Attachment F: Workload Data/ Capabilities – _____LRC DEVENS _________
ESTIMATED WORKLOADS. Fort Devens is opening a newly remodeled facility with no historical data to support is usage. The estimated headcount by month is provided in Section 8 below. These figures in no way guarantee that the Contractor will experience the same number of meals as the estimated headcount. The projected daily headcounts will be provided by the Government IAW the Fort Devens Unit Food Service Support Requests/Headcount Projections Standard Operating Procedure (SOP). The anticipated daily headcounts shall be determined by the contractor using the projected daily headcount provided by the Government.
A. DINING FACILITY, BUILDING NUMBER # 657 Full Food Service – (Design Capacity 465)
1. Operating schedule:
Weekdays per week: 5 Weekend days per week: 2
2. Meal serving hours:
Weekdays Saturday Sunday
Breakfast: 0730-0900 0730-0900 0730-0900 Lunch: 1130-1300 1130-1300: 1130-1300 Dinner: 1700-1830 1700-1830
3. Capacity:
Number of tables: 40 Number of booths: 9 Number of chairs: 172
4. Number of Headcounts Stations 2
5. Type and number of serving lines
Regular menu line 1 Both lines are configured for
Regular or short order menu
Short order line: 1
Both lines are configured for Regular or short order menu
Deli (sandwich bar) 2 Self-service lines: 2
6. Interior/exterior dining facility areas:
Floors Square Feet Type Material
Dining room 4,989
VCT Floor, GWB &
Masonry walls, Acoustical ceiling
Kitchen
2,056
Epoxy floor, Masonry walls, plaster ceiling
Storage rooms
Masonry walls, Serving area 624
Masonry walls, Self Service
VCT Floor, GWB &
Masonry walls, Acoustical ceiling
Pot & pan area 221
GWB walls, Dishwashing Room
GWB walls, Loading dock
Concrete Floor, Exterior
Office
Carpet or epoxy Floor, GWB & Masonry walls, Acoustical ceiling
Toilets/Restroom
Ceramic Tile Floor, Masonry walls, Acoustical ceiling
Foyer/Misc
VCT Floor, GWB, Glass, & Masonry walls, Acoustical ceiling
Walk in units 410 Stainless Steel
Total Square Feet 11,339
Windows Number
Exterior Windows 19
Includes windows and glass curtain walls
Storm Windows None Blinds/Curtains TBD
Exhaust hoods Number Kitchen 2 Serving area 2 Pot & pan 1 Dishwasher Room 1
7. Policing outside areas, including sidewalks and loading docks, within 50 feet of facility, and 20 feet surrounding dumpsters, are cleaned to sight; and free of trash, cigarette butts, raw/ingredients, food waste, sand, and foreign matter.
8. Estimated Monthly Headcount for FY21:
Month Estimated Headcount October 7,412 November 9,053 December 2,850 January 3,673 February 3,566 March 5,171 April 6,828 May 10,631 June 17,045 July 10,963 August 2,347 September 5,765
9. Remote site feeding with unit pick-up is required; however, historical data is not available.