AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04 EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Small Business Multiple Award Task Order Contract (MATOC) for Construction Services for the United States Army Corps of Engineers (USACE) in Southwestern Division (SWD) and other SWF and SWD customers on a limited nationwide basis, is amended as follows:

See SF30 Continuation Sheet(s)

NOTE: The Phase 2 proposal receipt date is 24 June 2014, 2:00 p.m., Central Time, as previously stated.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA 15C. DATE SIGNED 15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer) (Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X 9A. AMENDMENT OF SOLICITATION NO.

W9126G-13-R-0014

X 9B. DATED (SEE ITEM 11)

02-May-2013

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

13-June-2014

CODE

US ARMY ENGINEER DISTRICT, FORT WORTH

ATTN: CESWF-CT

819 TAYLOR ST, ROOM 2A19

P.O. BOX 17300

FORT WORTH TX 76102-0300

W9126G 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODE CODE

EMAIL: TEL:

X

W9126G-13-R-0014

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

1. Replacement Sections: The following sections have been replaced in their entirety, bearing the notation “W9126G-13-R-0014, Amendment No. 0005”:

SEED TASK ORDER SECTIONS

DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS

• 00 11 00 – CONTRACT LINE ITEM SCHEDULE

DIVISION 01 – GENERAL REQUIREMENTS

• 01 10 00 – TASK ORDER STATEMENT OF WORK

3. Replacement Drawings: The following drawings from Appendix J have been replaced in their entirety, bearing the notation “W9126G-13-R-0014, Amendment No. 0005”:

• CU101

End of Summary of Changes

Estimated Estimated

Building 915 & 916 Renovate Training Barracks Joint Bas San Antonio (JBSA), Ft. Sam Houston, TX

Solicitation No.W9126G-13-R-0014

CLIN SCHEDULE

Estimated Estimated Item No. Description Quantity Unit Unit Price Amount

0001 All work required by the RFP documents to design JBSA Building

BASE OFFER: All work required by the Request for Proposal (RFP) documents for the renovation on bldgs 915 & 916, Fort Sam Houston, Texas, excluding Option Item(s).

documents to design JBSA Building 916 Renovate Training Barracks.

1 Job *** $

0002 All work required by the RFP documents to construct JBSA Building 916 Renovate Training Barracks. 1 Job *** $

(AM#5)

0003 CPS Energy Allowance cost for coordination, design and construction of electrical service for Building 916. 1 Job *** $ 32,000.00

(/AM#5)

OPTIONS

TOTAL BASE OFFER

0004 OPTION NO. 1: All work required by the RFP documents to design JBSA Building 915 Renovate Training Barracks. 1 Job *** $

0005 OPTION NO. 2: All work required b th RFP d t t t tby the RFP documents to construct JBSA Building 915 Renovate Training Barracks. 1 Job *** $

Section 00 11 00 Page 1

W9126G-13-R-0014, Amendment No. 0005

Joint Bas San Antonio (JBSA), Ft. Sam Houston, TX

Solicitation No.W9126G-13-R-0014

CLIN SCHEDULE

Estimated Estimated Item No. Description Quantity Unit Unit Price Amount

0006 OPTION NO. 3: All work required by the RFP documents to demolish and replace all sidewalks associated with B915 1 Job *** $

0007 OPTION NO. 4: All work required by the RFP documents to demolish and replace all sidewalks associated with B916. 1 Job *** $

(AM#4)

0008 OPTION NO. 5: All work required by the RFP documents to provide conduits, junction boxes, outlet boxes and pull wires for GFFI CCTV GFGI, door alarm and Access control systems associated with B915. 1 Job *** $

0009 OPTION NO 6: All work required0009 OPTION NO. 6: All work required by the RFP documents to provide conduits, junction boxes, outlet boxes and pull wires for GFFI CCTV GFGI, door alarm and Access control systems associated with B916. 1 Job *** $

(AM#5)

0010 OPTION NO. 7: CPS Energy

Allowance cost for coordination, design and construction of electrical service for Building 915. 1 Job *** $ 32,000.00

(/AM#5)

0011 OPTION NO 8: All work required0011 OPTION NO. 8: All work required by the RFP documents to provide copper communications upgrade to 50 pair in Building 916. 1 Job *** $

Section 00 11 00 Page 2

Joint Bas San Antonio (JBSA), Ft. Sam Houston, TX

Solicitation No.W9126G-13-R-0014

CLIN SCHEDULE

Estimated Estimated Item No. Description Quantity Unit Unit Price Amount

0012 OPTION NO. 9: All work required by the RFP documents to provide copper communications upgrade to 50 pair in Building 915. 1 Job *** $

0013 OPTION NO. 10: All work required by the RFP documents for the removal and reinstallation of EES Components as identified by the COR for Building 916. 1 Job *** $

0014 OPTION NO. 11: All work required by the RFP documents for the removal and reinstallation of EES Components as identified by the COR for Building 915. 1 Job *** $

(/AM#4)

PROJECT COMPLETION TIME ___540___ Calendar days for each Building (Bldg 915 and Bldg 916)*

TOTAL OFFER (BASE OFFER + ALL OPTIONS)

Building (Bldg 915 and Bldg 916)*

*Contract Duration in Calendar Days After the Notice to Proceed is Received (Not To Exceed the maximum time stated in Section 01 00 50.00 44 General Requirements

Section 00 11 00 Page 3

Joint Base San Antonio (JBSA), Ft. Sam Houston, TX

Solicitation No.W9126G-13-R-0014

CLIN SCHEDULE

Section 00 11 00 Page 4

NOTES:

1. ARITHMETIC DISCREPANCIES (EFARS 14.407-2)

(a) For the purpose of initial evaluation of bids, the following will be utilized in resolving arithmetic discrepancies found on the face of the bidding schedule as submitted by bidders:

(1) Obviously misplaced decimal points will be corrected;

(2) In case of discrepancy between unit price and extended price, the unit price will govern;

(3) Apparent errors in extension of unit prices will be corrected; and

(4) Apparent errors in addition of lump-sum and extended prices will be corrected.

