Base
| Base Year | |||||||
| CLIN # | Section 1-Campsite Maintenance | U/M | Unit Price | Unit Price | Estimated Quantity | Estimated Price | |
| Rounding Fix | |||||||
| A001 | CONCRETE WHEEL STOPS | EA | $60.00 | 1 | 0.00000 | ||
| A002 | TIMBER DELINIATORS, ONE TIER | LF | $8.00 | 1 | 0.00000 | ||
| A003 | TIMBER DELINIATORS,TWO TIER | LF | $8.00 | 1 | 0.00000 | ||
| A004 | TIMBER DELINIATORS, THREE TIER | LF | $8.00 | 1 | 0.00000 | ||
| A005 | TIMBER DELINIATORS, FOUR TIER | LF | $8.00 | 1 | 0.00000 | ||
| A006 | TIMBER DELINIATORS, TIER FIVE | LF | $8.00 | 1 | 0.00000 | ||
| A007 | UPRIGHT AND PEDASTAL GRILL INSTALLATION | LF | $30.00 | 1 | 0.00000 | ||
| A008 | FIRE RING AND GROUND MOUNTED COOKER INSTALLATION | EA | $25.00 | 1 | 0.00000 | ||
| A009 | LANTER HANGER POST INSTALLION | EA | $30.00 | 1 | 0.00000 | ||
| A010 | REPLACE/INSTALL VINYL COATED OR ALUMINIUM PICNIC TABLES | EA | $35.00 | 1 | 0.00000 | ||
| A011 | REPLACE/INSTALL PARK BENCHES | EA | $40.00 | 1 | 0.00000 | ||
| A012 | RETAINER WALL BLOCK INSTALLATION ONE | LF | $1.05 | 1 | 0.00000 | ||
| A013 | RETAINER WALL BLOCK INSTALLATION TWO | LF | $1.05 | 1 | 0.00000 | ||
| A014 | RETAINER WALL BLOCK INSTALLATION THREE | LF | $1.05 | 1 | 0.00000 | ||
| A015 | RETAINER WALL BLOCK INSTALLATION FOUR | LF | $1.05 | 1 | 0.00000 | ||
| A016 | RETAINER WALL BLOCK INSTALLATION FIVE | LF | $1.05 | 1 | 0.00000 | ||
| A017 | RIP RAP BAG INSTALLATION ONE | LF | $0.80 | 1 | 0.00000 | ||
| A018 | RIP RAP BAG INSTALLATION TWO | LF | $0.80 | 1 | 0.00000 | ||
| A019 | RIP RAP BAG INSTALLATION THREE | LF | $0.80 | 1 | 0.00000 | ||
| A020 | RIP RAP BAG INSTALLATION FOUR | LF | $0.80 | 1 | 0.00000 | ||
| A021 | RIP RAP BAG INSTALLATION FIVE | LF | $0.80 | 1 | 0.00000 | ||
| A022 | RIP RAP BAG INSTALLATION SIX | LF | $0.80 | 1 | 0.00000 | ||
| A023 | RIP RAP BAG INSTALLATION SEVEN | LF | $0.80 | 1 | 0.00000 | ||
| A024 | RIP RAP BAG INSTALLATION EIGHT | LF | $0.80 | 1 | 0.00000 | ||
| A025 | OTHER CAMPSITE MAINTENANCE | 0.00000 | |||||
| 0.00000 | |||||||
| Total Section 1 Base Year | 0.00000 | ||||||
| 0.00000 | |||||||
| CLIN # | Section 2-Carpentry and Painting | U/M | Unit Price | Unit Price | Estimated Quantity | Unit Price | ERROR:#VALUE! |
| 0.00000 | |||||||
| A026 | METAL PICNIC SHELTER INSTALLATION | EA | $605.00 | 1 | 0.00000 | ||
| A027 | ROOFING REMOVAL (COMPOSITION AND R-PANEL) | SF | $0.75 | 1 | 0.00000 | ||
| A028 | ROOF SHEATHING | SF | $1.45 | 1 | 0.00000 | ||
| A029 | TONGUE AND GROVE DECKING | SF | $1.81 | 1 | 0.00000 | ||
| A030 | FASCIA BOARD | LF | $10.45 | 1 | 0.00000 | ||
| A031 | COMPOSITION SHINGLE REPAIR/INSTALLATION | SF | $1.19 | 1 | 0.00000 | ||
| A032 | R-PANEL REPAIR/INSTALLATION | SF | $2.42 | 1 | 0.00000 | ||
| A033 | WALL SHEATING | SF | $1.34 | 1 | 0.00000 | ||
| A034 | SOFFIT SHEATHING | SF | $3.01 | 1 | 0.00000 | ||
| A035 | WALL SIDING | SF | $1.34 | 1 | 0.00000 | ||
| A036 | PLASTIC LAMINATE PANELS | SF | $2.51 | 1 | 0.00000 | ||
| A037 | LAP OR "V" GROOVED SIDING | SF | $2.34 | 1 | 0.00000 | ||
| A038 | TOILET PARTITION-SINGLE | EA | $181.00 | 1 | 0.00000 | ||
| A039 | TOILET PARTITION-DOUBLE | EA | $261.00 | 1 | 0.00000 | ||
| A040 | TOILET PARTITION-TRIPLE | EA | $341.00 | 1 | 0.00000 | ||
| A041 | SHOWER PARTITION | EA | $221.00 | 1 | 0.00000 | ||
| A042 | SHOWER/TOILET DOOR WITH PILASTER | EA | $161.00 | 1 | 0.00000 | ||
| A043 | URINAL PARTITION | EA | $141.00 | 1 | 0.00000 | ||
| A044 | PAINTING METAL PICNIC SHELTERS | SF | $0.97 | 1 | 0.00000 | ||
| A045 | PAINTING WOOD-OIL BASED PAINT | SF | $0.75 | 1 | 0.00000 | ||
| A046 | PAINTING WOOD-EXTERIOR LATEX PAINT | SF | $0.75 | 1 | 0.00000 | ||
| A047 | PAINTING WOOD-SEALER/STAIN | SF | $0.75 | 1 | 0.00000 | ||
| A048 | PAINTING WOOD-WATERPROOFING | SF | $0.75 | 1 | 0.00000 | ||
| A049 | PAINTING MASONRY-BLOCK SEALER/FILLER | SF | $0.75 | 1 | 0.00000 | ||
| A050 | PAINTING MASONRY-OIL BASED | SF | $0.75 | 1 | 0.00000 | ||
| A051 | PAINTING MASONRY-EXTERIOR LATEX PAINT | SF | $0.75 | 1 | 0.00000 | ||
| A052 | PAINTING METAL-OIL BASED PAINT | SF | $0.75 | 1 | 0.00000 | ||
| A053 | PAINTING METAL-EXTERIOR BASED PAINT | SF | $0.75 | 1 | 0.00000 | ||
| A054 | LOG VENEER SIDING | SF | $2.34 | 1 | 0.00000 | ||
| A055 | LOG SIDING | SF | $2.55 | 1 | 0.00000 | ||
| A056 | OTHER CARPENTRY AND PAINTING | 0.00000 | |||||
| 0.00000 | |||||||
| Total Section 2 Base Year | 0.00000 | ||||||
| 0.00000 | |||||||
| CLIN # | Section 3-Paving, Road Maintenance and Site Work | U/M | Unit Price | Unit Price | Estimated Quantity | Unit Price | ERROR:#VALUE! |
| 0.00000 | |||||||
| A057 | TOP SOIL | TN | $64.00 | 1 | 0.00000 | ||
| A058 | FILL MATERIAL | TN | $56.00 | 1 | 0.00000 | ||
| A059 | SAND MATERIAL | TN | $56.00 | 1 | 0.00000 | ||
| A060 | Intentionally Left Blank | $80.00 | 0.00000 | ||||
| A061 | AGGREGATE ROAD BASE MATERIAL | TN | 1 | 0.00000 | |||
| A062 | RIP RAP STONE 3"-5" | TN | $76.00 | 1 | 0.00000 | ||
| A063 | RIP RAP STONE 6"-12" | TN | $89.00 | 1 | 0.00000 | ||
| A064 | RIP RAP STONE 12"-18" | TN | $116.00 | 1 | 0.00000 | ||
| A065 | GALVANIZED CULVERT REPLACEMENT 15" | LF | $65.50 | 1 | 0.00000 | ||
| A066 | GALVANIZED CULVERT END SECTION 15", PAIR | EA | $270.00 | 1 | 0.00000 | ||
| A067 | GALVANIZED CULVERT REPLACEMENT 18" | LF | $66.28 | 1 | 0.00000 | ||
| A068 | GALVANIZED CULVERT END SECTION 18", PAIR | EA | $310.00 | 1 | 0.00000 | ||
| A069 | GALVANIZED CULVERT REPLACEMENT 24" | LF | $72.55 | 1 | 0.00000 | ||
| A070 | GALVANIZED CULVERT END SECTION 24", PAIR | EA | $370.00 | 1 | 0.00000 | ||
| A071 | GALVANIZED CULVERT REPLACEMENT 30" | LF | $82.25 | 1 | 0.00000 | ||
| A072 | GALVANIZED CULVERT END SECTION 30", PAIR | EA | $450.00 | 1 | 0.00000 | ||
| A073 | GALVANIZED CULVERT REPLACEMENT 36" | LF | $97.35 | 1 | 0.00000 | ||
| A074 | GALVANIZED CULVERT END SECTION 36", PAIR | EA | $650.00 | 1 | 0.00000 | ||
| A075 | POLYETHYLENE CULVERT REPLACEMENT 12" | LF | $58.50 | 1 | 0.00000 | ||
| A076 | POLYETHYLENE CULVERT REPLACEMENT 18" | LF | $65.00 | 1 | 0.00000 | ||
| A077 | POLYETHYLENE CULVERT REPLACEMENT 24" | LF | $73.25 | 1 | 0.00000 | ||
| A078 | POLYETHYLENE CULVERT REPLACEMENT 36" | LF | $92.75 | 1 | 0.00000 | ||
| A079 | POLYETHYLENE CULVERT REPLACEMENT 48" | LF | $113.75 | 1 | 0.00000 | ||
| A080 | ROAD BORING-2" CASING | LF | $15.00 | 1 | 0.00000 | ||
| A081 | ROAD BORING-4" CASING | LF | $26.00 | 1 | 0.00000 | ||
| A082 | ROAD BORING-6" CASING | LF | $37.00 | 1 | 0.00000 | ||
| A083 | ASPHALT PAVING AND PATCHING | SY | $18.00 | 1 | 0.00000 | ||
| A084 | SCARFYING AND RESHAPING BASE COURSE | SY | $5.75 | 1 | 0.00000 | ||
| A085 | BITUMINOUS TACK COAT | SY | $5.50 | 1 | 0.00000 | ||
| A086 | BITUMINOUS PRIME COAT | SY | $5.30 | 1 | 0.00000 | ||
| A087 | ASPHALT SECLING COATING | SY | $2.00 | 1 | 0.00000 | ||
| A088 | SECLING JOINTS AND CRACKS | LF | $9.00 | 1 | 0.00000 | ||
| A089 | PAINTING/MARKING TRAFFIC CONTROL | LF | $1.75 | 1 | 0.00000 | ||
| A090 | 4" CONCRETE SLAB | SF | $4.00 | 1 | 0.00000 | ||
| A091 | 4" CONTRETE SLAB WITH FOOTINGS | SF | $6.50 | 1 | 0.00000 | ||
| A092 | 6" CONCRETE SLAB | SF | $6.50 | 1 | 0.00000 | ||
| A093 | 6" CONCRETE SLAB WITH FOOTINGS | SF | $7.50 | 1 | 0.00000 | ||
| A094 | CONCRETE CURB | LF | $11.00 | 1 | 0.00000 | ||
| A095 | CONCRETE CURB, 24" CURB AND GUTTER | LF | $21.00 | 1 | 0.00000 | ||
| A096 | ROAD SHOULDER MAINTENANCE | LF | $1.57 | 1 | 0.00000 | ||
| A097 | PLAYGROUND MULCH REMOVAL AND DISPOSAL | CY | $52.81 | 1 | 0.00000 | ||
| A098 | BARK CHIP SUPPLY/DELIVERY | CY | $208.00 | 1 | 0.00000 | ||
| A099 | RUBBER MULCH SUPPLY/DELIVERY | CY | $331.00 | 1 | 0.00000 | ||
| A100 | LIMESTONE ROAD BASE | SF | $0.59 | 1 | 0.00000 | ||
| A101 | LAUNCH TYPE CONCRETE | SF | $8.75 | 1 | 0.00000 | ||
| A102 | OTHER PAVING, ROAD MAINTENANCE, AND SITE WORK | 0.00000 | |||||
| 0.00000 | |||||||
| Total Section 3 Base Year | 0.00000 | ||||||
| 0.00000 | |||||||
