B3_Amend-0003_W9126G18B0026.pdf

PDF 201 KB Posted

Attached to
USACE GIWW, Texas Placement Area Nos. 86/87 Improvements, Brazoria County, Texas
Solicitation number
W9126G18B0026
Issued by

About this file

Amendment 0003 - Bid Opening Date is extended to 15 August 2018 @ 2:00 p.m., local time.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W45VAK81364593

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is show n on the pages follow ing: See page 2

THE BID OPENING DATE IS EXTENDED TO 15 AUGUST 2018 @ 2:00 P.M. LOCAL TIME.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 33

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9126G18B0026

X 9B. DATED (SEE ITEM 11)

09-Jul-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

06-Aug-2018

CODE

US ARMY CORPS OF ENGINEERS FORT WORTH

2000 FORT POINT ROAD

GALVESTON TX 77550-1229

W9126G 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

x

W9126G18B0026

A0003-2

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

1. THE SPECIFICATIONS FOR SOLICITATION NO. W9126G18B0026, GULF

INTRACOASTAL WATERWAY, TEXAS, PLACEMENT AREA 86/87 IN BRAZORIA COUNTY,

TEXAS, CONTAINMENT DIKE RAISE, ARE HEREBY AMENDED AS FOLLOWS:

a) Specifications.

(1) SECTION 00 11 00.00 45, BID SCHEDULE – The enclosed SECTION 00 11 00.00 45 entitled BID SCHEDULE supersedes that issued with this Solicitation.

(2) SECTION 00 73 00.00 45, SPECIAL CONTRACT REQUIREMENTS, STANDARD – The enclosed SECTION 00 73 00.00 45 entitled SPECIAL CONTRACT REQUIREMENTS, STANDARD supersedes that issued with this Solicitation.

(3) SECTION 01 22 00.10, MEASUREMENT AND PAYMENT – The enclosed SECTION 01 22 00.10 entitled MEASUREMENT AND PAYMENT supersedes that issued with this Solicitation.

(4) SECTION 31 11 00.10 45 CLEARING, GRUBBING, AND REMOVAL OF DEBRIS – The enclosed SECTION 31 11 00.10 45 entitled CLEARING, GRUBBING, AND REMOVAL OF DEBRIS is added to this Solicitation.

(5) SECTION 35 41 00.01 45 EMBANKMENT CONSTRUCTION – The enclosed SECTION 35 41 00.00 45 entitled EMBANKMENT CONSTRUCTION supersedes that issued with this Solicitation.

2. This amendment shall be attached to and become a part of the solicitation.

5 Encls:

1. SECTION 00 11 00.00 45, BID SCHEDULE

2. SECTION 00 73 00.00 45, SPECIAL CONTRACT REQUIREMENTS, STANDARD

3. SECTION 01 22 00.10, MEASUREMENT AND PAYMENT

4. SECTION 31 11 00.10 45 CLEARING, GRUBBING, AND REMOVAL OF DEBRIS

5. SECTION 35 41 00.01 45 EMBANKMENT CONSTRUCTION

SWG FILE NO.: IWW 1150-1134 SOLICITATION NO.:W9126G18B0026

SECTION TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SECTION 00 11 00.00 45

BID SCHEDULE

PART 1 GENERAL

1.1 SCHEDULE NO. 1

-- End of Section Table of Contents --

DOCUMENT 00 11 00.00 45 Page 1

(TO ACCOMPANY AMENDMENT NO. 0003 TO SOLICITATION NO. W9126G18B0026)

SECTION 00 11 00.00 45

BID SCHEDULE

AMENDMENT NO. 0003

PART 1 GENERAL

1.1 SCHEDULE NO. 1

(TO BE ATTACHED TO STANDARD FORM 1442)

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

SCHEDULE NO. 1

0001 Mobilization and Demobilization 1 JOB SUM $___________

0002 Drop-Outlet Structure Rehabilitation

1 JOB SUM $___________

0003 Semi-Compacted Containment Dike Raise

91,700 C.Y. $_________ $___________

0004 Uncompacted Training Dike Raise

75,700 C.Y. $_________ $___________

0005 Turfing

1 JOB SUM $___________

0006 Clearing, Grubbing, and Removal of Debris

1 JOB SUM $___________

TOTAL SCHEDULE NO. 1 $___________

NOTE: Completion time stated in SECTION 00 73 00.00 45 SPECIAL CONTRACT REQUIREMENTS, STANDARD is for Schedule No. 1 work.

-- End of Document --

DOCUMENT 00 11 00.00 45 Page 2

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SECTION 00 73 00.00 45

SPECIAL CONTRACT REQUIREMENTS, STANDARD

PART 1 GENERAL

1.1 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) (FAR

52.211-10)

1.2 LIQUIDATED DAMAGES - CONSTRUCTION (SEP 2000) (FAR 52.211-12)

1.3 PHYSICAL DATA (APR 1984) (FAR 52.236-4)

1.4 QUANTITY SURVEYS (APR 1984) (FAR 52.236-16)

1.5 BASIS FOR SETTLEMENT OF PROPOSALS (MAR 1995) (UAI 52.249-5000)

1.6 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE(UAI 31.105-101

MAR 1995)

PART 2 PRODUCTS (Not Used)

PART 3 EXECUTION (Not Used)

-- End of Section Table of Contents --

DOCUMENT 00 73 00.00 45 Page 1

SECTION 00 73 00.00 45

SPECIAL CONTRACT REQUIREMENTS, STANDARD

AMENDMENT NO. 0003

PART 1 GENERAL

1.1 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) (FAR

52.211-10)

The Contractor shall be required to:

(a) Commence work under this contract within 10 calendar days after the date the Contractor receives the Notice to Proceed;

(b) Prosecute the work diligently, and

(c) Complete the entire work ready for use not later than (AM#3) 400 calendar days after the date the Contractor receives the Notice to Proceed. The time stated for completion shall include final cleanup of the premises.

