AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Houston Ship Channel, Texas, Bayport to Morgan's Point and Bayport Flare in Chambers County, Texas, Pipeline Dredging in which bids are due 17 August 2018 @ 2:00 PM is hereby amended as follows:

Continued on Page 2.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 62

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9126G18B0022

X 9B. DATED (SEE ITEM 11)

18-Jul-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

31-Jul-2018

CODE

US ARMY CORPS OF ENGINEERS FORT WORTH

2000 FORT POINT ROAD

GALVESTON TX 77550-1229

W9126G 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9126G18B0022

A0001-2

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

1. The specifications for Solicitation No. W9126G18B0022, Houston Ship Channel, Texas, Bayport to Morgan’s Point and Bayport Flare in Chambers County, Texas, Dredging, are hereby amended as follows:

a) Specifications.

(1) SECTION 00 11 00.00 45, BID SCHEDULE – The enclosed SECTION 00 11 00.00 45 entitled BID SCHEDULE supersedes that issued with this Solicitation.

(2) SECTION 00 73 00.01 45, SPECIAL CONTRACT REQUIREMENTS, STANDARD – The enclosed SECTION 00 73 00.01 45, entitled SPECIAL CONTRACT REQUIREMENTS, STANDARD, supersedes that issued with this Solicitation.

(3) SECTION 35 20 20.00 45, DREDGED MATERIAL PLACEMENT – The enclosed SECTION 35 20 20.00 45, entitled DREDGED MATERIAL PLACEMENT, supersedes that issued with this Solicitation.

(4) SECTION 35 20 23.16 45, DREDGING – The enclosed SECTION 35 20 23.16 45, entitled DREDGING, supersedes that issued with this Solicitation.

(5) SECTION 35 20 23.16 45, DREDGING, APPENDIX-1, QUANTITY SUMMARY TABLE –

The enclosed SECTION 35 20 23.16 45, entitled DREDGING, APPENDIX-1, QUANTITY SUMMARY TABLE, supersedes that issued with this Solicitation.

b) Drawings.

(1) DRAWINGS NO. G-002, C-103 THROUGH C-105 AND C-301 THROUGH C-321 - The enclosed Drawings No. G-002, C-103 through C-105 and C-301 through C-321, supersede that issued with this Solicitation.

2. This amendment shall be attached to and become a part of the solicitation.

6 Encls:

1. SECTION 00 11 00.00 45, BID SCHEDULE

2. SECTION 00 73 00.01 45, SPECIAL CONTRACT REQUIREMENTS, STANDARD

3. SECTION 35 20 20.00 45, DREDGED MATERIAL PLACEMENT

4. SECTION 35 20 23.16 45, DREDGING

5. SECTION 35 20 23.16 45, DREDGING, APPENDIX-1, QUANTITY SUMMARY TABLE

6. DRAWINGS NO. G-002, C-103 THROUGH C-105 AND C-301 THROUGH C-321

SWG FILE NO.:HSC 401-567 SOLICITATION NO.:W9126G18B0022

SECTION TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SECTION 00 11 00.00 45

BID SCHEDULE

PART 1 GENERAL

1.1 BID SCHEDULE

1.1.1 Schedule No. 1

1.1.2 Option No. 1

1.2 EVALUATION OF OPTIONS (July 1990) (FAR 52.217-5)

-- End of Section Table of Contents --

DOCUMENT 00 11 00.00 45 Page 1

(TO ACCOMPANY AMENDMENT NO. 0001 TO SOLICITATION NO. W9126G18B0022)

SECTION 00 11 00.00 45

BID SCHEDULE

AMENDMENT NO. 0001

PART 1 GENERAL

1.1 BID SCHEDULE

(TO BE ATTACHED TO STANDARD FORM 1442)

1.1.1 Schedule No. 1

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

SCHEDULE NO. 1

0001 Mobilization and Demobilization

1 JOB SUM $___________

0002 Pipeline Management 1 JOB SUM $___________

0003 Atkinson Island Dike Repairs

1 JOB SUM $___________

0004 Dredging

HSC,

Sections 1-6

699,000 C.Y. $_________ $___________

0005 Dredging Bayport Flare, Section 7

681,400 C.Y. $_________ $___________

0006 Monitor Surveys 1 JOB SUM $___________

TOTAL SCHEDULE NO. 1 $___________

NOTE: Completion time stated in SECTION 00 73 00.01 45 SPECIAL CONTRACT REQUIREMENTS, STANDARD is for Schedule No. 1 work.

DOCUMENT 00 11 00.00 45 Page 2

BID SCHEDULE (CONT'D)

(TO BE ATTACHED TO STANDARD FORM 1442)

1.1.2 Option No. 1

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

OPTION NO. 1

0007 Pipeline Management, Docks

1 JOB SUM $___________

0008 Dredging Bayport Cruise Terminal, Section 8

30,000 C.Y. $_________ $___________

0009 Dredging Bayport Terminals, Section 9

109,000 C.Y. $_________ $___________

0010 Standby for Docks 100 HR $_________ $___________

TOTAL OPTION NO. 1 $___________

TOTAL SCHEDULE NO. 1 AND OPTION NO. 1 $___________

NOTE FOR OPTION NO. 1: The Government may exercise this Option by written notice to the Contractor prior to completion of all authorized work. An additional time of 30 calendar days will be added to this Contract for completion of this Option.

