GARIBALDI – DEPOE BAY PIPELINE MAINTENANCE DREDGING 2019
W9127N19B0014
Pre‐Solicitation‐ MINUTES Date: 02 May 2019 ‐ Time‐ 1000‐1030 PDT
Call‐in:
888‐363‐4735 Access Code: 8699774 Security Code: 1234
Attendees:
USACE:
Jason Tanamor Mike Booton Terry Geroux Kate Groth Steve Straw Liz Smock
Contractors and Port Reps:
Greg Morrill, Bergerson Construction Mark Sutton, Dixon Marine Services
Introduction: The purpose of this meeting is to openly share information and discuss the project and assumptions prior to the solicitation being issued. Any items discussed are subject to change, and the final solicitation set should be reviewed when posted. This is now a planned dredging contract, and all communication regarding this contract should go through the proper channels.
Corps of Engineers Roles and Responsibilities:
USACE: Primary Members of the Product Deliver Team:
Karla Ellis, Chief, Waterways Maintenance
Terry Geroux, Dredging Contracts Team Lead
Liz Smock, Technical Lead
Todd Hash, Technical Team Member
Kate Groth, Coastal Project Manager
Travis Davidson, Construction Branch
David Dvorak, Contracting Officer
Jason Tanamor, Contract Specialist
Post‐Award: Vancouver Resident Office:
Travis Davidson, Resident Engineer / ACO
Project Engineers and COR to be determined after award
Input/Support from Project Manager and Dredging Contracts
Contract Schedule (Projected Dates):
Public Review 25 APR – 06 May 2019
Advertise 28 MAY 2019
Bid Opening 27 JUN 2019
Award 10 JUL 2019
NTP 15 JUL 2019
Project Start 29 JUL 2019
Scope:
o Garibaldi, OR
Main channel and partial boat basin access channel
40,000 CY Base, 10,000 CY Option
Flow‐Lane placement – less than 1 mile (approx. 1500‐4700 ft.)
Water Quality Monitoring by instrument for dredging and placement areas
In‐Water work window 15 JUL – 15 MAR o Depoe Bay, OR
Depoe Bay (Full Federal Limit)
15,000 CY Base, 5,000 CY Option
Flow‐Lane placement – less than 1 mile (approx. 450‐1500 ft.)
In‐Water work window 1 JUL – 15 MAR
Water Quality Monitoring by instrument for dredging area only o Discussion Points
Tidal restriction at Garibaldi. Ebb tide discharge only.
Depoe Bay dredge prism includes docks with boats; material under docks and boats is payable, but not a factor for acceptance of work.
Questions and Answers o Q: Does the discharge pipe need to be moved within the Depoe Bay placement area?
A: There is no requirement to move the discharge pipe at Depoe Bay placement area but there is a requirement to evenly disperse the material throughout the disposal site and to demonstrate Quality Control measures for how to accomplish that.
o Additional clarification for Garibaldi placement area to identify the requirement to move the discharge pipe three times per day during daylight hours.
o Q: Will Water Quality Monitoring be required for the placement area at Depoe Bay?
A: No. (The requirements have been identified above under each project scope.)