1.2 LIQUIDATED DAMAGES - CONSTRUCTION (SEP 2000) (FAR 52.211-12)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $3,516 for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

1.3 PHYSICAL DATA (APR 1984) (FAR 52.236-4)

Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

(a) The indications of physical conditions on the drawings and in the specifications are the result of site surveys.

(b) Weather Conditions. Under ordinary conditions, the mean tidal range is about 2 feet. The height of tide is largely dependent on the force, direction, and duration of the wind. Strong northerly winds may depress the water surface as much as, and in some instances more than,

2.5 feet below NAVD 88, while southerly winds may raise the water surface as much as, and in some instances more than, one foot above

NAVD 88.

(c) Transportation Facilities. The immediate vicinity is served by highway, and shallow draft channels.

DOCUMENT 00 73 00.00 45 Page 2

1.4 QUANTITY SURVEYS (APR 1984) (FAR 52.236-16)

(a) Quantity surveys shall be conducted, and the data derived from these surveys shall be used in computing the quantities of work performed and the actual construction completed and in place.

(b) The Government shall conduct the original and final surveys and make the computations based on them. The Contractor shall conduct the surveys for any periods for which progress payments are requested and make the computations based on these surveys. All surveys conducted by the Contractor shall be conducted under the direction of the Contracting Officer, unless the Contracting Officer waives this requirement in a specific instance.

(c) Promptly upon completing a survey, the Contractor shall furnish the originals of all field notes and all other records relating to the survey or to the layout of the work to the Contracting Officer, who shall use them as necessary to determine the amount of progress payments. The Contractor shall retain copies of all such material furnished to the Contracting Officer.

1.5 BASIS FOR SETTLEMENT OF PROPOSALS (MAR 1995) (UAI 52.249-5000)

Actual costs will be used to determine equipment costs for a settlement proposal submitted on the total cost basis under FAR 49.206-2(b). In evaluating a terminations settlement proposal using the total cost basis, the following principals will be applied to determine allowable equipment costs:

(1) Actual costs for each piece of equipment, or groups of similar serial or series equipment, need not be available in the Contractor's accounting records to determine total actual equipment costs.

(2) If equipment costs have been allocated to a contract using predetermined rates, those charges will be adjusted to actual costs.

(3) Recorded job costs adjusted for unallowable expenses will be used to determine equipment operating expenses.

(4) Ownership costs (depreciation) will be determined using the Contractor's depreciation schedule (subject to the provisions of

FAR 31.205.11)

(5) License, taxes, storage, and insurance costs are normally recovered as an indirect expense and unless the Contractor charges these costs directly to contracts, they will be recovered through the indirect expense rate.

1.6 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE(UAI 31.105-101 MAR

1995)

(a) This special contract requirement does not apply to terminations. See 52.249-5000, Basis for Settlement of Proposals, and FAR Part 49.

(b) Allowable cost for construction and marine plant and equipment in sound workable condition owned or controlled and furnished by a contractor or subcontractor at any tier shall be based on actual cost data for each

DOCUMENT 00 73 00.00 45 Page 3 piece of equipment or groups of similar serial and series for which the Government can determine both ownership and operating costs from the con-tractor's accounting records. When both ownership and operating costs cannot be determined for any piece of equipment or groups of similar serial or series equipment from the contractor's accounting records, costs for that equipment shall be based upon the applicable provisions of EP 1110-1-8, Construction Equipment Ownership and Operating Expense Schedule, Region VI. Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the contracting officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retroactive pricing, the schedule in effect at the time the work was performed shall apply.

(c) Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii) and FAR 31.205-36, Rental Costs. Rates for equipment rented from an organization under common control, lease-purchase arrangements, and sale-leaseback arrangements, will be determined using the schedule, except that actual rates will be used for equipment leased from an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees.

(d) When actual equipment costs are proposed and the total amount of the pricing action exceeds the SAT, the contracting officer shall request the contractor to submit either certified cost or pricing data, or partial/limited data, as appropriate. The data shall be submitted on Standard Form 1411, Contract Pricing Proposal Cover Sheet.

NOTE: A copy of EP 1110-1-8, "CONSTRUCTION EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE," is available at the following website:

http://www.publications.usace.army.mil/USACEPublications/EngineerPamphlets.aspx

PART 2 PRODUCTS (Not Used)

PART 3 EXECUTION (Not Used)

-- End of Document --

DOCUMENT 00 73 00.00 45 Page 4

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00.10

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 SUBMITTALS

1.2 LUMP SUM PAYMENT ITEMS

1.2.1 Mobilization and Demobilization

1.2.1.1 Payment

1.2.1.2 Unit of Measure

1.2.2 Drop-Outlet Structure Rehabilitation

1.2.2.1 Payment

1.2.2.2 Unit of Measure

1.2.3 Turfing

1.2.3.1 Payment

1.2.3.2 Unit of Measure

1.2.4 (AM#3) Clearing, Grubbing, and Removal of Debris

1.2.4.1 Payment

1.2.4.2 Unit of Measure

1.3 UNIT PRICE PAYMENT ITEMS

1.3.1 Semi-Compacted Containment Dike Raise

1.3.1.1 Payment

1.3.1.2 Measurement

1.3.1.3 Unit of Measure

1.3.2 Uncompacted Training Dike Raise

1.3.2.1 Payment

1.3.2.2 Measurement

1.3.2.3 Unit of Measure

PART 2 PRODUCTS (Not Used)

PART 3 EXECUTION (Not Used)

-- End of Section Table of Contents --

SECTION 01 22 00.10 Page 1

SECTION 01 22 00.10

MEASUREMENT AND PAYMENT

AMENDMENT NO. 0003

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:

SD-02 Shop Drawings

Surveys; G

Submit drawings of surveys during progress of work.