(b) For the purpose of bid evaluation, the Government will proceed on the assumption that the bidder intends his bid to be evaluated on the basis of the unit prices, the totals arrived at by resolution of arithmetic discrepancies as provided above and the bid will be so reflected on the abstract of bids.

(c) These correction procedures shall not be used to resolve any ambiguity concerning which bid is low.

2. If a modification to a proposal based on unit prices is submitted, which provides for a lump sum adjustment to the total estimated cost, the application of the lump sum adjustment to each unit price in the CLIN Schedule must be stated. If it is not stated, the offeror agrees that the lump sum adjustment shall be applied on a pro rata basis to every unit price in the CLIN Schedule.

3. Offerors must bid on all items.

4. Costs attributable to Division 01 - General Requirements are assumed to be prorated among bid items listed.

5. Responders are advised that this requirement may be delayed, cancelled or revised at any time during the solicitation, selection, evaluation, negotiation and/or final award process based on decisions related to DOD changes in force structure and disposition of the Armed Forces.

6. 52.217-5 EVALUATION OF OPTIONS (JUL 1990)

(a) Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).

Joint Base San Antonio (JBSA), Ft. Sam Houston, TX

Solicitation No.W9126G-13-R-0014

CLIN SCHEDULE

Section 00 11 00 Page 5

(b) The Government may reject an offer as nonresponsive if it is materially unbalanced as to prices for the basic requirement and the option quantities. An offer is unbalanced when it is based on prices significantly less than cost for some work and prices which are significantly overstated for other work.

7. EXERCISE OF OPTIONS (SWDR 715-1-1 (16 January 1996))

The Government reserves the right to exercise the option(s) by written notice to the Contractor either singularly or in any combination for up to 120 calendar days after award of the Base Offer without an increase in the Offeror's Price. Completion of added items shall continue at the same schedule as the Base Offer unless otherwise noted in Section 01 00 50.00 44 GENERAL REQUIREMENTS, paragraph

1.4 entitled 52.211-10 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK (APR 1984).

8. The Army will procure this facility through a design and cost competition in accordance with the provisions set forth in this Request for Proposals (RFP). When a contract is awarded, it will be a "Firm Fixed Price Contract."

9. Any proposal that is materially unbalanced as to prices for the Base CLIN Schedule may be rejected. An unbalanced proposal is one that is based on prices significantly less than the cost for some work and prices that are significantly overstated for other work and can also exist where only overpricing or under pricing exists.

END OF CLIN SCHEDULE

SECTION 01 10 00

TASK ORDER STATEMENT OF WORK

TABLE OF CONTENTS

1.0 PROJECT OBJECTIVES

1.1. SECTION ORGANIZATION

2.0 SCOPE

2.1. GENERAL

2.2. NOT USED

2.3. SITE

2.4. GOVERNMENT-FURNISHED GOVERNMENT-INSTALLED EQUIPMENT (GFGI)

2.5. FURNITURE REQUIREMENTS

3.0 FUNCTIONAL AND OPERATIONAL REQUIREMENTS

3.1. GENERAL REQUIREMENTS

3.2. FUNCTIONAL AND AREA REQUIREMENTS

3.3. SITE REQUIREMENTS

3.4. ARCHITECTURAL REQUIREMENTS

3.5. STRUCTURAL REQUIREMENTS

3.6. COMPLIANCE WITH THE ENERGY POLICY ACT OF 2005

3.7. MECHANICAL REQUIREMENTS

3.8. ELECTRICAL AND TELECOMMUNCATIONS REQUIREMENTS

3.9. FIRE ALARM REQUIREMENTS

3.10. MASS NOTIFICATION REQUIREMENTS

4.0 APPLICABLE CRITERIA

4.1. INDUSTRY CRITERIA

4.2. MILITARY CRITERIA

5.0 GENERAL TECHNICAL REQUIREMENTS

5.1. SITE PLANNING AND DESIGN

5.2. SITE ENGINEERING

5.3. ARCHITECTURE AND INTERIOR DESIGN

5.4. STRUCTURAL DESIGN

5.5. THERMAL PERFORMANCE

5.6. PLUMBING

5.7. ELECTRICAL AND TELECOMMUNICATIONS SYSTEMS

5.8. HEATING, VENTILATING AND AIR CONDITIONING

5.9. ENERGY CONSERVATION

5.10. FIRE PROTECTION

5.11. SUSTAINABLE DESIGN

5.12. CONSTRUCTION AND DEMOLITION (C&D) WASTE MANAGEMENT

5.13. SECURITY (ANTI-TERRORISM STANDARDS)

6.0 PROJECT SPECIFIC REQUIREMENTS

6.1. GENERAL

6.2. APPROVED DEVIATIONS

6.3. SITE PLANNING AND DESIGN

6.4. SITE ENGINEERING

6.5. ARCHITECTURE

6.6. STRUCTURAL DESIGN

6.7. THERMAL PERFORMANCE

6.8. PLUMBING

6.9. SITE ELECTRICAL AND TELECOMMUNICATIONS SYSTEMS

6.10. FACILITY ELECTRICAL AND TELECOMMUNICATIONS SYSTEMS

6.11. HEATING, VENTILATING AND AIR CONDITIONING

6.12. ENERGY CONSERVATION

6.13. FIRE PROTECTION

6.14. SUSTAINABLE DESIGN

6.15. ENVIRONMENTAL

6.16. PERMITS

6.17. DEMOLITION

End of Table of Contents

SECTION 01 10 00

TASK ORDER STATEMENT OF WORK

1.0 PROJECT OBJECTIVES

The project objective is to design and construct facilities for the military that are consistent with the design and construction practices used for civilian sector projects that perform similar functions to the military projects. For example, an AIT Barracks has the similar function as a Student Dormitory in the civilian sector; therefore the design and construction practices for a barracks should be consistent with the design and construction of a dormitory.

