A.02.02_Synopsis-VAPORHCS_A-E_Design_SATOC.pdf
PDF 525 KB Posted
- Attached to
- VAPORHCS A-E Design SATOC
- Solicitation number
- W9127N19R0009_VAPORHCS_A-E_DESIGN_SATOC
About this file
This synopsis requests Standard Form 330 proposals for a Veterans Affairs Portland Health Care System Architect-Engineer Design Single Award Task Order Contract. Key details include a contract capacity of $130 million over a potential 10-year term to provide seismic upgrades, renovations, construction of a new specialty care building and parking garage, and utility upgrades. Proposals are due November 20, 2018 and should include experience with seismic retrofits, medical facility design, and renovations involving inpatient care. Selection will evaluate specialized experience, qualifications, past performance, knowledge of local conditions, and capacity. Small business participation will be considered. The work involves design through construction and includes seismic analyses, building information modeling, and preparing sustainability documentation.
VAPORHCS A-E Design SATOC Synopsis
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INDEFINITE DELIVERY SINGLE AWARD TASK ORDER CONTRACT FOR A-E SERVICES
VETERANS AFFAIRS PORTLAND HEALTH CARE SYSTEM
THE U.S. ARMY CORPS OF ENGINEERS, PORTLAND DISTRICT
16 October 2018
Solicitation No: W9127N19R0009
Agency: Department of Army
Office: U.S. Army Corps of Engineers, Portland District
Location: Portland, OR
I. CONTRACT INFORMATION
A. General
The objective of this contract is to provide engineering and architectural (A-E) services in support of the U.S. Department of Veterans Affairs (DVA) Health Care System, Portland, Oregon. Services will include all engineering and architectural work necessary to provide seismic upgrades and ancillary renovation, construction of new specialty care building, construction of a new parking garage, upgrades to utility/energy plant, and the demolition of a number of buildings. This may include the development and evaluation of alternatives, design, and support during construction.
B. Potential for Organizational Conflict of Interest and Mitigation Required
The Contracting Officer has determined a significant potential organizational conflict of interest (OCI) exists between the contract that will result from this synopsis, and a future requirement for A-E services, Solicitation No. W9127N19R0010, entitled, “A-E Technical Services in support of VA Medical Facility Requirements.” The Contracting Officer has also determined a significant potential OCI exists between the contract that will result from this synopsis and the DVA awarded “Project Book” contract, Contract No. 36C10F18R0471.
As result of the above, the following provisions and clauses are included in this synopsis, and will be included in the formal solicitation and resulting contract award.
Provisions:
(1) OCI Between Project Book, Contract No. 36C10F18R0471, and Design SATOC, Solicitation No. W9127N19R0009:
In accordance with FAR Subpart 9.5, Organizational and Consultant Conflicts of Interest, the Contracting Officer has determined that a significant potential for an organizational conflict of interest exists for firms currently performing under contract number 36C10F18R0471 (“Project Book contract”), awarded by the Department of Veterans Affairs for the development of the Project Book for the Veterans Affairs Portland Health Care System project.
Contained within the Project Book contract scope are requirements to make recommendations to the Government, which the contractor awarded this Design SATOC will be required to review and validate. This presents an impaired objectivity organizational conflict of interest for the current Project Book contractor and associated subcontractors. As such, the Project Book contractor is precluded from receiving an award under the subject synopsis. In addition, should a firm submitting an SF 330 in response to the synopsis include a subcontractor or team member currently performing a portion of the Project Book scope, and that firm is selected as the most highly qualified firm, the firm will be required to submit an acceptable mitigation plan to the Government, addressing how it will prevent any organizational conflict of interest. At a minimum, the contractor or subcontractor currently performing under the Project Book contract may not be associated with any individual tasks that involve the review or validation of work or recommendations performed by the Project Book contractor. Should the firm be unable to produce an acceptable mitigation plan, negotiations will proceed with the next most highly qualified firm.
(2) OCI Between Design SATOC, Solicitation No. W9127N19R0009, and Technical Services SATOC, Solicitation No. W9127N19R0010:
In accordance with FAR Subpart 9.5, Organizational and Consultant Conflicts of Interest, the Contracting Officer has determined that a significant potential for an organizational conflict of interest exists between the contractor awarded the Design SATOC (Solicitation No.
