AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
1. Acknow ledge this amendment in block 14 of the SF33.
2. The due date for receipt of proposals remain as previously established, June 5, 2018, 2:00pm central time.
3. Changes are denoted by strikethrough, bold and/or italic fonts w here section replacements are provided.
4. Section C, Technical Provisions (TPs) is hereby revised. Remove entire section and replace w ith attached revision. A change has been made at paragraph 7.4.
5. Section L, Instructions to Offerors is hereby revised. Make a "pen and ink" change at Paragragraph 3.0 Volume II Price/Cost Proposal and add the follow ing submission: d. Listing of Labor Categories and Hourly Rates for TPs 2-6 denoting DOL/non-DOL.
1. CONTRACT ID CODE PAGE OF PAGES
U 1 60
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 18-May-2018
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9127818R0014
X 9B. DATED (SEE ITEM 11)
28-Mar-2018
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
18-May-2018
CODE
ENDIST MOBILE CONTRACTING DIVISION
109 ST JOSEPH ST
MOBILE AL 36602
W91278 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9127818R0014
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
The following have been added by full text:
REVISED TECHNICAL PROVISIONS
Descriptions/Specifications/Work Statement Technical Provisions (TPs)
Allatoona Lake
TP-1 General Information
TP-2 Management
TP-3 Cleaning, Custodial Services, and Refuse Removal
TP-4 Maintenance of Grass, Landscaped Areas, Saddle Dikes, and Trees
TP-5 Operation of Visitor Center
TP-6 Boundary Line Clearing and Maintenance
TP-7 Maintenance of Buildings, Structures, Facilities, Trails, Mechanical, Plumbing, and Electrical Systems
TP-8 Maintenance of Signs, Barricades, Bumper Blocks, Posts, Guardrails, Gates, Fencing, Fire Extinguishers, and Traffic Counters
TP-9 Beach Maintenance, Aids to Navigation, and Courtesy Deck Maintenance
TP-10 Natural Resource Management, Pest Species Control, Driftwood Removal, Limb Trimming, and Tree Cutting
TP-11 General Maintenance and Repair of Paved and Unpaved Roads, Parking Areas, Launching Ramps, Road Shoulders, and Drainage Structures
TP-12 Maintenance of Government-Owned Vehicles and Equipment
TP-13 Personnel and Equipment Support for Powerhouse
TP-14 Hazardous Waste Operations and Emergency Response (HAZWOPER)
TP-15 Emergency Services for Saddle Dikes
TP-16 Shoreline and Rip-Rap Repair
TP-17 Recreation Facility Repairs
TP-1 - GENERAL INFORMATION
TP-1.0 Purpose: The purpose of this contract is to provide for the operation, maintenance, and repair of the Allatoona Lake Project, as described below.
TP-1.1 Intent: It is the intent of the following technical provisions to procure for the Government, complete and efficient operation, maintenance, and repair on the Allatoona Lake Project. Allatoona Lake is on the Etowah River in Northwest Georgia-, approximately 40 miles north of Atlanta, Georgia. The project is situated in Bartow, Cobb, and Cherokee Counties, Georgia. Cities around the project include Cartersville, Canton, Woodstock and Acworth, Georgia. Site maps may be reviewed at the Allatoona Lake Operations Project Management Office, Allatoona Lake, off Georgia Highway 20 Spur, 4 miles from the intersection of I-75 and Georgia Highway 20. Additional information about the project is also available on the Internet at http://www.sam.usace.army.mil/Missions/Civil-Works/Recreation/Allatoona-Lake/. Technical Provisions 2-6 are the Fixed Price portion of the contract. Supervision and management of this contract (Technical Provisions 2 – 17) shall be the responsibility of the contractor’s management team. The management team shall include competent personnel to supervise and take care of everyday work assignments. The Contractor will be responsible for furnishing all personnel, materials, supplies and other items as necessary to accomplish requirements as specified herein.
Technical Provisions 7-17 are the Cost Reimbursable portion of the contract. The Contractor will be responsible for furnishing all personnel, materials, supplies, and other items as necessary to accomplish requirements as specified herein and will be reimbursed for all allowable and allocable costs, in accordance with the Federal Acquisition Regulation (FAR) and Cost Accounting Standards (CAS). The Contractor shall assure that all services are conducted in accordance with the contract and all applicable laws, regulations, codes, or directives.
Performance shall be in accordance with all Terms, Conditions, General, Specific and Technical Provisions, Drawings, and Attachments contained herein or incorporated by reference.
