Amendment 01 PWS _FINAL_179SEP2024.pdf
PDF 302 KB Posted
- Attached to
- Scaffolding Bonneville Dam (Phased)
- Solicitation number
- W9127N24Q0119
About this file
This document is a Performance Work Statement (PWS) for a federal contract opportunity to provide scaffolding services at Bonneville Lock and Dam in Multnomah County, Oregon.
The contractor shall install, maintain, and remove scaffolding in the draft tube of Unit 3, and potentially Units 8, 6, 5, 7, 2, and 9 in Powerhouse 1 to support inspection and repair of the Main Unit turbine nose cone and blade seals. The contract will be for a firm-fixed price commercial service with an approximate 161-day period of performance. The government will provide crane support, electrical power, and water. The contractor is responsible for all other equipment, materials, and labor. The contractor must comply with various safety and security requirements, including completing antiterrorism and site access training. The performance will be evaluated based on installation, maintenance, relocation, and removal of the scaffolding to meet the government's requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 7N24Q0119_Amend01_Final.pdf | ||
| RFQ_W9127N24Q0119_9SEP2024_route_Final.pdf | ||
| Site Visit Roster_W9127N24Q0119 SAMPLE.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Work Statement
Power House 1, Powerhouse 1 Scaffolding Unit 3, 8, 6, 5, 7, 2, 9
Scaffolding At Bonneville Lock and Dam
Multnomah County
Cascade Locks, Oregon
1.0 General Statement. The contractor shall provide all personnel, equipment, tools, materials, vehicles, supervision, and other items and services necessary to install, maintain, and relocate scaffolding in the draft tube of Unit 3 in Powerhouse 1, Bonneville Lock and Dam. Scaffolding will be utilized to conduct inspection and repair of the Main Unit turbine nose cone and blade seals. Service is 245/2 as defined in this Statement of Work at Bonneville Lock and Dam in Multnomah County, Oregon. The Contractor shall perform to the standards in the contract and comply with all local, state, and federal regulations during the services performed.
This Firm Fixed Price Commercial Service Contract is for a duration of approximately (161) calendar days of site performance. Scheduled phase outage of the identified Units is currently in place. As this is a federal building site, scaffolding installation will take place after training, site access, personnel processing and verification finishes. On average, this AT OPSEC processing takes approximately (2 - 4) weeks after award. The contractor will receive an “all clear” per Bonneville's technical POC indicating completion of all initial training/processing and that they are authorized to access the federal site.
2.0 DEFINITIONS. Throughout this statement of work these terms are defined as follows:
Acceptable Quality Level (AQL). Acceptable Quality Level equals the performance standards listed in
5.2 Description of Services. The Contractor must re-perform all unsatisfactory work unless excused by government inspection.
Contracting Officer (KO): The Government employee who is authorized to enter into, administer, and/or terminate contracts and make related determinations and findings.
Contracting Officer’s Representative (COR). The Government employee who has been authorized in writing as the Contracting Officer’s Representative, acting within the limits of their authority.
Contract Discrepancy Report (CDR). A written record of unsatisfactory performance by the Contractor as observed by government inspection.
Technical POC – Bonneville Technical Point of Contact. When a COR is left un-designated, the Technical POC will perform government inspection in coordination with the Contracting Officer.
3.0 Government Will Furnish
3.1 Water and electric power necessary for the performance of the work required under these specifications will be furnished by the Government without cost to the Contractor.
Telephone service will not be provided. Any service charges incurred by the Contractor shall be deducted from the monthly payment.
The Government will furnish crane support to include a crane operator, riggers/utilities, and rigging support to lower and remove scaffolding components into and out of South end Powerhouse 1 roll up door at EL 55 to South end of draft tube gallery staging area at elevation -26.
4.0 Contractor Shall Furnish
4.1 The Contractor shall furnish all supervision, labor, equipment, materials necessary to perform the work required under these specifications except for those items specifically identified as government provided. Equipment shall be industrial grade.
equipment list throughout the period of this contract shall be submitted to the COR/Technical g2odbmdh Highlight
4.2 All electrical equipment used by the Contractor or the Contractor’s employees shall meet all applicable safety requirements. This equipment shall operate at full rated performance levels using existing building circuits. It shall be the responsibility of the Contractor to prevent the operation, or attempted operation, of electrical equipment or combinations of equipment, which require powers exceeding the capacity of existing building circuits.
