This document is an amendment to a solicitation for the design and construction of facilities at Tyndall Air Force Base in Florida. The amendment revises the submission deadline for Phase Two proposals to April 29, 2021 at 2:00 PM local time and reduces the number of required copies from five to three. It also modifies the evaluation criteria for past performance by limiting relevant experience to projects completed within the last eight years for prime contractors and six years for lead design firms, and adjusting the dollar value range for relevant projects. The solicitation is for the design and construction of a Weapons Evaluation Group headquarters facility, maintenance hangar, and aircraft parking apron at Tyndall AFB. The WEG HQ and hangar will provide office, operations, and maintenance space. The apron will support aircraft parking and servicing. The selected offeror will be required to begin work within eight calendar days of award and complete all work within the time defined in their proposal.

View the file

Other files

File Type Posted
EM 385-1-1.pdf PDF
20R0028 PHASE ONE SPECS.PDF PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

1 2

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE 4. REQUISITION/PURCHASE 5. PROJECT NO. (If applicable)

W9127820R0028-0001 5 APR 2021 MEF20037, MEF20038, MBF20010

6. ISSUED BY CODE 7. ADMINISTERED BY(If other than item 6)

CODE

Corps of Engineers 109 St. Joseph St.

Mobile, AL 36602

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP code) 9A. AMENDMENT OF SOLICITATION

NO.

W9127820R0028

9B. DATED (SEE ITEM 11)

15 MAR 2021

10A. MODIFICATION OF

CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE

FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (if required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO AUTHORITY OF FAR 43.103(b)

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible) The subject solicitation for: TWO-PHASE DESIGN/BUILD ZONE 3 WEG HQ/MAINTENANCE HANGAR AND APRON FACILITIES, TYNDALL AIR FORCE BASE, FLORIDA

Is modified in the following: REFER TO THE ENCLOSED SPECIFICATION REVISIONS FOR AMENDMENT NO. 0001.

NOTE: THE RECEIPT OF PROPOSAL DATE IS HEREBY REVISED BY THIS AMENDMENT. REFER TO THE ENCLOSED SF1442, SOLICITATION, OFFER & AWARD FORM.

Except as provided herein, all terms and conditions of the document reference in item 9A or 10A, as Heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICE (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

BY

(Signature of contracting officer)

16C. DATE SIGNED

NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV. 10-83)

PREVIOUS EDITION UNUSABLE Prescribed by GSA

TWO-PHASE DESIGN/BUILD ZONE 3 WEG HQ/MAINTENANCE HANGAR W9127820R0028

AND APRON FACILITIES, TYNDALL AFB, FLORIDA MEF20037, MEF20038 & MBF20010

SF 30 Page 2 Amendment No. 0001

PART I-REVISIONS MADE BY ADDED AND/OR REPLACEMENT PARAGRAPHS/PAGES/SECTIONS

The items listed below are to be replaced by the corresponding added and/or revised paragraphs/pages or sections. Added and/or revised paragraphs/pages or sections are indicated by a note in bottom right hand corner of each paragraph or page. Added sections are hereby made a part of the contract and are to be inserted in the specification in the proper numerical/alphabetical sequence.

Within the specifications, deletions from the specifications are indicated by strikethrough, e.g.: deletions are marked with strikethrough and additions to the specifications including revisions/substitutions are indicated in bold, italic and underlined, e.g.: additions are indicated thus.

Corresponding Added or Revised Paragraph SECTION Page, and/or Section

SF1442, Solicitation, Offer & Award Form Revised Block 13.A as indicated herein.

00 11 00 Revised Paragraphs 4.2 and 4.3

Encl as stated:

Revised and reissued pages of the specifications as indicated in Part I.

SOLICITATION, OFFER

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

W9127820R0028

2. TYPE OF

SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED

15 MAR 2021

PAGES OF PAGES

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

6. PROJECT NO.

MEF20037, MEF20038 & MBF20010

7. ISSUED BY CODE CT 8. ADDRESS OFFER TO

U.S. ARMY ENGINEER DISTRICT, MOBILE

CONTRACTING DIVISION (CESAM-CT)

109 SAINT JOSEPH STREET

MOBILE, AL 36628-0001

SAME AS BLOCK 7

9. FOR INFORMATION

CALL : Amanda Milheiser Richard Bonnell Carl Wade

A. NAME

Amanda.M.Milheiser@usace.army.mil Richard.Bonnell@usace.army.mil Carl.M.Wade@usace.army.mil

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

(251) 694-3858

(251) 694-3607

(251) 690-2348

SOLICITATION

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):

TWO-PHASE DESIGN/BUILD ZONE 3 WEG HQ/MAINTENANCE HANGAR AND APRON FACILITIES, TYNDALL AIR FORCE BASE, FLORIDA

* See Section 01 00 00, Paragraph “COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK”. (TO BE PROVIDED IN PHASE TWO) **Block 13A. : Refer to Section 00 11 00 for the number of copies to submit with the original offer.