1.2 LUMP SUM PAYMENT ITEMS

Payment items for the work of this Contract for which Contract lump sum payments will be made are listed in the BID SCHEDULE and specified below.

All costs for items of work, which are not specifically mentioned to be included in a particular lump sum or unit price payment item, shall be included in the listed lump sum item most closely associated with the work involved. The lump sum price and payment made for each item listed shall constitute full compensation for furnishing plant, labor, materials, and equipment, and performing any associated Contractor Quality Control, administrative requirements, environmental protection, meeting safety requirements, tests and reports, and for performing the work required for which separate payment is not otherwise provided.

1.2.1 Mobilization and Demobilization

1.2.1.1 Payment

Payment will be made for costs associated with "Mobilization and Demobilization" as defined in the SECTION 00 72 00 CONTRACT CLAUSES.

Payment for costs in connection with the plant necessary to perform the work, to include transportation and other costs incidental to delivery of the plant and other equipment to the general work area in condition ready for operation, and after completion of the work for removal of the plant and equipment from the work site.

1.2.1.2 Unit of Measure

Unit of measure: Job

SECTION 01 22 00.10 Page 2

1.2.2 Drop-Outlet Structure Rehabilitation

1.2.2.1 Payment

The Contract price for "Drop-Outlet Structure Rehabilitation", in Schedule No. 1, will include the cost necessary to clean and paint the structure;

replace the existing grating with new steel grating for structure platform and walkway; remove existing walkway, extend with matching members;

reinstall the walkway to match up with the raised dike; remove existing concrete footing and construct a new concrete footing for the walkway;

repair structural and safety deficiencies; to include incidental earthwork and welding of steel work as needed to achieve a safe and stable structure.

1.2.2.2 Unit of Measure

Unit of Measure: Job

1.2.3 Turfing

1.2.3.1 Payment

Payment for "Turfing", in Schedule No. 1, will be made for costs associated with turf establishment, which will include all equipment, labor, and material required for its completion.

1.2.3.2 Unit of Measure

Unit of measure: Job

1.2.4 (AM#3) Clearing, Grubbing, and Removal of Debris

1.2.4.1 Payment

Payment for clearing, grubbing, and removal of debris will be made at the Contract lump sum price for "Clearing, Grubbing, and Removal of Debris" in Schedule No. 1, which will include equipment, labor, and material to perform the work specified herein.

1.2.4.2 Unit of Measure

Unit of measure: Job

1.3 UNIT PRICE PAYMENT ITEMS

Payment items for the work in this Contract on which the Contract unit price payments will be made are listed in the BID SCHEDULE and specified below. The unit price and payment made for each item listed shall constitute full compensation for furnishing plant, labor, materials, and equipment, and performing any associated Contractor Quality Control, administrative requirements, environmental protection, meeting safety requirements, tests and reports, and for performing the work required for each of the unit price items.

1.3.1 Semi-Compacted Containment Dike Raise

1.3.1.1 Payment

Payment for "Semi-Compacted Containment Dike Raise" in Schedule No. 1, will be made for costs associated with raising the containment dikes and will

SECTION 01 22 00.10 Page 3 include stripping, excavation, hauling, placing, and semi-compaction of impervious fill, any third-party geotechnical verification and testing, and any other work in connection therewith.

1.3.1.2 Measurement

The total quantity of "Semi-Compacted Containment Dike Raise" material for which payment is to be made will be the neat-line volumes of in-place quantity between the pre-construction ground surface after clearing/ grubbing and stripping as determined by survey and the grade and slope of the final raised or repaired dike cross sections constructed as specified and as determined by Surveys conforming to SECTION 35 41 00.01 45 EMBANKMENT CONSTRUCTION paragraph titled SURVEYS. In the case of the dike repairs the excavated eroded areas will constitute the ground surface.

Cross sections used for quantity calculation will be taken no farther apart than every 100 feet and at changes in dike section. The theoretical quantity will be calculated by the average end-area method. No allowance will be made for material outside the required slope lines unless authorized.

1.3.1.3 Unit of Measure

Unit of measure: cubic yard

1.3.2 Uncompacted Training Dike Raise

1.3.2.1 Payment

Payment for "Uncompacted Training Dike Raise" in Schedule No. 1, will be made for costs associated with constructing the training dike raise and will include stripping, excavation, hauling, ditching, placement of ditch material, and placing uncompacted random fill, and any other work in connection therewith.