Comparison of Military Facilities to Civilian Facilities

Military Facility Civilian Facility

AIT Barracks Student Dormitory

It is the Army's objective that this building will have a 25-year useful design life before a possible re-use/repurpose or renovation requirement, and a 50-year building replacement life. Therefore, the design and construction should provide an appropriate level of quality to ensure the continued use of the facility over that time period, including normal sustainment, restoration, modernization activities that would be industry-acceptable to a major civilian sector project OWNER. The site infrastructure will have at least a 50-year life expectancy with industry-accepted maintenance and repair cycles.

The project should be developed for efficiency and to convey a sense of unity or connectivity with the adjacent buildings and with the Installation as a whole.

Requirements stated in this contract are minimums. Innovative, creative, and life cycle cost effective solutions, which meet or exceed these requirements are encouraged. Further, the OFFEROR is encouraged to seek solutions that will expedite construction (panelization, pre-engineered, etc.) and shorten the schedule. The intent of the Government is to emphasize the placement of funds into functional/operational requirements. Materials and methods should reflect this by choosing the lowest Type of Construction allowed by code for this occupancy/project allowing the funding to be reflected in the quality of interior/exterior finishes and systems selected.

1.1. SECTION ORGANIZATION

This Section is organized under 6 major “paragraphs”.

(1) Paragraph 1 is intended to define the project objectives and to provide a comparison between the military facility(ies) and comparable “civilian” type buildings.

(2) Paragraph 2 describes the scope of the project.

(3) Paragraph 3 provides the functional, operational and facility specific design criteria for the specific facility type(s) included in this contract or task order.

(4) Paragraph 4 lists applicable industry and government design criteria, generally applicable to all facility types, unless otherwise indicated in the Section. It is not intended to be all-inclusive. Other industry and government standards may also be used, where necessary to produce professional designs, unless they conflict with those listed.

(5) Paragraph 5 contains Army Standard Design Criteria, generally applicable to all facility types, unless otherwise indicated in the Section.

(6) Paragraph 6 contains installation and project specific criteria supplementing the other 5 paragraphs.

2.0 SCOPE

2.1. GENERAL

The goal of this project is to renovate Buildings 915 & 916 to meet AIT dormitory standards. These facilities are three-story structures and house single trainee soldiers in addition to company administrative, training and command operations.

The Design-Build (D-B) Contractor shall provide all labor, equipment, and materials to design and construct the renovation. The project specifications shall be prepared by the Designer of Record using current USACE Guide Specifications. The following link will take you through the Construction Criteria Base (CCB) to those guides. No CCB membership is required to access the guidelines. http://www.wbdg.org/ccb/browse_org.php?o=70 .

If a UFGS or SWF guide specification cannot be found, contact the Contracting Officer’s Representative (COR) for a determination if a guide specification exists. If a guide specification does not exist the DB Contractor will prepare a job-specific specification. The UFGS shall be edited and adapted by the designer for this project, incorporating UFGS instructions and recommendations in the notes to specifier contained in the guide specifications. The designer shall delete inapplicable portions of the guide specification and revise and/or supplement, as required, the applicable portions to provide a complete project specification.

The floor plans provided in Appendix J – Drawings indicate functional and operational arrangements that meet user operability requirements.

2.2 NOT USED

2.3. SITE:

Provide all site improvements necessary to support the building renovation. Refer to Paragraph 6 for site specific requirements. Antiterrorism/Force Protection measures shall also be included in the facility design in accordance with applicable criteria. The Contractor shall be responsible for all repairs to existing sidewalks, pavements, curb and gutter, utilities, and/or landscaping damaged as a result of his construction activities.

Refer to site layout in Appendix J - Drawings for the limits of construction.

2.4. GOVERNMENT-FURNISHED GOVERNMENT-INSTALLED EQUIPMENT (GFGI)

Coordinate with Government on GFGI item requirements and provide suitable structural support, brackets for <am#5>projectors/VCRs/</am#5>TVs, all utility connections and space with required clearances for all GFGI items. All <am#5>, Computers and related hardware, copiers, faxes, printers, video projectors, VCRs CCTV’s </am#5>and TVs are GFGI.

The following are also GFGI items: <am#5> Ice Machine, </am#5> Furniture <am#5> and Electronic Security System (ESS). Ice machines are not required.</am#5>

2.5. FURNITURE REQUIREMENTS

The procurement and installation of furniture is NOT included in this contract. Furniture will be provided and installed under a separate furniture vendor/installer contract. The general contractor shall accommodate that effort with allowance for entry of the furniture vendor/installer onto this project site at the appropriate time to permit completion of the furniture installation for a complete and usable facility to coincide with the Beneficial Occupancy Date (BOD) of this project. <am#5> The furniture vendor/installer contract will include all electrical pre-wiring and the whips for final connection to the building electrical systems however; the general contractor shall make the final connections to the building electrical systems under this contract. Furthermore, the general contractor shall provide all Information/Technology (IT) wiring (i.e.

LAN, phone, etc.) up to and including the face plate of all freestanding and/or systems furniture desk tops as applicable, the services to install the cable and face plates in the furniture, the coordination with the furniture vendor/installer to accomplish the installation at the appropriate time, and all the final IT connections to the building systems under this contract. </am#5> http://www.wbdg.org/ccb/browse_org.php?o=70

3.0 FUNCTIONAL AND OPERATIONAL REQUIREMENTS

3.1. GENERAL REQUIREMENTS

Advanced Individual Training (AIT) complexes are required by the Army to encompass living, dining, training, and administrative/command operations. This AIT project will be comprised of renovating Barracks 915 & 916.

Adjacent facilities will remain in operation throughout construction.

Barracks 915 & 916 are comprised of sleeping units, toilets, multipurpose space, storage, laundry area, day rooms, and company operations components.

