This document summarizes a federal contract solicitation for repair and renovation services at a dining facility located at Fort Hood, Texas. The U.S. Army Corps of Engineers Engineering District Fort Worth is seeking bids for a firm-fixed price contract between $1 million and $5 million to replace electrical, mechanical, and architectural finishes and upgrade the facility to current Army standards for dining facilities. The solicitation will be issued on July 23, 2021 with bids due in September and contract award anticipated later that month. The project is a total small business set-aside under NAICS code 236220 with a size standard of $39.5 million. The period of performance is 480 days from notice to proceed. Interested parties must register with the System for Award Management to be eligible for award. The primary point of contact is the named contract specialist.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04 EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The Solicitation for Repair DFAC Building 56425, Fort Hood, Texas is amended as follows.
See SF30 Continuation Sheet(s)
NOTE: Bid Receipt date and time has changed from August 27, 2021, 10:00am CT. To September 02, 2021, 10:00am CT
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA 15C. DATE SIGNED 15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer) (Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X 9A. AMENDMENT OF SOLICITATION NO.
W9126G21B0004
X 9B. DATED (SEE ITEM 11)
23-July-2021
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
26 -Aug-2021
CODE
US ARMY ENGINEER DISTRICT, FORT WORTH
ATTN: CESWF-CT
819 TAYLOR ST, ROOM 2A19
P.O. BOX 17300
FORT WORTH TX 76102-0300
W9126G 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODE CODE
EMAIL: TEL:
W9126G21B0004
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
CHANGES TO SOLICITATION W9126G21B0004
1. Bid Receipt Date: Change the proposal receipt date from " time August 27, 2021, 10:00am CT " to " September 02, 2021, 10:00am CT ".
2. Replacement Sections: Replace the following section with the accompanying new section of the same number and title bearing the notation W9126G21B0004 0002
00 21 00 - INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS
05 05 23.16 - STRUCTURAL WELDING
05 12 00 - STRUCTURAL STEEL
08 51 13 - ALUMINUM WINDOWS
FORT HOOD PRIVATIZED UTILITY PROVIDER POINTS OF DEMARCATION is an attachment to section 01 35 10.00 44 SPECIAL PROJECT PROCEDURES FOR FORT HOOD
3. Replacement Drawings.- Replace the drawings listed below with the attached new drawings(s) of the same number bearing the notation W9126G21B0004 0002
A-131 A-621 A-822
CU101
QF001
QF501
End of Summary of Changes
Section 00 21 00 - Instructions, Conditions and Notices to Offerors
SEALED BIDDING INSTRUCTIONS
SEALED BIDDING
INSTRUCTIONS, CONDITIONS, AND NOTICE TO OFFERORS
1. INQUIRIES
OFFEROR'S QUESTIONS AND COMMENTS
All questions and/or comments are to be submitted via ProjNet.
Bidder Inquiry in ProjNet at http://www.projnet.org/projnet
To submit and review bid inquiry items, bidders will need to be a current registered user or self-register into system. To self-register go to web page, click BID tab select Bidder Inquiry, select agency USACE, enter Key for this solicitation listed below, and your e-mail address, click login.
Fill in all required information and click create user. Verify that information on next screen is correct and click continue.
From this page you may view all bidder inquiries or add inquiry.
Bidders will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed.
The Solicitation Number is: W9126G21B0004 The Bidder Inquiry Key is: 2ANHGC-6NR8DT
Last day to submit ProjNet questions is 5 calendar days prior to bid closure date in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary.
Offerors are requested to review the specification in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.
The call center operates weekdays from 8AM to 5PM U.S. Central Standard Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.
2. INSTRUCTIONS TO OFFERORS
SPECIAL INSTRUCTIONS PERTAINING TO ELECTRONIC BIDS SUBMISSION (FAR
14.302 & 14.304)
a. All bids and a electronic copy of the SF24 Bid Bond MUST be received via email to
W9126G21B0004 0002 richard.feller@usace.army.mil and no later than, (AM-0002) 2 27 24 September August 2021, 10:00 AM (Central Time). (AM-0002) No original will be accepted. NO LATE
BIDSWILL BE OPENED.
b. Electronically submitted offers must include the completed SF 1442 (in accordance with FAR 52.214-18), Acknowledgement of all amendments, completed CLIN schedule, completed Section 00 45 00 and a copy of the original Bid Bond.
c. Offers received will be publicly opened at the following location:
US Army Engineer District, Fort Worth 819 Taylor St, Room 2A17 Fort Worth, TX 76102 (AM-0002) 2 27 24 September August 2021 (AM-0002) 2:00 PM (Central Time)
d. Teleconference Dial-in Information for the public is:
Call-in: 1-844-800-2712 (AM-0001) Meeting number (access code): 199 424 7158 1990 88 3534 (AM-0001) (AM-0001) *Press # when prompted to enter attendee ID number* (AM-0001)
e. Please note, oral explanations or instructions are not binding. Any information given to an Offeror which impacts the solicitation and/or offer will be given in the form of a written amendment to the solicitation.
f. SENDING FILES. In an effort to reduce paperwork and reduce cost, all bids shall be submitted electronically. All submissions should be in Adobe PDF format.