| CLIN # | Section 4-Plumbing | U/M | Unit Price | Unit Price | Estimated Quantity | Unit Price | ERROR:#VALUE! |
| 0.00000 | |||||||
| A103 | WATER VALVE INSTALLATION 3/4"-2" | EA | $16.00 | 1 | 0.00000 | ||
| A104 | WATER VALVE INSTALLATION 2 1/2"-4" | EA | $24.00 | 1 | 0.00000 | ||
| A105 | WATER LINE INSTALTATION 3/4"-2" | LF | $16.00 | 1 | 0.00000 | ||
| A106 | WATER LINE INSTALTATION 2 1/2"-4" | LF | $18.50 | 1 | 0.00000 | ||
| A107 | GRAVITY SEWER LINE INSTALLATION 4", LESS THAN 4' DEEP | LF | $75.65 | 1 | 0.00000 | ||
| A108 | GRAVITY SEWER LINE INSTALLATION 4", 4.1' TO 10' DEEP | LF | $177.50 | 1 | 0.00000 | ||
| A109 | GRAVITY SEWER LINE INSTALLATION 4", 10.1' TO 15' DEEP | LF | $202.50 | 1 | 0.00000 | ||
| A110 | GRAVITY SEWER LINE INSTALLATION 6", LESS THAN 4' DEEP | LF | $75.90 | 1 | 0.00000 | ||
| A111 | GRAVITY SEWER LINE INSTALLATION 6", 4.1' TO 10' DEEP | LF | $187.50 | 1 | 0.00000 | ||
| A112 | GRAVITY SEWER LINE INSTALLATION 6", 10.1' TO 15' DEEP | LF | $205.75 | 1 | 0.00000 | ||
| A113 | GRAVITY SEWER LINE INSTALLATION 8", LESS THAN 4' DEEP | LF | $79.50 | 1 | 0.00000 | ||
| A114 | GRAVITY SEWER LINE INSTALLATION 8", 4.1' TO 10' DEEP | LF | $192.75 | 1 | 0.00000 | ||
| A115 | GRAVITY SEWER LINE INSTALLATION 8", 10.1' TO 15' DEEP | LF | $209.50 | 1 | 0.00000 | ||
| A116 | COMMODE REPLACEMENT, CHINA /WALL MOUNTED | EA | $24.00 | 1 | 0.00000 | ||
| A117 | COMMODE REPLACEMENT, STAINLESS /WALL MOUNTED | EA | $24.00 | 1 | 0.00000 | ||
| A118 | COMMODE REPLACEMENT, CHINA /FLOOR MOUNTED | EA | $24.00 | 1 | 0.00000 | ||
| A119 | COMMODE REPLACEMENT, STAINLESS /FLOOR MOUNTED | EA | $24.00 | 1 | 0.00000 | ||
| A120 | URINAL REPLACEMENT, CHINA /WALL MOUNTED | EA | $24.00 | 1 | 0.00000 | ||
| A121 | URINAL REPLACEMENT, STAINLESS / WALL MOUNTED | EA | $24.00 | 1 | 0.00000 | ||
| A122 | LAVATORY REPLACEMENT, CHINA /WALL HUNG | EA | $24.00 | 1 | 0.00000 | ||
| A123 | LAVATORY REPLACEMENT, STAINLESS /WALL HUNG | EA | $24.00 | 1 | 0.00000 | ||
| A124 | WATER HEATER REPLACEMENT-50 GALLON | EA | $400.00 | 1 | 0.00000 | ||
| A125 | WATER HEATER REPLACEMENT-80 GALLON | EA | $550.00 | 1 | 0.00000 | ||
| A126 | SELINOID VALVE REPLACEMENT | EA | $24.00 | 1 | 0.00000 | ||
| A127 | PNEUMATIC VALVE REPLACEMENT | EA | $21.00 | 1 | 0.00000 | ||
| A128 | WATER HYDRANT ON 4" X 6" POST | EA | $19.00 | 1 | 0.00000 | ||
| A129 | OTHER PLUMBING | 0.00000 | |||||
| 0.00000 | |||||||
| Total Section 4 Base Year | 0.00000 | ||||||
| 0.00000 | |||||||
| CLIN # | Section 5-Civil Engineering Services | U/M | Unit Price | Unit Price | Estimated Quantity | Unit Price | ERROR:#VALUE! |
| 0.00000 | |||||||
| A130 | HAND OPERATED TOOLS | HR | $21.50 | 1 | 0.00000 | ||
| A131 | DUMP TRUCK, TWENTY TON | HR | $156.75 | 1 | 0.00000 | ||
| A132 | DUMP TRUCK, TWO AND ONE HALF TON | HR | $38.88 | 1 | 0.00000 | ||
| A133 | MOTOR GRADER, TWELVE FOOT MOLDBOARD | HR | $79.28 | 1 | 0.00000 | ||
| A134 | BULLDOZER, CRAWLER/TRACTOR TYPE, MINIMUM EIGHT FOOT BLADE | HR | $113.63 | 1 | 0.00000 | ||
| A135 | BULLDOZER, CRAWLER/TRACTOR TYPE, MINIMUM SIX FOOT BLADE | HR | $99.25 | 1 | 0.00000 | ||
| A136 | WATER TANK TRUCK | HR | $88.50 | 1 | 0.00000 | ||
| A137 | CRANE, TRUCK MOUNTED, 35 TON W/112' BOOM | HR | $240.63 | 1 | 0.00000 | ||
| A138 | SHEEP FOOT ROLLER/COMPACTOR | HR | $80.00 | 1 | 0.00000 | ||
| A139 | ROLLER/COMPACTOR, PNEUMATIC-TIRED | HR | $71.38 | 1 | 0.00000 | ||
| A140 | ROLLER/COMPACTOR, STEEL WHEELED | HR | $80.00 | 1 | 0.00000 | ||
| A141 | FRONT END LOADER, RUBBER TIRED TYPE | HR | $117.38 | 1 | 0.00000 | ||
| A142 | TRACTOR, RUBBER TIRED WITH BOX BLADE, AUGER, BUSH HOG ROTARTY MOWER, SIDE BOOM BRUSH HOG ROTARY MOWER | HR | $29.00 | 1 | 0.00000 | ||
| A143 | BACKHOE, RUBBER TIRED TYPE | HR | $67.81 | 1 | 0.00000 | ||
| A144 | BACKHOE (TRACKHOE) TRACK TYPE | HR | $157.91 | 1 | 0.00000 | ||
| A145 | TRACTOR, "SKID STEERING" TYPE LOADER | HR | $50.68 | 1 | 0.00000 | ||
| A146 | DITCHING MACHINE, CHAIN TYPE | HR | $46.08 | 1 | 0.00000 | ||
| A147 | TRENCHER, ROCK SAW, WHEEL TYPE | HR | $74.12 | 1 | 0.00000 | ||
| A148 | ROAD BROOM | HR | $54.13 | 1 | 0.00000 | ||
| A149 | ASPHALT MILLING MACHINE (COLD PLANER) | HR | $77.69 | 1 | 0.00000 | ||
| A150 | AIR COMPRESSOR | HR | $76.53 | 1 | 0.00000 | ||
| A151 | WELDER, TRUCK OR TRAILER, MOUNTED | HR | $41.15 | 1 | 0.00000 | ||
| A152 | VIBRATORY PLATE COMPACTOR | HR | $35.15 | 1 | 0.00000 | ||
| A153 | WATER PUMP, TWO INCH | HR | $22.65 | 1 | 0.00000 | ||
| A154 | WATER PUMP, FOUR INCH | HR | $26.10 | 1 | 0.00000 | ||
| A155 | WATER PUMP, SIX INCH | HR | $31.56 | 1 | 0.00000 | ||
| A156 | WASHER HIGH PRESSURE | HR | $20.93 | 1 | 0.00000 | ||
| A157 | CHIPPER, BRUSH/LIMB | HR | $42.34 | 1 | 0.00000 | ||
| A158 | CONCRETE/ASPHALT SAW | HR | $19.34 | 1 | 0.00000 | ||
| A159 | CHAIN SAW | HR | $21.33 | 1 | 0.00000 | ||
| A160 | LATTICE BOOM CRAWLER CRANE WITH TRACKS, 30-80 TON | HR | $198.75 | 1 | 0.00000 | ||
| A161 | RUBBER-TIRED HYDRALIC BOOM (TELESCOPIC) CRANE, 30-90 TON | HR | $221.75 | 1 | 0.00000 | ||
| A162 | RUBBER-TIRED TRUCK MOUNTER CRANE (BOOM TRUCK OR PICKER TRUCK), 25-50 TON | HR | $256.25 | 1 | 0.00000 | ||
| A163 | RUBBER TIRED ROUGH TERRAIN CRANE, 30-90 TON | HR | $233.25 | 1 | 0.00000 | ||
| A164 | ARTICULATING RUBBER-TIRED HYDRAULIC BOOM (TELESCOPIC) CRANE, 100-250 TON | HR | $281.55 | 1 | 0.00000 | ||
| A165 | OTHER ENGINEER SERVICES | 0.00000 | |||||
| 0.00000 | |||||||
| Total Section 5 Base Year | 0.00000 | ||||||
| 0.00000 | |||||||
| CLIN # | Section 6-Fencing | U/M | Unit Price | Unit Price | Estimated Quantity | Unit Price | ERROR:#VALUE! |
| 0.00000 | |||||||
| A166 | PIPE RAIL FENCING | LF | $15.35 | 1 | 0.00000 | ||
| A167 | PIPE RAIL FENCE GATE | EA | $296.00 | 1 | 0.00000 | ||
| A168 | GUARD POST AND CABLE | LF | $28.00 | 1 | 0.00000 | ||
| A169 | STEEL POST AND CABLE | LF | $67.00 | 1 | 0.00000 | ||
| A170 | TIMBER VEHICLE BARRIES | EA | $3.50 | 1 | 0.00000 | ||
| A171 | REPAIR/REPLACE GUARDRAIL FENCING | LF | $325.00 | 1 | 0.00000 | ||
| A172 | BARBED WIRE FENCING, STEEL POST, SIX (6) WIRE | LF | $340.00 | 1 | 0.00000 | ||
| A173 | INSTALLATION OF SWINGING GATE-4' | EA | $350.00 | 1 | 0.00000 | ||
| A174 | INSTALLATION OF SWINGING GATE-12' | EA | $390.00 | 1 | 0.00000 | ||
| A175 | INSTALLATION OF SWINGING GATE-14' | EA | $420.00 | 1 | 0.00000 | ||
| A176 | INSTALLATION OF SWINGING GATE-16' | EA | $218.00 | 1 | 0.00000 | ||
| A177 | OTHER FENCING | 0.00000 | |||||
| 0.00000 | |||||||
| Total Section 6 Base Year | 0.00000 | ||||||
| 0.00000 | |||||||
| CLIN # | Section 7-Sign and Buoy Maintenance | U/M | Unit Price | Unit Price | Estimated Quantity | Unit Price | ERROR:#VALUE! |
| 0.00000 | |||||||
| A178 | PARK SIGN INSTALLATION-SINGLE POST | EA | $21.00 | 1 | 0.00000 | ||
| A179 | PARK SIGN INSTALLATION-DOUBLE POST | EA | $32.00 | 1 | 0.00000 | ||
| A180 | PARK SIGN REPLACEMENT-SIGN ONLY-SINGLE POST | EA | $11.00 | 1 | 0.00000 | ||
| A181 | PARK SIGN REPLACEMENT-SIGN ONLY-DOUBLE POST | EA | $16.00 | 1 | 0.00000 | ||
| A182 | BOUY INSTALLATION | EA | $203.00 | 1 | 0.00000 | ||
| A183 | REPAIR/REPLACE PIPELINE FLOATING BARRIER | LF | $12.00 | 1 | 0.00000 | ||
| A184 | PIPELINE FLOATING BARRIER ANCHORS | EA | $203.00 | 1 | 0.00000 | ||
| A185 | OTHER SIGN AND BOUY MAINTENANCE | 0.00000 | |||||
| 0.00000 | |||||||
| Total Section 7 Base Year | 0.00000 | ||||||
| 0.00000 | |||||||
| CLIN | Section 8-Electrical | U/M | Unit Price | Unit Price | Estimated Quantity | Unit Price | ERROR:#VALUE! |
| 0.00000 | |||||||
| A186 | ELECTRIC LINE REPAIR/INSTALLATION, DIRECT BURIAL | LF | $8.00 | 1 | 0.00000 | ||
| A187 | ELECTRIC LINE REPAIR/INSTALLATION, IN CONDUIT | LF | $8.20 | 1 | 0.00000 | ||
| A188 | RV PEDESTAL INSTALLATION, SINGLE UNIT | EA | $120.00 | 1 | 0.00000 | ||
| A189 | RV PEDESTAL INSTALLATION, DOUBLE UNIT | EA | $160.00 | 1 | 0.00000 | ||
| A190 | METER BASE INSTALLATION | EA | $320.00 | 1 | 0.00000 | ||
| A191 | MAIN DISCONNECT PANEL INSTALLATION | EA | $350.00 | 1 | 0.00000 | ||