4.3 The Contractor shall insure that all employees demonstrate adequate knowledge of tools, equipment, and techniques necessary to competently perform the work.
Upon completion of this contract and prior to final payment being made, the Contractor and the Contractor’s employees shall breakdown all scaffolding within the timelines stated below, including vacate after the effective date of completion back to the original condition as existed when the contractor initially occupied the space.
5.0 Performance Standards and Guideline Requirements
5.1 The Contractor shall install, maintain, and remove scaffolding and components as established in Section 6. The Contractor shall provide sufficient supplies, materials, and equipment to adequately maintain the rental scaffolding, and must be certified by the Contractor. The Contractor is responsible for all work areas. The Contractor shall maintain these areas in accordance with these guidelines.
The following guidelines are for reference only and final results shall be the determining factor for the success or failure of this contract. Performance shall be based on the Contracting Officer’s or their designated representative’s evaluation of performance and quality results, not the frequency or method of performance.
5.2 Description of Services.
5.2.1 Installation of Scaffolding.
The contractor shall accomplish all tasks to meet the requirements of this PWS. Bonneville Lock and Dam will provide crane support consisting of a crane, crane operators, and riggers/utilities for movement of materials from South roll up door at EL 55 into the South end of Draft Tube Gallery staging area EL -26. The Contractor is responsible for the construction of an approximate 35-40 foot tall cylindrical stair tower with a landing at the Draft Tube door entrance within 1 foot of the bottom of door opening. Level 2 work platform at approximately elevation -12 or 5 feet bellow bottom of nose cone. Level 3 platform at approximately EL -2 or 2-3 feet bellow the bottom of the blades, work platform must go 360 degrees around turbine cone. Stairway from Level 1 to Level 3 is preferred over a vertical ladder if space allows.
See Drawing BDP-9-2-5_1_RE1 for further information. The Contractor will certify scaffolding complete, safe, capable of supporting government, and turnover for rental usage prior to Bonneville Project Personnel use. Document these steps for contracting purposes.
5.2.1.1 Maintenance of Scaffolding.
Any required safety modifications to the scaffolding will be mutually scheduled within 24 hours of a finding or request.
5.2.1.2 Removal of Scaffolding.
Bonneville Lock and Dam will provide crane support consisting of a crane, crane operators, and riggers/ utilities for removal of materials out of the South end of Draft Tube Gallery staging area. Disassembly must begin within the timelines identified below to remove scaffolding and scaffolding components.
Restoration along with scaffolding removal, as a result of the contractor’s work.
5.2.1.3 Timelines and CLIN specifics.
An approximate site timeline of work for the seven (7) phased units are covered by the CLINs
CLIN 0001 SETUP
Approximately 2 – 4 weeks after award to gain full site access for crew members. Government Notification clearing individuals will be made before proceeding to the site.
This contract intends two (2) initial unit setups in total under this CLIN and will occur in the draft tube gallery in Powerhouse 1, Bonneville Lock and Dam. After receiving site access, an initial unit setup must be complete within 10 business days for the first unit currently slated as Unit 3. The exact units currently scheduled may change to meet government needs. Approximately 60 days after Unit 3 completes initial setup, the government will notify the vendor to start scaffolding setup of the next initial Unit under this CLIN, currently slated as Unit 8. All other units after the initial first two units will be “Phase Relocation Units" (CLIN 0003), to be scaffolded using site scaffolding from the first two existing scaffolding units.
CLIN 0002 RENTAL PERIOD
Each unit is anticipated to have approximately a 35 day rental period averaged out. Due to the issues on the ground as the government works on the Powerhouse units, the dates per unit may adjust to accommodate the actual rental needs. An initial estimated 245 days of actual daily scaffolding rental are funded in this CLIN to cover all unit rental days. Over time, the total days may become more (if modified providing additional funding to cover additional days), or less days. A modification at the end of the contract will follow to reduce any excess days from the contract. The daily rate will be used to reduce and/or add days for this CLIN.