1.3.2.2 Measurement

The total quantity of material for which payment is to be made will be the neat-line volumes in-placed quantity between the pre-construction ground surface after clearing/grubbing and stripping as determined by a survey and the grade and slope of the new training dike cross sections as specified and as determined by surveys conforming to SECTION 35 41 00.01 45 EMBANKMENT CONSTRUCTION paragraph titled SURVEYS. Cross sections used for quantity calculation will be taken no farther apart than every 100 feet and at changes in dike section. The theoretical quantity will be calculated by the average end-area method. No allowance will be made for material outside the required slope lines unless authorized.

1.3.2.3 Unit of Measure

Unit of measure: cubic yard

PART 2 PRODUCTS (Not Used)

PART 3 EXECUTION (Not Used)

-- End of Section --

SECTION 01 22 00.10 Page 4

DIVISION 31 - EARTHWORK

SECTION 31 11 00.10 45

CLEARING, GRUBBING, AND REMOVAL OF DEBRIS

PART 1 GENERAL

1.1 SUMMARY

1.2 MEASUREMENT AND PAYMENT

1.3 DEFINITIONS

1.3.1 Clearing

1.3.2 Grubbing

PART 2 PRODUCTS (Not Used)

PART 3 EXECUTION

3.1 PROTECTION

3.1.1 Roads and Walks

3.2 CLEARING

3.2.1 Excavation and Fill Areas

3.3 TREE REMOVAL

3.4 GRUBBING

3.5 REMOVAL OF DEBRIS

3.6 DISPOSAL OF MATERIAL

3.6.1 Burying

-- End of Section Table of Contents --

SECTION 31 11 00.10 45 Page 1

SECTION 31 11 00.10 45

CLEARING, GRUBBING, AND REMOVAL OF DEBRIS

AMENDMENT NO. 0003

PART 1 GENERAL

1.1 SUMMARY

The work covered in this Section consists of furnishing plant, labor, and equipment necessary to perform the operations in connection with clearing, grubbing, removal of debris and trash from the areas specified herein, and the satisfactory disposal of cleared and removed materials. The site has wooded dense vegetation in areas.

1.2 MEASUREMENT AND PAYMENT

Measurement and payment for clearing, grubbing, and removal of debris will be paid for in accordance with provisions of the SECTION 01 22 00.10

MEASUREMENT AND PAYMENT.

1.3 DEFINITIONS

1.3.1 Clearing

Clearing consists of the removal and satisfactory disposal of all aboveground and below ground trees, downed timber, snags, slash, brush, garbage, trash, debris, fencing, and other items occurring in the designated areas to be cleared.

1.3.2 Grubbing

Grubbing consists of the removal and satisfactory disposal of stumps, roots larger than 3-inches in diameter, and matted roots from the designated grubbing areas. Grubbing also includes filling of holes from the grubbing operation.

PART 2 PRODUCTS (Not Used)

PART 3 EXECUTION

3.1 PROTECTION

3.1.1 Roads and Walks

Keep roads and walks free of dirt and debris at all times.

3.2 CLEARING

Clearing is to include the satisfactory disposal of trees, trash, downed timber, snags, brush, broken concrete, rubbish, and other debris occurring within the limits of the work areas. Trees, stumps, roots, brush, and other vegetation are to be cut off flush with or slightly below the original ground surface. Clearing operations are to be conducted to prevent damage by falling trees to existing structures and installations, SECTION 31 11 00.10 45 Page 2 to those under construction, and to provide for the safety of employees and others. Blasting trees and stumps will not be permitted.

3.2.1 Excavation and Fill Areas

Excavation and fill areas shown are to be cleared prior to placement of fill.

3.3 TREE REMOVAL

Where indicated or directed, trees and stumps that are designated as trees are to be removed from areas outside of the areas designated for clearing and grubbing. This work is to include the felling of these trees and the removal of their stumps and roots as specified in the Paragraph:

GRUBBING. Trees are to be disposed as specified in the Paragraph:

DISPOSAL OF MATERIALS below.

3.4 GRUBBING

Grubbing is to consist of the removal and disposal of stumps and roots larger than 3-inches in diameter to a minimum depth of 12-inches below the finished or existing grade and matted roots from the required work areas.

Depressions excavated below the original ground surface for or by the removal of stumps and roots, are to be filled with satisfactory material and compacted so the surface is to conform to the surrounding ground surface.

3.5 REMOVAL OF DEBRIS

Rubbish, timber, automobile tires, piling, riprap, and other objectionable materials are to be completely removed from the area within the right-of-way limits. Also, the Contractor may be directed to remove other debris from the project location.

3.6 DISPOSAL OF MATERIAL

Materials obtained from clearing, grubbing, and removal of debris operations are to be removed from the construction area and disposed in the designated disposal area in approved locations. Debris consisting of inert and essentially insoluble industrial solid wastes including, but not limited to rock, brick, dirt, concrete, shingles, and glass materials that are not readily decomposable, and that are categorized as Class III wastes, are to be removed from the construction area and disposed in the designated disposal area. Class III wastes are defined in Title 30, Part 1, Chapter 335, Subchapter A, Rule 335.1 of the Texas Administrative Code. Debris consisting of trees, shrubs, and logs are to be disposed in a Type IV landfill as approved. Other classes of waste materials including, but not limited to metal, plastic, and rubber are to be disposed in appropriate areas furnished by the Contractor. Automobiles, abandoned boats, and tires are to be disposed in a Type VIII landfill as approved.

3.6.1 Burying

Subject to applicable Federal, State, and local burying restrictions, the Contractor may bury the cleared and grubbed material in the placement area.

No material is to be buried within 300 feet of the embankment inside toe.

Material disposed by burying is to be covered with a minimum of 12 inches of earth.