TP- 1.2 Procuring Contracting Officer: The Procuring Contracting Officer (PCO) has the overall responsibility for administration of the contract requirements. The PCO has the authority to administer, terminate, or modify the contract. The PCO is responsible for ensuring that all necessary actions are taken to achieve effective contract administration and that the Contractor complies with the provisions of the contract. Some responsibilities may be delegated to the
COR.
TP-1.3 Contracting Officer’s Representative (COR)/Government Representative: The COR provides feedback to the PCO in the administration of the contract requirements. The COR maintains direct communication with the Contractor and verifies that the Contractor performs the technical requirements of the contract. The COR accepts and approves services performed under the contract and may re-direct the Contractor on any item of work requirement pending correction of a deficiency.
TP-1.4 Quality Assurance Representative (QAR) and Specialized Inspectors (SI): The QAR/SI receives and reviews the Contractor’s submittals, plans, charts, and reports for accuracy and completeness, and recommends appropriate action to the COR. The QAR/SI performs random inspections to determine if the contract requirements are being met and if the Contractor’s Quality Control Plan is being implemented effectively. The QAR/SI advises the COR of contract status, deficiencies, recommended actions, and other information pertinent to the administration of the contract.
TP-1.5 Contractor Employees: All Contractor personnel utilized in performance of the contract shall be legal residents of the United States. Personnel shall be able to read, write, speak, and understand the English language to the extent necessary in adequately reading and understanding regulations and instructions to complete and safely perform the contract services.
TP-1.6 Contractor Personnel Identification and Appearance: Contractor personnel shall present a neat appearance and be easibly recognized as Contractor employees. The Contractor shall provide each employee with a uniform (i.e. pant and shirt) bearing the name of the corporation. Uniforms shall be worn by the Prime Contractor employees at all times while performing work under this contract and all Contractor employees (both prime and subcontractor) shall be distinct from the public and Government personnel.
TP-1.7 Employee Conduct: The majority of work will be performed in the presence of the general public. All contract employees shall conduct themselves in a proper manner at all times.
The Contractor shall be responsible for insuring that its employees strictly comply with all Federal, State, and Local laws. The COR may require the Contractor to immediately remove from the work site any employee of the Contractor or subcontractor, who, in the opinion of the COR, is incompetent, or is under the influence of alcohol or drugs, or endangers persons or property, or is negligent in the use of safety equipment or established safety policies or procedures, or interferes with or impedes the public use of the project, or engages in criminal activity, or whose physical or mental condition is such that it would impair the employee's ability to safely or satisfactorily perform their work. Repeated or ongoing safety infractions shall be grounds for dismissal. Notification of objection by the COR will be made promptly to the Contractor in writing if time or circumstances permit. These requirements shall not be the basis of any claim for compensation and/or damages against the United States and/or any of its officers or agents. In addition, no such removal will reduce the Contractor's obligation to perform all the work under this contract and immediate replacement will be made as required.
TP-1.8 Employee Capability: All Contractor employees performing work under this contract shall be physically able to do their assigned work. The Contractor shall not allow any employee(s) under the influence of alcohol or is incapacitated by restricted substances to perform any work.
TP-1.9 Cooperation with Other Contractors and Government Personnel: The Government may award contracts for additional and/or similar work. The Contractor shall cooperate with such other Contractors, its employees and/or Government employees, as directed by the Contracting Officer’s Representative (COR). The Contractor shall not commit or permit any act of interference in the performance of work of other Contractors or Government employees.
TP-1.10 Non-Personal Services. The Government shall neither supervise Contractor employees nor control the method by which the Contractor performs the required tasks. Under no circumstances shall the Government assign tasks to, or prepare work schedules for, individual Contractor employees. It shall be the responsibility of the Contractor to manage its employees and to guard against any actions that are of the nature of personal services, or give the perception of personal services. If the Contractor believes that any action(s) constitute, or are perceived to constitute personal services, it shall be the Contractor’s responsibility to notify the Procuring Contracting Officer (PCO) immediately.
TP-1.11 Maps: Recreation area and access road maps are included in this contract showing general mowing and litter pickup limits. Note that these maps are approximate and only included for offerors information only. It is the responsibility of each offeror to conduct site visits prior to submitting proposals. Some locations, including trails, riprap on dams, and herbicide application areas are not shown on these maps.
