The purpose of this amendment is to revise section J Attachment 3 and include Mock Project Drawings for Bldg 1184. All changes are highlighted in yellow.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to Revise Section J, Attachment 3 and include Mock Project Draw ings Bldg 1184. All changes have been highlighted in yellow .

1. CONTRACT ID CODE PAGE OF PAGES

J 1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 30-Sep-2016

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9124M-16-R-0003

X 9B. DATED (SEE ITEM 11)

10-Aug-2016

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

30-Sep-2016

CODE

MISSION & INSTALLATION CONTRACTING CMND

MICC CENTER FORT BRAGG

FORT BRAGG NC 28306

W9124M 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9124M-16-R-0003

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

The following have been modified:

ATTACHMENT 3

Attachment 3

Renovate Men’s Restroom bldg.1184

Mock JOC Project

Plumbing Scope of Work

Contractor shall remove one existing twenty gallon domestic electric water heater and install one new twenty gallon

Small-Capacity Electric Domestic Water heater A.O Smith ProMax and one 19” diameter, 3" deep, water heater drain pan. Install in same location.

Contractor shall remove two existing 20” x 18” vitreous china self-rimming drop in lavatories, and install two new

20” x 18” vitreous china self-rimming drop in lavatories, (American Standard 0491.019.020 or equivalent). New lavatories faucets shall be polished chrome, (Chicago Faucet 895-31FCABCP) deck mount 4 inch center set lavatory faucet or equivalent, to include wrist action handles with hot and cold identifiers, gooseneck spout, p-trap, drain line guard and shutoff covers, and flexible supplies.

Contractor shall remove one existing wall hung urinal, flush valve and install one each washout, wall hung vitreous china urinal, American Standard Wash brook® or equivalent and one new exposed manual urinal flush valve, 3/4"

Top Spud (Sloan Regal 186) or equivalent.

Contractor shall remove one existing tank type water closet and install new two Piece Tank Type, Pressure Assisted, Siphon Jet, Floor Mounted, Floor Outlet, and Handicap Accessible, Elongated Vitreous China Water (American

Standard Cadet Right Height™ ADA or equivalent. Include new wax ring, hold down bolts, flexible stainless steel supply line and toilet seat without lid.

HVAC Scope of Work

1. Contractor shall demo existing exhaust fan only; duct shall remain in place to be reused.

2. Contractor shall install new exhaust fan (Loren Cook Co. GEMINI 180 Series, or equivalent) of same type, size, voltage, and CFM as existing.

3. Contractor shall demo existing A/C supply diffuser; duct shall remain in place to be reused.

4. Contractor shall install new aluminum, surface mounted lay-in 24”X 24”, 3 way blow, louver face, adjustable pattern, with adjustable damper, (TITUS MCD-AA series or equivalent) A/C supply diffuser.

5. Contractor shall remove and reinstall air transfer grille.

The Contractor shall remove and replace existing ceiling tiles as necessary to facilitate.

Structural Scope of Work

The following items are to demolished: 14.5 SF of 1/4" clear mirror glass, 24” deep x 5 LF of plastic laminate countertop with backsplash and with a 4” drop down across the front, 2 EA plastic laminate end splashes, 1 EA 36" x 58" x 1", laminate plastic ADA compliant toilet partition door, 1 EA 36” x 58” x 1”, laminate plastic toilet partition panel, 1 EA 3" x 83" x 1" laminate plastic toilet partition pilaster, 1 EA 12" x 83" x 1" laminate plastic toilet partition pilaster, 1 EA surface mounted, touch less paper towel dispenser (GP enMotion 71002), 1 EA 36" length, 1-1/4" diameter, stainless steel grab bar (Bobrick B-5806x36), 1 EA 42" length, 1-1/4" diameter, stainless steel grab bar (Bobrick B-5806x42), 1 EA two roll, surface mounted, chrome plated toilet paper holder, 1 EA 1-3/4" height, 1-1/4" width, satin chrome finish, brass coat and hat hook (Ives 571). The contractor shall remove and dispose of all listed items.

Contractor shall apply 1 coat of primer and two coats of paint on all existing painted surfaces. Quantities of required painting are 352 SF of drywall and 17 LF of interior metal door frame. Protect existing wood door from paint.

Contractor shall install 5 LF of plastic laminate counter top with backsplash, and 4” plastic laminate drop down across the front. Install 2 EA plastic laminate end splashes; counter top/front drop down and end splashes will have plywood base and with a square edges, no particle board. Contractor shall field cut 2 holes for the drop in lavatories.

The Contractor shall install 14.5 SF of ¼” clear mirror glass onto the wall over the back splash. Install 1 EA surface mounted touch less paper towel dispenser (GP enMotion 71002 or equivalent at the same location old paper dispenser was removed from.

The Contractor shall install one 36” and one 42” in length 1-1/4” diameter stainless steel grab bar Bobrick B-

5806x36 and Bobrick B-5806x42.

The Contractor shall install new toilet partitions. All toilet partition items shall have heavy gauge stainless steel brackets and full-height hinge. Toilet partition will be installed from wall to wall across the bathroom in the same location of the old one that was removed. Install one 36" x 58" x 1" laminate plastic toilet partition panel, install one 3” x 83" x 1", laminate plastic toilet partition pilaster, install one 12" x 83" x 1" laminate plastic toilet partition pilaster. Install one each, two roll surface mounted chrome plated toilet paper holder. Toilet paper holder shall be commercial/institutional grade. Install on the back of the toilet partition door, one 1-3/4” height x 1-1/4” width brass coat and hat hook with a satin chrome finish, Ives 571 or equivalent.

Electrical SOW

This SOW is to be used for the electrical work at Building 1184 at Fort Stewart, Ga. It is the intent of the specifications and SOW to replace electrical items in restroom at Bldg. 1184. Any item/items not specifically listed, but normally required to conform to the intent, are to be considered part of the project. Work consists of, but is not limited to, the following:

1. Contractor shall demo existing, wall switch, GFI receptacle and light fixture in restroom.

2. Contractor shall install (1) new 2’x4” lay-in prismatic lens LED fixture in restroom. Use Lithonia #2TL4-

4,600 lumens fixture or equal. Install new light where existing fixture was removed from.

3. Contractor shall install (1) new 20 amp 120 volt, GFI receptacle. (Ivory in color) with stainless steel cover plate.

4. Contractor shall install (1) new 20 amp 120/277 volt single pole light switch.(ivory in color) with stainless steel cover plate

5. Contractor shall install check voltage and test all items after installation for proper voltage and operation.

6. Contractor shall use proper lock out/tag out procedures.

End Renovation mock project

(End of Summary of Changes)

1062640495.civ Typewritten Text Mock Project Bld 1184

1062640495.civ Typewritten Text Bathroom

1062640495.civ Typewritten Text

W9124M-16-R-0003-0005
JOC Mock Proj. 1184 BATHROOM FLOOR PLAN