am_2.pdf

PDF 15 MB Posted

Attached to
ARNORTH Building 44 Renovation Federal contract opportunity
Solicitation number
W9126G18B0036
Issued by
Department of the Army Corps of Engineers Engineering District Fort Worth

About this file

AM 02

View the file

Other files for this federal contract opportunity

Other files attached to ARNORTH Building 44 Renovation, newest first.
File Type Posted
am_6.pdf PDF
am_5.pdf PDF
am_4.pdf PDF
am_3.pdf PDF
am_2.zip ZIP file
g18b0036_AM1.pdf PDF
2nd_Flr_Plans.pdf PDF
180716_-_B44_-_Final_CID_Attachment_M.pdf PDF
Attachment_G_ACMLBPSpecs.pdf PDF
A1.2_3rd_Flr_Plans.pdf PDF
A1.2_Appendix_B_-_B44_-_Final_Geotechnical_Report.pdf PDF
B3_Solicitation_W9126G18B0036.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The Solicitation for FY18 ARNORTH B44 Renovation, JBSA/FSH, San Antonio, Texas is amended as follows.

See SF30 Continuation Sheet(s)

NOTE: Proposal Receipt date is 11 September 2018 at 2:00 PM Central Time, as previously announced.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X 9A. AMENDMENT OF SOLICITATION NO.

W9126G18B0036

X 9B. DATED (SEE ITEM 11)

09-Aug-2018

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

August 21, 2018

CODE

US ARMY ENGINEER DISTRICT, FORT WORTH

ATTN: CESWF-CT

819 TAYLOR ST, ROOM 2A19

P.O. BOX 17300

FORT WORTH TX 76102-0300

W9126G 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9126G18B0036

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

This Amendment is to issue the 100% Design. Division 00, 01, and Appendices are unchanged. See the attached updated specifications and drawings (provided as a separate pdf), each bearing the notation “W9126G18B0036- 0002”.

CHANGES TO THE SPECIFICATIONS

1. New Sections: The following section has been added to the solicitation and option 1, bearing the notation “W9126G18B0036-0002”.

Solicitation:

01 91 00.15 TOTAL BUILDING COMMISSIONING

03 30 00 CAST - IN - PLACE CONCRETE

05 05 23.16 STRUCTURAL WELDING

05 12 00 STRUCTURAL STEEL

05 30 00 STEEL DECKS

07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS

08 45 23 2 – ¾” INSULATED TRANSLUCENT FIBERGLASS SANDWICH PANEL

23 09 23 BACNET DIRECT DIGITAL CONTROLS (DDC) SYSTEM FOR FORT SAM HOUSTON

23 21 23 HYDRONIC PUMPS

31 63 29 DRILLED CONCRETE PIERS AND SHAFTS

Option 1:

01 91 00.15 TOTAL BUILDING COMMISSIONING

05 05 23.16 STRUCTURAL WELDING

05 12 00 STRUCTURAL STEEL

07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS

07 22 00 ROOF AND DECK INSULATION

07 27 10.00 10 BUILDING AIR BARRIER SYSTEM

07 27 19.01 SELF-ADHERING AIR BARRIERS

08 45 23 2 – ¾” INSULATED TRANSLUCENT FIBERGLASS SANDWICH PANEL

23 09 23 BACNET DIRECT DIGITAL CONTROLS (DDC) SYSTEM FOR FORT SAM

HOUSTON

2. Deleted Sections: The following section has been deleted from the solicitation and option 1.

Solicitation:

27 13 23.00 40 COMMUNICATIONS OPTICAL BACKBONE CABLING

27 21 00.00 20 INTERCOMMUNICATION SYSTEM

27 21 00.00 40 INTERCOMMUNICATION SYSTEM

28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM

Option 1:

12 36 00 COUNTERTOPS

27 13 23.00 40 COMMUNICATIONS OPTICAL BACKBONE CABLING

27 21 00.00 20 INTERCOMMUNICATION SYSTEM

27 21 00.00 40 INTERCOMMUNICATION SYSTEM

28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM

End of Summary of Changes

FY18 ARNORTH B44 Renovation FSH18ANSRMB44LS

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 11 00.01 SOLICITATION, OFFER AND AWARD, SF-1442

00 11 00.02 CONTRACT LINE ITEM SCHEDULE

00 21 00 INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS

00 45 00 REPRESENTATIONS AND CERTIFICATIONS

00 72 00 CONTRACT CLAUSES

00 73 00 SPECIAL CONTRACT REQUIREMENTS

00 73 46 WAGE DETERMINATION SCHEDULE

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00.00 44 CONSTRUCTION SCHEDULE

01 32 01.00 10 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 13.01 44 SPECIAL PROJECT PROCEDURES FOR JOINT BASE SAN

ANTONIO/FORT SAM HOUSTON

01 35 13.02 44 ISSUANCE OF ACCESS TO NON-COMMON ACCESS CARD CONTRACTORS,

VENDORS, AND NON-DOD CIVILIANS

01 35 13.03 44 TECHNICAL SUPPLEMENT TO THE DESIGN GUIDE FOR JOINT BASE

SAN ANTONIO/FORT SAM HOUSTON

01 35 13.10 00 SPECIAL PROJECT PROCEDURES - SURVEYING

01 35 13.20 00 SPECIAL PROJECT PROCEDURES - CAD

01 35 13.30 00 SPECIAL PROJECT PROCEDURES - GIS

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 10 QUALITY CONTROL

01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE(RMS CM)

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 57 20.00 10 ENVIRONMENTAL PROTECTION

