W9127N23B0003 Amendment 1 Summary of Changes.pdf
PDF 119 KB Posted
- Attached to
- West Coast Hopper Maintenance Dredging 2023
- Solicitation number
- W9127N23B0003
About this file
This document provides an amendment to the solicitation for the West Coast Hopper Maintenance Dredging 2023 project. Key details include:
The scope of work involves hopper dredging at multiple locations on the West Coast of the United States, including Humboldt Bay, CA, the Mouth of the Columbia River in OR/WA, the Lower Columbia River in OR/WA, San Clemente, CA, and Encinitas and Solana Beaches, CA. The amendment revises plans and specifications, updates restrictions and timelines for beach operations, and provides clarification on pre- and post-dredge surveys to be conducted by the Government. Bidders must furnish supervision, labor, materials and equipment to perform dredging and beach placement in accordance with contract requirements. The bid opening is March 30, 2023 at 1:00PM Pacific Time. The USACE-NWP Contracting Office is the sole point of contact for questions.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W9127N23B0003 AMENDMENT 01 - SUMMARY OF CHANGES
Table of Contents –
A29 CONTENTS DELETED AND INTENTIONALLY LEFT BLANK
A31 San Clemente Boring Logs and Geotech Data
A32 CONTENTS DELETED AND INTENTIONALLY LEFT BLANK
A33 CONTENTS DELETED AND INTENTIONALLY LEFT BLANK
A35 CONTENTS DELETED AND INTENTIONALLY LEFT BLANK
A36 CONTENTS DELETED AND INTENTIONALLY LEFT BLANK
01 11 00.42 – 3.2 BORROW AREA GOVERNMENT SURVEYS -Added as new Subpart
3.2.1 Pre-Dredge and Post-Dredge Surveys
a. Notify the Contracting Officer not less than 15 calendar days prior to the scheduled commencement of dredging. The Government will perform a pre-dredge survey. The Government pre-dredge survey will be performed as close to commencement of dredging as possible. For the post-dredge survey, notify the Contracting Officer not less than 10 days prior to completion of the entire work. The Government will perform the post-dredge survey as soon as possible after completion of the entire work, generally within 10 days.
b. If the Government is unable to perform the post-dredge survey(s) due to the failure of the Contractor to complete the work in accordance with the prior notification, the Contracting Officer will charge the cost of the survey plant and standby labor, at $5,000.00 per day, to the Contractor.
Preliminary data from the final Government survey will be available within 10 days.
3.2.2 Method of Soundings
The Government intends to perform pre-dredge and post-dredge surveys utilizing multi-beam swath methods. However, the Government reserves the right to take soundings by any methods including: lead line, trigonometric leveling (total station)/differential leveling, 200 kHz single-beam acoustic methods, acoustic multi-beam swath methods. The Contractor has the option of being present when such soundings are made.
01 22 00.00 82 - 3.1.10, 3.1.11, 3.1.12, 3.1.13, 3.1.14, and 3.1.15 – Subpart title number 3.1.9 was unintentionally skipped. Title numbering corrected to advance the aforementioned Subparts by one.
01 22 00.00 82 - 3.1.13 a.
a. Measurement and payment will be made for costs associated with mobilization and demobilization for San Clemente Shoreline dredging and beach placement operations, as defined in SUPPLEMENTARY CONDITION 252.236-7004 PAYMENT FOR MOBILIZATION AND DEMOBILIZATION. For bidding purposes, this item is considered separate from CLIN 0001 Mobilization and Demobilization; and pricing should be based on the transportation to and from the job site only for the portion of transport where it is necessary to deviate from the mobilization and demobilization paid for under CLIN 0001. Additionally, the Government will only award this CLIN following the award of CLIN 0016 for mobilization and demobilization for San Diego County dredging. Therefore, this CLIN should be treated as an inter-beach mobilization and demobilization only and priced accordingly. Work includes, but is not limited to, transporting the marine plant and all items of attendant equipment to the work site, installation of temporary facilities including the staging and storage area, beach work area, protection of existing facilities, repair to any facilities damaged, dredge access, preparation of all submittals and Project Record Documents, including as-built drawings and obtaining and complying with all permits (local, state and federal). Upon completion of all phases of the work, remove the plant and equipment from the site, complete in place and accepted.