DOCUMENT 00 11 00.00 45 Page 3

BID SCHEDULE (CONT'D)

(TO BE ATTACHED TO STANDARD FORM 1442)

1.2 EVALUATION OF OPTIONS (July 1990) (FAR 52.217-5)

Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).

-- End of Document --

DOCUMENT 00 11 00.00 45 Page 4

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SECTION 00 73 00.01 45

SPECIAL CONTRACT REQUIREMENTS, STANDARD

PART 1 GENERAL

1.1 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) (FAR

52.211-10)

1.2 LIQUIDATED DAMAGES - CONSTRUCTION (SEPT 2000) (FAR 52.211-12)

1.3 PHYSICAL DATA (APR 1984) (FAR 52.236-4)

1.4 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE(MAR 1995)

1.5 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 1984) (52.236-1)

PART 2 PRODUCTS (Not Used)

PART 3 EXECUTION (Not Used)

-- End of Section Table of Contents --

DOCUMENT 00 73 00.01 45 Page 1

SECTION 00 73 00.01 45

SPECIAL CONTRACT REQUIREMENTS, STANDARD

AMENDMENT NO. 0001

PART 1 GENERAL

1.1 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) (FAR

52.211-10)

The Contractor shall be required to:

(a) Commence work under this contract within 10 calendar days after the date the Contractor receives the Notice to Proceed

(b) Prosecute the work diligently, and

(c) AMD#1 Complete the entire work ready for use not later than 245 calendar days after the date the Contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises.

1.2 LIQUIDATED DAMAGES - CONSTRUCTION (SEPT 2000) (FAR 52.211-12)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $3,640.00 for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

1.3 PHYSICAL DATA (APR 1984) (FAR 52.236-4)

Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

(a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by surveys.

(b) Weather Conditions. Under ordinary conditions, the mean tidal range is about 1.5 feet. The height of tide is largely dependent on the force, direction, and duration of the wind. Strong northerly winds may depress the water surface as much as, and in some instances more than 3.0 feet below Mean Lower Low Water (MLLW), while southerly winds may raise the water surface as much as, and in some instances more than

1.7 feet above MLLW.

(c) Transportation Facilities. The immediate vicinity is served by railroad, highway, and deep and shallow draft channels. The work site is accessible by water via the Houston Ship Channel and Galveston Bay from embarkation points at surrounding public and private boat ramps.

DOCUMENT 00 73 00.01 45 Page 2

(d) Other Information. Channel traffic consists of deep draft ships, small boats of various sizes, fishing vessels, ferries, tugs, tows consisting of a tug and one or more barges. Traffic will interfere with dredging operations to some extent.

The general shape of the existing section of channel to be dredged is shown by cross sections on the Contract drawings. The Contractor is caustioned that portions of the Bayport to Morgans Point reach of the Houston Ship Channel have been previously mined to depths as great as 70 feet. Material which has settled in these mined areas is expected to be unconsolidated.

1.4 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE(MAR 1995)

(a) This special contract requirement does not apply to terminations. See 52.249-5000, Basis for Settlement of Proposals, and FAR Part 49.

(b) Allowable cost for construction and marine plant and equipment in sound workable condition owned or controlled and furnished by a contractor or subcontractor at any tier shall be based on actual cost data for each piece of equipment or groups of similar serial and series for which the Government can determine both ownership and operating costs from the con-tractor's accounting records. When both ownership and operating costs cannot be determined for any piece of equipment or groups of similar serial or series equipment from the contractor's accounting records, costs for that equipment shall be based upon the applicable provisions of EP 1110-1-8, Construction Equipment Ownership and Operating Expense Schedule, Region VI. Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the contracting officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retroactive pricing, the schedule in effect at the time the work was performed shall apply.

(c) Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii) and FAR 31.205-36, Rental Costs. Rates for equipment rented from an organization under common control, lease-purchase arrangements, and sale-leaseback arrangements, will be determined using the schedule, except that actual rates will be used for equipment leased from an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees.

(d) When actual equipment costs are proposed and the total amount of the pricing action exceeds the SAT, the contracting officer shall request the contractor to submit either certified cost or pricing data, or partial/limited data, as appropriate. The data shall be submitted on Standard Form 1411, Contract Pricing Proposal Cover Sheet.

NOTE: A copy of EP 1110-1-8, "CONSTRUCTION EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE," is available at the following website:

http://www.publications.usace.army.mil/USACEPublications/EngineerPamphlets.asp

1.5 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 1984) (52.236-1)

The Contractor shall perform on the site, and with its own organization, work equivalent to at least sixty percent (65%) percent of the total amount

DOCUMENT 00 73 00.01 45 Page 3 of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performance of the work, the Contractor requests a reduction and the Contracting Officer determines that the reduction would be to the advantage of the Government.

