US Army Corps of Engineers
BUILDING STRONG®
Ft Bliss Replacement Hospital Pre-proposal Conference
Fort Bliss Hospital Replacement Project
PRINCIPALS MEETING
August 28, 2012
Contracting Officer: John Rodgers
Contracting Specialist: Ashley Morgan
Construction Manager: Michael Vonasek, PE
Senior Project Manager: Jeffrey Allen
Agenda
Introduction Source Selection/Award Project Delivery Team Project Description Schedule Incremental Funding Construction Update Site Tour
INTRODUCTION
Contract Specialist is your main point of contact for the duration of this solicitation
Any contractual actions will come from Contract Specialist or Contracting Officer
STANDARD FORM 1442
Proposals due September 25, 2012 If changed it will be by an amendment on SF 30 (posted to FBO) IAW FAR 52.228-1 - Offer Guarantee is required ($3M or 20% of the bid price whichever is less) The performance period is 1,277 calendar days after Notice to
Proceed Work will not begin until a Signed NTP is received from the
Contracting Officer Offerors providing less than 90 150 (Am 0002) calendar days for
Government acceptance after the date offers are due may be rejected
SECTION 00 21 00, INSTRUCTION,
CONDITIONS AND NOTICES TO OFFERORS
All copies, amendments, and any other necessary correspondence will be available by Internet only using the Federal Business Opportunity Website at FBO.gov.
Questions and comments will be through Projnet at projnet.org.
Register to get access to submit and view bidder inquiry items.
Use the bidder inquiry key to locate this solicitation. The Bidder Inquiry
Key is: JWGMZB-5BF64O.
The bidder Inquiry system will be unavailable for new inquiries 15 Calendar days (COB Sept 10, 2012) prior to proposal submission in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation if necessary.
General Proposal Format lays out exactly how to organize and submit your proposal
SECTION 00 21 00, CONTINUED
If you choose to hand deliver your proposal please DO NOT loiter on the 2nd Floor hallways and in the reception room after you have delivered your proposal.
Specific Instructions for Joint Ventures (i.e. all members shall sign the SF 1442 and bid bond or provide written agreement designating one firm authority to bind the other member of the JV, and provide copy of JV agreement).
All Large Businesses are required to submit a subcontracting plan. This outlines your planned subcontracting goals for the duration of the project.
That is a different submission from Factor 5 (small business participation) but the two must be consistent.
The CLIN Schedule shall be completed. All costs for work not specifically mentioned in the CLIN Schedule shall be included in the contract prices for the items listed.
SECTION 00 21 11
DESIGN-BID-BUILD SELECTION PROCEDURES
Firm Fixed Price Contract solicited competitively through an unrestricted solicitation process. This Design-Bid-Build contract is the vertical construction phase of the Ft Bliss Replacement Hospital project that will ultimately replace William Beaumont Army Medical Center. Fully Designed.
Proposal shall be complete and specific in every detail and describe your capabilities to satisfactorily perform the contract.
DBB TRADE-OFF PROCESS
Allows Tradeoffs among cost or price and non-cost factors, which allows the Government to accept other than the lowest priced proposal
Source Selection Evaluation Board reviews, evaluates and rates the proposals against the source selection criteria in the RFP
The proposal that offers the Best Value and is fair and reasonable will be selected as determined by the Source Selection Authority
All factors other than price, when combined, are significantly more important than price
Government intends to award WITHOUT discussions but if discussions are necessary, it will set a competitive range and conduct discussions
VOLUME I, TECHNICAL PROPOSAL
Evaluation Factors Location Factor Description Relative Importance
TAB A Factor 1 Past Performance Most important
TAB B Factor 2 Prime Contractor Key Personnel Equal to factor 3
TAB C Factor 3 Organization & Technical Approach
Equal to factor 2
TAB D Factor 4 Proposed Schedule Less important than either factor 2 or 3
TAB E Factor 5 Small Business Participation Less important than factor 4
EVALUATION FACTORS
Factor 1 – Past Performance ► Rated on Relevancy and Confidence ► Projects will be considered relevant to this procurement If they are similar in complexity in type, scope and magnitude ► The confidence rating will be established based on the past performance of the firms Factor 2 – Prime Contractor Key Personnel
► The offeror shall provide names and resumes for key construction personnel for Project Manager, Construction Project Superintendent, Contractor Quality Control System Manager, Site Safety and Health Officer, LEED Project Manager, and Designated Scheduler.
► The SSEB will evaluate the credentials of each person
EVALUATION FACTORS
Factor 3 – Organizational and Technical Approach ► Offerors are to describe their risk management approach, management and technical capabilities and subcontractor involvement.
Factor 4 – Proposed Schedule
► The Government will evaluate the schedule to assess the strength of understanding, logic, reasonableness and the affect of incremental funding.
Factor 5 – Small business Participation ► All offerors (both large and small) will be evaluated on the extent of participation of small business concerns in performance of this contract opportunity.