TP-1.12 Criteria and Publications: The Contractor shall perform all work in accordance with applicable publications to include, but not limited to, the listing below:
Safety:
EM 385-1-1 (Corps of Engineer’s Safety Manual) EP 310-1-6a and EP 310-1-6b (U. S. Army Corps of Engineers’ Sign Standards Manual) Environmental Review Guide for Operations
Equipment Manufacturer's:
Operating Manuals Repair Manuals
Industrial Standards and Codes: (Latest Editions) Air Moving and Conditioning Association American Association of Nurserymen, Inc.
American Concrete Institute American Institute of Steel Construction American Society of Heating, Air-Conditioning and Air-Conditioning and Refrigeration Institute American Society of Heating, Refrigeration and Air-Conditioning Engineers American Society for Testing and Materials American National Standards Institute American Welding Society Architectural Aluminum Manufacturers Association Architectural Graphics Standards Asphalt Institute Consumer Products Safety Commissions Handbook for Public Playground Safety International Fire Code with Georgia Amendments National Association of Architectural Metal Manufacturers National Association of Fan Manufacturers National Electrical Code
National Fire Protection Association National Plumbing Codes Standards Illustrated National Warm Air and Air Conditioning Association Portland Cement Association Sheet Metal Manufacturers SBCCI Standard Building Code with Georgia Amendments SBCCI Standard Gas Code with Georgia Amendments The Aluminum Association Underwriter's Laboratories, Inc.
Other General Services Administration (GSA) guidelines and schedules for vehicle maintenance.
EM 1110-1-400 Engineering and Design –Recreation Facility and Customer Services and Standards-
TP-1.13 Site Closures, Consolidations, and Responsibilities: Facilities or recreational areas may be subject to lease, closure, and/or consolidation at any time. As a result of a lease, closure, and/or consolidation, the number and type of facilities located in each area may fluctuate on a temporary and/or permanent basis. The Contractor’s work schedule must be sufficiently flexible to meet these changing needs. All closure and/or consolidation actions will be done only with approval of the COR.
TP-1.14 Key Control: The Government will issue Contractor personnel keys to all locked areas that will be operated and maintained by the Contractor. The Contractor shall establish and implement methods of ensuring all keys issued to the Contractor by the Government are not lost or misplaced and are not used by unauthorized persons. No keys issued to the Contractor shall be duplicated. The Contractor shall immediately report any occurrences of lost or duplicated keys to the COR. The Contractor shall prohibit the use of Government issued keys by any persons other than the Contractor’s employees. The Contractor shall prohibit the opening of locked areas by Contractor employees to permit entrance of persons other than Contractor employees or personnel authorized by the COR.
TP-1.15 Accident Reporting: The Contractor is responsible for reporting all accidents to the COR immediately. Prompt action shall be taken to ensure immediate and appropriate medical treatment. Initial notification will be verbal with follow-up in writing as directed by the COR.
The Contractor shall maintain an accurate record of any accident(s) in the manner and on the forms prescribed by the COR for each type of accident. The Contractor shall maintain an OSHA 300 Log of On-the-Job injuries and first aid treatments.
TP-1.16 Safeguarding Government Property: The Contractor shall cooperate with Government personnel in safeguarding Government property. The Contractor shall ensure that all contract personnel are aware of the responsibility to be good stewards of Government property entrusted to them. The Contractor may be held liable for damaged, stolen or lost Government property due to negligence. When it is determined that the Government is due compensation, the Contracting Officer will issue a written request to the Contractor. Any equipment that breaks and is no longer useable shall be reported to the COR for disposal. If not due to negligence, the item may be replaced at Government discretion and expense. The Contractor shall be responsible for reporting to the COR, QAR, or any ranger on duty, all acts of vandalism, larceny, pilferage, or damage within 24 hours after discovery by the Contractor.
The COR will insure that local law enforcement personnel are notified. On a monthly basis, the Contractor will provide a consolidated report of property damage, acts of vandalism, larceny, pilferage or other damages or loss of Government facilities maintained by the Contractor.
TP-1.17 Damage or Loss of Contractor’s Supplies and Property: The Contractor is responsible for taking the action necessary to protect Contractor supplies, materials and the personal property of Contractor employees form loss, damage or theft. The Government assumes no responsibility for theft, damage, etc., of the above. All incidents of theft (or suspected theft) of contractor materials, supplies, or personal property from project lands shall be reported to the COR.