PART 2 PRODUCTS (Not Used)

PART 3 EXECUTION (Not Used)

-- End of Document --

DOCUMENT 00 73 00.01 45 Page 4

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

SECTION 35 20 20.00 45

DREDGED MATERIAL PLACEMENT

PART 1 GENERAL

1.1 SCOPE OF WORK

1.2 MEASUREMENT AND PAYMENT

1.2.1 Fill Material Placement

1.3 SUBMITTALS

1.4 NOTIFICATION PRIOR TO COMMENCEMENT OF DREDGING OPERATIONS

1.5 CONTRACTOR SUPPLIED AIRBOAT

1.6 CREWS

PART 2 PRODUCTS (Not Used)

PART 3 EXECUTION

3.1 ORDER OF WORK

3.2 DISTRIBUTION OF DREDGED MATERIALS

3.3 FILLING OF ATKINSON MARSH CELLS

3.4 REPAIR AND MAINTENANCE OF CONTAINMENT DIKES

3.5 UNAUTHORIZED DISPOSAL OF MATERIAL

3.6 CONTRACTOR QUALITY CONTROL

3.6.1 Quality Control Plan

3.6.2 Quality Control Reports

3.6.3 Compliance Inspection

3.6.4 Records

3.7 PROJECT SCHEDULE

3.8 SURVEYS

-- End of Section Table of Contents --

SECTION 35 20 20.00 45 Page 1

SECTION 35 20 20.00 45

DREDGED MATERIAL PLACEMENT

AMENDMENT NO. 0001

PART 1 GENERAL

1.1 SCOPE OF WORK

The work covered in this Section consists of furnishing plant, equipment, labor, and materials to hydraulically fill cells M1/M2, M3, M4, and M5/M6 at Atkinson Marsh as shown. The work specified herein covers filling the Cells at Atkinson to create a marsh. Up to two 15- to 20-day testing periods will be required to determine if enough marsh fill material has been placed into each Cell of Atkinson Marsh. During the days required to survey and sample the Cell, the Contractor shall be required to stop Marsh filling activities into the active Cell and place into the remaining Cells as directed. Specific distribution of dredged materials throughout each Cell is critical to the development of the Marsh.

1.2 MEASUREMENT AND PAYMENT

Measurement and payment for Dredged material placement will be paid for in accordance with provisions of the SECTION 01 22 00.10 MEASUREMENT AND

PAYMENT.

1.2.1 Fill Material Placement

Fill Material Placement shall be measured by the cubic yard as specified in the SECTION 35 20 23.16 45 entitled PIPELINE DREDGING.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Notification Prior To Commencement of Dredging Operations; G

Quality Control Plan; G

The Contractor shall submit a Quality Control Plan as it pertains to filling the Atkinson Marsh Cells, including equipment and procedures for measuring fill elevations, discharge pipe placement, and regular levee inspections. The Plan shall be submitted prior to the start of the work.

SD-02 Shop Drawings

SD-03 Product Data

SECTION 35 20 20.00 45 Page 2

Project Schedule; G

SD-06 Test Reports

Surveys; G

1.4 NOTIFICATION PRIOR TO COMMENCEMENT OF DREDGING OPERATIONS

The Contractor shall submit a Plan prior to starting work for placing material into the Atkinson Marsh Cells and shall include the following at a minimum:

(1) Proposed discharge pipeline placement for filling the cells at Atkinson Marsh, including the location of Y-valves, shunts, and shore connections.

(2) Sequence of dredging, with beginning and ending stations, dredging depths, and estimated daily production rates.

(3) Beginning and ending dredge stations associated with each anticipated discharge location specified in the Paragraph: ORDER OF WORK below.

(4) Complete list of plant and equipment to be used during construction.

1.5 CONTRACTOR SUPPLIED AIRBOAT

The Contractor shall, at its expense, provide and maintain an airboat or other approved watercraft and an operator for use by a Government representative for the duration of the filling operations at Atkinson Marsh and for a period of 30 calendar days after fill operations are complete.

The airboat shall be capable of running on the dredge fill within the Cells. The Government representative will give the Contractor 24-hour notice prior to use of the airboat. The airboat will be used to perform sampling and topographic surveys of the dredge fill throughout the Cells, and shall be capable of carrying a minimum of four (4) passengers other than the operator.

1.6 CREWS

The Contractor shall provide "around-the-clock" crews for the duration of the placement operations at a particular placement site. The crews at the sites shall consist of necessary personnel and equipment to accomplish the required placement operation within the requirements and restrictions specified herein. Crews shall have radio communication with the dredge at all times. Communication and staffing shall be sufficient to ensure that no violation of the placement process occurs and immediate correction or dredge shutdown can be accomplished. The crews shall have available and in operating condition at all times, a marine vessel for transporting the crew members to and from the placement site for inspection, monitoring or operation and maintenance purposes. The Contractor shall provide sufficient portable lighting to light the discharge corridor and check the drop-outlet structure operation during the night.

SECTION 35 20 20.00 45 Page 3

PART 2 PRODUCTS (Not Used)

PART 3 EXECUTION

3.1 ORDER OF WORK

The dredge pipe and Y valves to the specified discharge locations at the Atkinson Marsh Cells shall be in place and ready for use prior to commencement of dredging. Discharge locations shall be available for use within 4 hours of notification from the Government. The Contractor shall completely fill Cells M1/M2, M3, M4, and M5/M6 at Atkinson Marsh as directed. Circumstances during the construction may dictate filling out of sequence, as directed. The Contractor shall be responsible for distribution of dredged materials within each discharge location at the Atkinson Marsh Cells so that the elevation of discharge mounds formed does not exceed Elevation +2.5 feet Mean Lower Low Water (MLLW). The Contractor shall relocate the discharge point within 4-hours of notification by the Contracting Officer to relocate. Direction may include extending the discharge further into the interior of the cell. Upon this direction, the Contractor shall perform the relocations at no additional cost to the Government. The Contractor shall expect directed changes in discharge location for every 100,000 cubic yards dredged at a minimum. During sampling periods, the Contractor shall relocate the discharge to the location specified or directed. Relocation, changes of operations or shut down of operations are at Contractor's expense. The order of placement shall be filling of Cell M3, Cell M4, Cell M1/M2, and Cell M5/M6 or as directed.