| A192 | LOAD CENTER PANEL | EA | $850.00 | 1 | 0.00000 | ||
| A193 | OTHER ELECTRICAL |
| Total Section 8 Base Year |
| Total Option Base Year Sections 1-8 (CLINs A001-A193) |
OP1
| OP1 | |||||||
| CLIN # | Section 1-Campsite Maintenance | U/M | Unit Price | Estimated Quantity | Estimated Price | ||
| Rounding Fix | |||||||
| B001 | CONCRETE WHEEL STOPS | EA | 1 | 69 | $0.00 | ||
| B002 | TIMBER DELINIATORS, ONE TIER | LF | 1 | 9.2 | $0.00 | ||
| B003 | TIMBER DELINIATORS,TWO TIER | LF | 1 | 9.2 | $0.00 | ||
| B004 | TIMBER DELINIATORS, THREE TIER | LF | 1 | 9.2 | $0.00 | ||
| B005 | TIMBER DELINIATORS, FOUR TIER | LF | 1 | 9.2 | $0.00 | ||
| B006 | TIMBER DELINIATORS, TIER FIVE | LF | 1 | 9.2 | $0.00 | ||
| B007 | UPRIGHT AND PEDASTAL GRILL INSTALLATION | LF | 1 | 34.5 | $0.00 | ||
| B008 | FIRE RING AND GROUND MOUNTED COOKER INSTALLATION | EA | 1 | 28.75 | $0.00 | ||
| B009 | LANTER HANGER POST INSTALLION | EA | 1 | 34.5 | $0.00 | ||
| B010 | REPLACE/INSTALL VINYL COATED OR ALUMINIUM PICNIC TABLES | EA | 1 | 40.25 | $0.00 | ||
| B011 | REPLACE/INSTALL PARK BENCHES | EA | 1 | 46 | $0.00 | ||
| B012 | RETAINER WALL BLOCK INSTALLATION ONE | LF | 1 | 1.2075 | $0.00 | ||
| B013 | RETAINER WALL BLOCK INSTALLATION TWO | LF | 1 | 1.2075 | $0.00 | ||
| B014 | RETAINER WALL BLOCK INSTALLATION THREE | LF | 1 | 1.2075 | $0.00 | ||
| B015 | RETAINER WALL BLOCK INSTALLATION FOUR | LF | 1 | 1.2075 | $0.00 | ||
| B016 | RETAINER WALL BLOCK INSTALLATION FIVE | LF | 1 | 1.2075 | $0.00 | ||
| B017 | RIP RAP BAG INSTALLATION ONE | LF | 1 | 0.92 | $0.00 | ||
| B018 | RIP RAP BAG INSTALLATION TWO | LF | 1 | 0.92 | $0.00 | ||
| B019 | RIP RAP BAG INSTALLATION THREE | LF | 1 | 0.92 | $0.00 | ||
| B020 | RIP RAP BAG INSTALLATION FOUR | LF | 1 | 0.92 | $0.00 | ||
| B021 | RIP RAP BAG INSTALLATION FIVE | LF | 1 | 0.92 | $0.00 | ||
| B022 | RIP RAP BAG INSTALLATION SIX | LF | 1 | 0.92 | $0.00 | ||
| B023 | RIP RAP BAG INSTALLATION SEVEN | LF | 1 | 0.92 | $0.00 | ||
| B024 | RIP RAP BAG INSTALLATION EIGHT | LF | 1 | 0.92 | $0.00 | ||
| B025 | OTHER CAMPSITE MAINTENANCE | $0.00 | |||||
| $0.00 | |||||||
| Total Section 1 Option Year 1 | $0.00 | ||||||
| $0.00 | |||||||
| CLIN # | Section 2-Carpentry and Painting | U/M | Unit Price | Estimated Quantity | Unit Price | Unit Price | ERROR:#VALUE! |
| 0 | $0.00 | ||||||
| B026 | METAL PICNIC SHELTER INSTALLATION | EA | 1 | 695.75 | $0.00 | ||
| B027 | ROOFING REMOVAL (COMPOSITION AND R-PANEL) | SF | 1 | 0.8625 | $0.00 | ||
| B028 | ROOF SHEATHING | SF | 1 | 1.6675 | $0.00 | ||
| B029 | TONGUE AND GROVE DECKING | SF | 1 | 2.0815 | $0.00 | ||
| B030 | FASCIA BOARD | LF | 1 | 12.0175 | $0.00 | ||
| B031 | COMPOSITION SHINGLE REPAIR/INSTALLATION | SF | 1 | 1.3685 | $0.00 | ||
| B032 | R-PANEL REPAIR/INSTALLATION | SF | 1 | 2.783 | $0.00 | ||
| B033 | WALL SHEATING | SF | 1 | 1.541 | $0.00 | ||
| B034 | SOFFIT SHEATHING | SF | 1 | 3.4615 | $0.00 | ||
| B035 | WALL SIDING | SF | 1 | 1.541 | $0.00 | ||
| B036 | PLASTIC LAMINATE PANELS | SF | 1 | 2.8865 | $0.00 | ||
| B037 | LAP OR "V" GROOVED SIDING | SF | 1 | 2.691 | $0.00 | ||
| B038 | TOILET PARTITION-SINGLE | EA | 1 | 208.15 | $0.00 | ||
| B039 | TOILET PARTITION-DOUBLE | EA | 1 | 300.15 | $0.00 | ||
| B040 | TOILET PARTITION-TRIPLE | EA | 1 | 392.15 | $0.00 | ||
| B041 | SHOWER PARTITION | EA | 1 | 254.15 | $0.00 | ||
| B042 | SHOWER/TOILET DOOR WITH PILASTER | EA | 1 | 185.15 | $0.00 | ||
| B043 | URINAL PARTITION | EA | 1 | 162.15 | $0.00 | ||
| B044 | PAINTING METAL PICNIC SHELTERS | SF | 1 | 1.1155 | $0.00 | ||
| B045 | PAINTING WOOD-OIL BASED PAINT | SF | 1 | 0.8625 | $0.00 | ||
| B046 | PAINTING WOOD-EXTERIOR LATEX PAINT | SF | 1 | 0.8625 | $0.00 | ||
| B047 | PAINTING WOOD-SEALER/STAIN | SF | 1 | 0.8625 | $0.00 | ||
| B048 | PAINTING WOOD-WATERPROOFING | SF | 1 | 0.8625 | $0.00 | ||
| B049 | PAINTING MASONRY-BLOCK SEALER/FILLER | SF | 1 | 0.8625 | $0.00 | ||
| B050 | PAINTING MASONRY-OIL BASED | SF | 1 | 0.8625 | $0.00 | ||
| B051 | PAINTING MASONRY-EXTERIOR LATEX PAINT | SF | 1 | 0.8625 | $0.00 | ||
| B052 | PAINTING METAL-OIL BASED PAINT | SF | 1 | 0.8625 | $0.00 | ||
| B053 | PAINTING METAL-EXTERIOR BASED PAINT | SF | 1 | 0.8625 | $0.00 | ||
| B054 | LOG VENEER SIDING | SF | 1 | 2.691 | $0.00 | ||
| B055 | LOG SIDING | SF | 1 | 2.9325 | $0.00 | ||
| B056 | OTHER CARPENTRY AND PAINTING | $0.00 | |||||
| $0.00 | |||||||
| Total Section 2 Option Year 1 | $0.00 | ||||||
| $0.00 | |||||||
| CLIN # | Section 3-Paving, Road Maintenance and Site Work | U/M | Unit Price | Estimated Quantity | Unit Price | Unit Price | ERROR:#VALUE! |
| 0 | $0.00 | ||||||
| B057 | TOP SOIL | TN | 1 | 73.6 | $0.00 | ||
| B058 | FILL MATERIAL | TN | 1 | 64.4 | $0.00 | ||
| B059 | SAND MATERIAL | TN | 1 | 64.4 | $0.00 | ||
| B060 | Intentionally Left Blank | 92 | $0.00 | ||||
| B061 | AGGREGATE ROAD BASE MATERIAL | TN | 1 | 92 | $0.00 | ||
| B062 | RIP RAP STONE 3"-5" | TN | 1 | 87.4 | $0.00 | ||
| B063 | RIP RAP STONE 6"-12" | TN | 1 | 102.35 | $0.00 | ||
| B064 | RIP RAP STONE 12"-18" | TN | 1 | 133.4 | $0.00 | ||
| B065 | GALVANIZED CULVERT REPLACEMENT 15" | LF | 1 | 75.325 | $0.00 | ||
| B066 | GALVANIZED CULVERT END SECTION 15", PAIR | EA | 1 | 310.5 | $0.00 | ||
| B067 | GALVANIZED CULVERT REPLACEMENT 18" | LF | 1 | 76.222 | $0.00 | ||
| B068 | GALVANIZED CULVERT END SECTION 18", PAIR | EA | 1 | 356.5 | $0.00 | ||
| B069 | GALVANIZED CULVERT REPLACEMENT 24" | LF | 1 | 83.4325 | $0.00 | ||
| B070 | GALVANIZED CULVERT END SECTION 24", PAIR | EA | 1 | 425.5 | $0.00 | ||
| B071 | GALVANIZED CULVERT REPLACEMENT 30" | LF | 1 | 94.5875 | $0.00 | ||
| B072 | GALVANIZED CULVERT END SECTION 30", PAIR | EA | 1 | 517.5 | $0.00 | ||
| B073 | GALVANIZED CULVERT REPLACEMENT 36" | LF | 1 | 111.9525 | $0.00 | ||
| B074 | GALVANIZED CULVERT END SECTION 36", PAIR | EA | 1 | 747.5 | $0.00 | ||
| B075 | POLYETHYLENE CULVERT REPLACEMENT 12" | LF | 1 | 67.275 | $0.00 | ||
| B076 | POLYETHYLENE CULVERT REPLACEMENT 18" | LF | 1 | 74.75 | $0.00 | ||
| B077 | POLYETHYLENE CULVERT REPLACEMENT 24" | LF | 1 | 84.2375 | $0.00 | ||
| B078 | POLYETHYLENE CULVERT REPLACEMENT 36" | LF | 1 | 106.6625 | $0.00 | ||
| B079 | POLYETHYLENE CULVERT REPLACEMENT 48" | LF | 1 | 130.8125 | $0.00 | ||
| B080 | ROAD BORING-2" CASING | LF | 1 | 17.25 | $0.00 | ||
| B081 | ROAD BORING-4" CASING | LF | 1 | 29.9 | $0.00 | ||
| B082 | ROAD BORING-6" CASING | LF | 1 | 42.55 | $0.00 | ||
| B083 | ASPHALT PAVING AND PATCHING | SY | 1 | 20.7 | $0.00 | ||
| B084 | SCARFYING AND RESHAPING BASE COURSE | SY | 1 | 6.6125 | $0.00 | ||
| B085 | BITUMINOUS TACK COAT | SY | 1 | 6.325 | $0.00 | ||
| B086 | BITUMINOUS PRIME COAT | SY | 1 | 6.095 | $0.00 | ||
| B087 | ASPHALT SECLING COATING | SY | 1 | 2.3 | $0.00 | ||
| B088 | SECLING JOINTS AND CRACKS | LF | 1 | 10.35 | $0.00 | ||
| B089 | PAINTING/MARKING TRAFFIC CONTROL | LF | 1 | 2.0125 | $0.00 | ||
| B090 | 4" CONCRETE SLAB | SF | 1 | 4.6 | $0.00 | ||
| B091 | 4" CONTRETE SLAB WITH FOOTINGS | SF | 1 | 7.475 | $0.00 | ||
| B092 | 6" CONCRETE SLAB | SF | 1 | 7.475 | $0.00 | ||
| B093 | 6" CONCRETE SLAB WITH FOOTINGS | SF | 1 | 8.625 | $0.00 | ||
| B094 | CONCRETE CURB | LF | 1 | 12.65 | $0.00 | ||
| B095 | CONCRETE CURB, 24" CURB AND GUTTER | LF | 1 | 24.15 | $0.00 | ||
| B096 | ROAD SHOULDER MAINTENANCE | LF | 1 | 1.8055 | $0.00 | ||
| B097 | PLAYGROUND MULCH REMOVAL AND DISPOSAL | CY | 1 | 60.7315 | $0.00 | ||
| B098 | BARK CHIP SUPPLY/DELIVERY | CY | 1 | 239.2 | $0.00 | ||
| B099 | RUBBER MULCH SUPPLY/DELIVERY | CY | 1 | 380.65 | $0.00 | ||
| B100 | LIMESTONE ROAD BASE | SF | 1 | 0.6785 | $0.00 | ||
| B101 | LAUNCH TYPE CONCRETE | SF | 1 | 10.0625 | $0.00 | ||
| B102 | OTHER PAVING, ROAD MAINTENANCE, AND SITE WORK | $0.00 | |||||
| $0.00 | |||||||
| Total Section 3 Option Year 1 | $0.00 | ||||||
| $0.00 | |||||||
| CLIN # | Section 4-Plumbing | U/M | Unit Price | Estimated Quantity | Unit Price | Unit Price | ERROR:#VALUE! |