TP-1.18 Pre-Work Conference: The contractor shall attend a pre-work conference prior to the start of work and no later than 15 days after award of contract. During this conference, the COR will establish the line of authority and government procedures for contractual, administrative and work matters. A review of critical aspects of the contract will be conducted as well as attention brought to specific FAR, technical and special contract clauses. A thorough review, discussion and understanding of the firm fixed price and cost reimbursement technical provisions will be reached. A letter of record documenting all pre-work conference discussions will be furnished by the government to all attendees. The contractor shall submit at the pre-work conference, or as otherwise required and appropriate in the specifications, the following draft plans, programs and certificates:
- Section H Required Insurance
- TP-1.19.1 Accident Prevention Plan (Draft)
- TP-1.19.2 Contractor Quality Control Plan (Draft)
- TP-1.19.3 Inventory Control and Property Management Plan (Draft)
- TP-1.19.4 Facility Maintenance Plan (Draft)
- TP-1.19.5 Invasive Species and Pest Control Plan (Draft)
- TP-1.19.6 Spill Prevention and Response Plan (Draft)
- TP-1.19.7 Hazardous Energy Plan (Draft)
- TP-1.19.8 Employee Uniform and Identification Plan (Final)
- TP-1.19.9 Purchasing Plan (Final)
Review and approval of all draft plans will be performed by the Government within 15 days of submission for final submission of documents within 30 days of contract award.
TP-1.19 Plans: Submission of the following plans will be a requirement of the contract.
TP-1.19.1 Accident Prevention: The Contractor shall submit a detailed Accident Prevention Plan (APP) in accordance EM 385-1-1. The EM 385-1-1 version in place at time of award will govern the contract performance period unless changed by contract modification. Interim approval of this plan shall be obtained before starting work. The APP shall interface with the Contractor’s overall safety and health program, and the Contactor shall include any portions referenced in the APP in the applicable APP element and made site-specific. The Government considers the Prime Contractor to be the “controlling authority” for all work site safety and health of the Subcontractors. Contractors are responsible for the informing their subcontractors of the safety provisions under the terms of the contract and the penalties for noncompliance, coordinating the work to prevent one craft from interfering with or creating hazardous working conditions for other crafts, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out.
TP-1.19.2 Contractor Quality Control (CQC): The Contractor will establish a comprehensive quality control program and submit a Quality Control Plan detailing the Contractor’s plan to assure compliance with the contract specifications. The plan should describe quality control concepts, purpose, and provide a general program overview. It should address the methods to be utilized to ensure that the CQC program is effective and efficient, including the inspection program to be utilized to ensure quality control goals are met. It should also include the frequency and schedule for inspecting significant project facilities and how corrective measures will be applied. The plan should address the interaction and coordination efforts that will occur between the Contractor and Government personnel involved in Quality Assurance. The plan will be in sufficient detail to indicate to the Government that the Contractor is cognizant of the contract requirements. The plan should show the duties of the QC person and to whom this person reports deficiencies to. In no case shall the QC person be responsible for collateral duties that will interfere with the daily inspection routine. The QC person may not at any time be responsible for the project when the Project Manager is sick or otherwise not on site. A matrix should be provided showing the responsibility of each supervisor and how the QC person will relate deficiencies up the chain of command. In addition to the above, the plan should address the following areas of concern:
a. Indoctrination and training of personnel, to assure employees are knowledgeable of their work assignments and regulations or guidelines pertaining to their assignments such as fire reporting, safety, erosion of embankments, etc.
b. Employee performance and evaluation.
c. Identification of declines in quality of product and how substandard performance and deficiencies will be corrected.
d. Employee health and hygiene.
e. Security of facilities and equipment (including key control).
f. Maintenance of facilities and equipment.
g. Proper reporting of maintenance needs by Contractor employees.
h. Preparation and submission of required reports to appropriate Government personnel.
Determination of work required to maintain and repair facilities, buildings, structures, and systems in a safe and efficient operating condition is the responsibility of the Contractor. The COR, however, may direct the Contractor to perform repairs or maintenance if deficiencies are observed. This notification may be verbal or in writing. The Contractor shall respond as soon as possible, but no later than 24 hours after notification to repair such work items, unless otherwise approved by the COR. Failure to respond within these guidelines without acceptable justification may be counted against the Contractor as evidence of unsatisfactory performance in evaluation for award fees.
QC Inspections shall include subcontractor performance, inventory control, and procurement of supplies. Government QA inspectors will assure that the CQC plan is being implemented and is effective, but the presence or absence of a Government inspector shall not relieve the Contractor of responsibility for the proper execution of work in accordance with the specifications.
