, the Government will determine cubic yard quantities for payment and acceptance by utilizing electronic depth sounding and horizontal positioning equipment.

b. The dredging pay prism is defined by the intersection of the maximum pay depth and the pay slope, as shown by Attachment A5, Descriptive Sketch. Slopes are assumed to be vertical, regardless of whether it is found to be representative of the actual side slope conditions.

Material removed from outside of the maximum pay prism will not be considered for payment.

c. Cubic yard volumes will be computed using Hypack software with the Triangulated Irregular Network (TIN) surface, TIN to CHANNEL volume computation method. The channel template will be created using the Advanced Channel Design. Computed pay volumes will be the difference between the TIN to CHANNEL computation of the post-dredge survey and the TIN to CHANNEL computation of the pre-dredge survey. No adjustments will be made for infill material from any cause. See Section 35 20 23.00 82, DREDGING AND CHANNEL CLEARING, regarding non-payable material. For computation purposes soundings will be a median sort on a 5-foot by 5-foot matrix.

d. Furnish to the Government all originals of field notes, sounding plots, and electronic survey data described in Section 01 45 00.00 82, QUALITY CONTROL (DREDGING) for all Contractor surveys, along with all other records relating to the survey or to the layout of the work. The Government may consider Contractor surveys to the extent necessary to determine the amount of progress payments. Retain copies of all such material furnished to the Government.Contractor surveys and survey data may be utilized to the extent necessary to determine the amount of progress payments.

e. Notify the Government Quality Assurance Representative (GQAR) in advance of any Contractor surveys conducted and the GQAR will have the option of attending these surveys. Conduct all surveys in accordance with EM-1110-2-1003.

-- End of Section --

AMD #0003 SECTION 01 22 00.00 25 Page 7

SECTION TABLE OF CONTENTS

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

SECTION 35 20 23.00 82

DREDGING AND CHANNEL CLEARING

PART 1 GENERAL

1.1 GENERAL INFORMATION

1.2 REFERENCES

1.3 SUBMITTALS

1.4 COORDINATION WITH CHANNEL USERS

1.5 OBSTRUCTIONS

PART 2 PRODUCTS

2.1 CHARACTER OF MATERIALS

PART 3 EXECUTION

3.1 DREDGING

3.1.1 General

3.1.2 Breaking for Other Work

3.1.3 In-fill Areas

3.1.4 Excavation Depths

3.1.5 Equipment

3.1.6 Layout of Work

3.1.7 Pre-Installation Inspection

3.2 PLACEMENT OF EXCAVATED MATERIAL

3.2.1 General

3.2.2 Dispersal of Material

3.2.3 Placement Site Surveys

3.2.4 Additional Requirements

3.2.5 Miscellaneous Trash and Debris

-- End of Section Table of Contents --

AMD #0003 SECTION 35 20 23.00 82 Page 1

SECTION 35 20 23.00 82

DREDGING AND CHANNEL CLEARING

PART 1 GENERAL

1.1 GENERAL INFORMATION

This Section covers furnishing suitable floating plant and performing all work to prepare the site for stoplog installation as indicated and placement of the removed sediment within the material placement sites, as shown or specified. All equipment must meet all applicable U.S. Coast Guard regulations.

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

OREGON DEPARTMENT OF ENVIRONMENTAL QUALITY (ODEQ)

OAR 340-041-0205 Water Quality Standards Not to be Exceeded

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. The following must be submitted in accordance with this Section and Section

01 33 00, SUBMITTAL PROCEDURES.

SD-06 Test Reports

1.4 COORDINATION WITH CHANNEL USERS

Coordination with local channel users will be necessary throughout the job. Thoroughly research the local traffic conditions between the Bonneville Navigation Lock 1 work area and the material placement site and expect the operations will have delays due to marine traffic locking through. Additionally, local events are not anticipated in the work area but may occur in the region. Government directed standby will not be authorized for marine traffic delays caused by any such events. Commercial shipping traffic and vessel cargo offloading activities must have precedence over the Contractor's activities. Stop, move or adjust to accommodate commercial vessel operations.

1.5 OBSTRUCTIONS

Anchors, cables, and other Contractor equipment that may be hazardous to navigation must be adequately marked with lights, signs, and buoys as necessary to prevent accidental contact by vessels in the area. Do not obstruct navigational traffic by the deployment of anchor systems that may pose a threat to safe passage as determined by the onsite Government representative.

AMD #0003 SECTION 35 20 23.00 82 Page 2

PART 2 PRODUCTS

2.1 CHARACTER OF MATERIALS

Snags, logs, rocks, gravel, boulders, swifter wire, commercial fishing gear, discarded boat hardware, and miscellaneous debris may be encountered in the excavation area. Anticipated material types at the Bonneville Navigational Lock 1, based on November 2023 sampling, is composed predominately of sand (72.0 percent) with some silt (21.6 percent), trace gravel (2.2 percent), and trace clay (4.2 percent). Further information can be made available upon request.