Title the file(s) in the following format:
W9126G21B0004_COMPANY NAME_DESCRIPTION
Upload Completion & Deadline. Interested parties shall submit responses no later than the date specified on solicitation document. The time & date of bid receipt will be the upload completion / delivery time & date recorded.
g. Original copies of the Bid Bond shall be submitted to the following point of contact two (2) business days after the bid due date.
US Army Engineer District, Fort Worth ATTN: Richard Feller 819 Taylor St, Room 2A17 Fort Worth, TX 76102-0300
h. FACSIMILE OFFERS. Facsimile offers, modifications thereto, or cancellations of offers will
NOT BE ACCEPTED.
i. EMAIL. Modifications and cancellations of offers will be accepted if received by the time specified in the solicitation.
k. RESPONSIBILITY. Award will be made to the lowest, responsible bidder whose bid, conforming to the invitation for bids, will be the most advantageous to the Government. To be determined responsible, the apparent low bidder shall:
(1) Have adequate financial resources to perform the contract, or the ability to obtain them. The contractor will be required to provide the Name of the Financial Institution, POC, and phone number.
(2) Have a satisfactory performance record. The contractor shall have no performance annotated with an individual rating of less than SATISFACTORY within the last six years.
(3) Have a satisfactory record of integrity and business ethics. Awardee will be required to provide at least three (3) references for like work, to include Business Name, Point of Contact, and telephone number.
(4) Have the necessary organization, experience, accounting and operational controls, and technical skills, or the ability to obtain them (including, as appropriate, such elements as production control procedures, property control systems, quality assurance measures, and safety programs applicable to materials to be produced or services to be performed by the prospective contractor and subcontractors).
(5) Have the necessary production, construction, and technical equipment and facilities, or the ability to obtain them; and
(6) Be otherwise qualified and eligible to receive an award under applicable laws and regulations
3. NOTIFICATION OF UNSUCCESSFUL BIDDERS. All contract award information for this solicitation will be published electronically on SAM.gov at www.sam.gov Solicitation Number W9126G21B0004. Written unsuccessful bidder letters will not be issued.
4. PREPROPOSAL CONFERENCE / SITE VISIT
SITE VISIT. See FAR clause 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) –
ALTERNATE I (FEB 1995)
IMPORTANT NOTES. (1) Remarks and explanations addressed during the conference shall not qualify or alter the terms and conditions of the solicitation. (2) The terms and conditions of the solicitation remain unchanged unless the solicitation is formally amended in writing.
CLAUSES INCORPORATED BY REFERENCE
52.204-6 Unique Entity Identifier OCT 2016 52.204-7 System for Award Management OCT 2018 52.204-22 Alternative Line Item Proposal JAN 2017 52.214-35 Submission Of Offers In U.S. Currency APR 1991 52.232-13 Notice Of Progress Payments APR 1984 252.236-7006 Cost Limitation JAN 1997 252.236-7008 Contract Prices-Bidding Schedules DEC 1991
CLAUSES INCORPORATED BY FULL TEXT
52.211-14 NOTICE OF PRIORITY RATING FOR NATIONAL DEFENSE, EMERGENCY PREPAREDNESS, AND ENERGY PROGRAM USE (APR 2008)
Any contract awarded as a result of this solicitation will be ( ) DX rated order; ( X ) DO rated order certified for national defense, emergency preparedness, and energy program use under the Defense Priorities and Allocations System (DPAS) (15 CFR 700), and the Contractor will be required to follow all of the requirements of this regulation.
(End of provision)
52.214-3 AMENDMENTS TO INVITATIONS FOR BIDS (DEC 2016)
(a) If this solicitation is amended, then all terms and conditions which are not modified remain unchanged.
(b) (1) Bidders shall acknowledge receipt of any amendment to this solicitation--
(i) By signing and returning the amendment;
(ii) By identifying the amendment number and date in space provided for this purpose on the form for submitting a bid;
(iii) By letter;
(iv) By facsimile, if facsimile bids are authorized in the solicitation; or
(v) By email, if email bids are authorized in the solicitation.
(2) The Government must receive the acknowledgement by the time and at the place specified for receipt of bids.