01 58 00 PROJECT IDENTIFICATION

01 62 35 RECYCLED / RECOVERED MATERIALS

01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATION AND MAINTENANCE DATA

01 91 00.15 TOTAL BUILDING COMMISSIONING

DIVISION 02 - EXISTING CONDITIONS

02 41 00 DEMOLITION

DIVISION 03 - CONCRETE

03 30 00 CAST-IN-PLACE CONCRETE

03 35 43 POLISHED CONCRETE FINISHING

DIVISION 04 - MASONRY

04 20 00 UNIT MASONRY

DIVISION 05 - METALS

05 05 23.16 STRUCTURAL WELDING

05 12 00 STRUCTURAL STEEL

05 30 00 STEEL DECKS

05 50 13 MISCELLANEOUS METAL FABRICATIONS

05 51 00 METAL STAIRS

PROJECT TABLE OF CONTENTS Page 1

W9126G18B0036-0002

05 51 33 METAL LADDERS

05 52 00 METAL RAILINGS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 10 00 ROUGH CARPENTRY

06 20 00 FINISH CARPENTRY

06 41 16.00 10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS

06 61 16 SOLID SURFACING FABRICATIONS

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS

07 11 13 BITUMINOUS DAMPPROOFING

07 21 16 MINERAL FIBER BLANKET INSULATION

07 22 00 ROOF AND DECK INSULATION

07 24 00 EXTERIOR INSULATION AND FINISH SYSTEMS

07 27 10.00 10 BUILDING AIR BARRIER SYSTEM

07 27 19.01 SELF-ADHERING AIR BARRIERS

07 27 36 SPRAY FOAM AIR BARRIERS

07 54 19 POLYVINYL-CHLORIDE ROOFING

07 60 00 FLASHING AND SHEET METAL

07 84 00 FIRESTOPPING

07 92 00 JOINT SEALANTS

DIVISION 08 - OPENINGS

08 11 13 STEEL DOORS AND FRAMES

08 14 00 WOOD DOORS

08 31 00 ACCESS DOORS AND PANELS

08 41 13 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS

08 45 23 2-3/4" INSULATED TRANSLUCENT FIBERGLASS SANDWICH PANEL

WALL SYSTEM

08 71 00 DOOR HARDWARE

08 81 00 GLAZING

08 91 00 METAL WALL LOUVERS

DIVISION 09 - FINISHES

09 06 00 SCHEDULES FOR FINISHES

09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD

09 29 00 GYPSUM BOARD

09 30 10 CERAMIC, QUARRY, AND GLASS TILING

09 51 00 ACOUSTICAL CEILINGS

09 65 00 RESILIENT FLOORING

09 68 00 CARPETING

09 90 00 PAINTS AND COATINGS

DIVISION 10 - SPECIALTIES

10 11 00 VISUAL DISPLAY UNITS

10 14 00.20 INTERIOR SIGNAGE

10 21 13 TOILET COMPARTMENTS

10 22 39 FOLDING PANEL PARTITIONS

10 26 00 WALL AND DOOR PROTECTION

10 28 13 TOILET ACCESSORIES

10 44 16 FIRE EXTINGUISHERS

DIVISION 12 - FURNISHINGS

PROJECT TABLE OF CONTENTS Page 2

12 24 13 ROLLER WINDOW SHADES

12 50 00.13 10 FURNITURE AND FURNITURE INSTALLATION

12 59 00 SYSTEMS FURNITURE

DIVISION 14 - CONVEYING EQUIPMENT

14 21 23 ELECTRIC TRACTION PASSENGER ELEVATORS

DIVISION 21 - FIRE SUPPRESSION

21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION

DIVISION 22 - PLUMBING

22 00 00 PLUMBING, GENERAL PURPOSE

22 07 19.00 40 PLUMBING PIPING INSULATION

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS

23 01 30.41 HVAC SYSTEM CLEANING

23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS

23 05 15 COMMON PIPING FOR HVAC

23 05 48.00 40 VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND

EQUIPMENT

23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC

23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS

23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC

23 21 23 HYDRONIC PUMPS

23 31 13.00 40 METAL DUCTS

23 34 23.00 40 HVAC POWER VENTILATORS

23 36 00.00 40 AIR TERMINAL UNITS

23 37 13.00 40 DIFFUSERS, REGISTERS, AND GRILLS

23 52 43.00 20 LOW PRESSURE WATER HEATING BOILERS (UNDER 800,000 BTU/HR

OUTPUT)

23 64 10 WATER CHILLERS, VAPOR COMPRESSION TYPE

23 73 13.00 40 MODULAR INDOOR CENTRAL-STATION AIR-HANDLING UNITS

DIVISION 26 - ELECTRICAL

26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS

26 05 00.00 40 COMMON WORK RESULTS FOR ELECTRICAL

26 05 19.10 10 INSULATED WIRE AND CABLE

26 05 71.00 40 LOW VOLTAGE OVERCURRENT PROTECTIVE DEVICES

26 09 23.00 40 LIGHTING CONTROL DEVICES

26 20 00 INTERIOR DISTRIBUTION SYSTEM

26 24 16.00 40 PANELBOARDS

26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS

26 51 00 INTERIOR LIGHTING

26 52 00.00 40 EMERGENCY LIGHTING

DIVISION 27 - COMMUNICATIONS

27 05 14.00 10 CABLE TELEVISION PREMISES DISTRIBUTION SYSTEM

27 05 28.36 40 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS

27 05 29.00 10 PROTECTIVE DISTRIBUTION SYSTEM (PDS) FOR SIPRNET

COMMUNICATION SYSTEMS

27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM

PROJECT TABLE OF CONTENTS Page 3

27 13 23.00 40 27 21 00.00 20 27 21 00.00 40 27 21 10.00 40

COMMUNICATIONS OPTICAL BACKBONE CABLING

INTERCOMMUNICATION SYSTEM

INTERCOMMUNICATION SYSTEM </AM#0002>

FIBER OPTIC DATA TRANSMISSION SYSTEM

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

28 05 26.00 40 28 08 10 28 10 05 28 31 76 28 31 76.10

GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY

ELECTRONIC SECURITY SYSTEM ACCEPTANCE TESTING

ELECTRONIC SECURITY SYSTEMS (ESS)

INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM </AM#0002>

INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM

DIVISION 31 - EARTHWORK

31 63 29 DRILLED CONCRETE PIERS AND SHAFTS

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 4

<AM#0002>

<AM#0002>

W9126G18B0036-0002 m2ecdcwn Cross-Out m2ecdcwn Cross-Out m2ecdcwn Cross-Out

SECTION 01 91 00.15

TOTAL BUILDING COMMISSIONING

PART 1 GENERAL

1.1 SUMMARY

Commission the building systems listed herein. Employ the services of an independent Commissioning Firm. The Commissioning Firm must be a 1st tier subcontractor of the General or Prime Contractor and must be financially and corporately independent of all other subcontractors. The Commissioning Firm must employ a Lead Commissioning Specialist that coordinates all aspects of the commissioning process. Conform to the commissioning procedures outlined in this specification.

1.2 SYSTEMS TO BE COMMISSIONED

Commission the following systems:

Heating, Ventilating, Air Conditioning, and Refrigeration Systems (HVAC) Building Automation System Lighting Systems Service Water Heating Systems Plumbing Systems Energy and Water Utility Metering Systems and Sub-Meters

1.3 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING

ENGINEERS (ASHRAE)

ASHRAE 202 (2013) Commissioning Process for Buildings and Systems

ASSOCIATED AIR BALANCE COUNCIL (AABC)

ACG Commissioning Guideline (2005) Commissioning Guideline

NATIONAL ENVIRONMENTAL BALANCING BUREAU (NEBB)

NEBB Commissioning Standard (2009) Procedural Standards for Whole Building Systems Commissioning of New Construction; 3rd Edition

SHEET METAL AND AIR CONDITIONING CONTRACTORS' NATIONAL ASSOCIATION

(SMACNA)

SMACNA 1429 (1994) HVAC Systems Commissioning Manual, 1st Edition

SECTION 01 91 00.15 Page 1

1.4 COMMUNICATION WITH THE GOVERNMENT

The Lead Commissioning Specialist (CxC) must submit all plans, schedules, reports, and documentation directly to the Contracting Officer Representative concurrent with submission to the CQC System Manager. The Lead Commissioning Specialist must have direct communication with the Contracting Officer's Representative regarding all elements of the commissioning process; however, the Government has no direct contract authority with the Lead Commissioning Specialist.

1.5 SEQUENCING AND SCHEDULING

1.5.1 Sequencing

Complete the following prior to starting Functional Performance Tests of mechanical systems:

a. All equipment and systems have been completed, cleaned, flushed, disinfected, calibrated, tested, and operate in accordance with contract documents and construction plans and specifications.

b. Performance Verification Tests of the controls systems have been completed and the Performance Verification Test Report has been submitted and approved.

c. Testing, Adjusting, and Balancing has been completed and the Testing, Adjusting, and Balancing Report, has been submitted and approved in accordance with Specification Section 23 05 93 TESTING, ADJUSTING, AND

BALANCING FOR HVAC.

d. The Pre-Functional Checklists have been submitted and approved.

e. The Certificate of Readiness for mechanical systems has been submitted and approved.

Complete the following prior to starting Functional Performance Tests of the electrical systems:

a. All electrical and lighting equipment and systems have been completed, calibrated, tested, and operate in accordance with contract documents and construction plans and specifications.

c. Ceiling tiles, floor coverings, and window coverings are in place.

d. The Certificate of Readiness for electrical systems has been submitted and approved.

1.5.2 Project Schedule

Include the following tasks in the project schedule required by Section 01 32 01.00 10 PROJECT SCHEDULE. Ensure sufficient time is scheduled to accommodate the requirements of this specification section. The order of items listed below is not intended to imply a specified sequence:

a. Submission and approval of the Commissioning Firm and Commissioning Specialist

b. Submission and approval of the Testing, Adjusting, and Balancing (TAB) Firm and TAB Specialist specified in Section 23 05 93 TESTING, SECTION 01 91 00.15 Page 2

ADJUSTING, AND BALANCING FOR HVAC

c. Submission of the Design Review Report specified herein.

d. Submission of the Design Review Report specified in Section 23 05 93

TESTING, ADJUSTING, AND BALANCING FOR HVAC.

e. Submission and approval of the Construction Phase Commissioning Plan

f. Installation of permanent utilities (gas, water, electric)

g. Drainage and Vent, Building Sewers, Water Supply Systems and Backflow Prevention Assembly Tests specified in Section 22 00 00 PLUMBING, GENERAL PURPOSE

h. Factory Acceptance Testing for each of the systems to be commissioned as required by technical specifications

i. Manufacturer's Equipment Start-Up for each of the systems to be commissioned.

j. Potable Water System Flushing specified in Section 22 00 00 PLUMBING, GENERAL PURPOSE

k. Operational Tests of the plumbing system specified in Section 22 00 00

PLUMBING, GENERAL PURPOSE.