3.2. FUNCTIONAL AND AREA REQUIREMENTS

Gross building area shall be calculated in accordance with Appendix Q. Net area is measured to the inside face of the room or space walls. Minimum dimension where stated shall be measured to the inside face of the defining enclosure. Net area requirements for programmed spaces are included in this paragraph. If net area requirements are not specified, the space shall be sized to accommodate the required function and to comply with code requirements, overall gross area limitations, and any other requirement of this RFP. Area requirements for corridors, stairs, and mechanical rooms will typically be left to the discretion of the offeror.

Previous submittal floor plans and as-builts have been provided as reference only. New floor plans shall be prepared and submitted for evaluation in response to this RFP since requirements may have changed.

3.2.1. AITB Functional Space Requirements

3.2.1.1. Sleeping Units

(a) Bedroom: Each sleeping unit shall have two bedroom areas. Bedrooms must be of equal size and able to accommodate scheduled GFGI furniture with adequate circulation. Provide one full length wall mirror (16 to 24 inches by 72 inches). Mount full length wall mirror at the end of plumbing chase in each sleeping unit. Provide a ceiling fan for each sleeping <am#5> unit area</am#5>.

(b) Bathroom: Each sleeping unit shall have one bathroom with water closet and shower. Extend ceramic tile shower surround to ceiling. Provide tamper resistant showerhead with an elevation of 6’-6” <am#5> and two towel bars</am#5>.

(c) Entry: Each sleeping unit entry area shall have <am#5> three lockable built-in closets and</am#5> a lavatory with a solid surface vanity countertop. Each vanity shall have storage cabinets below, recessed mirrored medicine cabinet, light, and a towel bar. Locate vanity immediately outside of bathroom.

(d) Utility Closet: Provide one utility closet per sleeping unit to house the HVAC fan cooling/heating unit.

Utility closet shall be accessed from the corridor only. <am#5> All utility closest shall be keyed to the FSH mechanical keying system. Hardware does not need to connect to the new ESS. All utility closets will be provided with light and a convenience 125V power outlet.

(e) Data Drops: There will be 9 dual data drops on the first floor. The first four Living Units in the north wing (adjacent to the Laundry and CQ Station) will have two dual drops per room, and the last dual drop will be in a room identified by the User. In the future the four living spaces will be converted to Admin rooms. The details for the drop lines will be confirmed during the design after award process.</am#5>

3.2.1.2. Common Areas

(a) Stair: Stairs are existing; renovate as required <am#5> to comply with applicable codes. DB contractor shall be responsible for repairing all noticeable damage and ensuring stairs to comply with FSH and industry standards. </am#5>

(b) Corridors: <am#5>Some Corridor walls may be are</am#5> load-bearing and will require headers in any new opening.

(c) Charge of Quarters (CQ) Station: Provide a reception station located in the vestibule of the lobby with a minimum area of 50 net square feet. A small desk and chair will be provided GFGI in lieu of a built-in station. CQ Station provides visual control of building circulation. <am#5> Any door or partition leading to the CQ Station shall be fully glazed to allow for continuous visual monitoring. </am#5>

(d) Day Room: There are two day rooms on each floor. Day room functions as a soldier’s lounge and includes a TV, sofa, and lounge chairs (GFGI). Locate a vending area on first floor to accommodate two full size vending machines. Provide power receptacles for vending machines. <am#5> All day rooms will have two quad voice/data drops in each room, totaling sixteen drops for each floor for the day rooms. One of the drops will be a dedicated voice for the Sexual Harassment Line. The details for the drops will be confirmed during the design after award process. One of the Day Rooms will also serve as a Training/Classroom/Computer Learning Center area and shall be equipped with a GFGI TV, computer hook-ups, and ceiling mounted VCR.

Contracting Officer will instruct as to which Day Room will be assigned as such. </am#5>

(f) <am#5> Luggage Storage: Provide lockable storage for luggage with a minimum of six 24 inch deep storage shelves, spaced at 24 inches on center vertically and capable of supporting a minimum of 30 pounds per linear foot. Total linear footage of storage shelves shall be three times the perimeter of the storage room.

(g) General Storage: Provide a lockable multipurpose storage room on the second and third floors.

(h) </am#5> Janitor: Provide one janitor’s closet per<am#5> upper floor inside adjacent to</am#5> the Laundry Area. Each janitor’s closet shall have a 10 inch deep floor mounted stainless steel mop sink, with hot and cold service faucet, a four holder mop rack and two 18 inch deep by 48 inch long heavy duty stainless steel shelves for storage of cleaning supplies. Each janitor’s closet shall have space for storage of buckets and vacuum. Janitor closets are to be keyed individually<am#5> and shall be compatible with the New ESS.

(ig) </am#5 Mechanical, Electrical<am#5>, and Telecommunications</am#5> Rooms: Mechanical rooms shall accommodate space for equipment maintenance/repair access without having to remove other equipment.

Mechanical, electrical <am#5> and telecommunications</am#5> rooms shall be keyed separately for access by Installation maintenance personnel. Filter changes and preventative maintenance shall be performed without requiring access to the bedrooms. First floor exterior access is required for centralized mechanical room. <am#5> If required to accommodate mechanical equipment or service access, contractor shall provide an addition to enlarge the existing mechanical rooms. Provide an engineered foundation permanently attached to the existing foundation. Match the exterior wall and roof finish and provide keyed exterior door. Provide code required ventilation and conditioning.

(h) Fire Pump Room: If fire pump is required, provide a Fire Pump Room addition adjacent to the Mechanical Room. Provide an engineered foundation permanently attached to the existing foundation.

Match the exterior wall and roof finish and provide keyed exterior door. Provide code required ventilation and conditioning.

(j) Telecommunications Rooms (TR): </am#5>All telecommunications rooms shall be conditioned space.