Compliance inspections shall be documented and records of deficiencies observed and corrective actions taken shall be furnished to the Government. If recurrent deficiencies indicate that the quality control system is inadequate, corrective action will be taken as directed by the COR. The COR must approve any proposed changes to the plan prior to their implementation.
TP-1.19.3 Inventory Management and Property Control: The Contractor shall submit Contractor’s recommendation for Government Furnished Property (GFP) stock items and levels for approval of the COR. Contractor’s Inventory Management and Property Control Plan, including control of Government property, shall be implemented upon approval. The inventory control program will utilize FEM. The Contractor shall inventory existing stock items and materials available at the beginning of the contract and shall input the results of the inventory into FEM. The plan shall contain provisions to protect, preserve, account for, and control all GFP from its acquisition to disposition. The following will be documented in FEM:
The name, description, and NSN/NCN Quantity received (or fabricated), issued, and on hand Unit price Contract number or equivalent code designation Location Disposition Posting reference and date of transaction Bar Code Serial Number (if applicable) Manufacturer Summary price for all property
The plan will be forwarded to the Property Administrator (PA) for approval. If for any reason the plan is disapproved, the PA will notify the Contractor in writing, requesting prompt correction of deficiencies. If the Contractor does not correct the deficiencies within a reasonable period, the PA will:
1. Notify the Contractor in writing of any required corrections and establish a schedule for completion of actions.
2. Caution the Contractor that failure to take the required corrective actions within the time specified will result in withholding or withdrawing plan approval.
3. Advise the Contractor that its liability for loss of or damage to Government property will increase if approval is withheld or withdrawn.
All property furnished to the Contractor will be controlled by means of the established inventory list. This inventory list will be maintained by the Contractor and will be in FEM. It will include all property which is currently in use by the Contractor and any additional property items procured throughout the life of the contract and assigned to the Contractor. The purchase of new accountable-property items will require approval of the Contracting Officer.
The Contractor will designate, in writing, a Contractor Property Officer (CPO), who will be responsible for maintaining accountability and record keeping. This individual will be a management official and may be assigned other duties by the Contractor.
An interim inventory management and property control system may be utilized by the Contractor with the approval of the COR. This interim system will only be utilized until the proper training and credentials for use of the FEM system are accomplished by the Contractor.
Excess/Disposal/Returns: All property returned by the Contractor to the Government, for whatever reason, will be accompanied with the property records. The CPO will notify the COR when serviceable GFP equipment is not needed to perform the work and otherwise will remain inactive.
The COR will review the Contractor’s inventory as frequently as conditions warrant. These reviews will take place at any time during contract performance, upon contract completion or termination, or at any time thereafter during the period the Contractor is required to retain such records. The Contractor will make all such records and related correspondence available to the
COR.
TP-1.19.4 Facilities Maintenance: The Contractor shall submit a quarterly and annual plan for all routine maintenance and duties covered by the specifications. In addition, the Contractor shall prepare weekly schedules detailing all planned activities. A weekly schedule of upcoming work will be provided to the COR at least seven (7) days in advance. The frequency of submittal of plans and schedules may be adjusted as needed and directed by the COR.
Work incidental or related to contract work items, but not specifically identified or described in each section, may be required of the Contractor. This work will be accomplished by the existing work force utilizing existing equipment and will be performed by rescheduling and/or reapportioning the Contractor’s long range and weekly schedules, as approved by the COR.
TP-1.19.5 Invasive Species and Pest Control: The Contractor will be required to develop a Pest Control Plan for Allatoona Lake Project to control or eradicate undesirable plants, animals, and insects by chemical, mechanical, or biological means. Submit the Invasive Species and Pest
Control Plan to the COR within 30 days of commencing work. The Invasive Species and Pest Control Plan shall list chemicals to be used, storage procedures, pesticide application rates, areas to be treated, capture and disposal procedures for animal pests, disposal procedures for unused pesticides and empty pesticide containers, record keeping procedures, applicator licensing procedures, material safety data sheets, and user and public safety measures. The plan shall not be implemented until it is approved by the COR. Contractor shall provide labor, supplies, and equipment necessary to implement the plan.
Control or eradicate unwanted vegetation such as kudzu (typically 2-4 acres annually), autumn olive (typically 2-5 acres annually), Chinese privet, poison ivy (near campsites and other public use sites), vegetation in riprap, brush along rights-of-way, and weeds and grass growing in impact sites, sidewalks, and roadways.