l. Potable Water System Disinfection specified in Section 22 00 00

PLUMBING, GENERAL PURPOSE

m. Testing, Adjusting, and Balancing (TAB) Field Work required by Section

23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC

n. Submission and approval of the TAB Report specified in Section 23 05 93

TESTING, ADJUSTING, AND BALANCING FOR HVAC

o. TAB Field Acceptance Testing required by Section 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC

p. Submission and approval of the Start-Up Testing Report specified in Section .

q. Submission and approval of the Performance Verification Test Procedures specified in Section .

r. Performance Verification Tests required by Section

s. Performance Verification Test Report specified in Section

t. Pre-Functional Checklist Submittal

u. Functional Performance Testing for each system to be commissioned

v. Integrated Systems Tests

w. Post-Test Deficiency Correction for each system to be commissioned

x. Re-Testing

SECTION 01 91 00.15 Page 3

1.6 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Commissioning Firm; G

Lead Commissioning Specialist; G

Technical Commissioning Specialists; G

Commissioning Firm's Contract; G

SD-06 Test Reports

Design Review Report; G

Interim Construction Phase Commissioning Plan; G

Final Construction Phase Commissioning Plan; G

Pre-Functional Checklists; G

Issues Log

Commissioning Report; G

Post-Construction Trend Log Report; G

SD-07 Certificates

Certificate of Readiness; G

SD-10 Operation and Maintenance Data

Training Plan; G

Training Attendance Rosters; G

SD-11 Closeout Submittals

Construction Phase Commissioning Plan; S

Final Commissioning Report; S

1.7 COMMISSIONING FIRM

Provide a Commissioning Firm that is certified in commissioning by one of the following: the AABC Commissioning Group (ACG); the National Environmental Balancing Bureau (NEBB); the International Certification Board/Testing, Adjusting, and Balancing Bureau (ICB/TABB), the Building Commissioning Association (BCA); the Association of Energy Engineers (AEE).

The Commissioning Firm may employ a commissioning professional certified

SECTION 01 91 00.15 Page 4 by the University of Wisconsin-Madison or the American Society of Heating, Refrigeration, and Air Conditioning Engineers (ASHRAE) as required in paragraph LEAD COMMISSIONING SPECIALIST as an alternative to certification of the Commissioning Firm. The Commissioning Firm must be certified in all systems to be commissioned to the extent such certifications are available from the certifying body. Describe any lapses in certification or disciplinary action taken by the certifying body against the proposed Commissioning Firm or Lead Commissioning Specialist in detail. Any firm or commissioning professional that has been the subject of disciplinary action by the certifying body within the five years preceding contract award is not eligible to perform any duties related to commissioning.

a. Submit the Commissioning Firm's certification of qualifications including the name of the firm and certifications no later than 30 calendar days after Notice to Proceed. Submit one hard copy and an electronic copy.

b. The Commissioning Firm's and Commissioning Specialists' certifications must be maintained for the entire duration of the duties specified herein. If, for any reason, the firm or a specialist loses a certification during this period, immediately notify the Contracting Officer's Representative and submit another Commissioning Firm or Commissioning Specialist for approval. All work specified in this specification section performed by the Commissioning Firm or associated Commissioning Specialists is invalid if the Commissioning Firm or Commissioning Specialist loses its certification prior to contract completion and must be performed by an approved successor.

c. The Commissioning Firm must oversee and assist the General or Prime Contractor with the work specified herein.

1.7.1 Lead Commissioning Specialist

The Commissioning Firm must provide a Lead Commissioning Specialist (CxC) that has a minimum of five years of commissioning experience, including two projects of similar size and complexity, and that is one of the following:

a NEBB qualified Systems Commissioning Administrator (SCA); ACG Certified Commissioning Authority (CxA); ICB/TABB Certified Commissioning Supervisor;

BCA Certified Commissioning Professional (CCP); AEE Certified Building Commissioning Professional (CBCP); University of Wisconsin-Madison Qualified Commissioning Process Provider (QCxP); ASHRAE Commissioning Process Management Professional (CPMP).

a. Submit the Lead Commissioning Specialist's certification of qualifications including the name of the specialist and firm;

certifications; years of experience; and a listing of representative projects of similar size and complexity no later than 30 calendar days after Notice to Proceed. Submit one hard copy and an electronic copy.

b. The Lead Commissioning Specialists certifications must be maintained for the entire duration of the duties specified herein. If, for any reason, the specialist loses a certification during this period, immediately notify the Contracting Officer's Representative and submit another Lead Commissioning Specialist for approval. All work specified in this specification section to be performed by the Lead Commissioning Specialist is invalid if the Lead Commissioning Specialist loses its certification prior to contract completion and must be performed by an approved successor.

SECTION 01 91 00.15 Page 5

c. The Lead Commissioning Specialist must lead and oversee the commissioning work specified herein and be the primary point of contact for the Government regarding the commissioning work.

1.7.2 Technical Commissioning Specialists

Technical Commissioning Specialists, employed by the Commissioning Firm and that have the following qualifications, must perform the technical work specified herein associated with each system to be commissioned:

a. The technical work associated with mechanical systems including Heating, Ventilating, Air Conditioning, and Refrigeration Systems;

Building Automation System; Service Water Heating Systems; Plumbing Systems; ; ; ; Energy and Water Utility Metering Systems must be performed by a Commissioning Specialist certified by NEBB, ACG, ICB/TABB, or BCA in the commissioning of HVAC systems with five years of experience in the commissioning of HVAC systems.

b. The technical work associated with electrical systems including Lighting Systems; Power Distribution Systems; ; Automatic Wet-Pipe and Dry-Pipe Fire Sprinkler Systems; Fire Alarm/Mass Notification Systems must be performed by an engineering technician certified by the InterNational Electrical Testing Association (NETA) or the National Institute for Certification in Engineering Technologies (NICET) with five years of experience inspecting, testing, and calibrating electrical distribution and generation equipment, systems, and devices.

c. Submit the Technical Commissioning Specialist's certification of qualifications including the name of the specialist and firm;

certifications; years of experience; and a listing of representative projects of similar size and complexity no later than 30 calendar days after Notice to Proceed. Submit one hard copy and an electronic copy.

