W9124J-20-B-0002-0001_final I_pdp12524.pdf

PDF 1 MB Posted

Attached to
Concrete, Installation and Maintenance Construction Services National Capital Region
Solicitation number
W9124J-20-B-0002
Issued by

About this file

This is a solicitation for concrete installation, repair, and maintenance construction services in the National Capital Region. The Army Materiel Command Mission and Installation Contracting Command is seeking these services on an indefinite delivery/indefinite quantity contract with a maximum value of $43.8 million and minimum value of $1,500 per task order. The solicitation is set aside 100% for competitive 8(a) small businesses with a NAICS code of 237310 and size standard of $39.5 million. Bids are due by 1:00pm CST on April 7, 2020. Pricing will be firm fixed price determined by task orders with a minimum of $1,500 and maximums of $1.5 million for new work and $5 million for repair, alteration, or maintenance.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

The Contract Maximum Amount $43,875,796.70. The Contract Minimum Amount $1,500.00.

This is an Invitation for Bids (IFB) for a Firm Fixed Price (FFP) Indefinite Delivery/Indefinite Quantity (IDIQ) contract for Concrete Installation & Maintenance. All w ork shall be in compliance w ith Federal, State, Local, Industry regulations and standards

1. This is 100% 8(a) competitive set-aside under NAICS 237310 w ith a small business size standard of $39.5M.

2. As required by DFARS 236.204 the estimated magnitude of construction for this project is betw een $25,000,000.00 and $100,000,000.00.

3. The aw ardee of this contract w ill be required to provide a Superintendent at all times w ork is being performed on this project (see FAR clause 52.236-6). The Superintendent is considered a key position. This position SHALL NOT be subcontracted and must w ork directly for the prime contractor.

4. Bidders are required to provide a valid CAGE Code (Block 14), Point of Contact (POC) and email address w ith their bid.

5. Task Order minimum is $1,500.00 and maximum is $1,500,000.00; $750,000.00 for new w ork; $5,000,000.00 for repair, alteration, or maintenance.

X

ISRAEL GUTIERREZ 210-466-2208

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

06-Mar-2020

(RFP)

(IFB)

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______5 calendar days and complete it w ithin ________ calendar days after receiving aw ard, X notice to proceed. This performance period is mandatory, negotiable. (See _________________________Task Order

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________14 Apr 2020 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______180 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

MICC - FSH

ATTN: MICC - FSH

2205 INFANTRY POST RD

210-466-2145

FORT SAM HOUSTON TX 78234-1361

W9124J

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

01:00 PM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

210-466-2183FAX:TEL: 210-466-2145 (DSN 450) TEL: FAX:

W9124J20B0002 381

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

W9124J20B0002

Section SF 30 - BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Summary of Changes—Solicitation W9124J-20-B-0002, Amendment 0001

The purpose of this amendment is to provide revisions to the solicitation to address impacts caused by the public health emergency resulting from the COVID-19 virus pandemic, as well as providing responses to Industry submitted questions.

The immediate impact to this solicitation is to the deadline for bid submission, and the time and manner in which the bid opening will be conducted. As previously indicated in the Instructions to Bidders document included with the solicitation, interested parties are required to submit their bids electronically via email to the KO and KS, Regina M.

Espinoza and Israel Gutierrez, respectively. This has not changed.

To allow enough time prepare for the bid opening and for bidders to submit their bids, the due date for bid is extended to 1:00pm CDT, 14 April 2020; while the bid opening will no longer be held via video teleconference, but rather in adherence with prescribed directives designed to curb the effects of COVID-19 will now be conducted through a teleconference where attendees will be allowed to call-in. The bid opening will commence at 1:30pm CDT, 14 April 2020.

The Instructions to Bidders document has been updated to conform to the information provided here and elaborate on the processes that will be followed at the bid opening.

