Questions_and_Answers__1.pdf

PDF 9 KB Posted

Attached to
History of the Portland District - 2000 to 2015
Solicitation number
W9127N-16-R-0075
Issued by

About this file

Questions and Answers 1 08/09/2016

View the file

Other files

File Type Posted
W9127N-16-R-0075-0001.pdf PDF
W9127N-16-R-0075.pdf PDF
Past_Performance_Questionnaire.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation W9127N-16-R-0075 History of the Portland District – 2000 to 2015

Questions and Answers #1

Question 1.

The requirements for key personnel (Tab 3) indicate that the “majority” of the research and writing for this project shall be completed by a historian with a Ph.D. Would the Portland District consider having the work product is overseen by a PhD but the book is written by a historian with specialized historical knowledge of USACE history and operations and has written histories for other Districts?

Answer:

It is ok, so long as the product is overseen by a PhD. Amendment 0001 has been issued to cover this change in the requirement.

Question 2.

The Past Performance Questionnaire (Tab 2), could you clarify what is meant by: “Offerors shall not incorporate by reference into their proposal PPQs or CPARS previously submitted for other solicitations.”

Answer:

This is a complex way to say that the PPQ or a CPARS rating cannot be referred to as being a document found in another proposal. The actual PPQ MUST be submitted. Your proposal shall not make similar reference to a CPARS report submitted with another proposal.