Animal pests may include any domestic animal or nuisance wild animal within any public use area, as well as mice or rats in buildings and other structures and any other animal identified by the COR. Capture domestic animals using live traps, snares, or other acceptable methods. After capture, dispose of these animals in a humane manner and in compliance with applicable local, state, and federal laws. Make a reasonable effort to identify and return captured domestic animals to their owners. Advise the COR immediately upon the determination of the identity of the owner of a domestic animal.
TP-1.19.6 Spill Prevention and Response: The Contractor shall develop a plan to address required response/cleanup effort. This plan will include any associated subcontractors, vendors, or technical advisement that the Contractor would use during the spill event, equipment and material requirements/methods of procurement, methods of response, and levels/sources of training for response personnel.
TP-1.19.7 Hazardous Energy: The Contractor shall develop a plan to address lines of authority during a lock out/tag out event. Explain how personnel will be protected and warned when equipment is being worked on that requires a LOTO procedure. Explain how this system will meet or exceed the National Electrical Code.
TP-1.19.8 Employee Uniform and Identification: The Contractor shall provide a brief plan addressing how his employees will be identified at times while work is being performed.
TP-1.19.9 Purchasing Plan (applicable for Cost Reimbursable portion of the contract): The Contractor shall provide a brief plan outlining his plan for acquiring items for reimbursable work at the project. The Contractor shall maintain a purchasing system which will assure efficiency in expending Government funds. The Federal Acquisition Regulation (FAR) shall be used as a guide in establishing purchasing procedures and standards commensurate with the policies and techniques contained therein. The Contractor shall afford Small Business concerns an equitable opportunity to compete for all contracts they can perform. The Contractor's purchasing system is subject to review and approval by the Contracting Officer. Title to all property acquired by the Contractor in this manner shall inure to the Government for which it was purchased upon receipt by the Contractor.
The Contractor may not purchase any piece of equipment or property which would require placement on the Contractor's property account without prior approval. Lost, damaged, or destroyed items may not be replaced or repaired without prior approval. In the event that emergency repairs are required, and it is not possible to obtain advance procurement approval from the COR, the Contractor is authorized and shall be required to procure those parts necessary to affect immediate repair in order to protect personnel and/or property. The Government reserves the right to make major purchases for the Contractor through other Government sources at any time.
TP-1.20 Antiterrorism and Operations Security (AT/OPSEC) Requirements: In accordance with OPORD 2013-74, Annex A, the following paragraphs apply to this requirement.
TP-1.20.1 AT Level I Training: All contractor employees, to include subcontractor employees, requiring access to Army installations, facilities, controlled access areas, or require network access, shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. Upon request, the contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer (if a COR is not assigned), within 5 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website:
http://jko.jten.mil/courses/atl1/launch.html; or it can be provided by the RA ATO in presentation form which will be documented via memorandum.
TP-1.20.2 Access and General Protection/Security Policy and Procedures: All contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.
TP-1.20-3 For Contractors requiring Common Access Card (CAC): The contractor and all sub-contractors employees will be issued a CAC only if duties involve one of the following: (1) Both physical access to a DoD facility and access, via logon, to DoD networks on-site or remotely; (2) Remote access, via logon, to a DoD network using DoD-approved remote access procedures; or (3) Physical access to multiple DoD facilities or multiple non-DoD federally controlled facilities on behalf of the DoD on a recurring basis for a period of 6 months or more.
At the discretion of the sponsoring activity, an interim CAC may be issued based on a favorable review of the FBI fingerprint check and a successfully scheduled NACI at the Office of Personnel Management.
TP-1.20.4 For Contractors who do not require CAC, but require access to a DoD Facility or Installation: The contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05 / AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative, as NCIC and TSDB are available), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
TP-1.20.5 Suspicious Activity Reporting Training (e.g. iWATCH, CorpsWatch, or See Something, Say Something): The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after the completion of the training.
TP-1.20.6 Contractor Employees Who Require Access to Government Information Systems: All contractor employees with access to a government info system must be registered in the Army Training Certification Tracking System (ATCTS) at commencement of services, and must successfully complete the DOD Information Assurance Awareness prior to access to the information systems and then annually thereafter in accordance with personnel security standards listed in AR 25-2 (Information Assurance), an appropriate background investigation will be conducted prior to accessing the government information systems.
TP-1.20.7 For Contracts that Require OPSEC Training: All new contractor employees will complete Level I OPSEC Training within 30 calendar days of their reporting for duty.
