C.04 - Abstract - 7N21B0024_s.pdf

PDF 309 KB Posted

Attached to
The Dalles Lock & Dam Miter Gate Repair
Solicitation number
W9127N21B0024
Issued by

About this file

This document contains an abstract of offers for the solicitation of miter gate repair work at The Dalles Lock and Dam. The U.S. Army Corps of Engineers, Portland District is seeking bids to perform mandatory and optional line items for structural modifications, concrete sill modifications, lower gate seal replacements, miter gate leaf gudgeon adjustment, and miter gate leaf quoin block adjustment. The estimated cost of the project is between $1 million to $5 million. Bids were due on September 20, 2021. Four offers were received ranging in total price from $1,379,036 to $2,897,000. The pre-solicitation notice identifies Charles Boswell and Kristina Morrow as points of contact for questions via email.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. SOLICITATION NO. 2. DATE ISSUED 3. DATE OPENED PAGE 1 OF 1 PAGES

8/20/2021 9/20/2021

4. ISSUING OFFICE

DISTRICT ENGINEER CONTRACT SPECIALIST SIGNATURE CONTRACTING OFFICER SIGNATURE

PORTLAND DISTRICT, CORPS OF ENGINEERS

P.O. BOX 2946

PORTLAND, OR 97208-2946

5. PROJECT TITLE 8. GOVERNMENT ESTIMATE 9. OFFERS

(CHECK A, B, OR C AND COMPLETE NO.1 NO.2 NO.3

D, E, AND F.) A. OFFEROR BCI CONSTRUCTION USA, INC.A. OFFEROR NORTHBANK CIVIL

A. HIRED LABOR

B. REASONABLE CONTRACT B. BID SECURITY

X (WITHOUT PROFIT) 20% of bid price 20% of bid price 20% of bid price

C. REASONABLE CONTRACT C. ADDENDA ACKNOWLEDGED C. ADDENDA ACKNOWLEDGED ADDENDA ACKNOWLEDGED

(INCLUDING PROFIT) YES YES YES

6. NUMBER OF ADDENDA ISSUED 1

7A.

ITEM E. UNIT F. ESTIMATED D. UNIT F. ESTIMATED D. UNIT F. ESTIMATED D. UNIT F. ESTIMATED

NO. QUANTITY UNIT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT

MANDATORY LINE ITEMS

0001 Mobilization and Demobilization 1 JOB 289,814.00$ 289,814.00$ 82,700.00$ 82,700.00$ 270,000.00$ 270,000.00$ 390,000.00$ 390,000.00$ 0002 Designated Reference Drawings 1 JOB 18,483.00$ 18,483.00$ 15,000.00$ 15,000.00$ 15,000.00$ 15,000.00$ 15,000.00$ 15,000.00$ 0003 Miter Gate Alignment Survey 1 JOB 65,075.00$ 65,075.00$ 35,000.00$ 35,000.00$ 150,000.00$ 150,000.00$ 35,000.00$ 35,000.00$ 0004 Miter Gate Tensioning 1 JOB 259,914.00$ 259,914.00$ 283,780.00$ 283,780.00$ 1,332,000.00$ 1,332,000.00$ 225,000.00$ 225,000.00$ 0005 Miter Block Adjustments 1 JOB 178,812.00$ 178,812.00$ 141,756.00$ 141,756.00$ 210,000.00$ 210,000.00$ 50,000.00$ 50,000.00$ 0006 Structural Modifications 1 JOB 754,719.00$ 754,719.00$ 259,050.00$ 259,050.00$ 375,000.00$ 375,000.00$ 250,000.00$ 250,000.00$ 0007 Concrete Sill Modifications 1 JOB 231,367.00$ 231,367.00$ 438,914.00$ 438,914.00$ 300,000.00$ 300,000.00$ 250,000.00$ 250,000.00$ 0008 Lower Gate Seal Replacements 1 JOB 134,333.00$ 134,333.00$ 70,960.00$ 70,960.00$ 145,000.00$ 145,000.00$ 90,000.00$ 90,000.00$

SUBTOTAL FOR MANDATORY LINE ITEMS 1,932,517.00$ 1,327,160.00$ 2,797,000.00$ 1,305,000.00$

OPTIONAL LINE ITEMS

0009 Miter Gate Leaf Gudgeon Adjustment 1 JOB 144,509.00$ 144,509.00$ 41,080.00$ 41,080.00$ 60,000.00$ 60,000.00$ 30,000.00$ 30,000.00$ 0010 Miter Gate Leaf Quoin Block Adjustment 1 JOB 83,743.00$ 83,743.00$ 10,796.00$ 10,796.00$ 40,000.00$ 40,000.00$ 20,000.00$ 20,000.00$

SUBTOTAL FOR OPTIONAL LINE ITEMS 228,252.00$ 51,876.00$ 100,000.00$ 50,000.00$

2,160,769.00$ 1,379,036.00$ 2,897,000.00$ 1,355,000.00$ TOTAL

45 EMPIRE DR.

BELLEVILLE, IL 62220

DUNS# 620184580

B. BID SECURITY

PO BOX 83599

PORTLAND, OR 97283

DUNS# 103017265

AND MARINE, INC.

4180 NW FRUIT VALLEY ROAD

VANCOUVER, WA 98660-1222

THE DALLES LOCK AND DAM MITER GATE REPAIR

7B. DESCRIPTION OF OFFERED ITEM 7C. EST D.

A. OFFEROR ADVANCED AMERICAN CONSTRUCITON

ABSTRACT OF OFFERS

W9127N21B0024

I CERTIFY THAT I HAVE OPENED, READ, AND RECORDED ON THIS ABSTRACT

ALL OFFERS RECEIVED IN RESPONSE TO THIS SOLICITATION.

NSN 7540-01-150-0981 1419-101 STANDARD FORM 1419 (10-3)

2021-09-20T19:11:13-0700
BOSWELL.CHARLES.MADISON.1235613685
2021-09-21T08:35:40-0700
MORROW.KRISTINA.KAYE.1290513320

File details come from the government source that posted it. Updated .