1.7.3 Commissioning Standard

Comply with the requirements of the commissioning standard under which the Commissioning Firm and Specialists qualifications are approved. When the firm and specialists are certified by BCA, AEE, ASHRAE, or the University of Wisconsin-Madison, comply with the requirements of one of the acceptable standards unless otherwise stated herein. The acceptable standards are ACG Commissioning Guideline, NEBB Commissioning Standard, SMACNA 1429, or ASHRAE 202. Comply with applicable NETA and NICET testing standards for electrical systems.

a. Implement all recommendations and suggested practices contained in the Commissioning Standard and electrical test standards.

b. Use the Commissioning Standard for all aspects of Commissioning, including calibration of instruments.

c. Where the instrument manufacturer calibration recommendations are more stringent than those listed in the Commissioning Standard, adhere to the manufacturer calibration recommendations.

d. All quality assurance provisions of the Commissioning Standard such as performance guarantees are part of this contract.

e. The Commissioning Specialists must develop commissioning procedures for any systems or system components not covered in the Commissioning

SECTION 01 91 00.15 Page 6

Standard.

f. Use any new requirements, recommendations, and procedures published or adopted prior to contract solicitation by the body responsible for the Commissioning Standard.

1.8 ISSUES LOG

The Lead Commissioning Specialist must develop and maintain an Issues Log for tracking and resolution of all deficiencies discovered through commissioning review, inspection, and testing. Include the date of final resolution of issues as confirmed by the Commissioning Specialist. Submit the Issues Log on a monthly basis at a minimum. At any point during construction, any commissioning team member finding deficiencies may communicate those deficiencies in writing to the Commissioning Specialist for inclusion into the Issues Log.

Track construction deficiencies identified in the Issues Log using QCS as specified in Specification Section 01 45 00.15 10 RESIDENT MANAGEMENT

SYSTEM CONTRACTOR MODE(RMS CM).

1.9 CERTIFICATE OF READINESS

Prior to scheduling Functional Performance Tests for each system, issue a Certificate of Readiness for the system certifying that the system is ready for Functional Performance Testing. The Certificate of Readiness must include, for each system to be commissioned, all equipment and system start-up reports; Performance Verification Test Reports; completed Pre-Functional Checklists; Testing, Adjusting, and Balancing (TAB) Report and HVAC Controls Start-Up Reports to the extent applicable to the system. The Contractor; the Lead Commissioning Specialist; the Contractor's Quality Control Representative; the Mechanical, Electrical, Controls, and TAB subcontractor representatives must sign and date the Certificate of Readiness. Submit the Certificate of Readiness for each system no later than 14 calendar days prior to Functional Performance Tests of that system. Submit one hard copy and an electronic copy. Do not schedule Functional Performance Tests for a system until the Certificate of Readiness for that system receives approval by the Government.

PART 2 PRODUCTS

Not used

PART 3 EXECUTION

3.1 CONSTRUCTION PHASE

3.1.1 Construction Commissioning Coordination Meeting

The Lead Commissioning Specialist must lead a Construction Commissioning Coordination Meeting no later than 14 days after approval of the Commissioning Firm and Commissioning Specialists to discuss the commissioning process including contract requirements, lines of communication, roles and responsibilities, schedules, documentation requirements, inspection and test procedures, and logistics as specified in this specification section. The Contractor's Superintendent or Project Manager, the Contractor's Quality Control Representative, and the Government must attend this meeting. Invite the User and a Base Civil Engineer Office Representative to attend this meeting.

SECTION 01 91 00.15 Page 7

3.1.2 Construction Phase Commissioning Plan

3.1.2.1 Interim Construction Phase Commissioning Plan

The Lead Commissioning Specialist (CxC) must prepare the Interim Construction Phase Commissioning Plan. Submit the Interim Construction Phase Commissioning Plan no later than 30 calendar days after the Construction Commissioning Coordination Meeting and no later than 14 days prior to the start of construction of the building envelope. Submit one hard copy and an electronic copy.

Identify the commissioning and testing standards and outline the overall commissioning process, the commissioning schedule, the commissioning team members and responsibilities, lines of communication, documentation requirements for the construction phase of the project in the Interim Construction Phase Commissioning Plan.

3.1.2.1.1 Checklists

Download example Pre-Functional Checklists, Functional Performance Test Checklists, and Integrated Systems Test Checklists for specification section 01 91 00.15 TOTAL BUILDING COMMISSIONING at the following location: http://www.wbdg.org/FFC/NAVGRAPH/graphtoc.pdf. The checklists submitted in the Interim and Final Construction Phase Commissioning Plans must contain the same level of detail shown in the examples. The submitted checklists are not required to match the format of the examples.

3.1.2.2 Final Construction Phase Commissioning Plan

The Lead Commissioning Specialist (CxC) must prepare the Final Construction Phase Commissioning Plan. Submit the Final Construction Phase Commissioning Plan no later than 30 calendar days prior to the start of Pre-Functional Checks. Submit one hard copy and an electronic copy.