| 0 | $0.00 | ||||||
| B103 | WATER VALVE INSTALLATION 3/4"-2" | EA | 1 | 18.4 | $0.00 | ||
| B104 | WATER VALVE INSTALLATION 2 1/2"-4" | EA | 1 | 27.6 | $0.00 | ||
| B105 | WATER LINE INSTALTATION 3/4"-2" | LF | 1 | 18.4 | $0.00 | ||
| B106 | WATER LINE INSTALTATION 2 1/2"-4" | LF | 1 | 21.275 | $0.00 | ||
| B107 | GRAVITY SEWER LINE INSTALLATION 4", LESS THAN 4' DEEP | LF | 1 | 86.9975 | $0.00 | ||
| B108 | GRAVITY SEWER LINE INSTALLATION 4", 4.1' TO 10' DEEP | LF | 1 | 204.125 | $0.00 | ||
| B109 | GRAVITY SEWER LINE INSTALLATION 4", 10.1' TO 15' DEEP | LF | 1 | 232.875 | $0.00 | ||
| B110 | GRAVITY SEWER LINE INSTALLATION 6", LESS THAN 4' DEEP | LF | 1 | 87.285 | $0.00 | ||
| B111 | GRAVITY SEWER LINE INSTALLATION 6", 4.1' TO 10' DEEP | LF | 1 | 215.625 | $0.00 | ||
| B112 | GRAVITY SEWER LINE INSTALLATION 6", 10.1' TO 15' DEEP | LF | 1 | 236.6125 | $0.00 | ||
| B113 | GRAVITY SEWER LINE INSTALLATION 8", LESS THAN 4' DEEP | LF | 1 | 91.425 | $0.00 | ||
| B114 | GRAVITY SEWER LINE INSTALLATION 8", 4.1' TO 10' DEEP | LF | 1 | 221.6625 | $0.00 | ||
| B115 | GRAVITY SEWER LINE INSTALLATION 8", 10.1' TO 15' DEEP | LF | 1 | 240.925 | $0.00 | ||
| B116 | COMMODE REPLACEMENT, CHINA /WALL MOUNTED | EA | 1 | 27.6 | $0.00 | ||
| B117 | COMMODE REPLACEMENT, STAINLESS /WALL MOUNTED | EA | 1 | 27.6 | $0.00 | ||
| B118 | COMMODE REPLACEMENT, CHINA /FLOOR MOUNTED | EA | 1 | 27.6 | $0.00 | ||
| B119 | COMMODE REPLACEMENT, STAINLESS /FLOOR MOUNTED | EA | 1 | 27.6 | $0.00 | ||
| B120 | URINAL REPLACEMENT, CHINA /WALL MOUNTED | EA | 1 | 27.6 | $0.00 | ||
| B121 | URINAL REPLACEMENT, STAINLESS / WALL MOUNTED | EA | 1 | 27.6 | $0.00 | ||
| B122 | LAVATORY REPLACEMENT, CHINA /WALL HUNG | EA | 1 | 27.6 | $0.00 | ||
| B123 | LAVATORY REPLACEMENT, STAINLESS /WALL HUNG | EA | 1 | 27.6 | $0.00 | ||
| B124 | WATER HEATER REPLACEMENT-50 GALLON | EA | 1 | 460 | $0.00 | ||
| B125 | WATER HEATER REPLACEMENT-80 GALLON | EA | 1 | 632.5 | $0.00 | ||
| B126 | SELINOID VALVE REPLACEMENT | EA | 1 | 27.6 | $0.00 | ||
| B127 | PNEUMATIC VALVE REPLACEMENT | EA | 1 | 24.15 | $0.00 | ||
| B128 | WATER HYDRANT ON 4" X 6" POST | EA | 1 | 21.85 | $0.00 | ||
| B129 | OTHER PLUMBING | $0.00 | |||||
| $0.00 | |||||||
| Total Section 4 Option Year 1 | $0.00 | ||||||
| $0.00 | |||||||
| CLIN # | Section 5-Civil Engineering Services | U/M | Unit Price | Estimated Quantity | Unit Price | Unit Price | ERROR:#VALUE! |
| 0 | $0.00 | ||||||
| B130 | HAND OPERATED TOOLS | HR | 1 | 24.725 | $0.00 | ||
| B131 | DUMP TRUCK, TWENTY TON | HR | 1 | 180.2625 | $0.00 | ||
| B132 | DUMP TRUCK, TWO AND ONE HALF TON | HR | 1 | 44.70625 | $0.00 | ||
| B133 | MOTOR GRADER, TWELVE FOOT MOLDBOARD | HR | 1 | 91.166825 | $0.00 | ||
| B134 | BULLDOZER, CRAWLER/TRACTOR TYPE, MINIMUM EIGHT FOOT BLADE | HR | 1 | 130.66875 | $0.00 | ||
| B135 | BULLDOZER, CRAWLER/TRACTOR TYPE, MINIMUM SIX FOOT BLADE | HR | 1 | 114.1375 | $0.00 | ||
| B136 | WATER TANK TRUCK | HR | 1 | 101.772125 | $0.00 | ||
| B137 | CRANE, TRUCK MOUNTED, 35 TON W/112' BOOM | HR | 1 | 276.71875 | $0.00 | ||
| B138 | SHEEP FOOT ROLLER/COMPACTOR | HR | 1 | 92 | $0.00 | ||
| B139 | ROLLER/COMPACTOR, PNEUMATIC-TIRED | HR | 1 | 82.08125 | $0.00 | ||
| B140 | ROLLER/COMPACTOR, STEEL WHEELED | HR | 1 | 92 | $0.00 | ||
| B141 | FRONT END LOADER, RUBBER TIRED TYPE | HR | 1 | 134.98125 | $0.00 | ||
| B142 | TRACTOR, RUBBER TIRED WITH BOX BLADE, AUGER, BUSH HOG ROTARTY MOWER, SIDE BOOM BRUSH HOG ROTARY MOWER | HR | 1 | 33.347125 | $0.00 | ||
| B143 | BACKHOE, RUBBER TIRED TYPE | HR | 1 | 77.9815 | $0.00 | ||
| B144 | BACKHOE (TRACKHOE) TRACK TYPE | HR | 1 | 181.599375 | $0.00 | ||
| B145 | TRACTOR, "SKID STEERING" TYPE LOADER | HR | 1 | 58.27625 | $0.00 | ||
| B146 | DITCHING MACHINE, CHAIN TYPE | HR | 1 | 52.98625 | $0.00 | ||
| B147 | TRENCHER, ROCK SAW, WHEEL TYPE | HR | 1 | 85.240875 | $0.00 | ||
| B148 | ROAD BROOM | HR | 1 | 62.24375 | $0.00 | ||
| B149 | ASPHALT MILLING MACHINE (COLD PLANER) | HR | 1 | 89.340625 | $0.00 | ||
| B150 | AIR COMPRESSOR | HR | 1 | 88.006625 | $0.00 | ||
| B151 | WELDER, TRUCK OR TRAILER, MOUNTED | HR | 1 | 47.323075 | $0.00 | ||
| B152 | VIBRATORY PLATE COMPACTOR | HR | 1 | 40.423075 | $0.00 | ||
| B153 | WATER PUMP, TWO INCH | HR | 1 | 26.0475 | $0.00 | ||
| B154 | WATER PUMP, FOUR INCH | HR | 1 | 30.015 | $0.00 | ||
| B155 | WATER PUMP, SIX INCH | HR | 1 | 36.296875 | $0.00 | ||
| B156 | WASHER HIGH PRESSURE | HR | 1 | 24.06375 | $0.00 | ||
| B157 | CHIPPER, BRUSH/LIMB | HR | 1 | 48.6887 | $0.00 | ||
| B158 | CONCRETE/ASPHALT SAW | HR | 1 | 22.2453125 | $0.00 | ||
| B159 | CHAIN SAW | HR | 1 | 24.526625 | $0.00 | ||
| B160 | LATTICE BOOM CRAWLER CRANE WITH TRACKS, 30-80 TON | HR | 1 | 228.5625 | $0.00 | ||
| B161 | RUBBER-TIRED HYDRALIC BOOM (TELESCOPIC) CRANE, 30-90 TON | HR | 1 | 255.0125 | $0.00 | ||
| B162 | RUBBER-TIRED TRUCK MOUNTER CRANE (BOOM TRUCK OR PICKER TRUCK), 25-50 TON | HR | 1 | 294.6875 | $0.00 | ||
| B163 | RUBBER TIRED ROUGH TERRAIN CRANE, 30-90 TON | HR | 1 | 268.2375 | $0.00 | ||
| B164 | ARTICULATING RUBBER-TIRED HYDRAULIC BOOM (TELESCOPIC) CRANE, 100-250 TON | HR | 1 | 323.7825 | $0.00 | ||
| B165 | OTHER ENGINEER SERVICES | $0.00 | |||||
| $0.00 | |||||||
| Total Section 5 Option Year 1 | $0.00 | ||||||
| $0.00 | |||||||
| CLIN # | Section 6-Fencing | U/M | Unit Price | Estimated Quantity | Unit Price | Unit Price | ERROR:#VALUE! |
| 0 | $0.00 | ||||||
| B166 | PIPE RAIL FENCING | LF | 1 | 17.6525 | $0.00 | ||
| B167 | PIPE RAIL FENCE GATE | EA | 1 | 340.4 | $0.00 | ||
| B168 | GUARD POST AND CABLE | LF | 1 | 32.2 | $0.00 | ||
| B169 | STEEL POST AND CABLE | LF | 1 | 77.05 | $0.00 | ||
| B170 | TIMBER VEHICLE BARRIES | EA | 1 | 4.025 | $0.00 | ||
| B171 | REPAIR/REPLACE GUARDRAIL FENCING | LF | 1 | 373.75 | $0.00 | ||
| B172 | BARBED WIRE FENCING, STEEL POST, SIX (6) WIRE | LF | 1 | 391 | $0.00 | ||
| B173 | INSTALLATION OF SWINGING GATE-4' | EA | 1 | 402.5 | $0.00 | ||
| B174 | INSTALLATION OF SWINGING GATE-12' | EA | 1 | 448.5 | $0.00 | ||
| B175 | INSTALLATION OF SWINGING GATE-14' | EA | 1 | 483 | $0.00 | ||
| B176 | INSTALLATION OF SWINGING GATE-16' | EA | 1 | 250.7 | $0.00 | ||
| B177 | OTHER FENCING | $0.00 | |||||
| $0.00 | |||||||
| Total Section 6 Option Year 1 | $0.00 | ||||||
| $0.00 | |||||||
| CLIN # | Section 7-Sign and Buoy Maintenance | U/M | Unit Price | Estimated Quantity | Unit Price | Unit Price | ERROR:#VALUE! |
| 0 | $0.00 | ||||||
| B178 | PARK SIGN INSTALLATION-SINGLE POST | EA | 1 | 24.15 | $0.00 | ||
| B179 | PARK SIGN INSTALLATION-DOUBLE POST | EA | 1 | 36.8 | $0.00 | ||
| B180 | PARK SIGN REPLACEMENT-SIGN ONLY-SINGLE POST | EA | 1 | 12.65 | $0.00 | ||
| B181 | PARK SIGN REPLACEMENT-SIGN ONLY-DOUBLE POST | EA | 1 | 18.4 | $0.00 | ||
| B182 | BOUY INSTALLATION | EA | 1 | 233.45 | $0.00 | ||
| B183 | REPAIR/REPLACE PIPELINE FLOATING BARRIER | LF | 1 | 13.8 | $0.00 | ||
| B184 | PIPELINE FLOATING BARRIER ANCHORS | EA | 1 | 233.45 | $0.00 | ||
| B185 | OTHER SIGN AND BOUY MAINTENANCE | $0.00 | |||||
| $0.00 | |||||||
| Total Section 7 Option Year 1 | $0.00 | ||||||
| $0.00 | |||||||
| CLIN | Section 8-Electrical | U/M | Unit Price | Estimated Quantity | Unit Price | Unit Price | ERROR:#VALUE! |
| 0 | $0.00 | ||||||
| B186 | ELECTRIC LINE REPAIR/INSTALLATION, DIRECT BURIAL | LF | 1 | 9.2 | $0.00 | ||
| B187 | ELECTRIC LINE REPAIR/INSTALLATION, IN CONDUIT | LF | 1 | 9.43 | $0.00 | ||
| B188 | RV PEDESTAL INSTALLATION, SINGLE UNIT | EA | 1 | 138 | $0.00 | ||
| B189 | RV PEDESTAL INSTALLATION, DOUBLE UNIT | EA | 1 | 184 | $0.00 | ||
| B190 | METER BASE INSTALLATION | EA | 1 | 368 | $0.00 | ||
| B191 | MAIN DISCONNECT PANEL INSTALLATION | EA | 1 | 402.5 | $0.00 | ||
| B192 | LOAD CENTER PANEL | EA | 1 | 977.5 | $0.00 | ||
| B193 | OTHER ELECTRICAL |
| Total Section 8 Option Year 1 |
| Total Option Option Year 1 Sections 1-8 (CLINs B001-B193) |
OP2
| OP2 | |||||||
| CLIN # | Section 1-Campsite Maintenance | U/M | Unit Price | Estimated Quantity | Estimated Price | ||