52.214-4 FALSE STATEMENTS IN BIDS (APR 1984)
Bidders must provide full, accurate, and complete information as required by this solicitation and its attachments.
The penalty for making false statements in bids is prescribed in 18 U.S.C. 1001.
52.214-5 SUBMISSION OF BIDS (DEC 2016)
(a) Bids and bid modifications shall be submitted in sealed envelopes or packages (unless submitted by electronic means) (1) addressed to the office specified in the solicitation, and (2) showing the time and date specified for receipt, the solicitation number, and the name and address of the bidder.
(b) Bidders using commercial carrier services shall ensure that the bid is addressed and marked on the outermost envelope or wrapper as prescribed in subparagraphs (a)(1) and (2) of this provision when delivered to the office specified in the solicitation.
(c) Facsimile bids, modifications, or withdrawals, will not be considered unless authorized by the solicitation.
(d) Bids submitted by electronic commerce shall be considered only if the electronic commerce method was specifically stipulated or permitted by the solicitation.
52.214-7 LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS (NOV 1999)
(a) Bidders are responsible for submitting bids, and any modifications or withdrawals, so as to reach the Government office designated in the invitation for bids (IFB) by the time specified in the IFB. If no time is specified in the IFB, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that bids are due.
(b)(1) Any bid, modification, or withdrawal received at the Government office designated in the IFB after the exact time specified for receipt of bids is “late” and will not be considered unless it is received before award is made, the Contracting Officer determines that accepting the late bid would not unduly delay the acquisition; and--
(i) If it was transmitted through an electronic commerce method authorized by the IFB, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of bids; or
(ii) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of bids and was under the Government's control prior to the time set for receipt of bids.
(2) However, a late modification of an otherwise successful bid that makes its terms more favorable to the Government, will be considered at any time it is received and may be accepted.
(c) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the bid wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.
(d) If an emergency or unanticipated event interrupts normal Government processes so that bids cannot be received at the Government office designated for receipt of bids by the exact time specified in the IFB and urgent Government requirements preclude amendment of the IFB, the time specified for receipt of bids will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.
(e) Bids may be withdrawn by written notice received at any time before the exact time set for receipt of bids. If the IFB authorizes facsimile bids, bids may be withdrawn via facsimile received at any time before the exact time set for receipt of bids, subject to the conditions specified in the provision at 52.214-31, Facsimile Bids. A bid may be withdrawn in person by a bidder or its authorized representative if, before the exact time set for receipt of bids, the identity of the person requesting withdrawal is established and the person signs a receipt for the bid.
52.214-18 PREPARATION OF BIDS--CONSTRUCTION (APR 1984)
(a) Bids must be (1) submitted on the forms furnished by the Government or on copies of those forms, and (2) manually signed. The person signing a bid must initial each erasure or change appearing on any bid form.
(b) The bid form may require bidders to submit bid prices for one or more items on various bases, including--
(1) Lump sum bidding;
(2) Alternate prices;
(3) Units of construction; or
(4) Any combination of subparagraphs (1) through (3) above.
(c) If the solicitation requires bidding on all items, failure to do so will disqualify the bid. If bidding on all items is not required, bidders should insert the words "no bid" in the space provided for any item on which no price is submitted.
(d) Alternate bids will not be considered unless this solicitation authorizes their submission.
52.214-19 CONTRACT AWARD--SEALED BIDDING--CONSTRUCTION (AUG 1996)
(a) The Government will evaluate bids in response to this solicitation without discussions and will award a contract to the responsible bidder whose bid, conforming to the solicitation, will be most advantageous to the Government, considering only price and the price-related factors specified elsewhere in the solicitation.
(b) The Government may reject any or all bids, and waive informalities or minor irregularities in bids received.
(c) The Government may accept any item or combination of items, unless doing so is precluded by a restrictive limitation in the solicitation or the bid.
(d) The Government may reject a bid as nonresponsive if the prices bid are materially unbalanced between line items or subline items. A bid is materially unbalanced when it is based on prices significantly less than cost for some work and prices which are significantly overstated in relation to cost for other work, and if there is a reasonable doubt that the bid will result in the lowest overall cost to the Government even though it may be the low evaluated bid, or if it is so unbalanced as to be tantamount to allowing an advance payment.
(End of provison)
52.214-34 SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE (APR 1991)
Offers submitted in response to this solicitation shall be in the English language. Offers received in other than English shall be rejected.
52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a firm fixed price (FFP) contract resulting from this solicitation.