3.2 DISTRIBUTION OF DREDGED MATERIALS

For bidding purposes, material shall be distributed to the marsh cells as shown in Appendix 1-Quantity Summary Table, attached to this specification.

3.3 FILLING OF ATKINSON MARSH CELLS

AMD#1 Material dredged from Bayport Flare shall be transported and deposited in the ODMDS. Material dredged from the Houston Ship Channel, Bayport Docks, and Cruise Terminal shall be deposited as follows:

- Approximately 149,100 cubic yards of cut material shall be placed into Cell M3.

- Approximately 134,100 cubic yards of cut material shall be placed into Cell M4.

- Approximately 231,900 cubic yards of cut material shall be placed into Cell M1/M2.

- The remainder of the material shall be placed into Cell M5/M6.

Based on results of sampling and testing of the dredged material to be performed by the Government, the final fill quantity may be adjusted either up or down. The Government will take samples of material from within the Cells and perform a survey of the interior of the Cells approximately half way through the filling process and again near the completion of the filling process. When surveys are performed and the samples taken, the Contractor shall cease discharge to the respective Cell. The Contractor will be directed as to the final fill quantity of the Cell. The Contracting Officer will direct management of the weir boards at the drop-outlet structures and retains the right to direct the Contractor to adjust the weir boards with minimal advance notice. If upon completion of

SECTION 35 20 20.00 45 Page 4 filling the Cells, material remains within the designated dredging limits for marsh fill, the remaining Marsh fill material shall be discharged into Cell M5/M6.

3.4 REPAIR AND MAINTENANCE OF CONTAINMENT DIKES

The Contractor is advised that there are some breaches on the containment dike at Cell M5/M6 which require repair prior to placing dredged material.

Repairs will consist of utilizing surrounding material to re-build the dike using marsh excavators or similar equipment. The Contractor is responsible for maintenance of the dikes and shore protection system around the Cells, or other dikes traveled, and drop-outlet structures during the life of this contract. If damaged by equipment, construction methods, negligent or reckless discharge of material, the Contractor shall promptly make repairs at no cost to the Government. The Contractor shall conduct daily inspections of the dikes as part of the Quality Control Plan and the results of the inspections shall be included on the Contractor's Quality Control Report.

3.5 UNAUTHORIZED DISPOSAL OF MATERIAL

The Contractor shall not dispose rocks, anchors, chain, wire rope, rope, trash, dredge pipe, timbers or other unsuitable debris in the disposal site. If the aforementioned are found in the disposal site, the Contractor shall remove and dispose of them at no additional cost to the Government.

3.6 CONTRACTOR QUALITY CONTROL

3.6.1 Quality Control Plan

The Contractor shall implement a Quality Control Plan for filling of the Atkinson Marsh Beneficial Use Site. The Plan shall include, as a minimum, the following:

(1) Daily elevation surveys of the marsh fill surface during pumping operations. Elevations of water and fill shall be taken at the drop-outlet boxes and within 100 feet of the discharge pipe.

(2) Notation of topographic features developing or changing during discharge into the Cells.

(3) Daily visual inspections of the containment dikes and the drop-outlet structures for the site being filled.

(4) Reporting of the dredging stations, cut elevations, and dredge quantities placed at each discharge location during the last 24 hours.

3.6.2 Quality Control Reports

A copy of the records of Quality Control inspections and tests, as well as the records of corrective action, shall be filed daily and submitted as directed on approved Quality Control Report Forms. The Report shall include a description of the Control of Discharge and a discussion of prior and ongoing placement activities during the previous 24 hours, to include the following:

(1) Date.

SECTION 35 20 20.00 45 Page 5

(2) Location of dredging associated with the respective fill sites to date.

(3) Quantity of material dredged in the last 24 hours and quantity of material dredged to date for each fill site.

(4) Discharge or filling locations and progress to date.

(5) Fill and water depths at the overflow weir and drop-outlet structures.

(6) Control of Discharge, other comments.

3.6.3 Compliance Inspection

The Contractor shall inspect for compliance with contract requirements and record the inspection of operations including but not limited to, the following:

(1) Placement of fill at each site.

(2) Construction to lines and grades shown.

(3) Misplaced materials - Monitoring and removal if required.

3.6.4 Records

A copy of the records of the compliance inspections, tests, and the records of corrective action shall be submitted as directed.

3.7 PROJECT SCHEDULE

The overall Project Schedule shall identify filling of each Atkinson Marsh Cell as a separate line item.

3.8 SURVEYS

The Contractor shall submit, within 3 days of the survey, the results of the Quality Control Surveys taken while filling the Cells.