| Rounding Fix | |||||||
| C001 | CONCRETE WHEEL STOPS | EA | 1 | 72.45 | $0.00 | ||
| C002 | TIMBER DELINIATORS, ONE TIER | LF | 1 | 9.66 | $0.00 | ||
| C003 | TIMBER DELINIATORS,TWO TIER | LF | 1 | 9.66 | $0.00 | ||
| C004 | TIMBER DELINIATORS, THREE TIER | LF | 1 | 9.66 | $0.00 | ||
| C005 | TIMBER DELINIATORS, FOUR TIER | LF | 1 | 9.66 | $0.00 | ||
| C006 | TIMBER DELINIATORS, TIER FIVE | LF | 1 | 9.66 | $0.00 | ||
| C007 | UPRIGHT AND PEDASTAL GRILL INSTALLATION | LF | 1 | 36.225 | $0.00 | ||
| C008 | FIRE RING AND GROUND MOUNTED COOKER INSTALLATION | EA | 1 | 30.1875 | $0.00 | ||
| C009 | LANTER HANGER POST INSTALLION | EA | 1 | 36.225 | $0.00 | ||
| C010 | REPLACE/INSTALL VINYL COATED OR ALUMINIUM PICNIC TABLES | EA | 1 | 42.2625 | $0.00 | ||
| C011 | REPLACE/INSTALL PARK BENCHES | EA | 1 | 48.3 | $0.00 | ||
| C012 | RETAINER WALL BLOCK INSTALLATION ONE | LF | 1 | 1.267875 | $0.00 | ||
| C013 | RETAINER WALL BLOCK INSTALLATION TWO | LF | 1 | 1.267875 | $0.00 | ||
| C014 | RETAINER WALL BLOCK INSTALLATION THREE | LF | 1 | 1.267875 | $0.00 | ||
| C015 | RETAINER WALL BLOCK INSTALLATION FOUR | LF | 1 | 1.267875 | $0.00 | ||
| C016 | RETAINER WALL BLOCK INSTALLATION FIVE | LF | 1 | 1.267875 | $0.00 | ||
| C017 | RIP RAP BAG INSTALLATION ONE | LF | 1 | 0.966 | $0.00 | ||
| C018 | RIP RAP BAG INSTALLATION TWO | LF | 1 | 0.966 | $0.00 | ||
| C019 | RIP RAP BAG INSTALLATION THREE | LF | 1 | 0.966 | $0.00 | ||
| C020 | RIP RAP BAG INSTALLATION FOUR | LF | 1 | 0.966 | $0.00 | ||
| C021 | RIP RAP BAG INSTALLATION FIVE | LF | 1 | 0.966 | $0.00 | ||
| C022 | RIP RAP BAG INSTALLATION SIX | LF | 1 | 0.966 | $0.00 | ||
| C023 | RIP RAP BAG INSTALLATION SEVEN | LF | 1 | 0.966 | $0.00 | ||
| C024 | RIP RAP BAG INSTALLATION EIGHT | LF | 1 | 0.966 | $0.00 | ||
| C025 | OTHER CAMPSITE MAINTENANCE | $0.00 | |||||
| $0.00 | |||||||
| Total Section 1 Option Year 2 | $0.00 | ||||||
| $0.00 | |||||||
| CLIN # | Section 2-Carpentry and Painting | U/M | Unit Price | Estimated Quantity | Unit Price | Unit Price | ERROR:#VALUE! |
| $0.00 | |||||||
| C026 | METAL PICNIC SHELTER INSTALLATION | EA | 1 | 730.5375 | $0.00 | ||
| C027 | ROOFING REMOVAL (COMPOSITION AND R-PANEL) | SF | 1 | 0.905625 | $0.00 | ||
| C028 | ROOF SHEATHING | SF | 1 | 1.750875 | $0.00 | ||
| C029 | TONGUE AND GROVE DECKING | SF | 1 | 2.185575 | $0.00 | ||
| C030 | FASCIA BOARD | LF | 1 | 12.618375 | $0.00 | ||
| C031 | COMPOSITION SHINGLE REPAIR/INSTALLATION | SF | 1 | 1.436925 | $0.00 | ||
| C032 | R-PANEL REPAIR/INSTALLATION | SF | 1 | 2.92215 | $0.00 | ||
| C033 | WALL SHEATING | SF | 1 | 1.61805 | $0.00 | ||
| C034 | SOFFIT SHEATHING | SF | 1 | 3.634575 | $0.00 | ||
| C035 | WALL SIDING | SF | 1 | 1.61805 | $0.00 | ||
| C036 | PLASTIC LAMINATE PANELS | SF | 1 | 3.030825 | $0.00 | ||
| C037 | LAP OR "V" GROOVED SIDING | SF | 1 | 2.82555 | $0.00 | ||
| C038 | TOILET PARTITION-SINGLE | EA | 1 | 218.5575 | $0.00 | ||
| C039 | TOILET PARTITION-DOUBLE | EA | 1 | 315.1575 | $0.00 | ||
| C040 | TOILET PARTITION-TRIPLE | EA | 1 | 411.7575 | $0.00 | ||
| C041 | SHOWER PARTITION | EA | 1 | 266.8575 | $0.00 | ||
| C042 | SHOWER/TOILET DOOR WITH PILASTER | EA | 1 | 194.4075 | $0.00 | ||
| C043 | URINAL PARTITION | EA | 1 | 170.2575 | $0.00 | ||
| C044 | PAINTING METAL PICNIC SHELTERS | SF | 1 | 1.171275 | $0.00 | ||
| C045 | PAINTING WOOD-OIL BASED PAINT | SF | 1 | 0.905625 | $0.00 | ||
| C046 | PAINTING WOOD-EXTERIOR LATEX PAINT | SF | 1 | 0.905625 | $0.00 | ||
| C047 | PAINTING WOOD-SEALER/STAIN | SF | 1 | 0.905625 | $0.00 | ||
| C048 | PAINTING WOOD-WATERPROOFING | SF | 1 | 0.905625 | $0.00 | ||
| C049 | PAINTING MASONRY-BLOCK SEALER/FILLER | SF | 1 | 0.905625 | $0.00 | ||
| C050 | PAINTING MASONRY-OIL BASED | SF | 1 | 0.905625 | $0.00 | ||
| C051 | PAINTING MASONRY-EXTERIOR LATEX PAINT | SF | 1 | 0.905625 | $0.00 | ||
| C052 | PAINTING METAL-OIL BASED PAINT | SF | 1 | 0.905625 | $0.00 | ||
| C053 | PAINTING METAL-EXTERIOR BASED PAINT | SF | 1 | 0.905625 | $0.00 | ||
| C054 | LOG VENEER SIDING | SF | 1 | 2.82555 | $0.00 | ||
| C055 | LOG SIDING | SF | 1 | 3.079125 | $0.00 | ||
| C056 | OTHER CARPENTRY AND PAINTING | $0.00 | |||||
| $0.00 | |||||||
| Total Section 2 Option Year 2 | $0.00 | ||||||
| $0.00 | |||||||
| CLIN # | Section 3-Paving, Road Maintenance and Site Work | U/M | Unit Price | Estimated Quantity | Unit Price | Unit Price | ERROR:#VALUE! |
| $0.00 | |||||||
| C057 | TOP SOIL | TN | 1 | 77.28 | $0.00 | ||
| C058 | FILL MATERIAL | TN | 1 | 67.62 | $0.00 | ||
| C059 | SAND MATERIAL | TN | 1 | 67.62 | $0.00 | ||
| C060 | Intentionally Left Blank | 96.6 | $0.00 | ||||
| C061 | AGGREGATE ROAD BASE MATERIAL | TN | 1 | 96.6 | $0.00 | ||
| C062 | RIP RAP STONE 3"-5" | TN | 1 | 91.77 | $0.00 | ||
| C063 | RIP RAP STONE 6"-12" | TN | 1 | 107.4675 | $0.00 | ||
| C064 | RIP RAP STONE 12"-18" | TN | 1 | 140.07 | $0.00 | ||
| C065 | GALVANIZED CULVERT REPLACEMENT 15" | LF | 1 | 79.09125 | $0.00 | ||
| C066 | GALVANIZED CULVERT END SECTION 15", PAIR | EA | 1 | 326.025 | $0.00 | ||
| C067 | GALVANIZED CULVERT REPLACEMENT 18" | LF | 1 | 80.0331 | $0.00 | ||
| C068 | GALVANIZED CULVERT END SECTION 18", PAIR | EA | 1 | 374.325 | $0.00 | ||
| C069 | GALVANIZED CULVERT REPLACEMENT 24" | LF | 1 | 87.604125 | $0.00 | ||
| C070 | GALVANIZED CULVERT END SECTION 24", PAIR | EA | 1 | 446.775 | $0.00 | ||
| C071 | GALVANIZED CULVERT REPLACEMENT 30" | LF | 1 | 99.316875 | $0.00 | ||
| C072 | GALVANIZED CULVERT END SECTION 30", PAIR | EA | 1 | 543.375 | $0.00 | ||
| C073 | GALVANIZED CULVERT REPLACEMENT 36" | LF | 1 | 117.550125 | $0.00 | ||
| C074 | GALVANIZED CULVERT END SECTION 36", PAIR | EA | 1 | 784.875 | $0.00 | ||
| C075 | POLYETHYLENE CULVERT REPLACEMENT 12" | LF | 1 | 70.63875 | $0.00 | ||
| C076 | POLYETHYLENE CULVERT REPLACEMENT 18" | LF | 1 | 78.4875 | $0.00 | ||
| C077 | POLYETHYLENE CULVERT REPLACEMENT 24" | LF | 1 | 88.449375 | $0.00 | ||
| C078 | POLYETHYLENE CULVERT REPLACEMENT 36" | LF | 1 | 111.995625 | $0.00 | ||
| C079 | POLYETHYLENE CULVERT REPLACEMENT 48" | LF | 1 | 137.353125 | $0.00 | ||
| C080 | ROAD BORING-2" CASING | LF | 1 | 18.1125 | $0.00 | ||
| C081 | ROAD BORING-4" CASING | LF | 1 | 31.395 | $0.00 | ||
| C082 | ROAD BORING-6" CASING | LF | 1 | 44.6775 | $0.00 | ||
| C083 | ASPHALT PAVING AND PATCHING | SY | 1 | 21.735 | $0.00 | ||
| C084 | SCARFYING AND RESHAPING BASE COURSE | SY | 1 | 6.943125 | $0.00 | ||
| C085 | BITUMINOUS TACK COAT | SY | 1 | 6.64125 | $0.00 | ||
| C086 | BITUMINOUS PRIME COAT | SY | 1 | 6.39975 | $0.00 | ||
| C087 | ASPHALT SECLING COATING | SY | 1 | 2.415 | $0.00 | ||
| C088 | SECLING JOINTS AND CRACKS | LF | 1 | 10.8675 | $0.00 | ||
| C089 | PAINTING/MARKING TRAFFIC CONTROL | LF | 1 | 2.113125 | $0.00 | ||
| C090 | 4" CONCRETE SLAB | SF | 1 | 4.83 | $0.00 | ||
| C091 | 4" CONTRETE SLAB WITH FOOTINGS | SF | 1 | 7.84875 | $0.00 | ||
| C092 | 6" CONCRETE SLAB | SF | 1 | 7.84875 | $0.00 | ||
| C093 | 6" CONCRETE SLAB WITH FOOTINGS | SF | 1 | 9.05625 | $0.00 | ||
| C094 | CONCRETE CURB | LF | 1 | 13.2825 | $0.00 | ||
| C095 | CONCRETE CURB, 24" CURB AND GUTTER | LF | 1 | 25.3575 | $0.00 | ||
| C096 | ROAD SHOULDER MAINTENANCE | LF | 1 | 1.895775 | $0.00 | ||
| C097 | PLAYGROUND MULCH REMOVAL AND DISPOSAL | CY | 1 | 63.768075 | $0.00 | ||
| C098 | BARK CHIP SUPPLY/DELIVERY | CY | 1 | 251.16 | $0.00 | ||
| C099 | RUBBER MULCH SUPPLY/DELIVERY | CY | 1 | 399.6825 | $0.00 | ||
| C100 | LIMESTONE ROAD BASE | SF | 1 | 0.712425 | $0.00 | ||
| C101 | LAUNCH TYPE CONCRETE | SF | 1 | 10.565625 | $0.00 | ||
| C102 | OTHER PAVING, ROAD MAINTENANCE, AND SITE WORK | $0.00 | |||||
| $0.00 | |||||||
| Total Section 3 Option Year 2 | $0.00 | ||||||
| $0.00 | |||||||
| CLIN # | Section 4-Plumbing | U/M | Unit Price | Estimated Quantity | Unit Price | Unit Price | ERROR:#VALUE! |
| $0.00 | |||||||
| C103 | WATER VALVE INSTALLATION 3/4"-2" | EA | 1 | 19.32 | $0.00 | ||