(AM-0001)
52.217-5 EVALUATION OF OPTIONS (JUL 1990)
Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
(AM-0001)
52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT--CONSTRUCTION MATERIALS (MAY 2014)
(a) Definitions. “Commercially available off-the-shelf (COTS) item,” “construction material,” “domestic construction material,” and “foreign construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Buy American --Construction Materials” (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers. (1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign construction material not listed by the Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested--
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.
The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-
(c) The amount of the bid guarantee shall be twenty (20%) percent of the bid price or $3,000,000.00, whichever is less.-
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
52.233-2 SERVICE OF PROTEST (SEP 2006)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from U.S. Army Corps of Engineers, Fort Worth District, 819 Taylor Street, Rm 2A17 (Attn: CESWF-CT), Fort Worth, Texas 76102-0300. E-mail: john.h.rodgers@usace.army.mil.
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for--
See Section 00 21 30
(c) Participants will meet at--
See Section 00 21 30
52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
https://www.acquisition.gov/content/regulations
52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (APR 1984)
(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of"(DEVIATION)" after the date of the provision.
(b) The use in this solicitation of any DFARS (48 CFR Chapter 2) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
DFAC 56425 Repair and Renovation FH20B56425
SECTION 05 05 23.16
STRUCTURAL WELDING
AMENDMENT 0002
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN INSTITUTE OF STEEL CONSTRUCTION (AISC)
AISC 360 (2016) Specification for Structural Steel Buildings
AMERICAN SOCIETY FOR NONDESTRUCTIVE TESTING (ASNT)
ANSI/ASNT CP-189 (2016) ASNT Standard for Qualification and Certification of Nondestructive Testing Personnel (ANSI/ASNT CP-105-2006)
AMERICAN WELDING SOCIETY (AWS)
AWS A2.4 (2012) Standard Symbols for Welding, Brazing and Nondestructive Examination
AWS D1.1/D1.1M (2015; Errata 1 2015; Errata 2 2016) Structural Welding Code - Steel
AWS D1.3/D1.3M (2018) Structural Welding Code - Sheet Steel
AWS D1.4/D1.4M (2011) Structural Welding Code - Reinforcing Steel
AWS D14.4/D14.4M (2012) Specification for Welded Joints for Machinery and Equipment
AWS QC1 (2016) Specification for AWS Certification of Welding Inspectors
AWS Z49.1 (2012) Safety in Welding and Cutting and Allied Processes
ASTM INTERNATIONAL (ASTM)
ASTM E165/E165M (2012) Standard Practice for Liquid Penetrant Examination for General Industry
ASTM E709 (2015) Standard Guide for Magnetic Particle Examination
SECTION 05 05 23.16 Page 1
W9126G21B0004 0002W9126G21B0004 0002
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Welding Quality Assurance Plan ; G
SD-03 Product Data
Welding Procedure Qualifications ; G
Welder, Welding Operator, and Tacker Qualification
Previous Qualifications
Pre-Qualified Procedures ; G
Welding Electrodes and Rods
SD-06 Test Reports
Nondestructive Testing
Weld Inspection Log
SD-07 Certificates
Certified Welding Procedure Specifications (WPS)
Certified Brazing Procedure Specifications (BPS)
Certified Procedure Qualification Records (PQR)
Certified Welder Performance Qualifications (WPQ)
Certified Brazer Performance Qualifications (BPQ)
Certified Welding Inspector
Nondestructive Testing Personnel
1.3 QUALITY ASSURANCE
Except for pre-qualified (in accordance with AWS D1.1/D1.1M ) and previously qualified procedures, each Contractor performing welding must record in detail and qualify the welding procedure specification for any welding procedure followed in the fabrication of weldments. Conform welding procedure qualifications to AWS D1.1/D1.1M and to the specifications in this section. Submit for approval copies of the welding procedure specification and the procedure qualification records for each type of welding being performed. Submission of the welder, welding operator, or tacker qualification test records is also required. Approval
SECTION 05 05 23.16 Page 2 of any procedure, however, does not relieve the Contractor of the sole responsibility for producing a finished structure meeting all the specified requirements. Submit this information on the forms in Annex M of AWS D1.1/D1.1M . Individually identify and clearly reference on the detail drawings and erection drawings all welding procedure specifications, or suitably key them to the contract drawings. In case of conflict between this specification and AWS D1.1/D1.1M , this specification governs.
1.3.1 General Requirements
<AM#0002>Fabricate work in an AISC Certified Fabrication Plant, Category BU. Erect work by an AISC Certified Erector, Category CSE. </AM#0002>
a. For Structural Projects, provide documentation of the following:
(1) Component Thickness 1/8 inch and greater: Qualification documents (WPS, PQR, and WPQ) in accordance with AWS D1.1/D1.1M .
(2) Component Thickness Less than 1/8 inch : Qualification documents (WPS, PQR, and WPQ) in accordance with AWS D1.3/D1.3M .