-- End of Section --

SECTION 35 20 20.00 45 Page 6

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

SECTION 35 20 23.16 45

DREDGING

PART 1 GENERAL

1.1 SUMMARY

1.2 MEASUREMENT AND PAYMENT

1.3 WORK COVERED BY CONTRACT PRICE

1.3.1 Existing Conditions

1.3.2 Vertical Datum

1.4 REFERENCES

1.5 SUBMITTALS

1.6 MATERIAL TO BE REMOVED

1.6.1 Debris Within the Dredging Limits

1.7 EASEMENTS

1.8 UTILITIES ACROSS THE LIMITS OF DREDGING

1.8.1 Known Pipeline/Utility Crossings

1.9 ORDER OF WORK

1.9.1 Dredging Options

1.10 OBSTRUCTION OF CHANNEL

1.11 TEMPORARY REMOVAL OF AIDS TO NAVIGATION

1.12 NOTIFICATION PRIOR TO COMMENCEMENT OF DREDGING OPERATIONS

1.13 SIGNAL LIGHTS

1.14 NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM

1.15 PLANT

1.15.1 General Requirements

1.15.2 Capacity

1.16 INSPECTION

1.16.1 Equipment

1.16.2 Transportation

1.17 QUANTITY SURVEYS

1.18 FINAL EXAMINATION AND ACCEPTANCE

1.18.1 Acceptance

1.19 SHOALS

1.20 UNANTICIPATED SHOALING

1.21 VARIATIONS IN ESTIMATED QUANTITIES - DREDGING

1.22 CONTINUITY OF WORK

PART 2 PRODUCTS

2.1 BRIDGE-TO-BRIDGE RADIOTELEPHONE EQUIPMENT

2.2 LOOKOUTS AND RADIO COMMUNICATIONS

PART 3 EXECUTION

3.1 ESTIMATED QUANTITY OF MATERIAL

3.1.1 Quantity Summary

3.1.2 Required Dredging Prism

3.1.3 Allowable Overdepth

SECTION 35 20 23.16 45 Page 1

3.1.4 Side And End Slopes

3.1.5 Excessive Dredging

3.2 AREAS TO BE DREDGED

3.3 CONDUCT OF DREDGING WORK

3.3.1 Pre-Operations Safety Coordination Meeting

3.3.2 Protection of Existing Waterways

3.3.3 Adjacent Property and Structures

3.4 PLACEMENT OF EXCAVATED MATERIAL

3.4.1 General

3.4.1.1 Misplaced Material

3.4.1.2 Placement Operations Inspection

3.4.1.3 Placement Area Drainage

3.4.1.4 Maintenance of Existing Dike and Drop-outlet Structures

3.4.2 Spillway Operations

3.4.3 ODMDS

3.4.4 ODMDS Monitor Surveys

3.5 PRESERVATION OF PUBLIC AND PRIVATE PROPERTY

3.5.1 Damages

3.5.2 Accountability and Restoration

3.6 ALTERNATE PLACEMENT AREA(S) PROPOSED BY CONTRACTOR WITH BID AFTER

AWARD OF CONTRACT

3.6.1 Data Submittal

3.7 METHOD OF PLACEMENT

3.7.1 Pipeline Route

3.8 DISPOSAL IN PLACEMENT AREA

3.8.1 Utilities within the Placement Area

3.8.2 Unauthorized Placement of Material

3.8.3 Debris Disposal

3.9 DREDGE PIPELINES

3.9.1 Submerged Pipeline

3.9.2 Submerged Pipeline Lighting Requirements

3.9.3 Floating Pipeline

3.9.4 Pipeline Leaks

3.9.5 Magnetometer Survey Report

3.10 HOUSTON-GALVESTON VESSEL TRAFFIC SERVICE AREA

3.10.1 General

3.10.2 Report Changes

3.10.3 Vessel Traffic Service Location

3.10.4 Communications

3.10.5 Operations

3.11 WORK IN THE VICINITY OF OTHER GOVERNMENT CONTRACTORS

3.12 DREDGING AND DREDGE RELATED MARINE WORK (CESWG)

3.13 AUTOMATIC IDENTIFICATION SYSTEM

3.14 DREDGE PLANT INSTRUMENTATION

3.15 STANDBY

3.15.1 Manning

3.15.2 Lookouts

3.15.3 Measuring and Annotating

3.15.4 Dredge to Remain Stationary

3.15.5 Removal from Standby

3.15.6 Recording Standby

ATTACHMENTS:

Appendix 1 - QUANTITY SUMMARY TABLE

-- End of Section Table of Contents --

SECTION 35 20 23.16 45 Page 2

SECTION 35 20 23.16 45

DREDGING

AMENDMENT NO. 0001

PART 1 GENERAL

1.1 SUMMARY

The work in this Section consists of furnishing plant, labor, materials, and equipment and performing the operations necessary for the removal of materials to the required dimensions shown, satisfactory disposal thereof, and other operations incidental thereto. AMD#1 The Contractor shall use a pipeline dredge in performing the work on the Houston Ship Channel and Bayport Docks; however, the Contractor may only use a mechanical dredge with scow to dredge the Bayport Flare. Pipeline dredge with scow or hopper dredge shall not be used to dredge the Bayport Flare.

1.2 MEASUREMENT AND PAYMENT

Measurement and payment for pipeline dredging will be paid for in accordance with provisions of the SECTION 01 22 00.10 MEASUREMENT AND

PAYMENT.

1.3 WORK COVERED BY CONTRACT PRICE

Base bids on the quantity of dredging indicated. If the total quantity of dredging varies from that specified as the basis for bidding, the Contract price will be adjusted in accordance with the CONTRACT CLAUSE entitled VARIATION IN ESTIMATED QUANTITIES. The dredging conditions specified and indicated describe conditions which are known. However, the Contractor is responsible for other conditions encountered which are not unusual when compared to the conditions recognized in the dredging business as usual in dredging activities such as those required under this Contract. The Contract price for dredging will include the cost of removal and placement of the material as specified in the Paragraphs: CHARACTER OF MATERIAL and PLACEMENT OF EXCAVATED MATERIAL. The Contract price for dredging will include the costs for maintenance of dikes and ditches necessary to confine the material within the areas shown.