11. The Contractor shall begin performance within _8____ calendar days and complete it within __*__ calendar days after receiving award, notice to proceed.

This performance period is mandatory, negotiable. (See _ __ .)

12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

YES NO

12B. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and ___**___ copies to perform the work required are due at the place specified in Item 8 by _1400_ (hour) local time 15 29 APR 2021 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is, is not required for the Phase Two proposal submission.

C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than __120__calendar days for Government acceptance after the date Phase Two offers are due will not be considered and will be rejected.

NSN 7540-01-155-3212 1442-101

STANDARD FORM 1442(REV. 4-85)

Prescribed by GSA FAR(48 CFR) 53.236-1(e)

REVISED BY AMENDMENT NO. W9127820R0028-0001

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14)

CODE FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within _________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation - give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER

(Type or print)

20B. SIGNATURE 20C. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) ( ) 41 U.S.C. 253(c) ( )

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (contractor is required to sign this document and return _______ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work, requisitions identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award,

(b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED

TO SIGN (Type or print)

31A. NAME OF CONTRACTING OFFICER (Type or print)

30B. SIGNATURE

30C. DATE 31B. UNITED STATES OF AMERICA

BY

31C. AWARD

DATE

STANDARD FORM 1442 BACK (REV. 4-85)

REISSUED BY AMENDMENT NO. W9127820R0028-0001

SECTION 00 11 00

Revised by Amendment No. W9127820R0028-0001

00 11 00

4.2 Volume II - Factor 1 – Past Performance Information of the Prime Contractor. The Past Performance of the Prime Contractor (Offeror) consists of (a) Relevant Company Effort and (b) Quality of Past Performance. The Government will review recent, relevant company efforts and quality information provided by the owners of those efforts to assess the Offeror’s past experience and probability of successfully performing the work described in this solicitation. For this factor, a recent, relevant project is a construction project:

(a) Performed under a contract or task order, as those terms are defined in FAR 2.101, for the Federal Government, or similar contractual agreements for State or Local Governments, or the commercial or private sector. (Multiple projects under a single contract or task order are considered one project. However, do not combine multiple projects under separate contracts or task orders to create a single project.);

(b) That is “recent”; one that has been completed within ten (10) eight

(8) years of the solicitation issue date, or one where the construction is at least 50% complete (measured by performance period days) as of the solicitation issue date. (Offerors are responsible for providing start and completion dates for each completed project, or the start and scheduled completion dates for projects currently under construction.);

(c) That is “relevant”; one that is similar in scope (type, size, complexity and dollar value) to the project types described in this solicitation. In terms of dollar value, a relevant project is one ranging from $100M to $250M; however, projects outside of this dollar range may be considered when similar in scope and complexity. For a project to be assessed any degree of “relevancy” it must reflect performance of requirements as described by this solicitation.

(Note: The remainder of Paragraph 4.2 is unchanged by this amendment.)

4.3 Volume II - Factor 2 – Past Performance Information of the Lead Design Firm. The Past Performance of the Lead Design Firm consists of (a) Relevant Company Effort and (b) Quality of Past Performance. The Government will review recent, relevant company efforts and quality information provided by the owners of those efforts to assess the Lead Design Firm’s past experience and probability of successfully performing the work described in this solicitation. For this factor, a recent, relevant project is a design project:

(a) Performed under a contract or task order, as those terms are defined in FAR 2.101, for Federal Government, or similar contractual agreements for State or Local Governments, or the commercial or private sector. (Multiple projects under a single contract or task order are considered one project. However, do not combine multiple projects under separate contracts or task orders to create a single project.);

SECTION 00 11 00

Revised by Amendment No. W9127820R0028-0001

(b) That is “recent”; one that has been completed within ten (10) six

(6) years of the issue date. (Lead Design Firm’s are responsible for providing start and completion dates for each completed project);

(c) That is “relevant”; one that is similar in scope (type, size, complexity and dollar value) to the project types described in this solicitation. In terms of dollar value, a relevant project is one ranging from $100M to $250M; however, projects outside of this dollar range may be considered when similar in scope and complexity. For a project to be assessed any degree of “relevancy” it must reflect performance of design and construction requirements as described by this solicitation. The description of the project is as stated in paragraph 4.2 above.

(Note: The remainder of the section is unchanged by this amendment.)