PART 3 EXECUTION

3.1 DREDGING

3.1.1 General

a. This work is paid by the cubic yard; clear the stoplog site preparation area to the required dredging depth as shown in the cross section structural profile. Payment will be as described in Section

01 22 00.00 82, MEASUREMENT AND PAYMENT.

b. Excavate along the alignment and to the dimensions shown on the associated Contract drawing. Place all excavated material within the designated placement area. Clear the stoplog site preparation area to the cross section structural profile as required to facilitate the stoplog installation. Remove all sediment and debris from the project area, as shown on the associated layout drawings, by means of mechanical or hydraulic excavation, or combination of both.

c. No redistribution of material by dragging a beam (or other method) to achieve final grade will be allowed under this Contract.

d. Separate all debris such as, but not limited to logs, snags, rope, tires, and other man made debris from the excavated material. Separated debris will become the responsibility of the Contractor to dispose of in accordance with any applicable federal, state, and local regulations.

e. Maintain sufficient vertical and horizontal control of excavation equipment at all times during operation in order to avoid contact with the lock sill, side walls, and any other structure. The Government may require damages to the lock sill and walls to be repaired prior to installation of the stoplogs. These repairs will be at no additional expense to the Government.

f. Acceptance will be by Contractor diver directed or remote operated vehicle (ROV) video in accordance with Section 01 35 27.00 25, DIVING and Section 01 22 00.00 25, MEASUREMENT AND PAYMENT.

3.1.2 Breaking for Other Work

a. Breaking for other work is allowable under this solicitation provided that the work required by this Contract can still be completed within the allotted time. Any breaks in work must be submitted to the Government in writing at least two weeks prior to going off-Contract.

Include in the request, at a minimum, the following items:

(1) Proposed change to the schedule.

AMD #0003 SECTION 35 20 23.00 82 Page 3

(2) Repayment of GQAR expenses for standby on this Contract.

(3) Proposed method of acceptance and payment if the other work overlaps with the Federal work.

b. When going off-Contract for other work, the Government project signs will be taken down or adequately covered for the duration of off-Contract work.

3.1.3 In-fill Areas

In-fill at all project locations should be expected. Necessity of cleanup cuts in the navigation lock and around the stoplog slots in support of the stoplog installation should be expected.

3.1.4 Excavation Depths

The required dredging depth will be variable with the structural profile of the Navigation Lock as indicated on the cross section, located on the associated Contract drawings.

3.1.5 Equipment

a. Perform all work under this Contract using a tugboat, dredge and scow(s) in accordance with requirements outlined within this Subpart.

(1) Tugboat: The tug must be twin screw, with a minimum of 1200 horsepower, or of sufficient power to make headway in a max flood or ebb. In the event the fully loaded scow can't be controlled, a replacement boat or an assist boat will be required. The tug must have a good field of vision beyond the scow, when the scow is being pushed ahead. In the event the scow obstructs the vision of the tug operator, an experienced deckhand must be stationed as a lookout and that lookout must be in constant radio communication with the tug operator. In work areas that preclude use of a minimum 1200 horsepower, twin screw tug due to project depth, an alternate smaller tug may be utilized for scow handling within the project limits. The primary tug must be used for all loaded scow movements in areas where depth allows.

(2) Floating Clamshell Dredge: A floating clamshell dredge is required for all work areas within this Contract. Equipment must be of appropriate size and capacity to perform the work at all work areas with special consideration given to both the Oregon Coastal environment and shallow side channels adjacent to the Columbia River, and in accordance with Section 01 35 26.00 82, GOVERNMENTAL SAFETY REQUIREMENTS (DREDGING).

(3) Scows: All scows used to transport material must be either bottom dump or split hull and in good working condition to prevent any loss of material during loading and transporting of dredged material. Contractor personnel are not to be permitted on-board scows during transit to or from the material placement sites during the actual placement operation. The technique of "sandbagging" bottom dump seals is acceptable providing that all such sandbagging materials are of organic composition and are fully biodegradable. Equipment must be of appropriate size and capacity to perform the work at all work areas with special

AMD #0003 SECTION 35 20 23.00 82 Page 4 consideration given to both the Oregon Coastal environment and shallow side channels adjacent to the Columbia River, and in accordance with Section 01 35 26.00 82, GOVERNMENTAL SAFETY

REQUIREMENTS (DREDGING).

b. Failure to comply with the above conditions will be cause to require the replacement of such equipment with floating plant that can meet the requirements.

3.1.6 Layout of Work

A layout chart will be provided for the navigational lock site preparation area based on the schedule of work and the hydrosurvey requests. Depths at Bonneville Navigational Lock 1 are measured in NGVD29. The most current hydrosurvey information will be displayed on the layout charts. Other pertinent information to be included with each layout package will be coordinates for the material placement site, supplemental tide gauge information, horizontal control locations, and computed quantities.

Government hydrographic survey personnel may be available during their normal working hours to assist in locating control points and tidal gauges.

3.1.7 Pre-Installation Inspection

a. Conduct a pre-installation dive on the sill to ensure that the sill is sufficiently cleared and prepared to receive the stoplogs.

b. Provide 48 hours notice of inspection to allow the Government to observe the dive.

3.2 PLACEMENT OF EXCAVATED MATERIAL

3.2.1 General

Place all sediment removed from the Bonneville Navigational Lock 1 work areawithin the Government provided material placement area as shown in the associated Contract drawings.

3.2.2 Dispersal of Material

For all in-water material placement operations, place all sediments within the designated placement site in a manner to avoid mounding and uneven distribution of material that would otherwise prematurely reduce the usable capacity of the site unless specifically directed to do otherwise.

This is the start of the file's text. The full file is on GovTribe.