CLIN 0003 PHASE RELOCATE
The government will notify the contractor in writing/email at least 10 business days in advance of the end of a rental period at an existing scaffolded unit. This notification will end the current rental at that unit. The 10 business day notification will designate a new relocation of the scaffolding to the next scheduled unit. The contractor will have 24 hours to acknowledge and schedule takedown and relocation of scaffolding to the newly designated unit. Once relocation commences per schedule, the contractor will have up to 9 business days from notification to relocate the unit scaffolding to the new unit. Rental will begin the following day after contractor scaffolding setup/certify, with turnover to the government.
CLIN 0004 TAKEDOWN
The final two relocated units under rental will no longer have a phase relocation. The final step will be takedown (dismantle) and removal from the draft tube gallery, Powerhouse 1, Bonneville Lock and Dam.
This CLIN will cover the final takedown phase for those separate two remaining units as per contract, priced per unit and will be done at different times. At least 10 business days notification by the government to the contractor will be provided that the end of this final unit rental period. Rental will stop on the date in the notification. The vendor will have five business days to breakdown and remove the scaffolding starting on that end of rental date. The vendor will then have five additional workdays after scaffolding breakdown to clean up the site and vacate, turning in all badges and out processing per takedown unit.
6.0 Performance Requirements Summary.
The contractor service requirements are summarized into performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success.
It is intended to ensure that the Government receives the services for which it contracted. The Government will only pay for conforming services received. The Performance Requirement Summary (PRS) determines if the contractor meets the performance standards of the contract, as well as provides guidelines for how and when surveillance will be performed. It ensures timeliness, effectiveness, and that the contractor is delivering the results specified in the contract. Government contract quality assurance will be performed at such times and/or places as may be necessary to determine the services conform to contract requirements.
6.1.1 If the Contractor fails to perform at any time and the work is deemed critical by the COR, Government forces may be assigned to perform the work. If this occurs, the Contractor shall be required to reimburse the Government for the full costs of the work performed including labor, materials, transportation, and supervision.
6.1.2 Performance Requirements Summary
These are the criteria against which the performance will be evaluated. (Inspection and Acceptance Clause FAR 52.212-4 (a) for additional surveillance techniques)
Performance Objective
Performance Standard Validated Performance
Threshold
Method of Surveillance
Installation of Scaffolding, CLIN 0001
Install/Setup scaffolding. Certify safe, coordinate turnover to government
Scaffolding install, free of defects, certified. Timely setup
Inspection at complete.
Rental, Maintenance of Scaffolding
CLIN 0002
Rental period maintained to usable. Reply to safety/maintenance requests within 24 hours and schedule corrective action.
Assure rental integrity throughout. Rental will cease if unusable for rental until restored.
Less than 24 hours to acknowledge and schedule per 90 days due to maintenance, or lack of response.
Periodic Inspection 100% inspection at start/end of rental
Phase Relocation, CLIN 0003
Respond timely to relocation notice. Take all steps to relocate rental scaffolding to next unit within time allowances. Certify safe and ready for use and transfer to government to start rental period.
One untimely start or scheduled transfer of more than 24 hours per unit.
100% inspection at time of phase relocation and transfer
Removal of Scaffolding, CLIN 0004.
Begin removal of scaffolding at end of rental period. Contractor completes removal within schedule and completes restoration, timely.
One, up to 24 hour start delay and no more than one up to 24 hour end delay per unit.
100% inspection at time of phase relocation and transfer.
6.3.2.1 Surveillance. A Technical POC will provide quality assurance observations on behalf of the Contracting Officer. If the Technical POC discovers deficiencies and/or receives complaints, the Technical POC will notify the contractor of non-conformance.
6.3.2.2 Quality Control. The contractor remains responsible for quality control actions necessary to meet the quality standards set forth by the contract. The contractor may apply their standard commercial quality assurance practices to deliver satisfactory services for this contract. The Government reserves the right under the Contract Terms and Conditions— Commercial Items (FAR 52.212-4) to inspect and test the services called for by the contract. Payment is made for accepted conforming services. Non-conforming services shall be rejected.
