This is a Standard Form 1419 Abstract of Offers document for solicitation W9127N25B0005, showing bid details for the West Coast Hopper Maintenance Dredging 2025 project issued by the Portland District, Corps of Engineers. The solicitation was issued on 1/22/2025 with bids opening on 2/21/2025.
The document shows two offers, with Manson Construction Co. of Seattle, WA submitting a bid. The project includes mandatory CLINs for dredging work at multiple locations including Humboldt Bay (HUM), Lower Columbia River (LCR), and Mouth of Columbia River (MCR), with various placement requirements. The total government estimate for mandatory items is $24,463,400 and optional items is $8,695,000, for a total of $32,858,750. Major line items include mobilization/demobilization ($8.79M), dredging operations ranging from $4-5.10 per cubic yard depending on location, and various material placement options. The bid security requirement is 20% of the bid price, and all addenda were acknowledged by the bidder.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. SOLICITATION NO. 2. DATE ISSUED 3. DATE OPENED PAGE 1 OF 1
1/22/2025 2/21/2025
4. ISSUING OFFICE
DISTRICT ENGINEER CONTRACT SPECIALIST SIGNATURE CONTRACTING OFFICER SIGNATURE
PORTLAND DISTRICT, CORPS OF ENGINEERS
P.O. BOX 2946
PORTLAND, OR 97208-2946
5. PROJECT TITLE 8. GOVERNMENT ESTIMATE 9. OFFERS
(CHECK A, B, OR C AND COMPLETE NO.1 NO.2 NO.3
D, E, AND F.) A. OFFEROR A. OFFEROR A. OFFEROR
X A. HIRED LABOR
B. REASONABLE CONTRACT B. BID SECURITY
(WITHOUT PROFIT) 20% of bid price 20% of bid price 20% of bid price C. REASONABLE CONTRACT C. ADDENDA ACKNOWLEDGED C. ADDENDA ACKNOWLEDGED ADDENDA ACKNOWLEDGED
(INCLUDING PROFIT) YES YES
6. NUMBER OF ADDENDA ISSUED
7A.
ITEM D. E. UNIT F. ESTIMATED D. UNIT F. ESTIMATED D. UNIT F. ESTIMATED D. UNIT F. ESTIMATED
NO. QUANTITY UNIT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
MANDATORY CLINS
0001 Mobilization and Demobilization 1 JOB 8,790,000.00$ 8,790,000.00$ 8,250,000.00$ 8,250,000.00$ -$ -$ 0002 HUM, Bin Measure to Required Depth, HOODS Ocean Placement 600,000 CY 5.10$ 3,060,000.00$ 5.40$ 3,240,000.00$ -$ -$ 0004 LCR Maintenance, RM 3+00 to RM 25+00, Bin Measure, Flow Lane (FL) Placement 200,000 CY 4.70$ 940,000.00$ 4.70$ 940,000.00$ -$ -$ 0005 LCR Maintenance, RM 3+00 to RM 105+00, Pre/Post Dredge Survey, Flow Lane (FL) Placement 600,000 CY 4.80$ 2,880,000.00$ 5.00$ 3,000,000.00$ -$ -$ 0008 LCR Maintenance, RM 3+00 to RM 105+00, Bin Measure to Required Depth 200,000 CY 4.80$ 960,000.00$ 5.00$ 1,000,000.00$ -$ -$ 0009 LCR Increment Transit Miles for Material Placement Site (other than five miles one-way) - CY x Miles 1,500,000 CY 0.48$ 720,000.00$ 0.20$ 300,000.00$ -$ -$
0010 LCR Intra-Project Transit Miles 175 MILES 648.00$ 113,400.00$ 450.00$ 78,750.00$ -$ -$ 0013 MCR, Bin Measure, Shallow Water Site (SWS) or North Jetty Site (NJS) Placement 1,600,000 CY 4.00$ 6,400,000.00$ 4.50$ 7,200,000.00$ -$ -$ 0015 MCR, Bin Measure, Increment for Operations and Maintenance Deep Water Site (DWS) Placement 300,000 CY 2.00$ 600,000.00$ 2.50$ 750,000.00$ -$ -$
SUBTOTAL FOR MANDATORY LINE ITEMS 24,463,400.00$ 24,758,750.00$ -$ -$
OPTIONAL CLINS
0003 HUM, Bin Measure to Required Depth, HOODS Ocean Placement (OPTION) 300,000 CY 4.90$ 1,470,000.00$ 5.00$ 1,500,000.00$ -$ -$ 0006 LCR Maintenance, RM 3+00 to RM 105+00, Pre/Post Dredge Survey, (FL) Placement (OPTION) 250,000 CY 4.90$ 1,225,000.00$ 4.00$ 1,000,000.00$ -$ -$ 0007 LCR Maintenance, RM 3+00 to RM 105+00, Pre/Post Dredge Survey, (FL) Placement (OPTION) 250,000 CY 4.90$ 1,225,000.00$ 4.00$ 1,000,000.00$ -$ -$ 0011 COO, Mobilization and Demobilization (OPTION) 1 Job 360,000.00$ 360,000.00$ 350,000.00$ 350,000.00$ -$ -$ 0012 COO, Bin Measure to Required Depth, Site F Ocean Placement (OPTION) 400,000 CY 5.10$ 2,040,000.00$ 3.50$ 1,400,000.00$ -$ -$ 0014 MCR, Bin Measure, Shallow Water Site (SWS) or North Jetty Site (NJS) Placement (OPTION) 250,000 CY 4.00$ 1,000,000.00$ 4.40$ 1,100,000.00$ -$ -$ 0016 MCR, Bin Measure , Increment for Operations and Maintenance Deep Water Site (DWS) Placement (OPTION) 300,000 CY 2.00$ 600,000.00$ 2.50$ 750,000.00$ -$ -$ 0017 MCR, Bin Measure , Increment for Operations and Maintenance Deep Water Site (DWS) Placement (OPTION) 250,000 CY 2.00$ 500,000.00$ 2.50$ 625,000.00$ -$ -$ 0018 MCR, Bin Measure , Increment for Operations and Maintenance South Jetty Site (SJS) Placement (OPTION) 250,000 CY 1.10$ 275,000.00$ 1.50$ 375,000.00$ -$ -$
SUBTOTAL FOR OPTIONAL LINE ITEMS 8,695,000.00$ 8,100,000.00$ -$ -$
33,158,400.00$ 32,858,750.00$ -$ -$
NSN 7540-01-150-0981
West Coast Hopper Maintenance Dredging 2025
7B. DESCRIPTION OF OFFERED ITEM
TOTAL
ACCEPTANCE LIMITATION - DAYS
INFORMALITIES
Manson Construction Co.
5209 E Marginal Way S Seattle, WA 98134
B. BID SECURITY B. BID SECURITY
STANDARD FORM 1419 (10-3)
ABSTRACT OF OFFERS
W9127N25B0005
I CERTIFY THAT I HAVE OPENED, READ, AND RECORDED ON THIS ABSTRACT
ALL OFFERS RECEIVED IN RESPONSE TO THIS SOLICITATION.
| 2025-02-21T15:08:55-0800 | |
| LASICH.BRANDON.MATTHEW.1255369012 |
| 2025-02-21T15:15:33-0800 | |
| LUTJENS.IAN.KENNETH.1257945002 |
File details come from the government source that posted it. Updated .