W9127N19R0009) from this synopsis and the contractor awarded the Technical Services SATOC (Solicitation No. W9127N19R0010). A considerable portion of the work under the Technical Services SATOC will be to review deliverables, recommendations, and alternatives produced by the Design SATOC contractor. The Technical Services SATOC contractor will also be assisting with drafting the task order scopes of work for the Design SATOC. The contracting officer has determined this to be an impaired objectivity organizational conflict of interest.
As a result of the organizational conflict of interest, the contractor awarded this Design SATOC will be precluded from receiving an award under the Technical Services SATOC. If the Technical Services SATOC is awarded prior to the award of this Design SATOC, the Technical Services SATOC contractor will be precluded from receiving an award under this Design SATOC. This restraint applies to the prime and subcontractors associated with either contract.
Clauses (Note: Per FAR 9.507-2(a), the final terms of each clause may be changed subject to negotiations with the successful offeror):
(1) OCI Between Project Book, Contract No. 36C10F18R0471, and Design SATOC:
In accordance with FAR Subpart 9.5, Organizational Conflict of Interest, the Contracting Officer has determined that the potential for impaired objectivity will exist in the performance of anticipated task orders by firms currently performing under contract number 36C10F18R0471, awarded by the Department of Veterans Affairs, for the development of a Project Book. The mitigation plan approved by the Contracting Officer during the pre-award phase of this action will be continuously reviewed to ensure applicability and suitability for mitigation of conflicts at the task order level. Should the Contracting Officer identify a task order scope during the performance of the contract that could have additional potential for conflict, the offeror will be required to submit a supplemental mitigation plan.
(2) OCI Between Design SATOC and Technical Services SATOC, Solicitation No.
W9127N19R0010:
In accordance with FAR Subpart 9.5, Organizational and Consultant Conflicts of Interest, the Contracting Officer has determined that a significant potential for an organizational conflict of interest exists between this contract and the Technical Services SATOC to be issued under Solicitation No. W9127N19R0010. A considerable portion of the Technical Services SATOC work will be reviewing deliverables, recommendations, and alternatives produced under this contract. The Technical Services SATOC contractor will also be assisting with drafting the task order scopes of work for task orders issued under this contract. The Contracting Officer has determined that this creates an impaired objectivity organizational conflict of interest.
As a result of the organizational conflict of interest, the Design SATOC contractor, to include its subcontractors, is precluded from receiving the Technical Services SATOC issued under Solicitation No. W9127N19R0010.
C. Type and Number of Contracts
The USACE Portland District (NWP) intends to award one (1) indefinite delivery, firm-fixed-price, single award task order contract (SATOC). The awarded SATOC will consist of one
(1) 5-year base period (commencing upon the date of award of this base contract) and one
(1) 5-year option period for a total contract term not to exceed ten (10) years. The total capacity is $130 million. The minimum guaranteed amount for the SATOC is $20,000. Task orders issued under this SATOC will have a minimum ordering amount of $3,000.00.
Multiple task orders are anticipated to be awarded between $2M and $10M in support of this
Contract award is anticipated in the third quarter of Fiscal Year 2019.
D. Competition
The North American Industry Classification (NAICS) code for this acquisition is 541330 Engineering Services, which has a size standard of $15 million.
E. System for Award Management
To be eligible for contract award, a firm must be registered in the Department of Defense (DoD) System for Award Management (SAM). Register via the SAM website at https://www.sam.gov or by contacting the Service Desk at 1-866-606-8220. Firms must register prior to the due date for responses to this synopsis in order to enable the Contracting Officer’s review of SAM Exclusions.
F. Service Contract Act
Firms are advised that the resulting SATOC will require that the wages and benefits of listed services employees (see FAR 22.10) be at least equal to those determined by the Department of Labor under the Service Contract Act, as determined relative to the employee’s office location, not the location of the work. See http://www.wdol.gov for additional information.
II. SELECTION PROCESS
Selection for SATOC Negotiation
In accordance with 40 U.S.C. Chapter 11 (Selection of Architects and Engineers Statute), the applicable provisions of the Competition in Contracting Act (10 U.S.C. § 2304), the applicable provisions of the Federal Acquisition Streamlining Act (Pub. L. 103-355, 108 Stat.
3243), NWP will select a single firm for SATOC negotiation using the procedures set forth in FAR Subpart 36.6 and Defense Federal Acquisition Regulation Supplement (DFARS) Subpart 236.6:
In accordance with FAR 36.602-3(a), NWP will review the Standard Form (SF) 330s submitted in response to this synopsis.