SECTION 31 11 00.10 45 Page 3

-- End of Section --

SECTION 31 11 00.10 45 Page 4

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

35 41 00.01 45

EMBANKMENT CONSTRUCTION

PART 1 GENERAL

1.1 SUMMARY

1.2 MEASUREMENT AND PAYMENT

1.3 REFERENCE

1.4 PROTECTION OF EXISTING SERVICE LINES AND UTILITY STRUCTURES

1.5 CHANGES IN DIKE ALIGNMENT

1.6 STOCKPILING

1.7 (AM#3)DITCHING PLAN

1.8 EXCAVATION PLAN

1.9 CONSTRUCTION PLAN

1.10 COORDINATION MEETINGS

1.11 SUBMITTALS

PART 2 PRODUCTS

2.1 GENERAL

2.1.1 Satisfactory Materials

2.1.2 Borrow Materials

2.2 HAUL ROAD MATERIALS

2.3 FILL MATERIALS

2.3.1 Impervious Fill Materials

2.3.2 Random Fill Materials

PART 3 EXECUTION

3.1 CONSTRUCTION

3.1.1 Lines and Grades

3.1.2 Drainage

3.1.3 Conduct of the Work

3.1.4 Stripping

3.1.5 Volumes

3.1.6 Tolerances

3.1.7 Haul Roads

3.2 EXCAVATION

3.2.1 Over Excavation

3.2.1.1 Within Limits of Dike Foundation

3.2.2 Disposition of Excavated Materials

3.3 UTILITIES

3.4 BORROW AREAS

3.5 FOUNDATION PREPARATION

3.5.1 Containment Dike

3.5.2 Training Dike

3.6 EMBANKMENT CONSTRUCTION

3.6.1 General

3.6.2 Placement

SECTION 35 41 00.01 45 Page 1

3.6.2.1 Equipment Traffic

3.6.2.2 Gradation and Distribution

3.6.2.3 Uncompacted Random Fill

3.6.2.4 Semi-Compacted Impervious Fill

3.6.3 Moisture Control

3.6.3.1 Insufficient Moisture for Suitable Bond

3.6.3.2 Excessive Moisture for Suitable Bond

3.6.3.3 Moisture Adjustment

3.6.4 Compaction Equipment

3.6.4.1 Tamping Rollers

3.6.4.2 Rubber-tired Rollers

3.6.4.3 Hand Operated Compactors

3.6.4.4 Crawler-type Tractors

3.6.4.5 Sprinkling Equipment

3.6.4.6 Miscellaneous Equipment

3.6.5 Compaction

3.6.5.1 Compaction of Semi-compacted Impervious Fill

3.6.5.2 Compaction of Uncompacted Random Fill

3.7 EROSION AND SLIDES

3.8 SURVEYS

3.8.1 Topographic Surveys

3.8.2 Cross Sections

3.9 ACCEPTANCE AND CORRECTIVE ACTION

3.9.1 Acceptance of Completed Dike

3.9.2 Corrective Action

3.10 Turfing

3.11 QUALITY CONTROL

3.11.1 Excavations

3.11.2 Embankments

3.11.2.1 General

3.11.2.2 Fill Placement and Compaction

3.11.3 Records and Reporting

-- End of Section Table of Contents --

SECTION 35 41 00.01 45 Page 2

35 41 00.01 45

EMBANKMENT CONSTRUCTION

AMENDMENT NO. 0003

PART 1 GENERAL

1.1 SUMMARY

The work covered in this Section consists of furnishing plant, labor, equipment and performing the operations in connection with construction of dike raise, training dike raise, and rehabilitation of the drop-outlet structure in the placement area as shown. The Bidder is advised to perform a field inspection of the placement area prior to preparing its bid.

(AM#3)Be aware that this PA has been utilized as a dredge disposal placement area periodically throughout many years. Therefore, the deposited soil characteristics are non-uniform and vary from one location to another location. The Contractor is to anticipate encountering extremely soft and saturated materials throughout the interior placement area. It is the Contractors responsibility to determine its means and methods to accomplish the dike raise work.

1.2 MEASUREMENT AND PAYMENT

Measurement and payment for embankment construction will be paid for in accordance with provisions of the SECTION 01 22 00.10 MEASUREMENT AND

PAYMENT.

1.3 REFERENCE

The publication listed below forms a part of this specification to the extent referenced. The publication is referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM D2487 (2017) Standard Practice for Classification of Soils for Engineering Purposes (Unified Soil Classification System)

1.4 PROTECTION OF EXISTING SERVICE LINES AND UTILITY STRUCTURES

Existing utility lines that are shown or the locations of which are made known to the Contractor prior to excavation and that are to be retained, as well as utility lines constructed during excavation operations, are to be protected from damage during excavation and backfilling and if damaged, are to be repaired by and at the expense of the Contractor. If the Contractor damages existing utility lines that are not shown or the locations of which are not known to the Contractor, report of this damage is to be made immediately to the Contracting Officer. If it is determined that repairs are to be made by the Contractor, these repairs will be ordered in accordance with the CONTRACT CLAUSE entitled CHANGES.

SECTION 35 41 00.01 45 Page 3

There are pipelines and or utilities which are within the work limits.

Approximate Location

Permit No.