| C104 | WATER VALVE INSTALLATION 2 1/2"-4" | EA | 1 | 28.98 | $0.00 | ||
| C105 | WATER LINE INSTALTATION 3/4"-2" | LF | 1 | 19.32 | $0.00 | ||
| C106 | WATER LINE INSTALTATION 2 1/2"-4" | LF | 1 | 22.33875 | $0.00 | ||
| C107 | GRAVITY SEWER LINE INSTALLATION 4", LESS THAN 4' DEEP | LF | 1 | 91.347375 | $0.00 | ||
| C108 | GRAVITY SEWER LINE INSTALLATION 4", 4.1' TO 10' DEEP | LF | 1 | 214.33125 | $0.00 | ||
| C109 | GRAVITY SEWER LINE INSTALLATION 4", 10.1' TO 15' DEEP | LF | 1 | 244.51875 | $0.00 | ||
| C110 | GRAVITY SEWER LINE INSTALLATION 6", LESS THAN 4' DEEP | LF | 1 | 91.64925 | $0.00 | ||
| C111 | GRAVITY SEWER LINE INSTALLATION 6", 4.1' TO 10' DEEP | LF | 1 | 226.40625 | $0.00 | ||
| C112 | GRAVITY SEWER LINE INSTALLATION 6", 10.1' TO 15' DEEP | LF | 1 | 248.443125 | $0.00 | ||
| C113 | GRAVITY SEWER LINE INSTALLATION 8", LESS THAN 4' DEEP | LF | 1 | 95.99625 | $0.00 | ||
| C114 | GRAVITY SEWER LINE INSTALLATION 8", 4.1' TO 10' DEEP | LF | 1 | 232.745625 | $0.00 | ||
| C115 | GRAVITY SEWER LINE INSTALLATION 8", 10.1' TO 15' DEEP | LF | 1 | 252.97125 | $0.00 | ||
| C116 | COMMODE REPLACEMENT, CHINA /WALL MOUNTED | EA | 1 | 28.98 | $0.00 | ||
| C117 | COMMODE REPLACEMENT, STAINLESS /WALL MOUNTED | EA | 1 | 28.98 | $0.00 | ||
| C118 | COMMODE REPLACEMENT, CHINA /FLOOR MOUNTED | EA | 1 | 28.98 | $0.00 | ||
| C119 | COMMODE REPLACEMENT, STAINLESS /FLOOR MOUNTED | EA | 1 | 28.98 | $0.00 | ||
| C120 | URINAL REPLACEMENT, CHINA /WALL MOUNTED | EA | 1 | 28.98 | $0.00 | ||
| C121 | URINAL REPLACEMENT, STAINLESS / WALL MOUNTED | EA | 1 | 28.98 | $0.00 | ||
| C122 | LAVATORY REPLACEMENT, CHINA /WALL HUNG | EA | 1 | 28.98 | $0.00 | ||
| C123 | LAVATORY REPLACEMENT, STAINLESS /WALL HUNG | EA | 1 | 28.98 | $0.00 | ||
| C124 | WATER HEATER REPLACEMENT-50 GALLON | EA | 1 | 483 | $0.00 | ||
| C125 | WATER HEATER REPLACEMENT-80 GALLON | EA | 1 | 664.125 | $0.00 | ||
| C126 | SELINOID VALVE REPLACEMENT | EA | 1 | 28.98 | $0.00 | ||
| C127 | PNEUMATIC VALVE REPLACEMENT | EA | 1 | 25.3575 | $0.00 | ||
| C128 | WATER HYDRANT ON 4" X 6" POST | EA | 1 | 22.9425 | $0.00 | ||
| C129 | OTHER PLUMBING | $0.00 | |||||
| $0.00 | |||||||
| Total Section 4 Option Year 2 | $0.00 | ||||||
| $0.00 | |||||||
| CLIN # | Section 5-Civil Engineering Services | U/M | Unit Price | Estimated Quantity | Unit Price | Unit Price | ERROR:#VALUE! |
| $0.00 | |||||||
| C130 | HAND OPERATED TOOLS | HR | 1 | 25.96125 | $0.00 | ||
| C131 | DUMP TRUCK, TWENTY TON | HR | 1 | 189.275625 | $0.00 | ||
| C132 | DUMP TRUCK, TWO AND ONE HALF TON | HR | 1 | 46.9415625 | $0.00 | ||
| C133 | MOTOR GRADER, TWELVE FOOT MOLDBOARD | HR | 1 | 95.72516625 | $0.00 | ||
| C134 | BULLDOZER, CRAWLER/TRACTOR TYPE, MINIMUM EIGHT FOOT BLADE | HR | 1 | 137.2021875 | $0.00 | ||
| C135 | BULLDOZER, CRAWLER/TRACTOR TYPE, MINIMUM SIX FOOT BLADE | HR | 1 | 119.844375 | $0.00 | ||
| C136 | WATER TANK TRUCK | HR | 1 | 106.86073125 | $0.00 | ||
| C137 | CRANE, TRUCK MOUNTED, 35 TON W/112' BOOM | HR | 1 | 290.5546875 | $0.00 | ||
| C138 | SHEEP FOOT ROLLER/COMPACTOR | HR | 1 | 96.6 | $0.00 | ||
| C139 | ROLLER/COMPACTOR, PNEUMATIC-TIRED | HR | 1 | 86.1853125 | $0.00 | ||
| C140 | ROLLER/COMPACTOR, STEEL WHEELED | HR | 1 | 96.6 | $0.00 | ||
| C141 | FRONT END LOADER, RUBBER TIRED TYPE | HR | 1 | 141.7303125 | $0.00 | ||
| C142 | TRACTOR, RUBBER TIRED WITH BOX BLADE, AUGER, BUSH HOG ROTARTY MOWER, SIDE BOOM BRUSH HOG ROTARY MOWER | HR | 1 | 35.01448125 | $0.00 | ||
| C143 | BACKHOE, RUBBER TIRED TYPE | HR | 1 | 81.880575 | $0.00 | ||
| C144 | BACKHOE (TRACKHOE) TRACK TYPE | HR | 1 | 190.67934375 | $0.00 | ||
| C145 | TRACTOR, "SKID STEERING" TYPE LOADER | HR | 1 | 61.1900625 | $0.00 | ||
| C146 | DITCHING MACHINE, CHAIN TYPE | HR | 1 | 55.6355625 | $0.00 | ||
| C147 | TRENCHER, ROCK SAW, WHEEL TYPE | HR | 1 | 89.50291875 | $0.00 | ||
| C148 | ROAD BROOM | HR | 1 | 65.3559375 | $0.00 | ||
| C149 | ASPHALT MILLING MACHINE (COLD PLANER) | HR | 1 | 93.80765625 | $0.00 | ||
| C150 | AIR COMPRESSOR | HR | 1 | 92.40695625 | $0.00 | ||
| C151 | WELDER, TRUCK OR TRAILER, MOUNTED | HR | 1 | 49.68922875 | $0.00 | ||
| C152 | VIBRATORY PLATE COMPACTOR | HR | 1 | 42.44422875 | $0.00 | ||
| C153 | WATER PUMP, TWO INCH | HR | 1 | 27.349875 | $0.00 | ||
| C154 | WATER PUMP, FOUR INCH | HR | 1 | 31.51575 | $0.00 | ||
| C155 | WATER PUMP, SIX INCH | HR | 1 | 38.11171875 | $0.00 | ||
| C156 | WASHER HIGH PRESSURE | HR | 1 | 25.2669375 | $0.00 | ||
| C157 | CHIPPER, BRUSH/LIMB | HR | 1 | 51.123135 | $0.00 | ||
| C158 | CONCRETE/ASPHALT SAW | HR | 1 | 23.357578125 | $0.00 | ||
| C159 | CHAIN SAW | HR | 1 | 25.75295625 | $0.00 | ||
| C160 | LATTICE BOOM CRAWLER CRANE WITH TRACKS, 30-80 TON | HR | 1 | 239.990625 | $0.00 | ||
| C161 | RUBBER-TIRED HYDRALIC BOOM (TELESCOPIC) CRANE, 30-90 TON | HR | 1 | 267.763125 | $0.00 | ||
| C162 | RUBBER-TIRED TRUCK MOUNTER CRANE (BOOM TRUCK OR PICKER TRUCK), 25-50 TON | HR | 1 | 309.421875 | $0.00 | ||
| C163 | RUBBER TIRED ROUGH TERRAIN CRANE, 30-90 TON | HR | 1 | 281.649375 | $0.00 | ||
| C164 | ARTICULATING RUBBER-TIRED HYDRAULIC BOOM (TELESCOPIC) CRANE, 100-250 TON | HR | 1 | 339.971625 | $0.00 | ||
| C165 | OTHER ENGINEER SERVICES | $0.00 | |||||
| $0.00 | |||||||
| Total Section 5 Option Year 2 | $0.00 | ||||||
| $0.00 | |||||||
| CLIN # | Section 6-Fencing | U/M | Unit Price | Estimated Quantity | Unit Price | Unit Price | ERROR:#VALUE! |
| $0.00 | |||||||
| C166 | PIPE RAIL FENCING | LF | 1 | 18.535125 | $0.00 | ||
| C167 | PIPE RAIL FENCE GATE | EA | 1 | 357.42 | $0.00 | ||
| C168 | GUARD POST AND CABLE | LF | 1 | 33.81 | $0.00 | ||
| C169 | STEEL POST AND CABLE | LF | 1 | 80.9025 | $0.00 | ||
| C170 | TIMBER VEHICLE BARRIES | EA | 1 | 4.22625 | $0.00 | ||
| C171 | REPAIR/REPLACE GUARDRAIL FENCING | LF | 1 | 392.4375 | $0.00 | ||
| C172 | BARBED WIRE FENCING, STEEL POST, SIX (6) WIRE | LF | 1 | 410.55 | $0.00 | ||
| C173 | INSTALLATION OF SWINGING GATE-4' | EA | 1 | 422.625 | $0.00 | ||
| C174 | INSTALLATION OF SWINGING GATE-12' | EA | 1 | 470.925 | $0.00 | ||
| C175 | INSTALLATION OF SWINGING GATE-14' | EA | 1 | 507.15 | $0.00 | ||
| C176 | INSTALLATION OF SWINGING GATE-16' | EA | 1 | 263.235 | $0.00 | ||
| C177 | OTHER FENCING | $0.00 | |||||
| $0.00 | |||||||
| Total Section 6 Option Year 2 | $0.00 | ||||||
| $0.00 | |||||||
| CLIN # | Section 7-Sign and Buoy Maintenance | U/M | Unit Price | Estimated Quantity | Unit Price | Unit Price | ERROR:#VALUE! |
| $0.00 | |||||||
| C178 | PARK SIGN INSTALLATION-SINGLE POST | EA | 1 | 25.3575 | $0.00 | ||
| C179 | PARK SIGN INSTALLATION-DOUBLE POST | EA | 1 | 38.64 | $0.00 | ||
| C180 | PARK SIGN REPLACEMENT-SIGN ONLY-SINGLE POST | EA | 1 | 13.2825 | $0.00 | ||
| C181 | PARK SIGN REPLACEMENT-SIGN ONLY-DOUBLE POST | EA | 1 | 19.32 | $0.00 | ||
| C182 | BOUY INSTALLATION | EA | 1 | 245.1225 | $0.00 | ||
| C183 | REPAIR/REPLACE PIPELINE FLOATING BARRIER | LF | 1 | 14.49 | $0.00 | ||
| C184 | PIPELINE FLOATING BARRIER ANCHORS | EA | 1 | 245.1225 | $0.00 | ||
| C185 | OTHER SIGN AND BOUY MAINTENANCE | $0.00 | |||||
| $0.00 | |||||||
| Total Section 7 Option Year 2 | $0.00 | ||||||
| $0.00 | |||||||
| CLIN | Section 8-Electrical | U/M | Unit Price | Estimated Quantity | Unit Price | Unit Price | ERROR:#VALUE! |
| $0.00 | |||||||
| C186 | ELECTRIC LINE REPAIR/INSTALLATION, DIRECT BURIAL | LF | 1 | 9.66 | $0.00 | ||
| C187 | ELECTRIC LINE REPAIR/INSTALLATION, IN CONDUIT | LF | 1 | 9.9015 | $0.00 | ||
| C188 | RV PEDESTAL INSTALLATION, SINGLE UNIT | EA | 1 | 144.9 | $0.00 | ||
| C189 | RV PEDESTAL INSTALLATION, DOUBLE UNIT | EA | 1 | 193.2 | $0.00 | ||
| C190 | METER BASE INSTALLATION | EA | 1 | 386.4 | $0.00 | ||
| C191 | MAIN DISCONNECT PANEL INSTALLATION | EA | 1 | 422.625 | $0.00 | ||
| C192 | LOAD CENTER PANEL | EA | 1 | 1026.375 | $0.00 | ||
| C193 | OTHER ELECTRICAL |
| Total Section 8 Option Year 2 |
| Total Option Option Year 2 Sections 1-8 (CLINs C001-C193) |
OP3
| OP3 | |||||||