1.3.1 Existing Conditions

The drawings already prepared as specified in the CONTRACT CLAUSES Paragraph entitled CONTRACT DRAWINGS AND SPECIFICATIONS represent conditions existing as of the date of their preparation using average existing conditions. However, to reflect anticipated shoaling occurring between the dates of preparation of the drawings and the dates of the "before-dredging" sections, the estimated dredging quantities stated in the Bid Schedule have been adjusted accordingly. The depths and elevations shown will be verified and corrected by fathometer soundings taken by the Government before dredging. The Government will normally use a frequency of 200 kHz to conduct hydrographic surveys. If the surveys indicate the presence of fluff in the channel, a frequency of 40 kHz will be used.

Determination of quantities removed and the deductions made from them to determine quantities by in-place measurement to be paid for in the area

SECTION 35 20 23.16 45 Page 3 specified, after having once been made will not be reopened, except on evidence of collusion, fraud, or obvious error.

1.3.2 Vertical Datum

The channel template provided in the drawings is referenced to Mean Lower Low Water (MLLW) vertical datum. Previous dredging contracts in this reach of the Houston Ship Channel and Bayport Docks have been referenced to Mean Low Tide (MLT) datum. Cross sections in the drawings have been overlaid with after-dredge surveys from the previous dredging contract, converted to MLLW datum.

1.4 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

EM 1110-2-5025 (2015) Dredging and Dredged Material Management

1.5 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Notification Prior To Commencement of Dredging Operations; G

Indicate commencement of dredging operations, and location of dredge(s).

Temporary Removal of Aids To Navigation; G

SD-02 Shop Drawings

Submerged Pipeline; G

Indicate pipeline location and installation details as outlined in the Subparagraph: Submerged Dredge Pipeline.

Pipeline Route; G

A detailed pipeline diagram for each Placement Area detailing the pipeline route and anchor locations are to be submitted prior to commencing work on this project.

ODMDS Monitor Surveys; G

Surveys are to be submitted in ASCII XYZ format on compact disks

SECTION 35 20 23.16 45 Page 4 or electronic file promptly upon completion.

Post Disposal Summary Report; G

Reports are to be submitted promptly upon completion when using the Galveston ODMDS. Report format is to follow example Appendix E in the Site Management and Monitoring Plan (SMMP) attached at the end of this section.

SD-06 Test Reports

Magnetometer Survey Report; G

Report to be be submitted as specified.

1.6 MATERIAL TO BE REMOVED

The material to be removed is shoals which have accumulated over a period of time. However, some virgin material may be encountered in allowable overdepth, or side slope dredging. Portions of the areas to be dredged have not been dredging since Hurricane Harvey. Dredging in other sections of Houston Ship Channel post-Harvey have noted higher percentages of sand than on typical maintenance contracts. Bidders are expected to examine the worksite and the records of previous dredging, which are available in the Houston Resident Office and after investigation decide for themselves the character of materials.

1.6.1 Debris Within the Dredging Limits

Debris including but not limited to, metal bands, pallets, pieces of broken cable, rope, stumps, and broken piles may be encountered. Debris removed from the dredged area is to be removed from the water. Disposal is to be the responsibility of the Contractor and disposal is to be outside the limits of Government property. If the actual conditions differ from those stated or shown, an adjustment in Contract price or time of completion, or both, will be made in accordance with the CONTRACT CLAUSE entitled

DIFFERING SITE CONDITIONS.

1.7 EASEMENTS

Permits authorizing placement of dredge material in the Placement Area(s), are attached at the end of the specification. The instruments authorizing the laying of shore pipelines may contain certain restrictions relative to specific route, location, and general use of the land. These instruments form a part of these specifications and the Contractor is to strictly comply with the terms thereof.

1.8 UTILITIES ACROSS THE LIMITS OF DREDGING

It is the Contractor's responsibility to investigate the location of utility crossings. The Contractor is to take precautions against damages which can result from dredging operations in the vicinity of the utility crossings. If damage occurs as a result of dredging operations, the Contractor will be required to suspend dredging until the damage is repaired and approved. Costs of these repairs and downtime of the dredge and attendant plant is to be at the Contractor's expense.

SECTION 35 20 23.16 45 Page 5

1.8.1 Known Pipeline/Utility Crossings

There are pipelines and or utilities which are within the work limits. The following pipeline/utilities cross the area(s) to be dredged:

Approximate Station

Permit No. Description Owner

18+000 T4 Permit 06336

One 10-inch Pipeline

Davis Petroleum Pipeline

LLC

EVERY EFFORT HAS BEEN MADE TO GIVE ALL PERTINENT DETAILS ON THE LOCATION OF

PIPELINES/UTILITIES. THE DATA FURNISHED ON THE PLANS ARE BELIEVED TO BE

SUBSTANTIALLY CORRECT. HOWEVER, THE EXACT LOCATIONS MAY VARY FROM THAT

SHOWN: THEREFORE THE CONTRACTOR IS TO COOPERATE WITH THE RESPECTIVE OWNERS

TO ESTABLISH THE ACTUAL POSITION OF THE PIPELINES/UTILITIES.

THE FOLLOWING IS FURNISHED FOR INFORMATION ON VERIFYING PIPELINE OWNERSHIPS:

Lonestar Notification Center 1-800-545-6005 or online at www.Lonestar811.com

Texas 811 (Dig-Tess) 1-800-344-8377

1.9 ORDER OF WORK

The Contractor is to begin at the upstream end of the Channel first and proceed downstream. If Option No. 1 is exercised, Bayport Docks 2-5 and Cruise Terminal shall be dredged after completion of dredging at Houston Ship Channel. Bayport Flare shall be dredged last. The Government reserves the right to change the order of work at any time.