Telecommunications room will be provided in accordance with the latest Installation Information Infrastructure Architecture (I3A) guidance. <am#5>Provide one Telecommuncations room per building on the first floor. </am#5> Telecommunications room provides a demarcation point between the outside plant cable and the building telecommunications cabling. Refer to paragraphs 3.7 MECHANICAL REQUIREMENTS and 3.8 ELECTRICAL AND TELECOMMUNICATIONS REQUIREMENTS for additional information. <am#5> All telecommunications rooms shall be provided with a network cipher lock that meets the FSH NEC requirements. Only Government owned and maintained equipment will be allowed in the TR’s. </am#5>

3.2.1.3. Space Allocation

B/COF MINIMUM SQUARE FOOTAGE REQUIREMENTS (Totals per building)

NET SQUARE FEET (NSF)

1ST

FLOOR

2ND

3RD

TOTAL

SLEEPING UNIT –MAXIMUM NUMBER OF SLEEPING UNITS AS ALLOWED BY EXISTING

BUILDING FOOTPRINT (ESTIMATE – 47 UNITS PER BLDG.)

BEDROOM

10,152

BATHROOM

1,457

B/COF MINIMUM SQUARE FOOTAGE REQUIREMENTS

NET SQUARE FEET (NSF)

1ST

2ND

3RD

TOTAL

ENTRY

AS

NEEDED

UTILITY CLOSET

COMMON AREA

LOBBY AND VESTIBULES

AS NEEDED – MINIMUM 6’-0” WIDE

STAIR

AS NEEDED – Existing, renovate as required.

CORRIDORS AND VESTIBULES

AS NEEDED - MINIMUM 3’-6” WIDE

CQ STATION

DAY ROOM WITH STORAGE

LAUNDRY 1 PER FLOOR

Existing, renovate as required.

GENERAL STORAGE

JANITOR 1 PER FLOOR

AS NEEDED

MECHANICAL,

TELECOMMUNICATIONS AND

ELECTRICAL

AS NEEDED

3.3. SITE REQUIREMENTS

Refer to paragraphs 6.3 and 6.4 for site requirements.

3.4. ARCHITECTURAL REQUIREMENTS

3.4.1. Accessibility Requirements

Able-bodied soldiers occupy and manage the AITB facilities. The Americans with Disabilities Act requirements do not apply to the AITB except that an ADA compliant access to the first floor main entry and up to the CQ Station is required.

3.4.2. Hardware

Finish Hardware: <am#5> PUnless otherwise noted, p</am#5>rovide hardware<am#5> as needed</am#5> in accordance with the provisions of Appendix C of this document. All hardware shall be consistent and shall conform to ANSI/BMHA standards for Grade 1. All requirements for hardware keying shall be coordinated with the Contracting Officer. Hardware finish shall conform to ANSI/BHMA A156 18; coordinate finish with the 502d CES. Extension of the existing installation keying system shall be provided. Locksets shall have interchangeable cores. Cores shall have no fewer than seven pins. Locksets for mechanical, electrical, elevators and the like shall be keyed to the existing installation Master Keying System (U-keyway). All telecommunications rooms shall have network cipher lock conforming to 502d CES Telecommunication Room lock requirements. Deadbolt locks shall be installed on mechanical, <am#5> and electrical and telecommunications </am#5> rooms keyed to the Installation keying system. Disassembly of knob or lockset shall not be required to remove core from lockset <am#5> with the exception of U-Keyway system<am#5>. All locksets and exit devices shall accept same interchangeable cores. Plastic cores are unacceptable. Door hardware and security requirements must be coordinated with the functional requirements, the room-by-room criteria, and the electrical security/fire alarm system requirements of this document. Provide all hardware necessary to meet the requirements of applicable codes for fire doors and exit doors. Provide closers for all doors opening to corridors and as required by codes.

3.4.3. Special Acoustical Requirements

3.4.3.1. Exterior walls and roof/floor/ceiling assemblies, doors, windows and interior partitions shall be designed to provide for attenuation of external noise sources such as airfields in accordance with applicable criteria.

Provide sound insulation to meet a minimum rating of STC 42 at walls and floor/ceiling assemblies. At interior doors provide solid core wood doors in metal frame with sound insulation to meet a minimum rating of STC 33.

Provide sound insulation to meet a minimum rating of STC 50/IIC 55 at floors separating sleeping spaces.

3.4.3.2. Sound conditions and levels for interior spaces, due to the operation of mechanical and electrical systems and devices, shall not exceed levels as recommended by ASHRAE handbook criteria. Provide acoustical treatment for drain lines and other utilities to prevent noise transmission into the interior of sleeping units.

3.4.4. Exterior Design Objectives

3.4.4.1. Exterior Walls: Provide durable materials. Prior to any renovation work and after all demolition work is done, power-wash and thoroughly clean all remaining exposed surfaces as required to accept new finishes.

3.4.4.2. Roof System: Minimum roof slope for membrane roof systems shall be 1/4 inch per foot. Membrane roof systems shall be fully adhered. Roof system shall be Underwriters Laboratory (UL 580 Class 90) rated or Factory Mutual Global (FM) I-90 rated. Roof system shall comply with applicable criteria for fire rating. No other roofing type shall be accepted, reference to such other roof types in this RFP SHALL be disregarded.

(a) Roof Mounted Equipment: For roof mounted equipment, provide permanent access walkways and platforms to protect roof. Roof mounted equipment on membrane roof systems shall be completely screened by metal screening systems. <am#5> Provide a weatherproof hose bib and convenience 125V outlet next to roof mounted equipment for maintenance purposes. </am#5>

(b) Roof access from building exterior is existing.

3.4.4.3. Trim and Flashing: Gutters, downspouts, and fascias shall be factory pre-finished metal and shall comply with SMACNA Architectural Sheet Metal Manual.

3.4.4.4. Bird Habitat Mitigation: The Contractor shall provide details in the design necessary to eliminate the congregating and nesting of birds in the facility.