Include the information provided in the Interim Construction Phase Commissioning Plan. In addition, the Technical Commissioning Specialist must develop the Pre-Functional Checklists, Integrated Systems Test Checklists, and Functional Performance Test Checklists for each building, for each system required to be commissioned, and for each component for inclusion in the Final Construction Phase Commissioning Plan.

3.1.2.2.1 Pre-Functional Checklists

The Pre-Functional Checklists must include items for physical inspection or testing that demonstrate that installation and start-up of equipment and systems is complete. See paragraph Pre-Functional Checks for more information. Functional Performance and Integrated Systems Test test procedures must explain, step-by-step, the actions and expected results that will demonstrate that the system performs in accordance with the contract in the Functional Performance Test and Integrated Systems Test Checklists. See paragraph Functional Performance and Integrated Systems Tests for more information.

3.1.2.2.2 Functional Performance Test Checklists

Functional Performance Test Checklists must include procedures that explain, step-by-step, the actions and expected results that will demonstrate that the system performs in accordance with the contract. See

SECTION 01 91 00.15 Page 8 paragraph Functional Performance and Integrated Systems Tests for more information. Include the following sections and details appropriate to the systems being tested in the Functional Performance Test Checklists:

a. Notable system features including information about controls to facilitate understanding of system operation

b. Conclusions and recommendations. Conclusions must clearly indicate if system does or does not perform in accordance with contract requirements. Recommendation must clearly indicate that the system should or should not be accepted by the Government.

c. Test conditions including date, beginning and ending time, and beginning and ending outdoor air conditions

d. Attendees

e. Identification of the equipment involved in the test

f. Control system feature identification

g. Point-to-point observations including demonstrating system flow meters and sensors have been calibrated and are correctly displayed on the Operator work station

h. Actuator operation observations demonstrating actuator responses to commands from the control system

i. As-found condition of the system operation

j. List of test items with step numbers along with the corresponding feature or control operation, intended test procedure, expected system response, and pass/fail indication.

k. Space for comments for each test item.

3.1.2.2.3 Integrated Systems Test Checklists

Integrated Systems Test Checklists must include test procedures that explain, step-by-step, the actions and expected results that will demonstrate that the system performs in accordance with the contract. See paragraph Functional Performance and Integrated Systems Tests for more information. Include the following sections in the Integrated Systems Test Checklists:

a. Notable features of the interconnected systems organized by discipline including information to facilitate understanding of system operation

b. Conclusions and recommendations. Conclusions must clearly indicate if the systems do or do not perform in accordance with contract requirements. Recommendation must clearly indicate that the systems should or should not be accepted by the Government

c. Test conditions including date and beginning and ending time

d. Attendees

e. Identification of the equipment and systems involved in the test

SECTION 01 91 00.15 Page 9

f. List of test items with step numbers along with the corresponding feature or control operation, intended test procedure, expected system response, and pass/fail indication.

g. Space for comments for each test item.

3.1.3 Design Review

The Lead Commissioning Specialist and Technical Commissioning Specialists must review the construction contract plans and specifications, the Owner's Project Requirements, and the Basis of Design. The Owner's Project Requirements are attached as Appendix A. The Basis of Design is attached as Appendix B. The Owner's Project Requirements and Basis of Design documents are not contract documents and are provided for commissioning review purposes only.

a. Advise the Contracting Officer's Representative of any discrepancies between the Basis of Design and Owner's Project Requirements, deficiencies of the design to comply with the Owner's Project Requirements or Basis of Design, and deficiencies that would prevent the building systems and features from operating or performing effectively and from being adequately maintainable.

b. The Commissioning Specialists must provide a Design Review Report individually listing each deficiency and the corresponding proposed corrective action necessary for proper system operation or performance. Submit one hard copy and an electronic copy of the report to the Contracting Officer's Representative no later than 14 days after approval of the Commissioning Specialists.

c. The Lead Commissioning Specialist must participate in a meeting to discuss any items contained in the report no later than 14 calendar days after submission of the report.

3.1.4 Construction Submittals

Provide all submittals associated with the systems to be commissioned, including shop drawings; equipment submittals; test plans, procedures, and reports; and resubmittal's to the Commissioning Specialists. The Technical Commissioning Specialist must review the submittals to the extent necessary verify that the equipment and system installation will comply with the contract requirements and the requirements of the Basis of Design and the Owner's Project Requirements.

3.1.5 Inspection and Testing

Demonstrate that all system components have been installed, that each control device and item of equipment operates, and that the systems operate and perform, including interactive operation between systems, in accordance with contract documents and the Owner's Project Requirements. Requirements in related specification sections are independent from the requirements of this section and do not satisfy any of the requirements specified in this specification section. Provide all materials, services, and labor required to perform the Pre-Functional Checks, Integrated Systems Tests, and Functional Performance Tests.

3.1.5.1 Commissioning Team

Provide a commissioning representative for each sub-contractor associated

SECTION 01 91 00.15 Page 10 with the systems to be commissioned. Each commissioning representative is responsible for coordination of their respective sub-contractor's execution of the commissioning activities and participation in the inspection and testing required by this specification section. The designers listed below are the designers of record for their respective systems. Substitutes must be approved by the Contracting Officer's Representative .