6.3.2.3 Unacceptable Performance. When performance is determined unacceptable, as defined in the Performance Requirements Summary, the appointed Technical POC will inform the contractor’s on-site representative. If a Dispute arises refer the item to the contracting officer.
6.3.2.4 If any of the services do not conform to contract requirements, the government may require the Contractor to perform the services again in conformity with the contract requirements, at no increase in contract amount.
6.3.2.5 Correction of Non-Performance of Work.
The Contractor shall insure that any area found in non-conformance, shall be made acceptable by performance or re-performance of the work, where such re-performance is possible, during the first business day.
6.3.2.6 Standard. Recurring defects are not permitted for any of the above service items. For example, if the Technical POC discovers a defect in the installation of the scaffolding covered under the contract, the contractor is required to correct the defect through re-performance. However, if this same situation occurs
6.2. Reserved
6.3.2. Performance Requirements Summary (PRS)
again during the contract period, a defect will be recorded and reported to the Contracting Officer for appropriate action in accordance with FAR 52.212.4, Contract Terms and Conditions- Commercial Items (Dec 2022).
6.3.2.7 Contractor’s Supervision.
This is a non-personal services contract. The contractor shall supervise their own performance and crew. Supervision shall remain located in the work area and available at all times during assembly and disassembly, restoration. The contractor shall continually oversee the work at the time it is being performed, and shall have an individual available during performance to represent the Contractor in dealing with the Government.
6.4 Work Scheduling
6.4.1 Scaffolding work performed under this contract shall be coordinated by the Contractor with the Technical POC prior to commencement of work. The parties will agree on the timeline before start. Contractor rep will notify the Technical POC of the Contractor’s work schedule, indicate the location and time the required service is provided. This work must result in a minimum conflict between the contract work and other work in the area. Work Schedule shall indicate Contractor’s activity on the project at least five days in advance and shall be subject to adjustment upon notification by the Technical POC that a conflict with necessary project maintenance work has developed. Coordinate with the Technical POC of daily progress, any delays affecting the onsite progress
6.4.2 Hours of Operation.
6.5
6.6
6.7
6.8
6.9
6.10
The Technical POC will notify the Contractor of necessary schedule changes two business days in advance where possible. Scaffolding work will be performed by the Contractor Monday through Thursday, during the hours of 6:30 a.m. to 5:00 p.m. in the Draft Tube Gallery, Powerhouse 1, Bonneville Lock and Dam. In no event will scaffolding work commence at other than the stated times without coordination and acceptance by the Technical POC.
Verification of Work. If the Contractor performs outside the scheduled time, the Contractor must notify the Technical POC of completion so government inspection may occur timely. to secure any payment. Work performed at times other than posted on the schedule and not coordinated with the Technical POC shall be considered not completed. After the work schedule has been approved, a copy of it shall be posted in the various places that the Contractor shall be working. The Contractor shall initial this work schedule each day to show the specific items of work that were accomplished. Provide the Technical POC with daily updates for site work. When work concludes and is ready for government inspection, notify the government POC timely.
Damages Caused by the Contractor. The Contractor shall be held accountable and liable to the Government for any damages to government facilities, fixtures, furnishings, equipment, or grounds caused by the Contractor’s or their employees.
Interference with Government Operations. The Contractor and the Contractor’s employees shall perform all work in such a way as to not interfere with regularly scheduled Government operational activities.
Services During Repair Activities. It is expected that, during the period of this contract, occasional repairs may have to be made by maintenance personnel within the Draft Tube. All large debris generated by such activities will be removed by the Government personnel, who will also clean up the affected areas by sweeping and depositing such collected matter into wastebaskets or dumpsters. The Contractor will only be responsible for removing waste and debris generated by their own performance of the contract.
Lost and Found. The Contractor will instruct employees that all articles of possible personal or monetary value found by the Contractor’s employees must immediately be turned in to the Technical POC.
Other Contracts at the Contract Site. The Government may undertake or award other contracts for additional work and the Contractor shall fully cooperate with such other contractors and Government employees and carefully fit his own work to such additional work as may be directed by the Contracting Officer. The Contractor shall not commit or permit any act which shall interfere with the performance of work by any other contractor or by Government employees.