In accordance with FAR 36.602-3(b) and DFARS 236.602-1(a), NWP will evaluate those SF 330s in accordance with the criteria in FAR 36.602-1 and DFARS Procedures, Guidance, and Information (PGI) 236.602-1, as set forth in greater detail in this synopsis.
In accordance with FAR 36.602-3(c), NWP will hold discussions with at least three of the most highly qualified firms regarding concepts and the relative utility of alternative methods of furnishing the required services described in this synopsis.
On the basis of the above, in accordance with FAR 36.602-3(d), NWP will determine the firms most highly qualified to perform the required services described in this synopsis.
The Selection Authority will review the recommendations in accordance with FAR 36.602-3(d) and make the final selection of the most highly qualified firm.
III. PROJECT INFORMATION
This SATOC is intended to provide architectural and engineering support of planned construction projects at the Veterans Affairs Portland Healthcare System (VAPORHCS) located on Marquam Hill in Portland, OR. Preliminary planning is currently being performed to collect requisite information and better identify the requirements and details of these projects. The following information is tentative and meant to provide the A-E with an idea of the general nature of the anticipated work. The Government reserves the right to update this information as project planning documentation is published and updated. The information below represents the most current project scope information available and will be superseded upon the publication of the preliminary planning information (Project Book, see section 4.1 below) which will be provided to the selected A-E as Government-furnished information (GFI) post award:
3.1. Estimated Construction Cost (ECC). The current ECC is over $500,000,000. Ref. DFARS
236.204 Disclosure of Magnitude.
3.3. Construction Methodology. It is expected that there may be a variety of delivery methods employed for each facility involved in the VAPORHCS project (Ex. Design-Build, Design-Bid- Build, etc.). The Anticipated SATOC capacity includes pre-design services, design services and construction phase services; however, the full capacity may not be required to complete the
3.4. Construction Details. The following information represents the various construction objectives as they are currently known:
3.4.1. Seismic upgrade of Buildings 100 (9 stories above ground and 2 stories below, 638,843 GSF), 101 (130,850 GSF), 102 (108,000 GSF) and two pedestrian Sky Bridges (up to 600' length). This includes structural improvements to building frame members and may include the repair/replacement of the exterior façade of Buildings 100 & 101, which have had poor seismic performance to date.
The seismic upgrade will address Portland's remaining Extremely High Risk (EHR) Building structure / seismic condition gaps through a complete seismic retrofit to Building 100 (Portland's main hospital building), Building 101 (Research / Admin) and Building 102 (underground parking garage that supports the roadway in front of Buildings 100 and 101). Two Sky Bridges that connect Portland buildings and those of the neighboring Oregon Health & Science University (OHSU) will also be seismically upgraded, as necessary.
3.4.2. Renovation of up to 769,927 DGSF (Departmental Gross Square Feet) in Buildings 100 and 101, as necessary, to support the seismic retrofit and to correct deficiencies in the building, as listed below:
a. Correct (repair or replacement) the failing facade of Buildings 100 and 101.
b. Convert shared inpatient rooms to private rooms.
c. Upgrade substandard operating rooms.
d. Correct Sterile Processing Service deficiencies
3.4.3. Construction of a new Specialty Care Building, currently anticipated to be 248,000 DGSF/335,000 BGSF (Building Gross Square Feet).
The new building will be constructed on the Portland campus, and will provide essential swing space during the seismic retrofit and renovation work to the other buildings discussed above.
This new structure will house most of Portland's ambulatory care functions, and will free precious space in the main hospital building for acute inpatient functions and ancillary support departments.
3.4.4. Construction of a new 600-space attached parking garage.
3.4.5. Upgrade of utility/energy plant as necessary to support new construction.
3.4.6. Demolition of Building 41, Building T-51 and Trailer 1 (Total of 30,955 GSF).
3.4.7. Solar PV and Solar Hot Water Systems will be included in this project, as applicable.
3.5. Anticipated Project Schedule.
a. Jul 2019 – Award VAPORHCS A-E SATOC
b. Oct 2019 – 10% Design Charrette
c. Dec 2019 – 10% Concept Design and Alternatives Analysis Complete
d. Dec 2019 – Initiate 35% Design
e. Apr 2020 – 35% Design Complete
f. Jun 2020 – Congressional Budget Request
g. FY22 to FY29 – Phased Construction (pending Congressional approval)
IV. ELEMENTS OF ANTICIPATED TASK ORDERS.
The following is a tentative listing of task order elements that may be issued via task orders under the awarded SATOC, which will provide the engineering and architectural support to the project described in section III above. It generally describes the kind of support that may be required. The following information is tentative and meant to provide the A-E with an idea of the general nature of the anticipated work. The Government reserves the right to reduce, modify, add to any detail of this list as required to better meet the demands of the project as details become available:
4.1. Project Planning.
This will consist of the work required to advance the preliminary planning effort currently being performed through the DVA’s Project Book contract. The Project Book will be a requirements document, which will include the applicable planning information, codes and standards, existing site specific conditions, and other requirements and performance goals. NWP will provide the Project Book to the awardee of this SATOC as Government Furnished Information (GFI), which the SATOC contractor will be expected to use as a reference throughout its design process.