Description Owner

PA 86/87

Station 145+17

12062 36" Brine Line Top of Pipe at -25 MLLW abandoned in place

Dept of Energy

PA 86/87

Station 145+17

12062 24" parallel to 36" Dept of Energy

EVERY EFFORT HAS BEEN MADE TO GIVE ALL PERTINENT DETAILS ON THE LOCATION OF

PIPELINES/UTILITIES. THE DATA FURNISHED ON THE PLANS ARE BELIEVED TO BE

SUBSTANTIALLY CORRECT. HOWEVER, THE EXACT LOCATIONS MAY VARY FROM THAT

SHOWN: THEREFORE THE CONTRACTOR IS TO COOPERATE WITH THE RESPECTIVE OWNERS

TO ESTABLISH THE ACTUAL POSITION OF THE PIPELINES/UTILITIES.

THE FOLLOWING IS FURNISHED FOR INFORMATION ON VERIFYING PIPELINE

OWNERSHIPS:

Lonestar Notification Center 1-800-545-6005 or online at www.Lonestar811.com

Texas 811 (Dig-Tess) 1-800-344-8377

1.5 CHANGES IN DIKE ALIGNMENT

The right is reserved by the Government to make changes in the dike alignment as may be found necessary before completion of the work, but if it becomes necessary, through no fault of the Contractor, to abandon a line or location on which work has been done, payment for materials placed will be made as specified in the payment item.

1.6 STOCKPILING

When the excavation from designated borrow sources progresses at a faster rate than placement in the fill is being accomplished, such excavated material is to be stockpiled at approved locations adjacent to the work until its use is authorized. No payment will be made for such stockpiling nor for the reloading and hauling of this material to its final position in the containment dike.

1.7 (AM#3)DITCHING PLAN

Submit a Ditching Plan prior to starting this work. The Contractor is to determine dimensions, depths and locations. The plan shall cover the perimeter and lateral ditches, as needed.

1.8 EXCAVATION PLAN

A written Excavation Plan is to be submitted 21 calendar days prior to the beginning of excavation. Approval of the detailed Plan will be obtained prior to starting the work. If necessary, modify the Plan as required to meet field conditions upon modification approval. As a minimum, the Plan is to contain the following:

SECTION 35 41 00.01 45 Page 4

1. The proposed methods for controlling surface and ground water in the borrow areas and required excavations.

2. A complete list of construction equipment used for excavation and to transport the excavated material.

3. Sequence of work for excavating the borrow areas with plan and cross sectional views showing starting and final work locations and clearing, grubbing and stripping limits.

1.9 CONSTRUCTION PLAN

A written Construction Plan and Compaction Equipment list is to be submitted for approval thirty days prior to placement of material for containment dike construction. the plan shall include , but not limited to:

1. Location of haul roads and construction method.

2. List of construction equipment for fill material placement, handling, transport, and compaction.

3. Sequence of construction for containment dike.

4. Methods for controlling drainage.

1.10 COORDINATION MEETINGS

The Contractor will schedule and attend regular coordination meetings with the Government. Meetings are to be scheduled as directed. Schedule and format of meetings to be determined at the Pre-Construction Conference.

Contractor is responsible for preparation and dissemination of meeting minutes.

1.11 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Excavation Plan; G

Construction Plan; G

Compaction Equipment; G

Ditching Plan

SD-11 Closeout Submittals

Topographic Surveys; G

SECTION 35 41 00.01 45 Page 5

PART 2 PRODUCTS

2.1 GENERAL

Material for embankment fill is to be secured from onsite excavations and borrow areas. The intention is to use the most suitable material obtainable from these sources. Material to be wasted will be specifically designated at the time the material is excavated. Material containing brush, roots, sod or other perishable materials will not be considered suitable. The suitability of the materials will be subject to approval by the Contracting Officer with review of District's Geotechnical Engineer and their disposition in the embankment will be as directed.

Excavate in the borrow areas in the locations determined by the Contracting Officer with at least 100 feet away from interior toe of new dike, whenever such control is necessary to obtain the type of material required for the embankment.

The Contracting Officer, according to his judgment, may request a licensed 3rd party Geotechnical Engineer consultant to verify the suitability of the material with appropriate Geotechnical lab tests or equivalent procedures.

Costs associated with verification will be at Contractor expense.

2.1.1 Satisfactory Materials

Satisfactory materials for construction of haul roads, containment dike raise, training dike raise and slope erosion repair vary and are prescribed in the following subparts. Satisfactory materials are to be free from roots, trash, debris, and other organic materials.

2.1.2 Borrow Materials

Borrow materials may exhibit an unacceptable moisture content for compaction at the time of excavation. Borrow materials are to be handled and dried to the extent necessary so that it is considered satisfactory.

2.2 HAUL ROAD MATERIALS

Materials for haul road are to consist of satisfactory materials that include SW, SP, GW, GP, GM (as classified in accordance with ASTM D2487 and shell fragments which, from the standpoint of stability and are suitable for use in the haul road construction.

2.3 FILL MATERIALS

2.3.1 Impervious Fill Materials

Material for impervious fill is to consist of clays, sandy clays, or silty clays obtained from the designated borrow areas within the placement area.

Material for impervious fill is to consist of satisfactory materials classified in accordance with ASTM D2487 as CL, CH, SC, and CL-ML.

Materials used for the containment dike raise and slope erosion repairs are to be classified as impervious fill materials.

2.3.2 Random Fill Materials

Material for random fill applications is to be excavated from designated side-cast borrow locations within the placement area. Satisfactory random fill materials are to consist of materials classified in accordance with

SECTION 35 41 00.01 45 Page 6

ASTM D2487 as CL, CH, SC, GC, SP, SW and shell fragments. Materials used for training dike raise, interior berms, and other temporary earthwork construction are to be classified as random fill materials.