| CLIN # | Section 1-Campsite Maintenance | U/M | Unit Price | Estimated Quantity | Estimated Price | ||
| Rounding Fix | |||||||
| D001 | CONCRETE WHEEL STOPS | EA | 1 | 76.0725 | $0.00 | ||
| D002 | TIMBER DELINIATORS, ONE TIER | LF | 1 | 10.143 | $0.00 | ||
| D003 | TIMBER DELINIATORS,TWO TIER | LF | 1 | 10.143 | $0.00 | ||
| D004 | TIMBER DELINIATORS, THREE TIER | LF | 1 | 10.143 | $0.00 | ||
| D005 | TIMBER DELINIATORS, FOUR TIER | LF | 1 | 10.143 | $0.00 | ||
| D006 | TIMBER DELINIATORS, TIER FIVE | LF | 1 | 10.143 | $0.00 | ||
| D007 | UPRIGHT AND PEDASTAL GRILL INSTALLATION | LF | 1 | 38.03625 | $0.00 | ||
| D008 | FIRE RING AND GROUND MOUNTED COOKER INSTALLATION | EA | 1 | 31.696875 | $0.00 | ||
| D009 | LANTER HANGER POST INSTALLION | EA | 1 | 38.03625 | $0.00 | ||
| D010 | REPLACE/INSTALL VINYL COATED OR ALUMINIUM PICNIC TABLES | EA | 1 | 44.375625 | $0.00 | ||
| D011 | REPLACE/INSTALL PARK BENCHES | EA | 1 | 50.715 | $0.00 | ||
| D012 | RETAINER WALL BLOCK INSTALLATION ONE | LF | 1 | 1.33126875 | $0.00 | ||
| D013 | RETAINER WALL BLOCK INSTALLATION TWO | LF | 1 | 1.33126875 | $0.00 | ||
| D014 | RETAINER WALL BLOCK INSTALLATION THREE | LF | 1 | 1.33126875 | $0.00 | ||
| D015 | RETAINER WALL BLOCK INSTALLATION FOUR | LF | 1 | 1.33126875 | $0.00 | ||
| D016 | RETAINER WALL BLOCK INSTALLATION FIVE | LF | 1 | 1.33126875 | $0.00 | ||
| D017 | RIP RAP BAG INSTALLATION ONE | LF | 1 | 1.0143 | $0.00 | ||
| D018 | RIP RAP BAG INSTALLATION TWO | LF | 1 | 1.0143 | $0.00 | ||
| D019 | RIP RAP BAG INSTALLATION THREE | LF | 1 | 1.0143 | $0.00 | ||
| D020 | RIP RAP BAG INSTALLATION FOUR | LF | 1 | 1.0143 | $0.00 | ||
| D021 | RIP RAP BAG INSTALLATION FIVE | LF | 1 | 1.0143 | $0.00 | ||
| D022 | RIP RAP BAG INSTALLATION SIX | LF | 1 | 1.0143 | $0.00 | ||
| D023 | RIP RAP BAG INSTALLATION SEVEN | LF | 1 | 1.0143 | $0.00 | ||
| D024 | RIP RAP BAG INSTALLATION EIGHT | LF | 1 | 1.0143 | $0.00 | ||
| D025 | OTHER CAMPSITE MAINTENANCE | $0.00 | |||||
| $0.00 | |||||||
| Total Section 1 Option Year 3 | $0.00 | ||||||
| $0.00 | |||||||
| CLIN # | Section 2-Carpentry and Painting | U/M | Unit Price | Estimated Quantity | Unit Price | Unit Price | ERROR:#VALUE! |
| $0.00 | |||||||
| D026 | METAL PICNIC SHELTER INSTALLATION | EA | 1 | 767.064375 | $0.00 | ||
| D027 | ROOFING REMOVAL (COMPOSITION AND R-PANEL) | SF | 1 | 0.95090625 | $0.00 | ||
| D028 | ROOF SHEATHING | SF | 1 | 1.83841875 | $0.00 | ||
| D029 | TONGUE AND GROVE DECKING | SF | 1 | 2.29485375 | $0.00 | ||
| D030 | FASCIA BOARD | LF | 1 | 13.24929375 | $0.00 | ||
| D031 | COMPOSITION SHINGLE REPAIR/INSTALLATION | SF | 1 | 1.50877125 | $0.00 | ||
| D032 | R-PANEL REPAIR/INSTALLATION | SF | 1 | 3.0682575 | $0.00 | ||
| D033 | WALL SHEATING | SF | 1 | 1.6989525 | $0.00 | ||
| D034 | SOFFIT SHEATHING | SF | 1 | 3.81630375 | $0.00 | ||
| D035 | WALL SIDING | SF | 1 | 1.6989525 | $0.00 | ||
| D036 | PLASTIC LAMINATE PANELS | SF | 1 | 3.18236625 | $0.00 | ||
| D037 | LAP OR "V" GROOVED SIDING | SF | 1 | 2.9668275 | $0.00 | ||
| D038 | TOILET PARTITION-SINGLE | EA | 1 | 229.485375 | $0.00 | ||
| D039 | TOILET PARTITION-DOUBLE | EA | 1 | 330.915375 | $0.00 | ||
| D040 | TOILET PARTITION-TRIPLE | EA | 1 | 432.345375 | $0.00 | ||
| D041 | SHOWER PARTITION | EA | 1 | 280.200375 | $0.00 | ||
| D042 | SHOWER/TOILET DOOR WITH PILASTER | EA | 1 | 204.127875 | $0.00 | ||
| D043 | URINAL PARTITION | EA | 1 | 178.770375 | $0.00 | ||
| D044 | PAINTING METAL PICNIC SHELTERS | SF | 1 | 1.22983875 | $0.00 | ||
| D045 | PAINTING WOOD-OIL BASED PAINT | SF | 1 | 0.95090625 | $0.00 | ||
| D046 | PAINTING WOOD-EXTERIOR LATEX PAINT | SF | 1 | 0.95090625 | $0.00 | ||
| D047 | PAINTING WOOD-SEALER/STAIN | SF | 1 | 0.95090625 | $0.00 | ||
| D048 | PAINTING WOOD-WATERPROOFING | SF | 1 | 0.95090625 | $0.00 | ||
| D049 | PAINTING MASONRY-BLOCK SEALER/FILLER | SF | 1 | 0.95090625 | $0.00 | ||
| D050 | PAINTING MASONRY-OIL BASED | SF | 1 | 0.95090625 | $0.00 | ||
| D051 | PAINTING MASONRY-EXTERIOR LATEX PAINT | SF | 1 | 0.95090625 | $0.00 | ||
| D052 | PAINTING METAL-OIL BASED PAINT | SF | 1 | 0.95090625 | $0.00 | ||
| D053 | PAINTING METAL-EXTERIOR BASED PAINT | SF | 1 | 0.95090625 | $0.00 | ||
| D054 | LOG VENEER SIDING | SF | 1 | 2.9668275 | $0.00 | ||
| D055 | LOG SIDING | SF | 1 | 3.23308125 | $0.00 | ||
| D056 | OTHER CARPENTRY AND PAINTING | $0.00 | |||||
| $0.00 | |||||||
| Total Section 2 Option Year 3 | $0.00 | ||||||
| $0.00 | |||||||
| CLIN # | Section 3-Paving, Road Maintenance and Site Work | U/M | Unit Price | Estimated Quantity | Unit Price | Unit Price | ERROR:#VALUE! |
| $0.00 | |||||||
| D057 | TOP SOIL | TN | 1 | 81.144 | $0.00 | ||
| D058 | FILL MATERIAL | TN | 1 | 71.001 | $0.00 | ||
| D059 | SAND MATERIAL | TN | 1 | 71.001 | $0.00 | ||
| D060 | Intentionally Left Blank | 101.43 | $0.00 | ||||
| D061 | AGGREGATE ROAD BASE MATERIAL | TN | 1 | 101.43 | $0.00 | ||
| D062 | RIP RAP STONE 3"-5" | TN | 1 | 96.3585 | $0.00 | ||
| D063 | RIP RAP STONE 6"-12" | TN | 1 | 112.840875 | $0.00 | ||
| D064 | RIP RAP STONE 12"-18" | TN | 1 | 147.0735 | $0.00 | ||
| D065 | GALVANIZED CULVERT REPLACEMENT 15" | LF | 1 | 83.0458125 | $0.00 | ||
| D066 | GALVANIZED CULVERT END SECTION 15", PAIR | EA | 1 | 342.32625 | $0.00 | ||
| D067 | GALVANIZED CULVERT REPLACEMENT 18" | LF | 1 | 84.034755 | $0.00 | ||
| D068 | GALVANIZED CULVERT END SECTION 18", PAIR | EA | 1 | 393.04125 | $0.00 | ||
| D069 | GALVANIZED CULVERT REPLACEMENT 24" | LF | 1 | 91.98433125 | $0.00 | ||
| D070 | GALVANIZED CULVERT END SECTION 24", PAIR | EA | 1 | 469.11375 | $0.00 | ||
| D071 | GALVANIZED CULVERT REPLACEMENT 30" | LF | 1 | 104.28271875 | $0.00 | ||
| D072 | GALVANIZED CULVERT END SECTION 30", PAIR | EA | 1 | 570.54375 | $0.00 | ||
| D073 | GALVANIZED CULVERT REPLACEMENT 36" | LF | 1 | 123.42763125 | $0.00 | ||
| D074 | GALVANIZED CULVERT END SECTION 36", PAIR | EA | 1 | 824.11875 | $0.00 | ||
| D075 | POLYETHYLENE CULVERT REPLACEMENT 12" | LF | 1 | 74.1706875 | $0.00 | ||
| D076 | POLYETHYLENE CULVERT REPLACEMENT 18" | LF | 1 | 82.411875 | $0.00 | ||
| D077 | POLYETHYLENE CULVERT REPLACEMENT 24" | LF | 1 | 92.87184375 | $0.00 | ||
| D078 | POLYETHYLENE CULVERT REPLACEMENT 36" | LF | 1 | 117.59540625 | $0.00 | ||
| D079 | POLYETHYLENE CULVERT REPLACEMENT 48" | LF | 1 | 144.22078125 | $0.00 | ||
| D080 | ROAD BORING-2" CASING | LF | 1 | 19.018125 | $0.00 | ||
| D081 | ROAD BORING-4" CASING | LF | 1 | 32.96475 | $0.00 | ||
| D082 | ROAD BORING-6" CASING | LF | 1 | 46.911375 | $0.00 | ||
| D083 | ASPHALT PAVING AND PATCHING | SY | 1 | 22.82175 | $0.00 | ||
| D084 | SCARFYING AND RESHAPING BASE COURSE | SY | 1 | 7.29028125 | $0.00 | ||
| D085 | BITUMINOUS TACK COAT | SY | 1 | 6.9733125 | $0.00 | ||
| D086 | BITUMINOUS PRIME COAT | SY | 1 | 6.7197375 | $0.00 | ||
| D087 | ASPHALT SECLING COATING | SY | 1 | 2.53575 | $0.00 | ||
| D088 | SECLING JOINTS AND CRACKS | LF | 1 | 11.410875 | $0.00 | ||
| D089 | PAINTING/MARKING TRAFFIC CONTROL | LF | 1 | 2.21878125 | $0.00 | ||
| D090 | 4" CONCRETE SLAB | SF | 1 | 5.0715 | $0.00 | ||
| D091 | 4" CONTRETE SLAB WITH FOOTINGS | SF | 1 | 8.2411875 | $0.00 | ||
| D092 | 6" CONCRETE SLAB | SF | 1 | 8.2411875 | $0.00 | ||
| D093 | 6" CONCRETE SLAB WITH FOOTINGS | SF | 1 | 9.5090625 | $0.00 | ||
| D094 | CONCRETE CURB | LF | 1 | 13.946625 | $0.00 | ||
| D095 | CONCRETE CURB, 24" CURB AND GUTTER | LF | 1 | 26.625375 | $0.00 | ||
| D096 | ROAD SHOULDER MAINTENANCE | LF | 1 | 1.99056375 | $0.00 | ||
| D097 | PLAYGROUND MULCH REMOVAL AND DISPOSAL | CY | 1 | 66.95647875 | $0.00 | ||
| D098 | BARK CHIP SUPPLY/DELIVERY | CY | 1 | 263.718 | $0.00 | ||
| D099 | RUBBER MULCH SUPPLY/DELIVERY | CY | 1 | 419.666625 | $0.00 | ||
| D100 | LIMESTONE ROAD BASE | SF | 1 | 0.74804625 | $0.00 | ||
| D101 | LAUNCH TYPE CONCRETE | SF | 1 | 11.09390625 | $0.00 | ||
| D102 | OTHER PAVING, ROAD MAINTENANCE, AND SITE WORK | $0.00 | |||||
| $0.00 | |||||||
| Total Section 3 Option Year 3 | $0.00 | ||||||
| $0.00 | |||||||