While the main focus of the contract is design, task orders may include the following as needed to bridge the planning (Project Book) and design phases of the project:
a. Site master planning
b. Medical facility planning
c. Planning charrettes
d. Development of Concepts of Operations
e. Defining existing site conditions/tabulations of facility deficiencies
f. Collection of facility data from archives
g. Development of notional budgetary ‘fit test’ concept designs
h. Collecting healthcare workload projection data
i. Performing safety risk assessments
j. Development of project room contents lists
k. Development of block layouts
l. Conceptual site development
m. Programs for Design (for GSF and NSF allocation)
n. Site selection analysis
o. Economic analyses
p. Medical equipment planning
q. Initial outfitting and transition planning and other low-voltage equipment needs
r. Budgetary construction cost estimates (parametric)
s. Development of Owner’s Performance Requirements (OPR) for commissioning planning
t. Hazardous materials surveys and abatement specifications
u. Environmental Assessments
v. Preliminary Subsurface Investigation (e.g. soil borings, analyses, etc.)
w. Federal, State, and Local Permitting
x. Consolidated planning reporting and development of other data related to facility decision support
y. Site visits
z. Attendance and participation in coordination meetings, status meetings, and design review conferences.
4.2. Facility Design and Solicitation Document Development.
This work will consist of the detailed engineering and architectural products, plans, specifications, and construction bid documents required to accurately define and award the construction solution. The Government anticipates that the first task order will include review and validation of the Project Book recommendations of potential solutions/alternatives (including several seismic retrofit methods/technologies), and collaborative efforts with the Government that will lead to the selection of a recommended alternative and design to the 10% level. The Government anticipates that the second task order will be for the design from the 10% level to the 35% level. This work may be awarded as individual task orders or as a single task order with options for follow-on work. Task orders may include any or all of the following:
a. Architectural and engineering designs, drawings, plans, and specifications (all applicable disciplines)
b. Design charrettes
c. Engineering analyses and narratives (e.g. seismic, geotechnical, foundation, structural, civil, mechanical, electrical, etc.) to meet project requirements
d. Design quality management
e. Computer Aided Design (CAD)
f. Geographic Information Systems (GIS)
g. Building Information Modeling (BIM)
h. Sustainability certification documentation preparation (LEED)
i. Interior design
j. Architectural renderings & color boards
k. Construction cost estimates (budget, parametric, and detailed)
l. Construction schedule preparation
m. Engineering studies (to include testing of components / concepts for the seismic retrofit)
n. Topographic and/or geotechnical surveys
o. Subsurface investigation and foundation design
p. Environmental documentation (NEPA, etc.)
q. Permits, licenses, and approvals
r. Work categorization
s. Submittal registers
t. As-built drawing preparation and updating of Operation and Maintenance Manuals
u. Interim life safety measures (ILSM)
v. Infection control risk mitigation design
w. Construction phasing plans
x. Preparation of plans & specifications for Design-Bid-Build, Design-Build methodology, or other as appropriate
y. Draft completion of Government forms related to real property
z. Attendance and participation in coordination meetings, status meetings, and design review conferences
aa. Facilitation of, and documentation preparation for, Value Engineering activities
bb. Data management in support of file sharing and Government – A-E collaboration
cc. Support of Cost Schedule Risk Analysis (CSRA) and Project Definition Rating Index
(PDRI) activities
dd. Design Presentations to USACE and DVA Headquarters
4.3. Construction Phase Support.
This work will consist of all work necessary for the A-E firm to accurately communicate and represent its design intent after design (but prior to construction award), during construction, and during post-construction phases of the project. Utilization of these elements will vary by each feature of work and the selected construction acquisition strategy (e.g. design-build or design-bid-build). Task orders may include:
a. Answering bidder inquiries
b. Construction proposal evaluation (technical and/or cost)
c. Construction submittal review (documents, materials, fixtures, equipment, samples, plant materials, color samples, etc.)
d. Request for Information (RFI) support
e. Shop drawing review
f. Engineering change proposal review
g. Site visits & construction inspection services
h. Commissioning support services
i. Construction progress documentation
j. Engineering forensics
k. Engineering/design during construction
l. Periodic field visits
m. In-person meetings and teleconference attendance
n. Coordination with other stakeholders (i.e. Government, commissioning firm, etc.)
o. Attendance and participation in coordination meetings and status meetings (in-person and/or telecon)
p. Post occupancy validation of systems
q. Activation support.