7.0 Safety and Environmental Regulations
7.1 General.
The Contractor shall comply with applicable Occupational Safety and Health Act (OSHA) standards as well as the Corps of Engineers Safety Requirements Manual, EM 385-1-1, dated November 2014 or most current edition. The OSHA standards are subject to change and such changes may affect the Contractor during performance under the contract. It is the Contractor’s responsibility to be aware of such changes.
7.1.1 Job Safety Analysis.
The Contractor shall, during their on-site tour of the Project, determine those areas and activities in which possible safety hazards exist. The Contractor shall identify hazards in each phase of services performed and what preventive measures the Contractor proposes to take to prevent accidents. The JSA must be typewritten with a cover page. The JSA will be due within 10 days of the date of the contract, at the pre- work meeting and will be updated as needed.
7.1.3 Public Safety.
The Contractor shall maintain the public use areas so as to provide the best possible conditions for safe use by visitors. The Contractor shall be responsible for providing adequate personnel or barricades to insure the safety of the general public and project personnel during operations.
Use of the Government owned first aid kits shall be reported immediately to the Technical POC for refilling by the Government.
7.1.4 Health and Safety Requirements and Recommendations.
All employees that work in the Draft Tube Gallery will be exposed to confined space work. Employees must have completed confined space training.
7.1.5 Emergency Communications.
Bonneville Lock and Dam has a code call system which we use to notify Project Personnel and Contracted Personnel in the event of an emergency. The Contractor will be notified of the codes, what they mean, and responses to different emergencies as directed.
7.2 (Reserved)
7.3 (Reserved)
7.4 Accidents.
7.4.1 General.
In the event that an accident or injury should occur to either Contractor personnel or the public on Government lands, the Contractor shall first notify, via the control room, the appropriate emergency agency, the appropriate local authorities, and then the Technical POC. ALL emergency notifications are processed through Bonneville Lock and Dam Control Room.
7.4.2 Accident Reports.
The Contractor shall make a written report of each separate case of an injury or accident. The report shall include, but not be limited to, location, nature of the injury of accident, authorities notified, and the action taken along with any other pertinent information. The report shall be accompanied by sketches, graphs, drawings, and photographs as needed and forwarded to the Technical POC within 24 hours.
7.4.3 Report of Unusual Conditions.
The Contractor shall report to the Technical POC any unusual conditions which are observed during the performance of this contract. This shall include such items as plumbing, electrical, or mechanical issues.
7.5 Security Requirements.
7.5.1 General security requirements and guidance:
The security requirements described below apply to all contract personnel (including employees of the prime Contractor (“Contractor”) and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (e.g., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as “RAMs”), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures --this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clause of this contract, should the FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.
7.5.2 Antiterrorism (AT) Level I training:
All contract personnel requiring routine access to Army installations, facilities, and controlled access areas, or requiring network access shall complete initial and annual refresher AT Level I awareness training.
Online AT Level I awareness training is available at https://jko.jten.mil/ (website subject to change).
7.5.3 Physical security and access control requirements:
All contract personnel requiring physical access to a federal installation or facility shall comply with the access control procedures of that location. Contract personnel requiring unescorted access to meet contract performance requirements on a DoD installation in the US shall be vetted by the installation/facility Provost Marshal/Directorate of Emergency Services/Security Office using the National Crime Information Center-Interstate Identification Index (commonly referred to as “NCIC- III”) and Terrorist Screening Database (commonly referred to as “TSDB”). Contract personnel shall comply with all personal identity verification requirements specified in installation/facility policies and procedures. Contract personnel who do not meet requirements for unescorted access to USACE facilities shall coordinate escorted access with the Government representative, as needed. Contract personnel who receive keys, access cards, or lock combinations that provide access to government-owned property shall comply with key and lock control procedures of the
RA.
7.5.4 Suspicious Activity Reporting training (e.g. iWATCH, CorpsWatch, or See Something, Say Something):
All contract personnel shall receive initial and annual refresher training from the RA representative on the local suspicious activity reporting program. This locally developed training provides contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity.