3.4.4.5. Exterior Doors and Frames:

(a) Main Entrance Doors: Aluminum storefront doors and frames with Architectural Class 1 anodized finish, fully glazed, with medium or wide stile for entry into lobbies or corridors. Provide doors complete with frames, framing members, subframes, transoms, sidelights, trim, applied muntins, and accessories. Framing systems shall have thermal-break design. Storefront systems shall comply with wind-load requirements of applicable codes and criteria and shall comply with the requirements of UFC 4-010-01. Contractor shall make all necessary adjustments to existing structure and components to comply with this requirement.

(b) Exterior Non-entrance Doors: Exterior doors and frames opening to spaces other than corridors or lobbies shall be galvanized insulated hollow metal and comply with ANSI A250.8/SDI 100. Doors shall be heavy duty (grade 2) insulated with 18-gage steel cladding; top edge closed flush; A60 galvannealed. Frames shall be 12-gauge, with continuously welded mitered corners and seamless face joints. Doors and frames shall be constructed of hot dipped zinc coated steel sheet, complying with ASTM A653, Commercial Steel, Type B, minimum A40 coating weight; factory primed. Fire-rated openings shall comply with applicable codes, and the requirements of the labeling authority. Door and frame installation shall comply with applicable codes and criteria including UFC 4-010-01. Contractor shall make all necessary adjustments to existing structure and components to comply with this requirement.

3.4.4.6. Exterior Windows: Provide insulated, high efficiency window systems, with thermally broken frames complying with applicable codes and criteria including UFC 4-010-01. Curtain wall systems shall be capable of withstanding area wind loads, thermal and structural movement required by location and project requirements, and shall comply with applicable codes and criteria including UFC 4-010-01. Contractor shall make all necessary adjustments to existing structure and components to comply with this requirement.

3.4.4.7. Exterior Louvers: Exterior louvers shall have bird screens and shall be designed to exclude wind-driven rain. Exterior louvers shall be made to withstand wind loads in accordance with the applicable codes. Wall louvers shall bear the Air Movement & Control Association (AMCA) International certified ratings program seal for air performance and water penetration in accordance with AMCA 500-D and AMCA 511. Louver finish shall be factory applied.

3.4.5. Building Interior

Maximize use of daylighting. Provide durable interior surfaces that are easily maintained and replaced, easy to clean, light in color, and with a residential ambience.

3.4.5.1. Signage: At each sleeping unit, provide two room number and changeable two-line message strip signs, one on each side of entry door. Changeable message strip signs shall be of same construction as standard room signs to include a clear sleeve that will accept a paper or plastic insert with identifying changeable text. The insert shall be prepared typeset message photographically enlarged to size and mounted on paper card stock. <am#5> All signage shall be in accordance with UFC 3-120-01 Design: Sign Standards. </am#5>

3.4.5.2. Bulletin Boards: Provide one centrally located bulletin board per floor. Each bulletin board shall be 4 feet high and 6 feet wide and shall have a header panel and lockable, glazed doors. Coordinate colors with Contracting Officer.

3.4.5.3. Corner Guards: Provide surface mounted, high impact resistant, integral color, snap-on type resilient corner guards, extending from floor to ceiling for wall and column outside corners in high traffic areas. Factory fabricated end closure caps shall be furnished for top and bottom of surface mounted corner guards.

3.4.5.4. Chair Rail: Chair rails shall be installed in areas prone to hi-impact use, such as <am#5> corridors, </am#5> day rooms, and lobby seating areas. <am#5> Chair rails are not required on CMU walls, regardless of the space. </am#5>

3.4.5.5. Casework: Provide cabinets complying with Architectural Woodwork Institute Quality Standards<am#5> “Custom Grade” </am#5> for custom cabinetry. Countertops shall have waterfall front edge and integral coved backsplash.

3.4.5.6. Window Treatment: Provide horizontal mini blinds at all exterior windows. Uniformity of window covering color and material shall be maintained to the maximum extent possible throughout each building.

3.4.5.7. Toilet Accessories: Furnish and install the items listed below and all other toilet accessories necessary for a complete and usable facility. All toilet accessories shall be Type 304 stainless steel with satin finish.

Sleeping Unit Bathroom: Accessories shall include the following items.

1. Two heavy duty towel bars – minimum 24 inches wide each. Provide blocking in walls as necessary to support towel bars.

2. Mirrored medicine cabinet

3. Soap dish – in shower, built-in

4. Combination soap dish/toothbrush holder – at each lavatory

5. Double robe hook - on inside of bathroom door

6. Toilet paper holder

7. Shower curtain rod - extra heavy duty

8. Shower curtain – white anti-bacterial nylon/vinyl fabric shower curtain

3.4.5.8. Fire Extinguisher Cabinets and Fire Extinguisher Mounting Brackets: Furnish and install fire extinguisher cabinets <am#5> fire extinguisher M m</am#5>ounting brackets as required by applicable codes and criteria. Furnish a list of installed fire extinguisher cabinets and mounting brackets (including location, size and type) to the Contracting Office Representative. <am#5> Coordinate cabinet/bracket size and type with base Fire Marshal so that they are compatible with size and type of GFGI extinguisher being supplied. </am#5>

3.4.6. Finishes

3.4.6.1. Paint

(a) All paints used shall be listed on the "Approved Product List" of the Master Painters Institute (MPI).

Application criteria shall be as recommended by MPI guide specifications for the substrate to be painted and the environmental conditions existing at the project site.

(b) Exterior surfaces, except factory pre-finished material or exterior surfaces receiving other finishes shall be painted a minimum of one prime coat and two finish coats. Paints having a lead content over 0.06 percent by weight of nonvolatile content are unacceptable. Paints containing zinc-chromate, strontium-chromate, mercury or mercury compounds, confirmed or suspected human carcinogens shall not be used on this project. Exterior paints and coating products shall be classified as containing low volatile organic compounds (VOCs) in accordance with MPI criteria. Application criteria shall be as recommended by MPI guide specifications. Provide an MPI Gloss Level 5 Finish (semi-gloss), unless otherwise specified.