35 24 13.11 – 1.7 a.
a. Neither the SO-5 Del Mar or Oceanside Borrow Areas are not located within any known, historic artillery ranges and therefore, it is not anticipated that any munitions will be encountered during dredging or beach placement operations. However while working in the Oceanside Borrow Area, in the event that munitions are encountered at the Oceanside borrow area, immediately notify:
* Contracting Officer
* Orange County Hazardous Devices Section: 714-538-2694
* Camp Pendleton Provost Marshall Office (PMO): 760-725-9883
- PMO will contact the Camp Pendleton Explosive Ordnance Disposal (EOD)
35 24 13.11 - 3.5.3 a.
a. Place dredged material uniformly within the beach fill limits of the areas indicated and as specified. The fill elevations are ideal and the actual elevation of the fill may vary 0.5 feet above or below the indicated elevations. Deposit the dredged material in a uniform manner progressing from the shoreward side to the seaward side of the fill area. Complete the beach fill sections north(west) of each subline landing point before placing dredged material south(east) of the subline landing point. Fill each section where placement is required to the elevations indicated prior to moving to the next section. Provide the necessary equipment to shape, groom, and dress the beach during fill operations. Fully describe the construction of the beach fill in the Construction Plan, including methods for constructing end sections.
35 24 13.11 - 3.5.4 a.
a. If the construction template cannot be achieved at the toe of the section, then a compensated slope to offset voids in the construction fill template will be allowed. Excess material may be placed and graded on the foreshore slope between elevation +13.0 feet MLLW and +5.0 feet MLLW as long as the fill volume above tolerance does not exceed void volume on the foreshore slope below tolerance.
35 24 13.11 – 3.5.5
In the event that pre-placement condition survey volumes, verified and approved by the Contracting Officer or their representative, show that the space available within the template, including tolerance, does not equal is greater than the bid quantity, the template must be shifted by adjusting the seaward edge of berm uniformly throughout the length of the beach. Submit the proposed Volume-Based Template Adjustment prior to the start of dredging and beach fill operations for each beach fill site.
Include a matching adjustment of the seaward toe of slope to maintain the prescribed slope. (Ex. If the Bid Quantity = 100,000 CY and Template plus Tolerance Quantity is found to be 75,000 CY 125,000 CY from the pre-placement survey, then the seaward edge of berm must be retracted evenly along the full length of beach in order to conform the template and maintain the bid quantity as 100,000 CY).
35 24 13.11 - 3.10.1 d.
d. Wading is permitted for surveying in the surf zone in accordance with EM 385-1-1. No wader may enter the water if the Contracting Officer deems the conditions are unsafe.
35 24 13.11 - 3.11.1 a.
a. Within 14 days prior to the placement of dredged material at any placement site, provide a Pre- Construction Topographic Survey of the placement area. Extend the survey limits 500 feet beyond the respective longshore placement limits shown. At the San Clemente placement site, the survey must originate at the project baseline or landward-most obstruction and extend to Mean Lower Low Water. For Solana Beach and Encinitas placement sites, originate each survey from the base of the bluff and extend to Mean Lower Low Water. Obtain profile spot elevations at minimum one foot horizontal (X and Y) spacing. Perform the surveys in accordance with Section
01 11 00.42 SUMMARY OF WORK.
35 24 13.11 - 3.11.1 b. -DELETED
35 24 13.11 - 3.11.1 c. -Update paragraph lettering to “b.”
35 24 13.11 – 3.12 SURVEYING RESTRICTIONS -DELETED
35 24 13.11 - 3.13 DREDGING AND PLACEMENT SITE OPERATIONS -Reassigned as Subpart 3.12
35 24 13.11 – 3.12.1 a., b., c., d.
a. Dredging and pumping can be performed 24 hours per day, 7 days per week at all locations.
b. Beach operations are restricted to the hours of 7:00 AM to 7:00 PM Monday through Sunday. Do not conduct beach operations on Federal holidays. Beach operations are defined as the use of heavy equipment such as front loaders, bulldozers, skid steers, graders, or excavators to move or shape the beach profile; or the movement or cutting, welding or connecting of beach pipeline.
c. Beach operations in the vicinity of S. Cardiff Seaside Parking Lot are restricted to daylight hours (sunrise to sunset) Monday through Friday between March 15, 2024 and May 17, 2024.
d. Minimize operations at the areas listed during the following events:
1) OCT 2023 - Surfride DemoFest at S. Cardiff Seaside Parking Lot
2) NOV 2023 - Challenge MS Walk at S. Cardiff Seaside Parking Lot
3) NOV 2023 - A Walk on Water at S. Cardiff Seaside Parking Lot
4) DEC 2023 - Holiday Tree Lighting Ceremony at Fletcher Cove Park
5) APR 2024 - Ragnar at S. Cardiff Seaside Parking Lot
35 24 13.11 – 3.14 MARINE PLANT -Reassigned as Subpart 3.13
Plan Sheet WCH-SCS-CB101-000 – Replaced in its entirety. Changes indicated by marking in the mark section.
Plan Sheet WCH-SDB-CB301-000 – Replaced in its entirety. Changes indicated by marking in the mark section.