V. SUBMISSION REQUIREMENTS
A. General Instructions
Submit an SF 330, following the instructions set forth in the SF 330 form and as supplemented below. Do not submit any additional information that is not required by the SF 330 unless it is required in order to provide the additional information requested below. If the firm disregards these instructions and submits additional information not requested, the Government will not consider the additional information as part of its evaluation.
Except as otherwise permitted below, firms must use the fillable version of the SF 330 available on the U.S. General Services Administration website at https://www.gsa.gov/portal/forms/download/116486, using the space available and font settings embedded in that document. Firms may use “print to .pdf” functions to assemble its SF 330 package, number pages, etc. however, the fillable blocks shall be used for all data input.
Submit via email, the SF 330 package (SF 330 and required attachments) to the POCs listed below, no later than 2:00 PM on November 20, 2018. Should the SF 330 package exceed email attachment file size restrictions, firms shall email the POCs below an SF 330 cover sheet, notifying them the complete SF 330 package will be submitted through the AMRDEC Safe Access File Exchange (SAFE) system. A guide for use of the AMRDEC
SAFE system is found at https://safe.amrdec.army.mil/safe/guide.aspx.
NOTE: This is not a request for price proposal.
B. Supplemental Instructions
1. SF 330 Package Cover Page
Submit one (8.5” x 11”) cover page to the SF 330 package that includes the following information:
a. Point of Contact
b. Address
c. Phone Number
d. Email Address
e. CAGE Code (if Joint Venture (including Mentor-Protégé), provide the CAGE Code intended to be used should the firm receive an award)
f. Socioeconomic Category for NAICS 541330 (e.g., Large, Small, SDVOSB, etc.)
2. SF 330 Part I, Section C
If additional room is needed to complete Part I, Section C, because the proposed team consists of more than six firms, attach as many additional Part I, Section Cs as necessary to complete Part I, Section C. If submitting additional Part I, Section Cs, alter the identifiers in the first column (i.e., a. – f.) using the same convention so that each member of the team has a unique identifier. For example, the first six firms would be identified as
a. – f., the second six firms would be identified as g. – l., and so on.
3. SF 330 Part I, Section D
a. Organization Chart
Submit an organization chart illustrating all team members (i.e., firms listed in Part I, Section C) and disciplines, identifying the applicable experience levels as listed on Attachment B. Include the role of each listed individual as defined in Section 3, paragraph b below. The submitted org chart when printed shall be no larger than one page (11” x 17”) and provided in PDF format. See example provided. The intent of the example is to demonstrate the level of detail expected by the Government, not to dictate an organizational structure for the team or format for the organization chart.
See Attachment A for a list of all currently anticipated disciplines required to support this SATOC.
b. Organization Chart Summary Table
Utilizing the provided template (Attachment C), submit a summary of the submitted organization chart including the total number of personnel assigned by team member (firm), discipline, and experience level. The submitted table when printed shall be no larger than one page (8.5” x 11”) and provided in PDF format.
4. SF 330 Part I, Section E
a. For each of the disciplines below, submit resumes using Part I, Section E, for those persons that you propose to perform the work under this project. The number of resumes submitted for each discipline are limited to the quantities listed below.
NOTE: The Government will not review or consider resumes submitted that exceed the maximum quantities listed below. The Government also will not consider any resumes of individuals proposed to perform in disciplines that differ from those listed below.
Discipline Maximum Quantity
Project Manager 2 Architect 3 Structural Engineer 4 Geotechnical Engineer 3 Civil Engineer 2 Mechanical Engineer* 3 Electrical Engineer* 3 Fire Protection Engineer* 2 NEPA Specialist 2 Cost Estimator 1 Medical Facility Planner 2 Medical Equipment Planner 2 Medical Physicist (X-ray/MRI) 2 Communications Systems Professional 2 Construction Manager 1
*Denotes anticipated commissioning support discipline
b. Clearly identify the role of each individual on each resume submitted. For each discipline that allows for the submission of more than one resume, the firm shall have one individual responsible for overseeing the work associated with that discipline.