| CLIN # | Section 4-Plumbing | U/M | Unit Price | Estimated Quantity | Unit Price | Unit Price | ERROR:#VALUE! |
| $0.00 | |||||||
| D103 | WATER VALVE INSTALLATION 3/4"-2" | EA | 1 | 20.286 | $0.00 | ||
| D104 | WATER VALVE INSTALLATION 2 1/2"-4" | EA | 1 | 30.429 | $0.00 | ||
| D105 | WATER LINE INSTALTATION 3/4"-2" | LF | 1 | 20.286 | $0.00 | ||
| D106 | WATER LINE INSTALTATION 2 1/2"-4" | LF | 1 | 23.4556875 | $0.00 | ||
| D107 | GRAVITY SEWER LINE INSTALLATION 4", LESS THAN 4' DEEP | LF | 1 | 95.91474375 | $0.00 | ||
| D108 | GRAVITY SEWER LINE INSTALLATION 4", 4.1' TO 10' DEEP | LF | 1 | 225.0478125 | $0.00 | ||
| D109 | GRAVITY SEWER LINE INSTALLATION 4", 10.1' TO 15' DEEP | LF | 1 | 256.7446875 | $0.00 | ||
| D110 | GRAVITY SEWER LINE INSTALLATION 6", LESS THAN 4' DEEP | LF | 1 | 96.2317125 | $0.00 | ||
| D111 | GRAVITY SEWER LINE INSTALLATION 6", 4.1' TO 10' DEEP | LF | 1 | 237.7265625 | $0.00 | ||
| D112 | GRAVITY SEWER LINE INSTALLATION 6", 10.1' TO 15' DEEP | LF | 1 | 260.86528125 | $0.00 | ||
| D113 | GRAVITY SEWER LINE INSTALLATION 8", LESS THAN 4' DEEP | LF | 1 | 100.7960625 | $0.00 | ||
| D114 | GRAVITY SEWER LINE INSTALLATION 8", 4.1' TO 10' DEEP | LF | 1 | 244.38290625 | $0.00 | ||
| D115 | GRAVITY SEWER LINE INSTALLATION 8", 10.1' TO 15' DEEP | LF | 1 | 265.6198125 | $0.00 | ||
| D116 | COMMODE REPLACEMENT, CHINA /WALL MOUNTED | EA | 1 | 30.429 | $0.00 | ||
| D117 | COMMODE REPLACEMENT, STAINLESS /WALL MOUNTED | EA | 1 | 30.429 | $0.00 | ||
| D118 | COMMODE REPLACEMENT, CHINA /FLOOR MOUNTED | EA | 1 | 30.429 | $0.00 | ||
| D119 | COMMODE REPLACEMENT, STAINLESS /FLOOR MOUNTED | EA | 1 | 30.429 | $0.00 | ||
| D120 | URINAL REPLACEMENT, CHINA /WALL MOUNTED | EA | 1 | 30.429 | $0.00 | ||
| D121 | URINAL REPLACEMENT, STAINLESS / WALL MOUNTED | EA | 1 | 30.429 | $0.00 | ||
| D122 | LAVATORY REPLACEMENT, CHINA /WALL HUNG | EA | 1 | 30.429 | $0.00 | ||
| D123 | LAVATORY REPLACEMENT, STAINLESS /WALL HUNG | EA | 1 | 30.429 | $0.00 | ||
| D124 | WATER HEATER REPLACEMENT-50 GALLON | EA | 1 | 507.15 | $0.00 | ||
| D125 | WATER HEATER REPLACEMENT-80 GALLON | EA | 1 | 697.33125 | $0.00 | ||
| D126 | SELINOID VALVE REPLACEMENT | EA | 1 | 30.429 | $0.00 | ||
| D127 | PNEUMATIC VALVE REPLACEMENT | EA | 1 | 26.625375 | $0.00 | ||
| D128 | WATER HYDRANT ON 4" X 6" POST | EA | 1 | 24.089625 | $0.00 | ||
| D129 | OTHER PLUMBING | $0.00 | |||||
| $0.00 | |||||||
| Total Section 4 Option Year 3 | $0.00 | ||||||
| $0.00 | |||||||
| CLIN # | Section 5-Civil Engineering Services | U/M | Unit Price | Estimated Quantity | Unit Price | Unit Price | ERROR:#VALUE! |
| $0.00 | |||||||
| D130 | HAND OPERATED TOOLS | HR | 1 | 27.2593125 | $0.00 | ||
| D131 | DUMP TRUCK, TWENTY TON | HR | 1 | 198.73940625 | $0.00 | ||
| D132 | DUMP TRUCK, TWO AND ONE HALF TON | HR | 1 | 49.288640625 | $0.00 | ||
| D133 | MOTOR GRADER, TWELVE FOOT MOLDBOARD | HR | 1 | 100.5114245625 | $0.00 | ||
| D134 | BULLDOZER, CRAWLER/TRACTOR TYPE, MINIMUM EIGHT FOOT BLADE | HR | 1 | 144.062296875 | $0.00 | ||
| D135 | BULLDOZER, CRAWLER/TRACTOR TYPE, MINIMUM SIX FOOT BLADE | HR | 1 | 125.83659375 | $0.00 | ||
| D136 | WATER TANK TRUCK | HR | 1 | 112.2037678125 | $0.00 | ||
| D137 | CRANE, TRUCK MOUNTED, 35 TON W/112' BOOM | HR | 1 | 305.082421875 | $0.00 | ||
| D138 | SHEEP FOOT ROLLER/COMPACTOR | HR | 1 | 101.43 | $0.00 | ||
| D139 | ROLLER/COMPACTOR, PNEUMATIC-TIRED | HR | 1 | 90.494578125 | $0.00 | ||
| D140 | ROLLER/COMPACTOR, STEEL WHEELED | HR | 1 | 101.43 | $0.00 | ||
| D141 | FRONT END LOADER, RUBBER TIRED TYPE | HR | 1 | 148.816828125 | $0.00 | ||
| D142 | TRACTOR, RUBBER TIRED WITH BOX BLADE, AUGER, BUSH HOG ROTARTY MOWER, SIDE BOOM BRUSH HOG ROTARY MOWER | HR | 1 | 36.7652053125 | $0.00 | ||
| D143 | BACKHOE, RUBBER TIRED TYPE | HR | 1 | 85.97460375 | $0.00 | ||
| D144 | BACKHOE (TRACKHOE) TRACK TYPE | HR | 1 | 200.2133109375 | $0.00 | ||
| D145 | TRACTOR, "SKID STEERING" TYPE LOADER | HR | 1 | 64.249565625 | $0.00 | ||
| D146 | DITCHING MACHINE, CHAIN TYPE | HR | 1 | 58.417340625 | $0.00 | ||
| D147 | TRENCHER, ROCK SAW, WHEEL TYPE | HR | 1 | 93.9780646875 | $0.00 | ||
| D148 | ROAD BROOM | HR | 1 | 68.623734375 | $0.00 | ||
| D149 | ASPHALT MILLING MACHINE (COLD PLANER) | HR | 1 | 98.4980390625 | $0.00 | ||
| D150 | AIR COMPRESSOR | HR | 1 | 97.0273040625 | $0.00 | ||
| D151 | WELDER, TRUCK OR TRAILER, MOUNTED | HR | 1 | 52.1736901875 | $0.00 | ||
| D152 | VIBRATORY PLATE COMPACTOR | HR | 1 | 44.5664401875 | $0.00 | ||
| D153 | WATER PUMP, TWO INCH | HR | 1 | 28.71736875 | $0.00 | ||
| D154 | WATER PUMP, FOUR INCH | HR | 1 | 33.0915375 | $0.00 | ||
| D155 | WATER PUMP, SIX INCH | HR | 1 | 40.0173046875 | $0.00 | ||
| D156 | WASHER HIGH PRESSURE | HR | 1 | 26.530284375 | $0.00 | ||
| D157 | CHIPPER, BRUSH/LIMB | HR | 1 | 53.67929175 | $0.00 | ||
| D158 | CONCRETE/ASPHALT SAW | HR | 1 | 24.5254570312 | $0.00 | ||
| D159 | CHAIN SAW | HR | 1 | 27.0406040625 | $0.00 | ||
| D160 | LATTICE BOOM CRAWLER CRANE WITH TRACKS, 30-80 TON | HR | 1 | 251.99015625 | $0.00 | ||
| D161 | RUBBER-TIRED HYDRALIC BOOM (TELESCOPIC) CRANE, 30-90 TON | HR | 1 | 281.15128125 | $0.00 | ||
| D162 | RUBBER-TIRED TRUCK MOUNTER CRANE (BOOM TRUCK OR PICKER TRUCK), 25-50 TON | HR | 1 | 324.89296875 | $0.00 | ||
| D163 | RUBBER TIRED ROUGH TERRAIN CRANE, 30-90 TON | HR | 1 | 295.73184375 | $0.00 | ||
| D164 | ARTICULATING RUBBER-TIRED HYDRAULIC BOOM (TELESCOPIC) CRANE, 100-250 TON | HR | 1 | 356.97020625 | $0.00 | ||
| D165 | OTHER ENGINEER SERVICES | $0.00 | |||||
| $0.00 | |||||||
| Total Section 5 Option Year 3 | $0.00 | ||||||
| $0.00 | |||||||
| CLIN # | Section 6-Fencing | U/M | Unit Price | Estimated Quantity | Unit Price | Unit Price | ERROR:#VALUE! |
| $0.00 | |||||||
| D166 | PIPE RAIL FENCING | LF | 1 | 19.46188125 | $0.00 | ||
| D167 | PIPE RAIL FENCE GATE | EA | 1 | 375.291 | $0.00 | ||
| D168 | GUARD POST AND CABLE | LF | 1 | 35.5005 | $0.00 | ||
| D169 | STEEL POST AND CABLE | LF | 1 | 84.947625 | $0.00 | ||
| D170 | TIMBER VEHICLE BARRIES | EA | 1 | 4.4375625 | $0.00 | ||
| D171 | REPAIR/REPLACE GUARDRAIL FENCING | LF | 1 | 412.059375 | $0.00 | ||
| D172 | BARBED WIRE FENCING, STEEL POST, SIX (6) WIRE | LF | 1 | 431.0775 | $0.00 | ||
| D173 | INSTALLATION OF SWINGING GATE-4' | EA | 1 | 443.75625 | $0.00 | ||
| D174 | INSTALLATION OF SWINGING GATE-12' | EA | 1 | 494.47125 | $0.00 | ||
| D175 | INSTALLATION OF SWINGING GATE-14' | EA | 1 | 532.5075 | $0.00 | ||
| D176 | INSTALLATION OF SWINGING GATE-16' | EA | 1 | 276.39675 | $0.00 | ||
| D177 | OTHER FENCING | $0.00 | |||||
| $0.00 | |||||||
| Total Section 6 Option Year 3 | $0.00 | ||||||
| $0.00 | |||||||
| CLIN # | Section 7-Sign and Buoy Maintenance | U/M | Unit Price | Estimated Quantity | Unit Price | Unit Price | ERROR:#VALUE! |
| $0.00 | |||||||
| D178 | PARK SIGN INSTALLATION-SINGLE POST | EA | 1 | 26.625375 | $0.00 | ||
| D179 | PARK SIGN INSTALLATION-DOUBLE POST | EA | 1 | 40.572 | $0.00 | ||
| D180 | PARK SIGN REPLACEMENT-SIGN ONLY-SINGLE POST | EA | 1 | 13.946625 | $0.00 | ||
| D181 | PARK SIGN REPLACEMENT-SIGN ONLY-DOUBLE POST | EA | 1 | 20.286 | $0.00 | ||
| D182 | BOUY INSTALLATION | EA | 1 | 257.378625 | $0.00 | ||
| D183 | REPAIR/REPLACE PIPELINE FLOATING BARRIER | LF | 1 | 15.2145 | $0.00 | ||
| D184 | PIPELINE FLOATING BARRIER ANCHORS | EA | 1 | 257.378625 | $0.00 | ||
| D185 | OTHER SIGN AND BOUY MAINTENANCE | $0.00 | |||||
| $0.00 | |||||||
| Total Section 7 Option Year 3 | $0.00 | ||||||
| $0.00 | |||||||
| CLIN | Section 8-Electrical | U/M | Unit Price | Estimated Quantity | Unit Price | Unit Price | ERROR:#VALUE! |
| $0.00 | |||||||
| D186 | ELECTRIC LINE REPAIR/INSTALLATION, DIRECT BURIAL | LF | 1 | 10.143 | $0.00 | ||
| D187 | ELECTRIC LINE REPAIR/INSTALLATION, IN CONDUIT | LF | 1 | 10.396575 | $0.00 | ||
| D188 | RV PEDESTAL INSTALLATION, SINGLE UNIT | EA | 1 | 152.145 | $0.00 | ||
| D189 | RV PEDESTAL INSTALLATION, DOUBLE UNIT | EA | 1 | 202.86 | $0.00 |