C.04 - Abstract - W9127N20B0021_signed.pdf
PDF 103 KB Posted
- Solicitation number
- W9127N20B0021
About this file
This abstract of offers summarizes bids received in response to a solicitation for test pile installation at the mouth of the Columbia River on Sand Island. The solicitation sought bids for the installation of test piles using vibratory and impact pile driving methods at 30 test points. It required mobilization, pile installation with various attachments including cones, rings, and rock shoes, and demobilization. Three contractors submitted bids by the June 8, 2020 deadline: Bergerson Construction, Inc., Duwamish-Pacific Joint Venture, and Legacy Contracting, Inc. Bid prices ranged from $1,708,500 to $3,053,450.45 for the mandatory line items. The solicitation was issued by the USACE Portland District for pile installation to support evaluation of foundation conditions for a future project at the mouth of the Columbia River.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B.08 - bidder inquiry.pdf | ||
| B.08 - W9127N20B0021-0001.pdf | ||
| B.08 - SAND ISLAND TEST PILES - ADVERTISE SET 02212020.pdf | ||
| B.08 - W9127N20B0021 Full.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. SOLICITATION NO. 2. DATE ISSUED 3. DATE OPENED PAGE 1 OF 1 PAGES
5/8/2020 6/8/2020
4. ISSUING OFFICE
DISTRICT ENGINEER CONTRACT SPECIALIST SIGNATURE CONTRACTING OFFICER SIGNATURE
PORTLAND DISTRICT, CORPS OF ENGINEERS
P.O. BOX 2946
PORTLAND, OR 97208-2946
5. PROJECT TITLE 8. GOVERNMENT ESTIMATE 9. OFFERS
(CHECK A, B, OR C AND COMPLETE NO.1 NO.2 NO.3
D, E, AND F.) A. OFFEROR A. OFFEROR A. OFFEROR
A. HIRED LABOR
B. REASONABLE CONTRACT B. BID SECURITY
X (WITHOUT PROFIT) 20% of bid price 20% of bid price 20% of bid price
C. REASONABLE CONTRACT C. ADDENDA ACKNOWLEDGED C. ADDENDA ACKNOWLEDGED ADDENDA ACKNOWLEDGED
(INCLUDING PROFIT) YES YES YES
6. NUMBER OF ADDENDA ISSUED 1
7A.
ITEM E. UNIT F. ESTIMATED D. UNIT F. ESTIMATED D. UNIT F. ESTIMATED D. UNIT F. ESTIMATED
NO. QUANTITY UNIT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
0001 Mobilization and Demobilization 1 JOB 488,047.00$ 488,047.00$ 834,500.00$ 834,500.00$ 1,520,000.00$ 1,520,000.00$ 834,215.45$ 834,215.45$ 0002 Test Point 4-1C, Pile with Cone (Vibratory) 1 JOB 45,193.00$ 45,193.00$ 26,500.00$ 26,500.00$ 41,000.00$ 41,000.00$ 63,510.00$ 63,510.00$ 0003 Test Point 4-1C, Pile with Cone (Impact) 1 JOB 32,935.00$ 32,935.00$ 37,000.00$ 37,000.00$ 50,000.00$ 50,000.00$ 82,100.00$ 82,100.00$ 0004 Test Point 4-1F, Pile Only (Vibratory) 1 JOB 45,193.00$ 45,193.00$ 18,000.00$ 18,000.00$ 38,000.00$ 38,000.00$ 62,100.00$ 62,100.00$ 0005 Test Point 4-1F, Pile with Ring (Impact) 1 JOB 32,935.00$ 32,935.00$ 28,000.00$ 28,000.00$ 46,000.00$ 46,000.00$ 83,350.00$ 83,350.00$ 0006 Test Point 4-1F, Pile with Cone (Impact) 1 JOB 32,935.00$ 32,935.00$ 28,000.00$ 28,000.00$ 46,000.00$ 46,000.00$ 83,350.00$ 83,350.00$ 0007 Test Point 4-2C, Pile with Ring (Impact) 1 JOB 45,193.00$ 45,193.00$ 37,000.00$ 37,000.00$ 50,000.00$ 50,000.00$ 83,350.00$ 83,350.00$ 0008 Test Point 4-2C, Pile with Cone (Impact) 1 JOB 32,935.00$ 32,935.00$ 37,000.00$ 37,000.00$ 50,000.00$ 50,000.00$ 83,350.00$ 83,350.00$ 0009 Test Point 4-2F, Pile with Cone (Vibratory) 1 JOB 45,193.00$ 45,193.00$ 18,000.00$ 18,000.00$ 38,000.00$ 38,000.00$ 64,500.00$ 64,500.00$ 0010 Test Point 4-2F, Pile with Cone (Impact) 1 JOB 32,935.00$ 32,935.00$ 28,000.00$ 28,000.00$ 46,000.00$ 46,000.00$ 83,350.00$ 83,350.00$ 0011 Test Point 4-3C, Pile with Ring (Impact) 1 JOB 45,193.00$ 45,193.00$ 37,000.00$ 37,000.00$ 50,000.00$ 50,000.00$ 82,700.00$ 82,700.00$ 0012 Test Point 4-3C, Pile