Only one individual per discipline should be identified in an oversight role. The remaining personnel for each discipline shall be committed to performing the majority of the production work in their respective discipline. Clearly identify in Block 13 of each person’s resume whether that individual will be performing an oversight role (O), production role (P), or both (O/P)).
c. Do not submit the same person for more than one discipline.
d. Fill out each field in the resume form (or otherwise indicate that the field is not applicable).
5. SF 330 Part I, Section F
a. Submit up to ten (10) projects that demonstrate your team’s experience performing work similar to that described in this synopsis. To be considered, each project must have led to a construction project that was completed within ten (10) years of the date that SF 330s are due, with the following exception: two (2) of the ten (10) projects submitted may be for a completed design that has not yet been constructed.
The Government will not review or consider more than ten (10) projects submitted. If more than ten (10) projects are submitted, the Government will review the first ten (10) projects.
b. If additional room is needed to describe a project in Block 24, the firm may submit an additional Part I, Section F page (i.e., using the Part I, Section F form) for that project. However, the total quantity of Part I, Section F pages must not exceed fifteen (15) pages for all projects submitted. The Government will not review or consider more than fifteen (15) Part I, Section F pages (see exception in paragraph c).
c. If additional room is needed to complete Block 25 because more than six firms from
Part I, Section C were involved in the project, attach a continuation Part I, Section F page providing only the necessary additional Block 25 information. Alter the firm identifiers in the first column as needed for consistency with Part I, Section C.
Additional pages needed only for Block 25 will not count toward the fifteen (15) page limit for Part I, Section F.
d. Please note: For purposes of this evaluation, an indefinite-delivery/indefinite-quantity (IDIQ) base contract (or other similar ordering vehicle) itself is not considered a “project.” At least one executed task order under the ordering vehicle or stand-alone contract must have been completed in order to constitute a “project.”
Additionally, two or more contract actions that supported only one effort, will constitute only one “project.”
e. In addition to the written content for each project, the firm may attach up to two (2) graphics representing that project (e.g. drawings, renderings, photographs, etc.).
Each graphic shall be in PDF format and no larger than one page (8.5” x 11”) when printed.
6. SF 330 Part I, Section G
Submit up to two Part I, Section G pages (so all personnel with a Part I, Section F may be identified through a Part I, Section G, Block 28 “Example Projects Key”) per the SF 330 instructions.
7. SF 330 Part I, Section H
Submit one Part I, Section H for each of the requirements below.
a. Volume of DoD or DVA Contracts
Provide information regarding all DoD or DVA A-E contracts awarded to all firms listed in Part I, Section C within the past twelve (12) months from issue date of this synopsis. List all contract numbers, task orders, and modifications, and include their award dates and total negotiated fees. Submit additional pages only if necessary to provide complete information.
b. Small Business Participation
In the space allotted, provide a brief narrative explaining the roles proposed for small businesses on the team. Additionally, estimate the proposed extent of participation of Small Business, Small Disadvantaged Business, Woman-Owned Small Business, HUBZone Small Business, Service-Disabled Veteran-Owned Small Business, and Veteran Owned Small Business team members. Identify each firm's name, small business category, and proposed level of participation measured as a percentage of the overall estimated effort. NOTE: Should a large business be selected for award, it will be required to submit a Subcontracting Plan for approval by the Contracting Officer prior to award, which must match the representations made in this section.
8. Past Performance
Submit information regarding past performance as an attachment to the SF 330.
For each project submitted in Part I, Section F, submit one of the following:
A completed Contractor Performance Assessment Reporting System (CPARS) evaluation, if available.
If a completed CPARS evaluation is not available, submit a completed Past Performance Questionnaire (PPQ) for the project. The standard PPQ for USACE is Form PPQ-0 (9/30/11)(Attachment D), and is provided as an attachment to this synopsis. Firms are advised to ensure correct phone numbers and email addresses are provided for the client point of contact. Do not submit a PPQ when a completed CPARS evaluation is available.
o If the firm is unable to obtain a completed PPQ from a client for a project(s) before the submission closing date, the firm should complete and submit the first page of the PPQ, which will provide contract and client information for the respective project(s).
o Firms should follow up with clients/references to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government's points of contact, Carolyn J. Randolph and Jordan M. Quantock, via email, at carolyn.j.randolph@usace.army.mil and jordan.m.quantock@usace.army.mil prior to the submission closing date.