3.1.5.1.1 Mechanical System Pre-Functional Checks Team

The following team members must participate in Pre-Functional checks of mechanical systems:

Designation Function

CxM Mechanical System Technical Commissioning Specialist

QAR Contracting Officer's Quality Assurance Representative

CQC Contractor's Quality Control Personnel

MC Contractor's Mechanical Commissioning Representative

EC Contractor's Electrical Commissioning Representative

CC Contractor's Controls Commissioning Representative

TABC Contractor's TAB Commissioning Representative

PC Contractor's Plumbing Commissioning Representative

3.1.5.1.2 Electrical System Pre-Functional Checks Team

The following team members must participate in Pre-Functional checks of electrical systems:

Designation Function

CxE Mechanical System Technical Commissioning Specialist

QAR Contracting Officer's Quality Assurance Representative

CQC Contractor's Quality Control Personnel

EC Contractor's Electrical Commissioning Representative

3.1.5.1.3 Mechanical Systems Test Team

The following team members must participate in Functional Performance and Integrated Systems Testing of mechanical systems:

SECTION 01 91 00.15 Page 11

Designation Function

CxM Mechanical System Technical Commissioning Specialist

QAR Contracting Officer's Quality Assurance Representative

CQC Contractor's Quality Control Personnel

MC Contractor's Mechanical Commissioning Representative

EC Contractor's Electrical Commissioning Representative

CC Contractor's Controls Commissioning Representative

TABC Contractor's TAB Commissioning Representative

PC Contractor's Plumbing Commissioning Representative

3.1.5.1.4 Electrical Systems Test Team

The following team members must participate in Functional Performance and Integrated Systems Testing of electrical systems:

Designation Function

CxE Mechanical System Technical Commissioning Specialist

QAR Contracting Officer's Quality Assurance Representative

CQC Contractor's Quality Control Personnel

EC Contractor's Electrical Commissioning Representative

3.1.5.1.5 Other Pre-Functioanl and Functional Performance Participants

The following may participate as team members during Pre-Functional Checks and Functional Performance Testing:

Designation Function

DPW Directorate of Public Works Representative

BCE Base Civil Engineer Office Representative

User Using Agent's Representative

3.1.5.2 Pre-Functional Checks

Pre-Functional Checklists from the approved Final Construction Phase Commissioning Plan must be completed by the commissioning team. Complete one Pre-Functional Checklist for each individual item of equipment or system for each system required to be commissioned including, but not

SECTION 01 91 00.15 Page 12 limited to, ductwork, piping, equipment, fixtures (lighting and plumbing), and controls. Indicate commissioning team member inspection and acceptance of each Pre-Functional Checklist item by initials. Acceptance of each Pre-Functional Checklist item by each team member indicates that item conforms to the construction contract requirements in their area of responsibility. Technical Commissioning Specialist acceptance of each Pre-Functional Checklist item indicates that each item has been installed correctly and in accordance with contract documents and the Owner's Project Requirements. Submit the completed and initialed Pre-Functional Checklists no later than 7 calendar days after completion of inspection of all checklists items for each system. Submit one hard copy and an electronic copy. Include manufacturer start-up checklists associated with equipment with the submission of the Pre-Functional Checklists.

3.1.5.3 Testing, Adjusting, and Balancing (TAB) Report and Field Acceptance Testing

The Mechanical System Technical Commissioning Specialist must review the pre-final TAB Report required by Specification Section 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC. Identify any deficiencies to the Contracting Officer's Representative and the Contractor's Quality Control Personnel. Resolve all deficiencies prior to TAB Field Acceptance Testing.

The Mechanical System Technical Commissioning Specialist must witness the TAB Field Acceptance Testing specified by Section 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC. Include a certification by the Mechanical Technical Specialist that no outstanding deficiencies exist in the systems relative to Testing, Adjusting, and Balancing with the final TAB Report submittal.

3.1.5.4 HVAC Controls Test Reports

The Mechanical System Technical Commissioning Specialist must review the Performance Verification Testing Plan, Checklists, and Report. Include a certification by the Mechanical System Technical Commissioning Specialist that the submittals contain no deficiencies or that the submittals do not indicate any deficiencies in the HVAC systems or HVAC control systems with each of these submittals.

3.1.5.5 Tests

3.1.5.5.1 Functional Performance and Integrated Systems Tests

Schedule Functional Performance Tests for each system only after the Certificate of Readiness has been approved by the Government for the system. Correct all deficiencies identified through any prior review, inspection, or test activity before the start of Functional Performance Tests. Perform Integrated Systems Tests only after the Functional Performance Tests for each associated system are completed with all deficiencies resolved and after the related Functional Performance Test Checklists have been signed by each commissioning team member.

a. Functional Performance Tests and Integrated Systems Tests must be performed with the Contracting Officer's Quality Assurance Representative present.

b. Abort Functional Performance Tests or Integrated Systems Testswhen any system deficiency prevents the successful completion of the test.

SECTION 01 91 00.15 Page 13

c. Technical Commissioning Specialists must lead and document all Functional Performance Tests and Integrated Systems Tests for the systems to be commissioned with the Contractor and appropriate sub-contractors performing the Functional Performance Tests and Integrated Systems Tests. The representatives listed in the paragraph Commissioning Team must attend the tests. Abort Functional Performance Tests or Integrated Systems Tests when any required commissioning team member is not present for the test.

3.1.5.5.1.1 Checklist

Use the Functional Performance Test and Integrated Systems Test Checklists from the approved Final Construction Phase Commissioning Plan to guide the Functional Performance Tests and Integrated Systems Tests. Functional Performance Tests must be performed for each item of equipment and each system required to be commissioned and verify all sensor calibrations, control responses, safeties, interlocks, operating modes, sequences of operation, capacities, lighting levels, and all other performance requirements comply with construction contract regardless of the specific items listed within the Functional Performance Test and Integrated Systems Test Checklists provided. Testing must progress from equipment or components to subsystems to systems to interlocks and connections between systems. Integrated Systems Tests must be performed for the interactive operation between systems such as HVAC systems, fire protection systems, and other systems, and verify correct interactive operation, acceptable speed of response, and other contract requirements for both normal and failure modes. Examples of Integrated Systems Tests include the correct operation of HVAC systems during emergency system activation, lighting system operation during power outage or emergency system activation.The order of components and systems to be tested must be determined by the Technical Commissioning Specialists.