1.9.1 Dredging Options

The Government will award Dredging Options as specified.

1.10 OBSTRUCTION OF CHANNEL

The Government will not undertake to keep the Channel free from vessels or other obstructions, except to the extent of applicable regulations, if any, as may be prescribed by the Secretary of the Army, in accordance with the provisions of Section 7 of the River and Harbor Act approved 8 August 1917. The Contractor will be required to conduct the work using a method that will obstruct navigation as little as possible, and if the Contractor's plant does obstruct the Channel and makes passage of vessels difficult or endangers them, the plant is to be promptly moved on the approach of a vessel as far as may be necessary to afford a practicable passage. If multiple dredges are used, they shall not be allowed to work concurrently. Upon completion of the work, promptly remove plant, including ranges, buoys, piles, and other marks placed under this Contract.

1.11 TEMPORARY REMOVAL OF AIDS TO NAVIGATION

The temporary removal or changes in locations of channel markers may be required to facilitate dredging operations. Notify the Contracting Officer at least 30days prior to the date that the removal or change in location of channel markers will be required so the U.S. Coast Guard can perform the

SECTION 35 20 23.16 45 Page 6 work and so navigation interests may be informed sufficiently in advance of the proposed removal or change in location.

The Contractor is not to remove, change the location of, obstruct, willfully damage, make fast to, or interfere with aids to navigation.

Indicate temporary removal or changes in locations of channel markers required to facilitate dredging operations.

1.12 NOTIFICATION PRIOR TO COMMENCEMENT OF DREDGING OPERATIONS

Notify the Resident Engineer, Houston Resident Office, in writing, at least 10 days prior to commencement of dredging operations, the location or locations at which a dredge or dredges will be placed on the work. This information is required in addition to the progress charts and schedule provided for in the CONTRACT CLAUSE entitled SCHEDULE FOR CONSTRUCTION

CONTRACTS.

1.13 SIGNAL LIGHTS

Display signal lights and conduct operations in accordance with the General Regulations of the Department of the Army and of the U.S. Coast Guard governing the:

i) lights and day signals to be displayed by towing vessels with tows on which no signals can be displayed, vessels working on wrecks, dredges, and vessels engaged in laying cables or pipe or in submarine or bank protection operations;

ii) lights to be displayed on dredge pipe lines;

iii) day signals to be displayed by vessels of more than 65 feet in length moored or anchored in a fairway or channel;

iv) and the passing by other vessels of floating plant working in navigable channels as set forth in United States Coast Guard publication entitled Navigation Rules and Regulations Handbook. Web site location:

http://www.navcen.uscg.gov/?pageName=navRuleChanges

1.14 NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM

The work under this Contract requires use of the National Dredging Quality Management Program (DQM), formerly known as Silent Inspector (SI) to monitor the scow's status at all times during this Contract in accordance with the SECTION 35 20 23.13 NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM, SCOW TRACKING PROFILE.

1.15 PLANT

1.15.1 General Requirements

Keep the necessary dredge equipment and attendant plant on the job to meet the requirements of the work. The dredge equipment and attendant plant is to be in satisfactory operating condition and capable of safely and efficiently performing the work as set forth in specifications and be subject to inspection by the Contracting Officer's representative at all times.

SECTION 35 20 23.16 45 Page 7

1.15.2 Capacity

No reduction in the capacity of the dredge equipment and attendant plant employed to execute the work is to be made except by written direction of the Contracting Officer. The measure of the "Capacity of the Dredge and Attendant Plant" is to be its actual performance on the work to which these specifications apply.

1.16 INSPECTION

The Government will direct the maintenance of the gages, ranges, location marks, and limit marks in proper order and position; but the presence of the inspector shall not relieve the Contractor of responsibility for the proper execution of the work in accordance with the specifications. The Contractor shall be required to furnish the following items.

1.16.1 Equipment

At the request of the Government, the Contractor shall furnish the use of boats, boatmen, laborers, and material forming a part of the ordinary and usual equipment and crew of the dredging plant as may be reasonably necessary in inspecting and supervising the work. However, the Contractor will not be required to furnish facilities for the surveys, specified in the Paragraph: FINAL EXAMINATION AND ACCEPTANCE.

1.16.2 Transportation

At the request of the Government, the Contractor shall furnish suitable transportation from all points on shore designated by the Contracting Officer to and from the various pieces of plant, and to and from the Placement Areas. If the Contractor refuses, neglects, or delays compliance with these requirements, the specific facilities may be furnished and maintained by the Contracting Officer, and the cost thereof will be deducted from the amounts due or to become due the Contractor.

1.17 QUANTITY SURVEYS

(1) Quantity surveys shall be conducted, and the data derived from these surveys shall be used in computing the quantities of work performed and the actual construction completed and in place.

(2) The Contractor shall conduct surveys for any periods for which progress payments are requested. These surveys shall be conducted under the direction of a representative of the Contracting Officer, unless the Contracting officer waives this requirement in a specific instance. The Government will make the computations that are necessary to determine the quantities of work performed or finally in place. The Contractor shall make the computations based on the surveys for any periods for which progress payments are requested.

(3) Promptly upon completing a survey, the Contractor shall submit the originals of field notes and other records relating to the survey or to the layout of the work to the Contracting Officer, who will use them as necessary to determine the amount of progress payments. The Contractor shall retain copies of the material submitted to the Contracting Officer.