Firms shall instruct the clients to refer to the synopsis number in the subject line.
o PPQs are source selection materials. All successfully submitted PPQs will receive an email confirmation upon receipt. If the firm does not receive the confirmation, it is the firm’s responsibility to follow up to ensure the Government has received the information.
In addition to the above, the Government may review other sources of information for evaluating past performance. Other sources may include, but are not limited to, past performance information retrieved through the PPIRS (Past Performance Information Retrieval System) including CPARS, using all CAGE/DUNS (Commercial and Government Entity/Data Universal Numbering System) numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the firm’s SF 330, inquiries of owner representative(s), FAPIIS (Federal Awardee Performance and Integrity Information System), or other databases; telephone interviews with organizations familiar with the firm’s performance, Government personnel with personal knowledge of the firm’s performance capability, and any other known sources not provided by the firm.
While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate, and complete past performance information rests with the firm. In reviewing past performance information, the Government will take into account the relevancy of the past performed work in addition to how well the firm performed.
9. SF 330, Part II
Submit one SF 330, Part II for each firm listed in Part I, Section C.
VI. SELECTION CRITERIA
NWP will evaluate firms’ qualifications under the selection criteria set forth below. The selection criteria are listed in descending order of importance. Criteria A through E are primary factors and will be evaluated for all firms. The remaining criteria are secondary factors and will be used only to distinguish between technically equal firms. The firms that demonstrate the highest aggregate qualifications relevant to the primary selection criteria will be considered the most highly qualified to perform the required services described in this synopsis.
A. Specialized Experience and Technical Competence
NWP will evaluate firms’ specialized experience and technical competence in the type of work required based on the size, scope and complexity of project examples submitted in comparison to the size, scope and complexity of the VAPORHCS project.
The following types of project experience is listed in descending order of importance:
DVA medical facilities, Department of Defense (DoD) medical facilities, private sector or municipal medical facilities.
In determining the most highly qualified firm, the Government will assess the breadth and depth of firms’ demonstrated specialized experience and technical competence in the following:
a. Design of seismic retrofit for building foundations and structures for medical facilities.
Designs utilizing non-linear building analysis and in accordance with DVA H-18-8 Seismic Design Requirements will be considered more relevant. Cumulative project experience demonstrating diverse application of seismic retrofit methods and technologies will be considered more relevant.
b. Design of seismic retrofit for steel bridges. Projects including dynamic analysis of suspension bridges will be considered more relevant.
c. Design of medical facility renovations that contain inpatient care requiring departmental relocation, upgrade of operating rooms and other primary departments, reconfiguration/upgrade of inpatient rooms, construction phasing, and utilization of swing space. Projects with active inpatient facilities with considerations for providing healthcare services during construction are preferred.
d. Design of medical facility renovations including scopes of work requiring design by the key discipline areas are preferred; examples include architectural, structural in accordance with DVA H-18-8, HVAC, medical plumbing, fire protection and other life safety systems, low voltage and communications systems, design for medical equipment and supporting systems.
e. New medical facility design for sites with challenging space constraints.
f. Designs for projects with challenging subsurface geological conditions, deep foundations, shoring, and soil-structure interaction considerations.
g. Design of complex utilities, traffic control, and stormwater in dense urbanized environments.
h. Preparation of NEPA and Section 106 documentation in an urbanized environment.
Evaluation of Key Project Teaming Experience: The Government will evaluate the Section G matrix to assess the extent to which the proposed key personnel have worked together in the past on projects similar in size, scope, and complexity to the VAPORHCS project. The Government values a team that has successfully worked together in the past on similar projects.
B. Professional Qualifications Necessary for Satisfactory Performance
NWP will evaluate firms’ professional qualifications necessary for satisfactory performance of the required services with consideration of the following:
a. Professional Registrations. At a minimum, each key engineer must be a registered Professional Engineer in their respective discipline in at least one U.S. state or territory. In addition, at least two (2) of the Structural Engineers must be registered as a Structural Engineer (SE), Fire Protection (FP) Engineers must have the FP registration, and Geotechnical Engineers must have either a Geotechnical Engineer (GE) or Civil Engineer (CE) registration. Each key architect must be a Registered Architect in at least one U.S. state or territory. The Communications Systems Professional must have attained the Registered Communications Distribution Designer (RCDD) credential. The PM, NEPA Specialist, Cost Estimator, Medical Facility Planner, Medical Equipment Planner, Medical Physicist, and Construction Manager, do not require professional registrations.
b. Other Professional Qualifications. The Government will consider each individual’s relevant credentials, publications, awards, certifications, etc., as provided on Block 18.
c. Experience. The Government will evaluate each individual’s relevant project experience (as described in the Specialized Experience and Technical Competence criterion) submitted for each key discipline, to include the individual’s longevity of relevant experience.