Additionally, all contractor employees must complete annual OPSEC awareness training. The contractor shall submit certificates of completion for each affected contractor and subcontractor employee, to the COR or to the contracting officer (if a COR is not assigned), within 5 calendar days after completion of training. OPSEC awareness training is available at the following websites: https://www.iad.gov/ioss/ or http://www.cdse.edu/catalog/operations-security.html; or it can be provided by the RA OPSEC Officer in presentation form which will be documented via memorandum."
TP-1.20.8 For Information Assurance (IA)/Information Technology (IT) Training: All contractor employees and associated sub-contractor employees must complete the DoD IA awareness training before issuance of network access and annually thereafter. All contractor employees working IA/IT functions must comply with DoD and Army training requirements in DoDD 8570.01, DoD 8570.01-M and AR 25-2 within six months of employment."
TP-1.20.9 Pre-screen candidates using E-Verify Program: The Contractor must pre-screen candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The vendor must ensure that the candidate has two valid forms of Government-issued identification prior to employment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible candidates must be provided to the COR no later than 3 business days after the initial contract award. When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, with the designated Government representative. This form will be provided to the Contracting Officer and shall become part of the official contract file.
TP-2 - MANAGEMENT
TP-2.0 Scope: The Contractor shall provide adequate personnel on site to conduct appropriate management and administrative duties for all work occurring on this contract. These functions include, but are not limited to supervision, personnel management, work planning, scheduling, quality control, maintenance data entry, record keeping, office clerk duties, safety, and property management. Multiple responsibilities can be held by single employees, with the exception of the QC Inspector. For purposes of this contract, crew lead responsibilities are not considered managerial in nature. As a minimum, staffing should reflect:
TP-2.1 Managerial Staff: The on-site management staff must be led by someone that has the authority to act on behalf of the contractor, to make contract decisions and answer to the COR for any discrepancies that may require immediate attention. The person designated as “Project Superintendent” shall have at least 5 years’ experience in the type of work as described in the following Technical Provisions. The Management Plan must explain who will represent the Superintendent in their absence. This person must have the same experience as the Project Superintendent. When authority is passed to another person it must be done so in writing to the
COR.
TP-2.2 Quality Control Inspector: The Contractor is responsible for ensuring that all work performed under this contract, including any performed by subcontractors, is in accordance with specifications and workmanship standards. The Contractor shall have competent quality control inspector personnel to ensure that the Contractor’s Quality Control Plan is functioning as required. The Quality Control person shall report directly to the home office personnel and should not have major collateral duties, such as being on site to replace the project manager or superintendent in their absence. The presence of a Government inspector shall not relieve the Contractor of responsibility for the proper execution of the work in accordance with the technical provisions.
TP-2.3 Administrative: The Contractor is responsible for the management and stewardship of all Government furnished equipment. The Contractor shall ensure that the Contractor’s Inventory Management and Property Control Plan is functioning as required.
TP-2.4 FEM Work Order System: FEM (Facility & Equipment Maintenance System) work Order system and forms will be used for this contract for asset management and tracking. FEM is the USACE version of commercial, off the shelf maintenance software “Maximo”. The Government will provide computers and network connections for Contractor use. A Common Access Card will be required to use the computer and system. The Contractor will create repair work orders by inputting data to include labor hours, material costs, and brief summary of the work completed into FEM and change work order status when work is complete. A work order will be input into the system prior to the work occurring unless it is emergency work or a safety hazard. The Government is responsible for approving the status of FEM work orders. The COR will close the work order once the work has been completed and inspected. The Contractor will be provided training and access to the FEM system after contract award. The Government will be responsible for maintenance of FEM functionality.
TP-2.5 Minimum Personnel Qualifications: Technicians, tradesmen, consultants, and key personnel shall have the education and/or experience to enable them to adequately understand the systems and components to be operated, maintained, and repaired under these specifications.
The Contractor shall provide an adequate and efficient number of fully qualified personnel to supervise, maintain, repair, inspect, and operate the project in accordance with these specifications. The Contractor shall inform the COR of personnel status monthly.
TP-2.6 Subcontracts: Subcontractors may be utilized to perform specialized work or one-time type repair work. In some instances and for some duties, contract employees may be required to undergo background investigations prior to performing the duties.
TP-2.7 Key Personnel Changes: Any time there are changes in the Contractor’s key personnel, the Contractor will notify the COR in writing as soon as practical.