3.1.5.5.1.2 Acceptance

Indicate acceptance of each item of equipment and systems tested by signature of each commissioning team member for each Functional Performance Test or Integrated Systems Test Checklist. The Contractor's Quality Control Representative and the Technical Commissioning Specialists must indicate acceptance after the equipment and systems are free of deficiencies.

3.1.5.5.2 HVAC Test Methods

Perform Functional Performance Tests in accordance with the following:

3.1.5.5.2.1 Prior to Testing

Prior to testing operating modes, sequences of operation, interlocks, and safeties, complete control point-to-point observations, test sensor calibrations, and test actuator commands.

3.1.5.5.2.2 Simulating Conditions

Over-writing control input values through the controls system is not acceptable, unless approved by the Contracting Officer's Representative .

Identify proposed exceptions in a protocol submitted to the Contracting Officer's Representative for approval. Before simulating conditions, overwriting values (if approved), or changing set-points, calibrate all sensors, transducers and devices. Below are several examples of exceptions

SECTION 01 91 00.15 Page 14 that would be considered acceptable:

a. When varying static pressures inside ductwork can not be simulated within the duct, and where a sensor signals the controls system to initiate sequences at various duct static pressures, it is acceptable to simulate the various pressures with a Pneumatic Squeeze-Bulb Type Signaling Device with gauge temporarily attached to the sensing tube leading to the transmitter. It is not acceptable to reset the various set-points, nor to simulate an electric analog signal (unless approved as noted above).

b. Dirty filter pressure drops can be simulated using sheets of cardboard at filter face.

c. Freeze-stat safeties can be simulated by packing portion of sensor with ice.

d. High outside air temperatures can be simulated with a hair blower.

e. High entering cooling coil temperatures can be used to simulate entering cooling coil conditions.

f. Do not use signal generators to simulate sensor signals unless approved by the Contracting Officer's Representative, as noted above, for special cases.

g. Control set points can be altered. For example, to see the air conditioning compressor lockout work at an outside air temperature below 55 degrees F, when the outside air temperature is above 55 degrees F, temporarily change the lockout set point to be 0 degrees F above the current outside air temperature. Caution: Set points are not to be raised or lowered to a point such that damage to the components, systems, or the building structure and/or contents will occur.

h. Test duct mounted smoke detectors in accordance with the manufacturer's recommendations. Perform the tests with air system at minimum airflow condition in ductwork.

i. Test current sensing relays used for fan and pump status signals to control system to indicate unit failure and run status by resetting the set point on the relay to simulate a lost belt or unit failure while the unit is running. Confirm that the failure alarm was generated and received at the control system. After the test is conducted, return the set point to its original set-point or a set-point as indicated by the Contracting Officer's Representative .

3.1.5.5.2.3 Setup

Perform each test under conditions that simulate actual conditions as close as is practically possible. Provide all necessary materials and system modifications to produce the necessary flows, pressures, temperatures, and other conditions necessary to execute the test according to the specified conditions. At completion of the test, return the affected building equipment and systems to their pre-test condition.

3.1.5.5.3 Sample Strategy

Perform Functional Performance Tests using the following sample strategy.

Prepare and complete a Functional Performance Test Checklist for each item

SECTION 01 91 00.15 Page 15 of equipment or system to be tested. For sample sizes less than 100 percent for all similar equipment, the Government will select the specific equipment or system to be tested during testing. Equipment Identifiers are as indicated on the design drawings:

Equipment Identifier Sample Size (Percent)

CH 100

B 100

BCP 100

CHP 100

HWP 100

DOAS 100

VAV 100

AHU 100

EF 100

ACCU 100

MS 100

DWH 100

Lighting Controls 100

Fire Alarm/Mass Notification System 100

Automatic Fire Sprinkler System 100

Perform Integrated Systems Tests for all systems and equipment having interactive operation.

3.1.5.5.4 Seasonal Tests

3.1.5.5.4.1 Initial Functional Performance Tests

Perform Initial Functional Performance Tests as soon as all contract work is completed, regardless of the season. Develop and implement means of artificial loading to demonstrate, to a reasonable level of confidence, the ability of the HVAC systems to handle peak seasonal loads.

3.1.5.5.4.2 Full-Load Conditions

In addition to the Initial Functional Performance Tests, perform Functional Performance Tests of HVAC systems under full-load conditions during peak heating and cooling seasons during outdoor air condition design extremes.

Schedule Seasonal Functional Performance Tests in coordination with the

SECTION 01 91 00.15 Page 16

Government.

3.1.5.5.4.3 System Acceptance

Systems may be partially accepted prior to seasonal testing if they comply with all construction contract that can be tested during initial Functional Performance Tests. All Functional Performance Test procedures must be completed prior to full systems acceptance.

3.1.5.5.5 Aborted Tests and Re-Testing

Abort Functional Performance Tests, Integrated Systems Tests, or Seasonal Tests if any deficiency prevents successful completion of the test or if any required commissioning team member is not present for the test.

reimburse the Government for all costs associated with effort lost due to re-testing due to test failures and aborted tests.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it.