► Total small business goal is 25% of the total contract price.
PRICE PROPOSAL, VOLUME II
SF 1442 and Contract line Item Schedule Construction Spend Curve Bid Bond Financial Information Statement of Compliance Subcontracting Plan
Government / AE HA/TMA – Health Affairs/Tricare Management Activity
HFPA – Army Health Facilities Planning Agency WBAMC – William Beaumont Army Medical Center
USACE Ft. Worth District / Ft. Bliss Medical Construction Office Ft. Bliss Garrison
AE – HDR Architecture
Contractors Infrastructure Contract – Sundt Construction, Inc.
Water Tower Contract – Jamco Ventures, LLC Parking A – VEMAC
PROJECT DELIVERY TEAM
PROJECT DESCRIPTION
Replaces William Beaumont Army Medical Center
Design-Bid-Build Execution
1.132 M Sq Ft / 135 Beds
30 Primary & Specialty Care Clinics
Supports > 2000 Hospital Staff
Designed using Evidence Based Design / World Class Principles
LEED SILVER
260 Acre Undeveloped Site
PROJECT OVERVIEW
PACKAGE Cost Range AWARD AWARD METHOD
INFRASTRUCTURE Awarded Jul-11 MATOC
WATER TOWER Awarded May-11 SB MATOC
PARKING PKG A Awarded Jul-12 LPTA
HOSPITAL >$500 M Jan-13 BEST VALUE
HELIPAD $500 – 1 M Jun-13 SMALL BUSINESS
PARKING PKG B $1 – 5 M Dec-13 SMALL BUSINESS
ACPs $10 – 25 M Dec-14 SMALL BUSINESS
LANDSCAPING $10 – 25 M Jun-15 SMALL BUSINESS
Contract Schedule*
2011 2012 2013 2014 2015 2016 2017
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Water Tower Jul 11 – Jul 12
Infrastructure Aug 11 – Aug 13
Parking A Aug 12 – Feb 14
Hospital Feb 13 – Sep 16
Helipad Jul 13 – Jun 14
Parking B Jan 14 – Mar 15
ACPs Jan 15 – Jun 16
Landscaping Jul 15 – Dec 16
Schedule
C ur re nt
Q ua rte r
Construction Duration
Awarded/Const Progress
Construction Completion
IOT Progress
IOT Completion
*Dates are subject to change.
INCREMENTAL FUNDING
The Hospital Package will be awarded per DFARS Clause
252.232-7007, Limitation of Government's Obligation
Price Proposal includes submission of S-curve (placement curve) to demonstrate scheduled placement is within funding limitations
Follow instructions in Section 00 21-00 & 01 for schedule and placement curve
COMMERCIAL
INDUSTRIAL
AIRPORT
FORT BLISS/BIGGS
AIRFIELD
RESIDENTIAL
SITE
N
Project Location
Project Location
Butterfield Trail
Interstate
Golf Course
Spur
El Paso
Secondary Entrance
ACP
Staff Parking Zone
Primary Entrance
Ft. Bliss Hospital Site
Site Access
Main Arrival Plaza
View at Outdoor Dining Court
Main Entry Lobby
View at first floor Circulation Spine
View at Outpatient Lobby Entrance
CONSTRUCTION STATUS
Infrastructure
► Awarded to Sundt Construction – 27 July 2011 ► Approx. 70% Complete
Water Tower (Small Business) ► Awarded to JAMCO Construction – 17 Jun 11 ► Project Completed Aug 2012
Parking A (Small Business) ► Awarded – 19 July 12
Conclusion
The new William Beaumont Army Medical Center will improve health care for countless military members, their families, and veterans for decades to come. Participation in this project offers the opportunity to make a contribution to this future, and directly improve the lives of our Troops. As a part of this effort your participation today is greatly appreciated.
Thank You
| Ft Bliss Replacement Hospital�Pre-proposal Conference |
| Agenda |
| INTRODUCTION |
| STANDARD FORM 1442 |
| Section 00 21 00, Instruction, Conditions and Notices to Offerors |
| SECTION 00 21 00, CONTINUED |
| SECTION 00 21 11�DESIGN-BID-BUILD SELECTION PROCEDURES |
| DBB TRADE-OFF PROCESS |
| VOLUME I, TECHNICAL PROPOSAL |
| EVALUATION FACTORS |
| EVALUATION FACTORS |
| PRICE PROPOSAL, VOLUME II |
| Slide Number 13 |
| PROJECT DESCRIPTION |
| PROJECT OVERVIEW |
| Schedule |
| INCREMENTAL FUNDING |
| Slide Number 18 |
| Slide Number 19 |
| Ft. Bliss Hospital Site |
| Site Access |
| Main Arrival Plaza |
| Slide Number 23 |
| Slide Number 24 |
| View at Outdoor Dining Court |
| Main Entry Lobby |
| View at first floor Circulation Spine |
| View at Outpatient Lobby Entrance |
| CONSTRUCTION STATUS |
| Conclusion |