1 Summay Price Cost All Years
| Allatoona Lake |
| Summary Price/Costs - All Years |
| Solicitation No. W9127818R0014 |
Technical Provision(s) Base Year Option Yr 1 Option Yr 2 Option Yr 3 Option Yr 4 Total
Firm Fixed Price (TPs 2-6) $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
Total Firm Fixed Price: $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
Cost Plus Fixed Fee (TPs 7-17)
| Direct Labor | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Labor Burden | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Material & Supplies | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Other Direct Costs | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Subcontract Costs | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Costs | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| G&A Costs | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Costs + G&A | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Fixed Fee | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Cost Plus Fixed Fee | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
Contract Total $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
2 Estimated Costs by TP
| Allatoona Lake |
| Estimated Costs by Technical Provision |
| TP# - TP Description/Title |
| Solicitation No. W9127818R0014 |
Cost Element Hours Rate Base Year Option Yr 1 Option Yr 2 Option Yr 3 Option Yr 4 Total
| Direct Labor (List all that apply): | ||||||||
| Labor Category 1 | - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Labor Category 2 | - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Labor Category 3 | - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Labor: | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Labor Burden: | ||||||
| Labor Burden | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Labor + Labor Burden | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Materials & Supplies | ||||||
| List Each Mat'l and Supply Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Material & Supplies | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Other Direct Costs (ODC), (List all that apply): | ||||||
| ODC Item 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| ODC Item 2 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| ODC Item 3 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total ODC | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Subcontracts (List all that apply): | ||||||
| Subcontract 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Subcontract 2 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Subcontract 3 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Subcontracts | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
Total Direct Costs $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| G&A Costs | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Cost + G&A | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Fixed Fee: | |||||||
| % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
TOTAL - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
3 Limit on Sub
| Limitations on Subcontracting | |||||||
| Allatoona Lake | |||||||
| Soliciation No. W9127818R0014 | |||||||
| Base Year | OPTION 1 | OPTION 2 | OPTION 3 | OPTION 4 | TOTAL | ||
| A | Total Prime Labor Cost (NOT INCLUDING SUBCONTRACT LABOR) | $ | $ | $ | $ | $ | $ |
| B | Total Subcontracting Labor | $ | $ | $ | $ | $ | $ |
| C | Total Labor Cost | $ | $ | $ | $ | $ | $ |
| D | Limitation on Subcontracting Percentage | % | % | % | % | % | % |
| EXAMPLE: |
| A = Total Prime Labor = $3,000,000.00 |
| B = Total Subcontract Labor = $5,000,000.00 |
| C = Total Labor Costs = A + B = $8,000,000 |
| D = Limitation on Subcontracting Percentage = (B / C) = $5,000,000.00 / $8,000,000.00 = 62.5% |
| NOTE: |
| This percentage shall not be more than 50% for the offeror to be considered |
| for award. Therefore, the example given is NOT an acceptable bid. |