(3) Reinforcing Steel: Qualification documents (WPS, PQR, and WPQ) in accordance with AWS D1.4/D1.4M .
b. For other applications, provide documentation of the following:
(1) Submit two copies of the Certified Welding Procedure Specifications (WPS) , Certified Brazing Procedure Specifications (BPS) and Certified Procedure Qualification Records (PQR) to the Contracting Officer for approval .
(2) Submit two copies of the Certified Welder Performance Qualifications (WPQ) and Certified Brazer Performance Qualifications (BPQ) to the Contracting Officer for approval within fifteen calendar days prior to any employee welding on the project material.
(3) Machinery: Qualification documents (WPS, PQR, and WPQ) in accordance with AWS D14.4/D14.4M .
1.3.2 Previous Qualifications
Welding procedures previously qualified by test in accordance with AWS D1.1/D1.1M , may be accepted for this contract without re-qualification, upon receipt of the test results, if the following conditions are met:
a. Testing was performed by an approved testing laboratory, technical consultant, or the Contractor's approved quality control organization.
b. The qualified welding procedure conforms to the requirements of this specification and is applicable to welding conditions encountered under this contract.
c. The welder, welding operator, and tacker qualification tests conform to the requirements of this specification and are applicable to welding conditions encountered under this contract.
SECTION 05 05 23.16 Page 3
1.3.3 Pre-qualified Procedures
Welding procedures which are considered pre-qualified as specified in AWS D1.1/D1.1M will be accepted without further qualification. Submit for approval a listing or an annotated drawing to indicate the joints not pre-qualified. Procedure qualification is mandatory for these joints.
1.3.4 Welder, Welding Operator, and Tacker Qualification
Each welder, welding operator, and tacker assigned to work on this contract must be qualified in accordance with the applicable requirements of AWS D1.1/D1.1M and as specified in this section. Welders, welding operators, and tackers who make acceptable procedure qualification test welds will be considered qualified for the welding procedure used within the applicable essential variables for welder qualification.
1.3.4.1 Previous Personnel Qualifications
At the discretion of the Contracting Officer, welders, welding operators, and tackers qualified by test within the previous 6 months may be accepted for this contract without re-qualification if all the following conditions are met:
a. Copies of the welding procedure specifications, the procedure qualification test records, and the welder, welding operator, and tacker qualification test records are submitted and approved in accordance with the specified requirements for detail drawings.
b. Testing was performed by an approved testing laboratory, technical consultant, or the Contractor's approved quality control organization.
d. The welder, welding operator, and tacker qualification tests conform to the requirements of this specification and are applicable to welding conditions encountered under this contract.
1.3.4.2 Certificates
Before assigning any welder, welding operator, or tacker to work under this contract, submit the names and certification that each individual is qualified as specified. State in the certification the type of welding and positions for which the welder, welding operator, or tacker is qualified, the code and procedure under which the individual is qualified, the date qualified, and the name of the firm and person certifying the qualification tests. Keep the certification current, on file, and furnish 3 copies.
1.3.4.3 Renewal of Qualification
Re-qualification of a welder or welding operator is required under any of the following conditions:
a. It has been more than 6 months since the welder or welding operator has used the specific welding process for which he is qualified.
b. There is specific reason to question the welder or welding operator's ability to make welds that meet the requirements of these specifications.
c. The welder or welding operator was qualified by an employer other than
SECTION 05 05 23.16 Page 4 those firms performing work under this contract, and a qualification test has not been taken within the past 12 months. Submit as evidence of conformance all records showing periods of employment, name of employer where welder, or welding operator, was last employed, and the process for which qualified.
d. A tacker who passes the qualification test is considered eligible to perform tack welding indefinitely in the positions and with the processes for which he/she is qualified, unless there is some specific reason to question the tacker's ability or there has been a gap greater than 6 months since he/she last used the process. In such a case, the tacker is required to pass the prescribed tack welding test.
1.3.5 Inspector Qualification
Submit certificates indicating that certified welding inspector s meet the requirements of AWS QC1. Submit qualifications for nondestructive testing personnel in accordance with the requirements of ANSI/ASNT CP-189 for Levels I or II in the applicable nondestructive testing method. Level I inspectors must have direct supervision of a Level II inspector.
1.3.6 Symbols and Safety
Use symbols in accordance with AWS A2.4 , unless otherwise indicated.
Follow safe welding practices and safety precautions during welding in conformance with AWS Z49.1 .