SECTION 35 20 23.16 45 Page 8

1.18 FINAL EXAMINATION AND ACCEPTANCE

As soon as practicable after the completion of the entire work or any section thereof, if the work is divided into sections and in the opinion of the Contracting Officer will not be subject to damage by further operations under this Contract, this work will be thoroughly examined at the expense of the Government by sounding or by sweeping, or both, as directed. If shoals, lumps, or other lack of Contract depth are disclosed by this examination, the Contractor will be required to remove same by dragging the bottom or by dredging at the Contract rate for dredging but, if the bottom is soft and the shoal areas are small and form no material obstruction to navigation, the removal of the shoal may be waived at the discretion of the Contracting Officer. The Contractor or its authorized representative will be notified when soundings or sweepings are to be made and will be permitted to accompany the survey party. When the area is found to be in a satisfactory condition it will be accepted finally. If more than two sounding or sweeping operations by the Government over an area are necessary, by reason of work for the removal of shoals disclosed at a prior sounding or sweeping, the cost of the third and any subsequent sounding or sweeping operations will be charged against the Contractor at the rate of $6,709.00 per day for each day in which the Government plant is engaged in sounding or sweeping or is enroute to or from the site or held at or near the site for these operations.

1.18.1 Acceptance

Final acceptance of the whole or a part of the work and the deductions or corrections of deductions made thereon will not be reopened after having once been made, except on evidence of collusion, fraud, or obvious error, and the acceptance of a completed section will not change the time of payment of the retained percentages of the whole or any part of the work.

1.19 SHOALS

If, before this Contract is completed, shoals occur in a section previously accepted, redredging at the Contract price, within the limit of available funds, may be done if agreeable to both the Contractor and the Contracting Officer.

1.20 UNANTICIPATED SHOALING

During the course of this Contract, unanticipated dredging requirements may develop that require the use of the Contractor and Contractor's plant. The dredging required would be similar in scope to that required under the current contract and could include unanticipated shoals in the Houston Ship Channel Complex. Dredging would consist of limited portions of a section of channel, intended to remove critical shoals hindering commercial navigation. If such a need arises, the Contracting Officer may issue a Request for Proposal for the work under the CONTRACT CLAUSE entitled CHANGES, and the work performed upon the execution of a bilateral contract modification.

1.21 VARIATIONS IN ESTIMATED QUANTITIES - DREDGING

Where the quantity of a pay item in this Contract is an estimated quantity and where the actual quantity of material within the required dredging prism varies, an equitable adjustment will be processed in accordance with FAR 52.211-18, Variation in Estimated Quantity (April 1984). The equitable adjustment applies only to the quantity within the required dredging prism, SECTION 35 20 23.16 45 Page 9 which does not include the allowable overdepth.

If the total quantity of material to be paid for and actually removed under this Contract exceeds the limit established by FAR 52.211-18, Variation in Estimated Quantity (April 1984), an additional time will be allowed at the rate of 1 calendar day for each 10,000 cubic yards in excess of the established limit. The Contractor is not to exceed the estimated quantities in the Contract Line Items without prior authorization and only with a signed modification issued by the Contracting Officer.

1.22 CONTINUITY OF WORK

No payment will be made for work done in an area designated by the Contracting Officer until the full depth required under this Contract is secured in the whole of this area, unless prevented by ledge rock, nor will payment be made for excavation in an area not adjacent to and in prolongation of areas where full depth has been secured except by decision of the Contracting Officer. If a non-adjacent area is excavated to full depth during the operations carried on under this Contract, payment for the work therein may be deferred until the required depth has been reached in the area intervening. The Contractor may be required to suspend dredging when the gages or ranges cannot be seen or properly followed.

PART 2 PRODUCTS

2.1 BRIDGE-TO-BRIDGE RADIOTELEPHONE EQUIPMENT

Dredge and self-propelled attendant floating plant is to be radiotelephone equipped to comply with the provisions of the Vessel Bridge-to-Bridge Radiotelephone Act (Public Law 92-63). This will require, as a minimum, the radiotelephone equipment capable of transmitting and receiving on

156.65 MHz (Channel 13). Multi-channel equipment will also require 156.8 MHz (Channel 16). Dredge tugs and tenders will be considered towing vessels within the meaning of the Act.

2.2 LOOKOUTS AND RADIO COMMUNICATIONS

When working in the Houston Ship Channel, have a lookout person posted in the dredge control room at all times to visually monitor the movement of vessels around the dredge plant; to perform radio communications with company workboats; and to deliver passing arrangements with other commercial, fishing and recreational vessels. The lookout is to be competent in U.S. Coast Guard and Federal Communications Commission radio communications procedures and requirements and is to be trained in the Vessel Bridge to Bridge Radiotelephone Act. The lookout is to maintain up to the minute information on the status of each company workboat and approaching vessels, and will communicate this information as required to prevent collisions. Each company workboat is to check in with the lookout when arriving at the dredge and receive radio clearance from the lookout before departing the dredge.

FAILURE TO COMPLY WITH THIS REQUIREMENT WILL BE CONSIDERED A VIOLATION OF

THE SAFETY PROTOCOL ESTABLISHED HEREIN. PURSUANT TO THE DIRECTION OF THE

CONTRACTING OFFICER, THE CONTRACTOR MAY BE REQUIRED TO CEASE OPERATIONS

UNTIL THIS PROVISION IS COMPLIED WITH.