Preliminary-Abstract-W9126G18B0022.pdf
PDF 210 KB Posted
- Solicitation number
- W9126G18B0022
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Revised-Abstract-W9126G18B0022.pdf | ||
| Amend-0003-W9126G18B0022.pdf | ||
| Amend-0002-W9126G18B0022.pdf | ||
| AMEND-0001_W9126G18B0022.pdf | ||
| W9126G18B0022-Plans.pdf | ||
| W9126G18B0022-Specs.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNIT
PRICE TOTAL
1 JB SUM 2,225,000.00
1 JB SUM 175,000.00
1 JB SUM 44,800.00
699,000 CY 7.33 5,123,670.00
681,400 CY 8.90 6,064,460.00
1 JB SUM 50,000.00
13,682,930.00
1 JB SUM 150,000.00
30,000 CY 16.52 495,600.00
109,000 CY 15.72 1,713,480.00
100 HR 2,000.00 200,000.00
$2,559,080.00
$16,242,010.00
Atkinson Island Dike Repairs
Dredging HSC, Sections 1-6
Dredging Bayport Flare, Section 7
Monitor Surveys
Dredging Bayport Terminals, Section 9
Pipeline Management
TOTAL SCHEDULE NO. 1
TOTAL SCHEDULE NO. 1 & OPTION NO. 1
MARIA E. RODRIGUEZ
CONTRACTING OFFICER
ABSTRACT OF OFFERS Page 1 of 2
Solicitation No.: W9126G18B0022 Date Issued: 18 Jul 18 Date Opened: 23 Aug 18 Issuing Office: USAED-Galveston Project Title: Unrestricted Procurement for Houston Ship Channel, Texas, Bayport to Morgan's Point and Bayport Flare in Chambers County, Texas, Pipeline Dredging.
TOTAL OPTION NO. 1
Mobilization and Demobilization
Number of Amendments Issued: 0001 - 0003
Government Estimate (Without Profit)
NO.
SCHEDULE NO. 1ITEM
Standby for Docks
DESCRIPTION QUANTITY
OPTION NO. 1
Pipeline Management, Docks
* The apparent low bidder,Weeks Marine, Inc. is 36% above the Government's Estimate.
I CERTIFY THAT I HAVE OPENED, READ, AND RECORDED ON THIS ABSTRACT ALL OFFERS RECEIVED IN RESPONSE TO THIS SOLICITATION.
Dredging Bayport Cruise Terminal, Section 8
UNIT
PRICE TOTAL
1 JB SUM 3,925,000.00
1 JB SUM 500,000.00
1 JB SUM 125,000.00
699,000 CY 11.00 7,689,000.00
681,400 CY 11.00 7,495,400.00
1 JB SUM 150,000.00
19,884,400.00
1 JB SUM 200,000.00
30,000 CY 20.00 600,000.00
109,000 CY 9.00 981,000.00
100 HR 4,250.00 425,000.00
$2,206,000.00
$22,090,400.00
Dredging Bayport Cruise Terminal, Section 8
TOTAL SCHEDULE NO. 1
Pipeline Management
Dredging HSC, Sections 1-6
Dredging Bayport Flare, Section 7
Atkinson Island Dike Repairs
OPTION NO. 1
Pipeline Management, Docks
Monitor Surveys
Dredging Bayport Terminals, Section 9
Standby for Docks
Project Title: Unrestricted Procurement for Houston Ship Channel, Texas, Bayport to Morgan's Point and Bayport Flare in Chambers County, Texas, Pipeline Dredging.
Issuing Office: USAED-Galveston
TOTAL SCHEDULE NO. 1 & OPTION NO. 1
TOTAL OPTION NO. 1
ITEM SCHEDULE NO. 1
QUANTITY
Solicitation No.: W9126G18B0022 Date Issued: 18 Jul 18 Date Opened: 23 Aug 18
NO.
Mobilization and Demobilization
DESCRIPTION
ABSTRACT OF OFFERS (CONT'D) Page 2 of 2
Offeror: #1 Weeks Marine, Inc.
Business Size: LB
File details come from the government source that posted it.