(c) Interior surfaces, except factory pre-finished material or interior surfaces receiving other finishes, shall be painted a minimum of one prime coat and two finish coats. Paints having a lead content over 0.06 percent by weight of nonvolatile content are unacceptable. Paints containing zinc-chromate, strontium-chromate, mercury or mercury compounds, confirmed or suspected human carcinogens shall not be used on this project. Interior paints and coating products shall contain a maximum level of 150 grams per liter (g/l) of VOCs for non-flat coatings and 50 g/l of VOCs for flat coatings. Provide an MPI Gloss Level 5 Finish (semi-gloss) in wet areas and a flat finish in all other areas.

3.4.6.2. Minimum Interior Finishes-General

(a) Designers are not limited to finishes listed in the following INTERIOR FINISHES table(s) and are encouraged to offer higher quality finishes.

(b) Wall, ceiling and floor finishes shall conform to the requirements of the IBC, NFPA and UFC 3-600-01 Fire Protection Engineering for Facilities. Where code requirements conflict, the most stringent code requirement shall apply.

(c) Carpet shall not be used as a floor finish in the AIT.

(d) All walls shall be painted gypsum board, except where stated otherwise. Use impact resistant gypsum board in vestibules, classrooms, day rooms, corridors, stairs, laundry, vending areas and storage areas.

(e) Acoustical Tile Ceilings (ATC) are acceptable in public areas like day rooms, corridors and lobbies. Sleeping room units shall have “hard” gypsum board ceilings attached to existing floor or roof structure above.

(f) Use mold resistant products to the extent possible and use mold prevention strategies in areas prone to mold production like restrooms and shower rooms.

3.4.6.3. AIT Interior Finishes the following table is offered as a guide, some areas listed may not be part of the Scope of Work for this project.

3.5. STRUCTURAL REQUIREMENTS

Design and construct as a complete system in accordance with APPLICABLE CRITERIA.

3.5.1.Live Loads: Design live loads shall be per the IBC but not lower than the following minimums.

(a) Elevated slabs 60 pound per square foot (psf)

(b) Slab on grade 150 psf

(c) Centralized laundry area 150 psf, but not less than actual equipment loads.

3.6. ENERGY CONSERVATION REQUIREMENTS

3.6.1. The building, including the building envelope, HVAC systems, service water heating, power, and lighting systems shall be designed to achieve an energy consumption that is at least <am#5> 30%20%</am#5> below the consumption of a baseline building meeting the minimum requirements of ANSI/ASHRAE/IESNA Standard 90.1-2010. (see paragraph 5.9 Energy Conservation). <am#5> The building shall meet the requirements of ASHARE Standard 189.1 2011 with only exception being the renewable energy components of Section 7 ( Par 7.3.2 and 7.4.1.1). ASHRAE 189.1 is a comprehensive standard that covers building features beyond energy efficiency such as sustainability, water use efficiency, and indoor air quality. </am#5>Document compliance with the above energy performance utilizing the methodology described in ASHRAE 90.1, Appendix G as discussed in section 01 33 16 Design After Award. (see paragraph 5.9 Energy Conservation. Gas fired boilers and water heaters shall be minimum 90% efficient at operating conditions

3.6.5. Load and Set Point Schedules

The following facility schedules must be used in all facility energy simulations for purposes of documenting compliance with energy performance requirement. The peak values for indicated for each schedule shall be used for the baseline energy calculation. The hourly peak fraction values for various load components for each schedule shall be used for both the baseline and proposed design energy calculations.

AIT B/COF Common Area Internal Load Schedules

Hr Occupancy Lighting Washer/Dryer Use Washer SHW

Wk Sat Sun Wk Sat Sun Wk Sat Sun Wk Sat Sun 1-6 0.00 0.00 0.00 0.30 0.30 0.30 0.00 0.00 0.00 0.00 0.00 0.00 7-10 0.20 0.20 0.20 0.30 0.30 0.30 0.00 0.00 0.00 0.00 0.00 0.00

Hr Occupancy Lighting Washer/Dryer Use Washer SHW 11-18 0.00 0.00 0.00 0.30 0.30 0.30 0.00 0.00 0.00 0.00 0.00 0.00

19 0.00 0.00 0.00 0.80 0.80 0.80 0.00 0.00 0.00 0.00 0.00 0.00 20-21 0.20 0.20 0.20 0.80 0.80 0.80 0.50 0.50 0.50 0.50 0.50 0.50 22-23 0.40 0.40 0.40 0.80 0.80 0.80 1.00 1.00 1.00 1.00 1.00 1.00

24 0.20 0.20 0.20 0.80 0.80 0.80 0.50 0.50 0.50 0.50 0.50 0.50

Peak 5 occ/floor 1.0 W/ft2 (10.8 W/m2) 8.4 kW/floor 53.3 gal/hr/flr (202 L/hr/flr)

AIT B/COF Apartment Unit Internal Load Schedules

Hr Occupancy Lighting Plug Loads Service Hot Water

1-5 0.80 0.75 0.75 0.20 0.20 0.20 0.20 0.20 0.20 0.00 0.00 0.00 6 0.70 0.65 0.75 0.40 0.30 0.20 0.20 0.20 0.20 0.10 0.10 0.10 7 0.60 0.60 0.70 0.70 0.50 0.30 0.40 0.35 0.20 0.40 0.40 0.40 8 0.50 0.50 1.00 0.50 0.50 0.50 0.40 0.40 0.40 0.20 0.20 0.20 9 0.25 0.25 0.00 0.20 0.20 0.20 0.30 0.40 0.40 0.00 0.00 0.00