PART 3 EXECUTION

3.1 CONSTRUCTION

The Contract construction duration is based on the time needed for excavation, earthwork, handling, and drying of material as needed.

The soil profiles shown only represent general selective samples taken during initial subsurface soil investigation. Only if the designated borrow area materials are not suitable for a specified fill materials, the Contractor is permitted to relocate a different borrow area within the PA as a borrow source at the Contracting Officer's approval.

Be aware that the placement area has been utilized periodically through out the years, and anticipate extremely soft and wet newly dredged materials.

3.1.1 Lines and Grades

Containment dike raise, training dike raise and slope erosion repair are to be constructed to the lines, grades, and cross sections shown, unless otherwise directed. The Government reserves the right to make adjustments in dike alignments, foundation widths and slopes, or make other changes in the dike sections as may be considered necessary to produce safe, stable earthen structures. Changes in quantities resulting from revisions will not constitute justification for change in Contract unit prices, except as provided for in the CONTRACT CLAUSE entitled VARIATIONS IN ESTIMATED

QUANTITIES.

3.1.2 Drainage

Provide for the collection and disposal of surface and subsurface water encountered during construction. Completely drain construction site including dike foundation areas, and borrow excavations during periods of construction to keep soil materials sufficiently dry. Construct storm drainage features that can include ponds or basins, at the earliest stages of site development, and throughout construction, grade the construction area to provide positive surface water runoff away from the construction activity or provide temporary ditches, swales, and other drainage features and equipment as required to maintain dry soils. Once drainage of the Placement Area and sufficient drying of the foundation surfaces have been accomplished, borrow excavation and embankment construction can proceed.

When unsuitable working platforms for equipment operation and unsuitable soil support for subsequent construction features develop, remove unsuitable material and replace with satisfactory soil as specified herein, or work the existing soils in place to dry and recompact to provide suitable support for construction. It is the responsibility of the Contractor to assess the soil and groundwater conditions and to employ necessary methods that will permit construction to proceed at no additional cost to the Government.

3.1.3 Conduct of the Work

Maintain and protect the newly constructed perimeter containment dike raise, and training dike raise in a satisfactory condition during construction until final completion and acceptance of the work under this

SECTION 35 41 00.01 45 Page 7

Contract. If, in the opinion of the Contracting Officer, the hauling equipment causes horizontal shear planes or slickensides, rutting, quaking, heaving, cracking, or excessive deformation of the dikes or backfill berms, limit the type, load, or travel speed of the hauling equipment on the dike or backfill berm. The Contractor may be required to remove, at no additional payment, dike material placed outside of prescribed slope lines.

Approved dike or backfill material which is lost in transit or rendered unsuitable after being placed in the dike or backfill and before final acceptance of the work will be replaced using a satisfactory method at no additional cost to the Government. Excavate and remove from the dike or backfill material which is unsatisfactory, dispose this material, and refill the excavated area as directed, at no additional cost to the Government.

3.1.4 Stripping

Stripping is to be completed within the limits shown not more than 1,000 feet in advance of the embankment construction. Stripping is to be performed in accordance with SECTION 31 14 13.23 45 STRIPPING.

3.1.5 Volumes

Neat-line volumes of design templates for the embankment construction have been used by the U.S. Army Corps of Engineers to prepare the Government estimate. The volumes used are estimated based on the information available at the time of design. The Contractor is responsible for interpreting the provided plans and volumes provided to prepare his bid estimate. Adjustments for items such as overbuilding, compaction, settlement, foundation displacement, borrow factors, and waste are the Contractors responsibility. The neat-line volume is defined as the unadjusted, raw quantities computed using the dike templates.

3.1.6 Tolerances

Embankments are to be constructed to the grades, lines, and cross-sections shown. At every point a tolerance of 6-inches above or 0-inches below the prescribed grade will be permitted in the final dressing, provided that excess material is distributed to ensure that the crown of the dike drains to the PA interior and that there are no abrupt humps or depressions in the surfaces.

3.1.7 Haul Roads

Haul roads are to be constructed to facilitate transportation of borrow materials to the embankment construction areas as necessary and be located within the placement area limits. Haul roads are to be constructed to accommodate the intended traffic loads and frequency and be maintained in well-drained and functional condition during the Contract period. Haul roads are to be planned so as not to pond water or otherwise impede site drainage and be maintained during the Contract period to provide required drainage as described herein. The costs associated with construction of haul roads are to be considered a subsidiary obligation of the Contractor.

3.2 EXCAVATION

Excavation is to consist of removal of material in preparation of embankment foundations to the lines and grades shown, removal of material from ditches for drainage, removal of objectionable materials at the direction of the Contracting Officer, and obtaining required fill materials

SECTION 35 41 00.01 45 Page 8 from designated borrow areas within the placement area. If necessary, adjust the plan to account for field conditions as directed by the Contracting Officer.

3.2.1 Over Excavation

3.2.1.1 Within Limits of Dike Foundation

When over excavation occurs within the limits of the dike foundations, areas are to be backfilled to grade with satisfactory impervious fill and semi-compacted as specified.

3.2.2 Disposition of Excavated Materials

Satisfactory excavated material is to be incorporated in the appropriate zones of the dike templates. When direct placement is not practicable, satisfactory material from the excavation is to be stockpiled for subsequent use in parts of the work for which it is specified herein or as indicated. Excavated satisfactory material in excess of the quantity necessary to construct embankments are to be stockpiled for future construction work at locations designated by the Contracting Officer.