7.5.5 Escorting in classified and/or sensitive areas:
In accordance with applicable regulations, all contract personnel who do not possess the appropriate security clearance or access privileges will be escorted in areas where they may be exposed to classified information or operations, sensitive information or activities, or restricted areas.
7.5.6 Pre-screen candidates using E-Verify Program:
Contractors shall comply with the requirements set forth in FAR clause 52.222-54 Employment Eligibility Verification and FAR Subpart 22.18 in using the E-Verify Program at (https://www.e-verify.gov/) (website subject to change) to meet the contract employment eligibility requirements.
Contractors are encouraged to cooperate with Federal and State agencies responsible for enforcing labor requirements to include eligibility for employment under United States immigration laws in accordance with FAR 22.102-1(i). An initial list of verified/eligible candidates shall be provided to the COR no later than three business days after the initial contract award. When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, and submit it to the Contracting Officer to become part of the official contract file.
7.6 Identification of Contractor’s Employees
7.6.1 Contractor Uniform and Identification.
Each employee will maintain a clean and neat appearance. Dress will include either coveralls or long pants. Each employee must have valid identification to work on Bonneville Project.
7.6.2 Contractor Vehicle Identification.
In order to keep proper control of vehicles in the Project Area, all Contractors’ vehicles shall display suitable identification, as approved by the Technical POC. All contract employees will be issued a car tag by the project to hang on their rear view mirror identifying them as a contract employee.
7.7 Subcontracting
The Contractor shall notify the Technical POC in writing, of any work to be subcontracted.
Compliance with the provisions of this contract by subcontractors shall be the responsibility of the Contractor.
7.8 There is a NO SMOKING policy in all government buildings.
http://www.e-verify.gov/) http://www.e-verify.gov/)
7.9 Locations.
The Contractor will be performing work in the Main Unit Draft Tube galleries, Powerhouse 1, Bonneville Lock and Dam, covering a total of seven (7) units. Note: The seven (7) units requiring scaffolding are identically sized. The general size and configuration for scaffolding requirements for each unit are approximately identical. A Site Visit is provided to view and properly assess the site condition.
7.10 Parking:
The Contractor employees will be allowed to park in the Powerhouse 1, South Downstream parking lot at EL 55 while performing work associated with this contract. See MAP below.
| PWS DRAFT_3SEP2024_BonnevillePhased_ScaffoldingW_ATOPSEC_Edits.pdf |
| Scaffolding At Bonneville Lock and Dam Multnomah County, Oregon |
| 3.0 Government Will Furnish |
| 4.0 Contractor Shall Furnish |
| 5.0 Performance Standards and Guideline Requirements |
| 5.2 Description of Services. |
| 5.2.1.1 Maintenance of Scaffolding. |
| 5.2.1.2 Removal of Scaffolding. |
| 6.0 Performance Requirements Summary. |
| 6.1.2 Performance Requirements Summary |
| 6.3.2.5 Correction of Non-Performance of Work. |
| 6.3.7 Contractor’s Supervision. |
| 6.4 Work Scheduling |
| 6.4.2 Hours of Operation. |
| 7.0 Safety and Environmental Regulations |
| 7.1.1 Job Safety Analysis. |
| 7.1.3 Public Safety. |
| 7.1.4 Health and Safety Requirements and Recommendations. |
| 7.1.5 Emergency Communications. |
| 7.4.2 Accident Reports. |
| 7.4.3 Report of Unusual Conditions. |
| 7.5 Security Requirements. |
| 7.5.2 Antiterrorism (AT) Level I training: |
| 7.5.3 Physical security and access control requirements: |
| 7.5.4 Suspicious Activity Reporting training (e.g. iWATCH, CorpsWatch, or See Something, Say Something): |
| 7.5.5 Escorting in classified and/or sensitive areas: |
| 7.5.6 Pre-screen candidates using E-Verify Program: |
| 7.6 Identification of Contractor’s Employees |
| 7.6.2 Contractor Vehicle Identification. |
| 7.7 Subcontracting |
| 7.9 Locations. |
| 7.10 Parking: |