10-17 0.20 0.20 0.20 0.20 0.20 0.20 0.30 0.30 0.30 0.00 0.00 0.00 18 0.30 0.30 0.30 0.50 0.50 0.50 0.50 0.50 0.50 0.10 0.10 0.10 19 0.50 0.30 0.30 0.70 0.70 0.70 0.50 0.50 0.50 0.10 0.10 0.10 20 0.50 0.50 0.50 0.70 0.70 0.70 0.60 0.50 0.50 0.10 0.10 0.10 21 0.70 0.50 0.50 0.70 0.70 0.70 0.60 0.50 0.50 0.00 0.00 0.00 22 0.70 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.00 0.00 0.00 23 0.80 0.75 0.75 0.40 0.40 0.40 0.40 0.50 0.50 0.00 0.00 0.00 24 0.80 0.75 0.75 0.20 0.20 0.20 0.20 0.20 0.20 0.00 0.00 0.00 Peak 2 occ/unit 1.1 W/ft2 (10.8 W/m2) 1.7 W/ft2 (18 W/m2) 40 gal/hr (114 L/hr)

AIT B/COF Apartment Unit Thermostat Set-Point Schedules

Hr Heating ( F) Heating ( C) Cooling ( F) Cooling ( C)

1-24 68 68 68 20 20 20 75 75 75 24 24 24

AIT B/COF Unoccupied Zones (ie stairwells, mechanical rooms) Thermostat Set-Point Schedules

Hr Heating ( F) Heating ( C) Wk Sat Sun Wk Sat Sun

1-24 55 55 55 12.8 12.8 12.8

3.7. MECHANICAL REQUIREMENTS

3.7.1. Plumbing

3.7.1.1. Domestic water heating system. .

3.7.1.2. Domestic hot water pipe sizing shall be based on all showers flowing simultaneously at a rate of

2.0 gpm per shower. Waste stacks, and building waste drains, shall be sized with consideration to the increased flow rates as well. Shower heads and lavatory faucets shall be water conserving type with a maximum flow rate not to exceed 2.0 gpm. Size the domestic water heating system based on 20 gallons of 110 deg F hot water consumption per occupant during morning peak period. Peak period duration shall be 30 minutes (10 minute duration for shower and lavatory use per occupant per dwelling unit plus a 10 minute transition period). Base hot water storage capacity on 75% usable storage and a storage temperature of 140 deg F. Domestic hot-water distribution shall be at 120 deg F from a central mixing valve. Design domestic hot water distribution piping to manage up to 180 deg F water.

3.7.1.3 Solid Interceptor

Centralized laundry facilities shall be considered commercial laundries with respect to the IPC and shall be provided with solids interceptor in accordance with the IPC.

3.7.1.4 Plumbing Fixtures:

Laundry:

Provide water and drain connections for all washers. Supply 140 deg F water to laundry room for washing machines.

Bathroom Fixtures (Dwelling Unit):

(1) Water Closet: Furnish and install an elongated floor mounted flush tank type vitreous china water closet.

(2) Shower Head: Shall be of porcelain enameled cast-iron or enameled steel. Spray end of shower head shall be set at 78 inches above finish height of shower drain

3.7.2. Heating, Ventilating and Air-Conditioning (HVAC)

3.7.2.1. All sleeping unit HVAC units shall be located in utility closets accessible only through a corridor access door. Utility closet doors shall be sized for ease of service and maintenance of HVAC units. Access for maintenance shall not require entry into the sleeping unit. Air filters shall be located in duct mounted filter boxes within the utility closet. Provide hub drain in fan closet for condensate removal.

3.7.2.2. Each sleeping unit shall be positively ventilated using dedicated outdoor air units. Dedicated outdoor air units (DOAUs) shall continuously supply dehumidified, tempered air ducted directly to each sleeping unit or mechanical closet from DOAU. Supply air conditions from DOAU shall be between 68 and 75 degree F dry bulb and no greater than 48 degree F dew point. Supply quantity shall be 40 cfm per sleeping unit. Sleeping unit exhaust shall be 25 cfm continuous through a bathroom exhaust. (Note: This exceeds ASHRAE 62.1 but provides compliance with IMC chapter 4 and maintains slight building positive pressurization with respect to dwelling unit exhaust rate of 25 cfm). DOAU unit shall be direct expansion (DX) type and cooling/dehumidification shall be available 24/7/365. Refer to chapter 6 for site specific constraints. The number of exhaust fans and DOAUs shall be the same, and exhaust fans and DOAUs shall be arranged for and shall include exhaust air energy recovery. Exhaust and DOAU systems shall be provided with variable frequency drives (VFDs) and shall be provided with a control logic that provides reduced ventilation rates during periods of low interior humidity and still meet minimum ASHRAE 62.1 requirements.

3.7.2.3. AIT Barrack’s corridors shall be ventilated per ASHRAE 62.1 by supply from the dedicated outdoor air unit(s).

3.7.2.4. Sleeping unit room temperature control shall be through the direct digital control (DDC) system. Each sleeping unit shall have a heating/cooling unit. Occupant control will include on/off fan selection and an occupant temperature setpoint adjustment mechanism that allows +/- 2 degrees F of adjustment from the DDC programmed set points of 70 degrees F heating and 75 degrees F cooling. Additionally the DDC controls shall monitor each sleeping unit for sub-cooling. The DDC system shall record an alarm event if the space temperature drops below 71 degrees F (adjustable) when the outside air is greater than 85 degrees F (adjustable). DDC system shall record an alarm event if the space temperature drops below freezing during the winter months. Occupant control shall also include ability to select heating or cooling mode. HVAC system shall be able to provide for year round heating or cooling in individual sleeping units as selected by the occupants.

3.7.3. Fire Protection

Fire suppression systems shall be designed in accordance with the latest edition of UFC 3-600-01. However, the AITB shall be classified as mission essential and shall be provided with sprinkler protection regardless of other criteria or code provisions.