3.3 UTILITIES

The Contractor is responsible for movement of construction machinery and equipment over pipes and utilities during construction. For work immediately adjacent to or for excavations exposing a utility or other buried obstruction, excavate by hand. Start hand excavation on each side of the indicated obstruction and continue until the obstruction is uncovered or until clearance for the new grade is assured. Support uncovered lines or other existing work affected by the Contract excavation until approval for backfill is received. Report damage to utility lines immediately to the Contracting Officer.

3.4 BORROW AREAS

Approved borrow areas are to be excavated to the extent necessary to obtain satisfactory materials. The permissible depth(s) in the borrow areas vary based on field conditions during construction. Borrow areas are to be drained continuously and kept dry during excavation. Where possible, unsatisfactory materials in borrow areas are not to be removed. Borrow areas are to be graded to drain after completion of excavation.

Interior stockpile of satisfactory materials located within the placement area as specified in paragraph STOCKPILING is to be utilized as borrow materials if the material is suitable.

3.5 FOUNDATION PREPARATION

3.5.1 Containment Dike

The stripped containment dike foundation areas are to be semi-compacted before placing new fill materials for the containment dike raise and slope repair construction. Sinkholes, cavities and depressions in the stripped foundation areas are to be scarified and filled using satisfactory materials, placed in lifts, and semi-compacted in accordance with this Section.

SECTION 35 41 00.01 45 Page 9

3.5.2 Training Dike

Stripped training dike foundation areas are to be shaped to provide surfaces that will support the fill prior to placement of new fill materials. Sinkholes, cavities, and depressions in the stripped foundation areas are to be filled and shaped using suitable materials for the construction type as specified in this Section.

3.6 EMBANKMENT CONSTRUCTION

3.6.1 General

Prior to beginning placement of fill materials on the embankment foundations, notify the Government that the foundation is ready to receive fill. No fill is to be placed on the embankment foundation until these areas have been inspected and given final approval. Unless otherwise directed, the embankment is to be maintained at approximately the same elevation regardless of the number of types of materials being placed.

3.6.2 Placement

Before placing material for compacted fill, the foundation surface is to be cleared of existing vegetation and debris. Material not meeting the requirements for fill material as determined by the Contracting Officer will be removed. After filling depressions and immediately prior to placement of fill, the foundation surface is to be scarified to a depth of 6-inches. No fill material is to be placed in water. Soft or unsatisfactory material in the fill area will be removed as directed before placing the fill.

3.6.2.1 Equipment Traffic

Equipment traffic on a dike zone is to be routed to distribute the compactive effort as much as practicable. Ruts formed in the surface of a layer of spread material are to be filled before that material is compacted. If, in the opinion of the Contracting officer, the compacted surface of a layer of material is too smooth to bond properly with the succeeding layer, the surface is to be loosened by scarifying or other approved methods before material from the succeeding layer is placed.

3.6.2.2 Gradation and Distribution

The gradation and distribution of materials throughout each zone of the containment dike is to be so that the dike will be free from lenses, pockets, streaks, and layers of material differing substantially in texture or gradation from surrounding material of the same class. If lenses, pockets, or layers of materials differing substantially in texture or gradation from surrounding material occur in the spread material, the layer is to be mixed by harrowing or another approved method to blend the materials. During the placing and spreading process, continuously maintain a force of workers adequate to remove roots, debris, and oversize stones from the containment dike materials.

3.6.2.3 Uncompacted Random Fill

Uncompacted random fill is to be used for training dike raise construction. The location and extent of the fill is to be as shown.

Uncompacted random fill material is to be placed and spread in layers not more than 18-inches in uncompacted thickness, except that within 4-feet of

SECTION 35 41 00.01 45 Page 10 drop-outlet structure, the uncompacted layer thickness is to be reduced to 6-inches. The layers are to be uniformly spread, distributed, and otherwise manipulated during placement to such an extent that individual loads of material deposited on the fill will not remain intact, and large open voids in the fill will be eliminated. Fill layers are not to be placed in a manner which causes shrinkage cracks and open voids from developing in previously placed layers. Layers are to be started full out to the slope stakes and be carried substantially horizontal and parallel to the dike centerline with sufficient crown or slope to provide satisfactory drainage during construction.

3.6.2.4 Semi-Compacted Impervious Fill

Semi-compacted impervious fill is to be used for containment dike raise and slope erosion repair construction. The location and extent of the fill is to be as shown. Semi-compacted impervious fill is not to be placed in water. Fill material is to be placed and spread in layers not more than 12-inches in uncompacted thickness, except that within 4-feet of the drop-outlet structure, the uncompacted layer thickness is to be reduced to 6-inches. Layers are to be started full out to the slope stakes and be carried substantially horizontal and parallel to the dike centerline with sufficient crown or slope to provide satisfactory drainage during construction.

3.6.3 Moisture Control

The materials in each layer of the fill are to contain the amount of moisture, within the limits specified below or as directed, necessary to obtain the required compaction. Uncompacted random fill is to be placed at in-situ moisture content unless the in-situ moisture content is too wet or too dry to construct the required sections to the lines and grades shown;

in which case the fill is to be moisture adjusted as specified below.

Semi-compacted impervious fill is to be placed and compacted at uniform moisture contents that will allow suitable compaction and bond between layers.