PART 2 PRODUCTS
2.1 SYSTEM DESCRIPTION
Conform the design of welded connections to AISC 360 , unless otherwise indicated or specified. Material with welds will not be accepted unless the welding is specified or indicated on the drawings or otherwise approved. Perform welding as specified in this section, except where additional requirements are shown on the drawings or are specified in other sections. Do not commence welding until welding procedures, inspectors, nondestructive testing personnel, welders, welding operators, and tackers have been qualified and the submittals approved by the Contracting Officer. Perform all testing at or near the work site.
Maintain records of the test results obtained in welding procedure, welder, welding operator, and tacker performance qualifications.
2.1.1 Pre-erection Conference
Hold a pre-erection conference prior to the start of the field welding, to bring all affected parties together and to gain a naturally clear understanding of the project and the Welding Procedure Specifications (WPS) (submitted for all welding, including welding done using pre-qualified procedures). Mandatory attendance is required by all Contractor's welding production and inspection personnel and appropriate Government personnel. Include as items for discussion: responsibilities of various parties; welding procedures and processes to be followed;
welding sequence (both within a joint and joint sequence within the building); inspection requirements and procedures, both visual and nondestructive testing; welding schedule; and other items deemed necessary by the attendees.
SECTION 05 05 23.16 Page 5
2.2 WELDING EQUIPMENT AND MATERIALS
Provide all welding equipment, welding electrodes and rods, welding wire, and fluxes capable of producing satisfactory welds when used by a qualified welder or welding operator. Use E70XX welding electrodes.
Provide welding equipment and materials that comply with the applicable requirements of AWS D1.1/D1.1M and . Submit product data on welding electrodes and rods .
PART 3 EXECUTION
3.1 WELDING OPERATIONS
3.1.1 Requirements
Conform workmanship and techniques for welded construction to the requirements of AWS D1.1/D1.1M and AISC 360 . When AWS D1.1/D1.1M and the AISC 360 specification conflict, the requirements of AWS D1.1/D1.1M govern.
3.1.2 Identification
Identify all welds in one of the following ways:
a. Submit written records to indicate the location of welds made by each welder, welding operator, or tacker.
b. Identify all work performed by each welder, welding operator, or tacker with an assigned number, letter, or symbol to identify welds made by that individual. The Contracting Officer may require welders, welding operators, and tackers to apply their symbol next to the weld by means of rubber stamp, felt-tipped marker with waterproof ink, or other methods that do not cause an indentation in the metal. Place the identification mark for seam welds adjacent to the weld at 3 foot intervals. Identification with die stamps or electric etchers is not allowed.
3.2 QUALITY CONTROL
Perform testing using an approved inspection or testing laboratory or technical consultant; or if approved, the Contractor's inspection and testing personnel may be used instead of the commercial inspection or testing laboratory or technical consultant. A Certified Welding Inspector must perform visual inspection on 100 percent of all welds. Document this inspection in the Visual Weld Inspection Log . Test 100% of CJP welds using ultrasonic testing per Table 6.2 of AWS D1.1/D1.1M . Test 100% of all PJP and fillet welds or as indicated by magnetic particle or dye penetrant testing. Verify the welds conform to paragraph STANDARDS OF ACCEPTANCE.
Conform procedures and techniques for inspection with applicable requirements of AWS D1.1/D1.1M , ASTM E165/E165M , and ASTM E709. Submit a Welding Quality Assurance Plan and records of tests and inspections.
3.3 STANDARDS OF ACCEPTANCE
Conform dimensional tolerances for welded construction, details of welds, and quality of welds with the applicable requirements of AWS D1.1/D1.1M and the contract drawings. Submit all records of nondestructive testing .
SECTION 05 05 23.16 Page 6
3.3.1 Nondestructive Testing
The welding is subject to inspection and tests in the mill, shop, and field. Inspection and tests in the mill or shop do not relieve the Contractor of the responsibility to furnish weldments of satisfactory quality. When materials or workmanship do not conform to the specification requirements, the Government reserves the right to reject material or workmanship or both at any time before final acceptance of the structure containing the weldment. Any indication of a defect is regarded as a defect, unless re-evaluation by nondestructive methods or by surface conditioning shows that no unacceptable defect is present. Submit all records of nondestructive testing in accordance with paragraph STANDARDS
OF ACCEPTANCE.
3.3.2 Destructive Tests
Make all repairs when metallographic specimens are removed from any part of a structure. Employ only qualified welders or welding operators, and use the proper joints and welding procedures, including peening or heat treatment if required, to develop the full strength of the members and joints cut and to relieve residual stress.
3.4 GOVERNMENT INSPECTION AND TESTING
In addition to the inspection and tests performed by the Contractor for quality control, the Government will perform inspection and testing for acceptance to the extent determined by the Contracting Officer. The work may be performed by the Government's own forces or under a separate contract for inspection and testing. The Government reserves the right to perform supplemental nondestructive and destructive tests to determine compliance with paragraph STANDARDS OF ACCEPTANCE.