with Cone (Impact) 1 JOB 32,935.00$ 32,935.00$ 37,000.00$ 37,000.00$ 50,000.00$ 50,000.00$ 82,700.00$ 82,700.00$ 0013 Test Point 4-4C, Pile with Cone (Impact) 1 JOB 45,193.00$ 45,193.00$ 37,000.00$ 37,000.00$ 50,000.00$ 50,000.00$ 82,700.00$ 82,700.00$ 0014 Test Point 4-4C, Pile with Rock Shoe (Impact) 1 JOB 32,935.00$ 32,935.00$ 37,000.00$ 37,000.00$ 50,000.00$ 50,000.00$ 82,700.00$ 82,700.00$ 0015 Test Point 6-1C, Pile with Rock Shoe (Impact) 1 JOB 45,193.00$ 45,193.00$ 37,000.00$ 37,000.00$ 50,000.00$ 50,000.00$ 82,700.00$ 82,700.00$ 0016 Test Point 6-1C, Pile with Ring (Impact) 1 JOB 32,935.00$ 32,935.00$ 37,000.00$ 37,000.00$ 50,000.00$ 50,000.00$ 82,700.00$ 82,700.00$ 0017 Test Point 6-1F, Pile Only (Vibratory) 1 JOB 45,193.00$ 45,193.00$ 18,000.00$ 18,000.00$ 38,000.00$ 38,000.00$ 59,100.00$ 59,100.00$ 0018 Test Point 6-1F, Pile with Cone (Vibratory) 1 JOB 32,935.00$ 32,935.00$ 18,000.00$ 18,000.00$ 38,000.00$ 38,000.00$ 65,950.00$ 65,950.00$ 0019 Test Point 6-2C, Pile with Cone (Impact) 1 JOB 45,193.00$ 45,193.00$ 37,000.00$ 37,000.00$ 50,000.00$ 50,000.00$ 83,200.00$ 83,200.00$ 0020 Test Point 6-2C, Pile with Rock Shoe (Impact) 1 JOB 32,935.00$ 32,935.00$ 37,000.00$ 37,000.00$ 50,000.00$ 50,000.00$ 83,200.00$ 83,200.00$ 0021 Test Point 6-2F, Pile with Ring (Impact) 1 JOB 45,193.00$ 45,193.00$ 28,000.00$ 28,000.00$ 46,000.00$ 46,000.00$ 81,750.00$ 81,750.00$ 0022 Test Point 6-2F, Pile with Cone (Impact) 1 JOB 32,935.00$ 32,935.00$ 28,000.00$ 28,000.00$ 46,000.00$ 46,000.00$ 81,750.00$ 81,750.00$ 0023 Test Point 6-3C, Pile with Rock Shoe (Impact) 1 JOB 45,193.00$ 45,193.00$ 37,000.00$ 37,000.00$ 50,000.00$ 50,000.00$ 81,750.00$ 81,750.00$ 0024 Test Point 6-3C, Pile with Ring (Impact) 1 JOB 32,935.00$ 32,935.00$ 37,000.00$ 37,000.00$ 50,000.00$ 50,000.00$ 81,750.00$ 81,750.00$ 0025 Test Point 6-3F, Pile Only (Vibratory) 1 JOB 45,193.00$ 45,193.00$ 18,000.00$ 18,000.00$ 38,000.00$ 38,000.00$ 60,925.00$ 60,925.00$ 0026 Test Point 6-3F, Pile with Ring (Vibratory) 1 JOB 32,935.00$ 32,935.00$ 18,000.00$ 18,000.00$ 38,000.00$ 38,000.00$ 64,950.00$ 64,950.00$ 0027 Test Point 6-3F, Pile with Cone (Vibratory) 1 JOB 32,935.00$ 32,935.00$ 18,000.00$ 18,000.00$ 38,000.00$ 38,000.00$ 64,950.00$ 64,950.00$ 0028 Test Point 6-4C, Pile Only (Vibratory) 1 JOB 45,193.00$ 45,193.00$ 26,500.00$ 26,500.00$ 41,000.00$ 41,000.00$ 59,100.00$ 59,100.00$ 0029 Test Point 6-4C, Pile with Ring (Impact) 1 JOB 32,935.00$ 32,935.00$ 37,000.00$ 37,000.00$ 50,000.00$ 50,000.00$ 81,750.00$ 81,750.00$ 0030 Test Point 6-4C, Pile with Cone (Impact) 1 JOB 32,935.00$ 32,935.00$ 37,000.00$ 37,000.00$ 50,000.00$ 50,000.00$ 83,950.00$ 83,950.00$
SUBTOTAL FOR MANDATORY LINE ITEMS 1,602,516.00$ 1,708,500.00$ 2,848,000.00$ 3,053,450.45$
SUBTOTAL FOR OPTIONAL LINE ITEMS
1,602,516.00$ 1,708,500.00$ 2,848,000.00$ 3,053,450.45$
NSN 7540-01-150-0981 1419-101
Bergerson Construction, Inc.
55 Portway P.O. Box 387 Astoria, OR 97103
Mouth of the Columbia River Sand Island Test Piles
7B. DESCRIPTION OF OFFERED ITEM 7C. EST D.
TOTAL
ACCEPTANCE LIMITATION - DAYS
INFORMALITIES
Duwamish-Pacific, Joint Venture 6627 Ellis Ave South Seattle, WA 98108
B. BID SECURITY
Legacy Contracting, Inc.
PO Box I, 41850 Kingston Jordan Rd.
Stayton, OR. 97383
STANDARD FORM 1419 (10-3)
ABSTRACT OF OFFERS
W9127N20B0021
I CERTIFY THAT I HAVE OPENED, READ, AND RECORDED ON THIS ABSTRACT
ALL OFFERS RECEIVED IN RESPONSE TO THIS SOLICITATION.
| 2020-06-08T16:53:06-0700 | |
| BOSWELL.CHARLES.MADISON.1235613685 |
| 2020-06-09T10:46:18-0700 | |
| DVORAK.DAVID.LAWRENCE.1160820540 |
File details come from the government source that posted it. Updated .