TP-2.8 Removal of Contractor’s Employees: The COR may direct the immediate removal of any Contractor employee who is incompetent, or endangers persons or property, or whose physical or mental conditions is such that it would impair the employees’ ability to perform his work. Notification for removal will be in writing. Notification will be made by telephone, and later confirmed in writing if time and circumstances warrant. The Contractor shall take action to replace any dismissed employee.
TP-2.9 Communication Devices and Responsibilities: The Contractor shall procure telephone line and fax for the Contractor’s Maintenance Compound. The Contractor shall also procure sufficient cell phones to provide adequate telephone communications between the Government and Contractor’s superintendent and communication between the Contractor and his employees.
Any repairs or replacements of these devices will be the responsibility of the Contractor.
Maximum of five desk top computers will be provided by the Government. These will be utilized to perform various duties such as inventory control, maintenance management, Facilities and Equipment Maintenance (FEM) system, and the use of the Government e-mail system. This will require Common Access Cards (CAC) for the Contractor’s management and administrative staff who utilize the Government furnished computer equipment and network. Any software utilized by the Contractor for contract management will be subject to approval by the Government prior to installation. Any repairs or replacement of these devices will be the responsibility of the Government.
TP-2.10 Government-Furnished Facilities: The Government will furnish the Contractor office space, storage facilities, and operational facilities described in Section J or other areas defined in specific technical provisions. The Government will provide water and electric power for these facilities. The Contractor may modify them to meet work requirements after prior approval of the
COR.
TP-2.11 Government-Furnished Property: The Government will provide equipment and vehicles listed in Section J to perform work requirements outlined in all Technical Provisions. In the event an item is required that is not in the Contractor’s inventory, the Contractor will obtain prior approval from the COR prior to renting or otherwise acquiring such equipment. Some equipment may be shared between the Contractor and the Government. If both the Government workforce and the Contractor have a simultaneous demand for a piece of equipment listed for joint use, the Government will have priority. The Contractor will be responsible for the maintenance and repair of Government-owned equipment and GSA vehicles utilized on the project utilizing Government owned facilities, appropriate vendor relationships, or subcontracts with outside sources.
TP-2.12 Contractor-Furnished Materials and Supplies: The Contractor will be responsible for supplying and maintaining sufficient materials and supplies to satisfactorily perform the requirements of Technical Provisions 2-6 on a fixed price basis. The specific requirements for these materials and supplies are contained in each respective technical provision. Materials and supplies identified as the responsibility of the Contractor in those technical provisions will be reflected in the proposal price by the Contractor, and will not be cost reimbursable items.
TP-2.13 Vehicle Specifics: All vehicles utilized on this contract shall be presentable, serviceable, must meet all safety requirements set forth in EM 385-1-1, and shall comply with all applicable state and federal motor vehicle regulations. Any vehicle utilized under this contract that is found deficient shall be removed from the project. No vehicles shall be left unattended for any extended periods of time at any recreation area without prior approval of the COR. Vehicles shall be secured overnight at the Contractor’s O&M Maintenance Area compound. Vehicles shall be operated in accordance with posted regulations and traffic control signs and devices. The COR will closely monitor the Contractors speed in the contract area. All vehicles shall be identified with professionally made magnetic signs or pressure sensitive vinyl type decals with company name and/or logo displayed on both sides. Sign design, at a minimum will consist of company name, type of business, address, and telephone number displayed with 2” or larger lettering.
TP-2.14 Performance Evaluation Meetings: The Contractor, Superintendent, or both shall meet with the COR weekly or as determined necessary to the COR. However, a meeting shall be held not later than one (1) normal workday after a discrepancy has been reported. Mutual effort will be made to resolve problems identified.
TP-2.15 Contractor Quality Control (CQC): Contractor Quality Control (CQC) is the means by which the Contractor ensures all work complies with the contract requirements. The Contractor shall develop, implement and maintain and effective CQC plan and program.
TP-2.16 Compliance Inspections: Compliance inspections shall be recorded on a form approved by the COR. Documentation to monitor quality control, to include records of deficiencies observed and corrective action(s) taken shall be furnished to the Government. When an observation indicates defective performance, the COR or QAR shall require the Contractor representative at the site to initial the observation. The initialing of the observation does not necessarily constitute concurrence with the observation; only acknowledgement that he or she has been made aware of the defective performance. The QC reports shall be provided to the COR weekly.
TP-2.17 Corrective Action: At any time it is determined by the COR that the quality control system, personnel, instructions, controls, tests, or records are not providing results which conform to contract…