3.5 CORRECTIONS AND REPAIRS
If inspection or testing indicates defects in the weld joints, repair defective welds using a qualified welder or welding operator as applicable. Conduct corrections in accordance with the requirements of AWS D1.1/D1.1M and the specifications. Repair all defects in accordance with the approved procedures. Repair defects discovered between passes before additional weld material is deposited. Wherever a defect is removed and repair by welding is not required, blend the affected area into the surrounding surface to eliminate sharp notches, crevices, or corners. After a defect is thought to have been removed, and before re-welding, examine the area by suitable methods to ensure that the defect has been eliminated. Repaired welds must meet the inspection requirements for the original welds.
-- End of Section --
SECTION 05 05 23.16 Page 7
SECTION 05 12 00
STRUCTURAL STEEL
AMENDMENT 0002
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN INSTITUTE OF STEEL CONSTRUCTION (AISC)
AISC 303 (2016) Code of Standard Practice for Steel Buildings and Bridges
AISC 325 (2017) Steel Construction Manual
AISC 326 (2009) Detailing for Steel Construction
AISC 341 (2016) Seismic Provisions for Structural Steel Buildings
AISC 360 (2016) Specification for Structural Steel Buildings
AISC 420 (2010) Certification Standard for Shop Application of Complex Protective Coating Systems
AISC DESIGN GUIDE 10 (1997) Erection Bracing of Low-Rise Structural Steel Buildings
AMERICAN SOCIETY FOR NONDESTRUCTIVE TESTING (ASNT)
ANSI/ASNT CP-189 (2016) ASNT Standard for Qualification and Certification of Nondestructive Testing Personnel (ANSI/ASNT CP-105-2006)
AMERICAN WELDING SOCIETY (AWS)
AWS A2.4 (2012) Standard Symbols for Welding, Brazing and Nondestructive Examination
AWS D1.1/D1.1M (2015; Errata 1 2015; Errata 2 2016) Structural Welding Code - Steel
AWS D1.8/D1.8M (2016) Structural Welding Code—Seismic Supplement
AWS QC1 (2016) Specification for AWS Certification of Welding Inspectors
SECTION 05 12 00 Page 1
ASME INTERNATIONAL (ASME)
ASME B46.1 (2009) Surface Texture, Surface Roughness, Waviness and Lay
ASTM INTERNATIONAL (ASTM)
ASTM A123/A123M (2017) Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products
ASTM A29/A29M (2016) Standard Specification for General Requirements for Steel Bars, Carbon and Alloy, Hot-Wrought
ASTM A307 (2014; E 2017) Standard Specification for Carbon Steel Bolts, Studs, and Threaded Rod 60 000 PSI Tensile Strength
ASTM A36/A36M (2014) Standard Specification for Carbon Structural Steel
ASTM A500/A500M (2018) Standard Specification for Cold-Formed Welded and Seamless Carbon Steel Structural Tubing in Rounds and Shapes
ASTM A53/A53M (2018) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless
ASTM A563 (2015) Standard Specification for Carbon and Alloy Steel Nuts
ASTM A6/A6M (2017a) Standard Specification for General Requirements for Rolled Structural Steel Bars, Plates, Shapes, and Sheet Piling
ASTM A780/A780M (2009; R 2015) Standard Practice for Repair of Damaged and Uncoated Areas of Hot-Dip Galvanized Coatings
ASTM A992/A992M (2011; R 2015) Standard Specification for Structural Steel Shapes
ASTM B695 (2004; R 2016) Standard Specification for Coatings of Zinc Mechanically Deposited on Iron and Steel
ASTM C1107/C1107M (2017) Standard Specification for Packaged Dry, Hydraulic-Cement Grout (Nonshrink)
ASTM C827/C827M (2016) Standard Test Method for Change in Height at Early Ages of Cylindrical Specimens of Cementitious Mixtures
ASTM F1136/F1136M (2011) Standard Specification for Zinc/Aluminum Corrosion Protective Coatings for Fasteners
SECTION 05 12 00 Page 2
ASTM F1554 (2018) Standard Specification for Anchor Bolts, Steel, 36, 55, and 105-ksi Yield Strength
ASTM F2329/F2329M (2015) Standard Specification for Zinc Coating, Hot-Dip, Requirements for Application to Carbon and Alloy Steel Bolts, Screws, Washers, Nuts, and Special Threaded Fasteners
ASTM F2833 (2011; R 2017) Standard Specification for Corrosion Protective Fastener Coatings with Zinc Rich Base Coat and Aluminum Organic/Inorganic Type
ASTM F3125/F3125M (2015a) Standard Specification for High Strength Structural Bolts, Steel and Alloy Steel, Heat Treated, 120 ksi (830 MPa) and 150 ksi (1040 MPa) Minimum Tensile Strength, Inch and Metric Dimensions