C. Past Performance
NWP will evaluate firms’ past performance on projects submitted in SF 330 Part I, Section F, in terms of quality of work, adherence to performance schedule, cost control, management, small business subcontracting, and regulatory compliance.
D. Knowledge of the Locality
NWP will evaluate firms’ demonstrated knowledge of local conditions through the projects submitted. NWP will take into consideration projects that demonstrate similar conditions as those contained in this project. Examples of local conditions include geology, climate, unique or unusual local construction methods, site constraints, environmental conditions, and seismology.
E. Capacity to Accomplish the Work in the Required Time
NWP will evaluate firms’ ability to meet workload requirements (including multiple concurrent task orders) primarily through a review of Part II of firms’ SF 330s, but may consider any other relevant information bearing on capacity.
F. Small Business Participation (Secondary Criteria)
NWP will evaluate small business participation as proposed in Part I, Section H. SF 330s demonstrating a greater commitment to small business participation will be evaluated more favorably under this criterion.
Small Businesses submitting as the prime A-E will automatically be given the highest level of consideration for this criteria. Among firms proposing as large (unrestricted) businesses, greater consideration will be given to those firms which demonstrate a greater intended use of small businesses as a percentage of their overall estimated effort.
G. Geographic Proximity (Secondary Criteria)
NWP will evaluate firms’ geographic proximity to the work to be performed. Firms demonstrating a majority of performance closer to the Portland Metro area will be considered more favorably.
H. Volume of DoD or DVA Contracts (Secondary Criteria)
NWP will evaluate firms’ total volume of DoD or DVA contracts awarded in the twelve (12) months prior to the issue date of this synopsis as set forth in Part I, Section H.
VII. QUESTIONS AND INQUIRIES ABOUT THIS SYNOPSIS
Submit all inquiries regarding this synopsis via ProjNet-Bid. Telephone and email inquiries will not be accepted. ProjNet-Bid is a web-based program that allows submitters to post questions regarding the synopsis and to view all questions by other submitters and answers by NWP.
ProjNet-Bid can be accessed through ProjNet at https://www.projnet.org/projnet/. To access the ProjNet-Bid website the first time:
(1) Click the Bid tab
(2) Click Bidder Inquiry. (The Agency is USACE.)
(3) Enter the following information for access:
a. The Bidder Inquiry Key: 6H2IGC - PGQMHF
b. Valid business contact information (e.g., company name, contact person, business address, phone number and email address) (required on first project only)
c. Establish secret question and answer which will be used as a password. (Required on first project only.)
(4) For subsequent access use your email address, the Bid Inquiry Key and response to the secret question to access the ProjNet-Bid Module.
(5) Submit questions or review questions and answers. (A firm that submits a question will receive an automated email notification that its question has been received. When an answer is posted to a question, the question and answer are then available for all other firms to review.
(6) For a specific step-by-step for POSTING YOUR INQUIRIES, is available in the Reference link on the Contract Viewer.
(7) For questions about the ProjNet-Bid, please contact the Call Center help desk toll free at 1-800-428-HELP, which operates from 8:00 AM to 5:00 PM (Pacific US time zone).
ProjNet-Bid questions can also be emailed to the helpdesk at staff@rcesupport.com.
The cutoff for questions and inquires is November 9, 2018, 2:00 PM (Pacific). All firms submitting an SF 330 in response to this synopsis will be held to have reviewed the questions and responses in ProjNet-Bid prior to their submission.
Administrative questions should be directed to Carolyn J. Randolph at carolyn.j.randolph@usace.army.mil. The secondary point of contact Jordan M. Quantock at jordan.m.quantock@usace.army.mil.
The point of contact for small business questions or assistance is the Portland District Deputy for Small Business, Carol McIntyre at (503) 808-4602 or carol.a.mcintyre@usace.army.mil.
List of attachments:
1) Attachment A-Discipline List
2) Attachment B-Example Org Chart
3) Attachment C-Org Chart Table Template
4) Attachment D-NAVFAC/USACE PAST PERFORMANCE QUESTIONNAIRE (Form
PPQ-0)
File details come from the government source that posted it. Updated .