ASTM F436/F436M (2016) Standard Specification for Hardened Steel Washers Inch and Metric Dimensions
ASTM F844 (2007a; R 2013) Washers, Steel, Plain (Flat), Unhardened for General Use
ASTM F959/F959M (2017a) Standard Specification for Compressible-Washer-Type Direct Tension Indicators for Use with Structural Fasteners, Inch and Metric Series
SOCIETY FOR PROTECTIVE COATINGS (SSPC)
SSPC PA 1 (2016) Shop, Field, and Maintenance Coating of Metals
SSPC Paint 20 (2002; E 2004) Zinc-Rich Primers (Type I, Inorganic, and Type II, Organic)
SSPC Paint 29 (2002; E 2004) Zinc Dust Sacrificial Primer, Performance-Based
SSPC SP 3 (1982; E 2004) Power Tool Cleaning
SSPC SP 6/NACE No.3 (2007) Commercial Blast Cleaning
U.S. DEPARTMENT OF DEFENSE (DOD)
UFC 3-301-01 (2013; with Change 3) Structural Engineering
UFC 3-310-01 (2019) Structural Engineering
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR Part 1926, Subpart R Steel Erection
SECTION 05 12 00 Page 3
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Erection and Erection Bracing Drawings ; G,DO
SD-02 Shop Drawings
Fabrication Drawings Including Details of Connections; G,DO
SD-03 Product Data
Shop Primer
Welding Electrodes and Rods
Direct Tension Indicator Washers
Non-Shrink Grout
Tension Control Bolts
Recycled Content for Structural Steel ; S
Recycled Content for Structural Steel Tubing ; S
Recycled Content for Steel Pipe ; S
SD-05 Design Data
Design Calculations for Steel Connections ; G,DO
SD-06 Test Reports
Class B Coating
Bolts, Nuts, and Washers
Weld Inspection Reports
Direct Tension Indicator Washer Inspection Reports
Bolt Testing Reports
SD-07 Certificates
Steel
Bolts, Nuts, and Washers
Welding Procedures and Qualifications
SECTION 05 12 00 Page 4
Welding Electrodes and Rods
Certified Welding Inspector
NDT Technician
Welding Procedure Specifications (WPS)
<AM#0002>
1.3 AISC QUALITY CERTIFICATION
Work must be fabricated by an AISC Certified Structural Steel Fabricator, in accordance with AISC 207 , Category BU. Submit AISC Structural Steel Fabricator quality certification .
Work must be erected by an AISC Structural Steel Certified Erector, in accordance with AISC 207 , Category CSE. Submit AISC Structural Steel erector quality certification .
</AM#0002>
1.3 SEISMIC PROVISIONS
Provide the structural steel system in accordance with AISC 341 , Chapter J as amended by UFC 3-310-01 .
1.4 QUALITY ASSURANCE
1.4.1 Preconstruction Submittals
1.4.1.1 Erection and Erection Bracing Drawings
Submit for record purposes. Indicate the sequence of erection, temporary shoring and bracing. The erection drawings must conform to AISC 303 .
Erection drawings must be reviewed, stamped and sealed by a registered professional engineer.
1.4.2 Fabrication Drawing Requirements
Submit fabrication drawings for approval prior to fabrication. Prepare in accordance with AISC 303 , AISC 326 and AISC 325 . Fabrication drawings must not be reproductions of contract drawings. Sign and seal fabrication drawings by a registered professional engineer. Include complete information for the fabrication and erection of the structure's components, including the location, type, and size of bolts, welds, member sizes and lengths, connection details, blocks, copes, and cuts. Use AWS A2.4 standard welding symbols. Shoring and temporary bracing must be designed and sealed by a registered professional engineer and submitted for record purposes, with calculations, as part of the drawings. Clearly highlight any deviations from the details shown on the contract drawings highlighted on the fabrication drawings. Explain the reasons for any deviations from the contract drawings.
1.4.3 Delegated Connection Design
Design structural steel connection indicated in the contract documents per AISC 303 , Option 3, using the connection loads indicated. Submit design calculations for steel connections signed and sealed by a registered professional engineer.
SECTION 05 12 00 Page 5
1.4.4 Certifications
1.4.4.1 Welding Procedures and Qualifications
Prior to welding, submit certification for each welder stating the type of welding and positions qualified for, the code and procedure qualified under, date qualified, and the firm and individual certifying the qualification tests.