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES MAX

QUANTITY

UNIT UNIT PRICE MAX AMOUNT

0001 UNDEFINED

0001 - Removal

FFP

:Remove and replace deteriorated concrete roadway structures. Work shall include removal, excavation, formwork, compacting sub-base, aggregate base, installing vapor barrier, concrete and finishing, asphalt or concrete patching, backfilling, fine grading, topsoil, and seeding of adjacent areas.

MAX

NET AMT

UNIT UNIT PRICE MAX AMOUNT

0001AA 8,278 Linear Foot

0001AA - Curb (See plate #1)

FFP

:Curb (See plate #1) FOB: Destination

PSC CD: Y1LB

UNIT UNIT PRICE MAX AMOUNT

0001AB 17,480 Linear

0001AB - Combination Curb and Gutter

:Combination Curb and Gutter

UNIT UNIT PRICE MAX AMOUNT

0001AC 1,580 Square Yard

0001AC - Channel (See plate #3)

:Channel (See plate #3)

UNIT UNIT PRICE MAX AMOUNT

0001AD 395 Linear

0001AD - Gutter (See plate #2)

:Gutter (See plate #2)

UNIT UNIT PRICE MAX AMOUNT

0001AE 812 Square

0001AE - Reinforced 6" driveway pad

:Reinforced 6" driveway pad

UNIT UNIT PRICE MAX AMOUNT

0001AF 1,519 Linear

0001AF - Mountable curb and/or tack coat

:Mountable curb and/or tack coat

UNIT UNIT PRICE MAX AMOUNT

0002 11,920 Square

0002 - Remove existing

:Remove existing deteriorated sidewalks and replace as detailed on plate #4.

Work shall include removal, excavation, formwork, compacting sub-base, aggregate base, installing vapor barrier, concrete and finishing, backfilling, fine grading, topsoil, and seeding of adjacent areas

UNIT UNIT PRICE MAX AMOUNT

0003 UNDEFINED

0003 - Remove and replace

FFP

:Remove and replace existing with new commercial manufacture standards or cast-in-place concrete structures in asphalt and concrete surfaces. Work includes grates, frames, backfilling, compacting, and patching of surrounding areas.

UNIT UNIT PRICE MAX AMOUNT

0003AA 40 Cubic

0003AA - Drop inlets

:Remove and replace existing drop inlets in asphalt and concrete roads.

UNIT UNIT PRICE MAX AMOUNT

0003AB 103 Cubic

0003AB - Curb drop inlets

:Remove and replace existing curb drop inlets in asphalt concrete roads.

UNIT UNIT PRICE MAX AMOUNT

0003AC 8 Cubic

0003AC - Manhole

:Remove and replace existing manhole in asphalt and concrete roads.

UNIT UNIT PRICE MAX AMOUNT

0003AD 32 Cubic

0003AD - Drop inlets (grassy areas)

:Remove and replace existing drop inlets. (To be used in grassy areas).

UNIT UNIT PRICE MAX AMOUNT

0003AE 32 Cubic

0003AE - Manhole (grassy areas)

:Remove and replace existing manhole. (To be used in grassy areas).

UNIT UNIT PRICE MAX AMOUNT

0003AF 32 Cubic

0003AF - Provide new commercial

:Provide new commercial manufacturer's standard pre-cast concrete manhole, or cast-in-place concrete manhole. (To be used in grassy areas).

UNIT UNIT PRICE MAX AMOUNT

0004 UNDEFINED

0004 - Remove and replace existing storm

FFP

:Remove and replace existing storm drainage pipe with concrete pipe under unpaved areas. Replacement work includes excavations, bedding material, compaction, laying pipe, connections to manholes, backfilling, fine grading topsoil, and seeding.

UNIT UNIT PRICE MAX AMOUNT

0004AA 158 Linear

0004AA - 12" - 18" diameter pipe

:12" to 18" diameter pipe

UNIT UNIT PRICE MAX AMOUNT

0004AB 108 Linear

0004AB - 21" - 36" diameter pipe

:21" to 36" diameter pipe

UNIT UNIT PRICE MAX AMOUNT

0005 UNDEFINED

0005 - Remvoe and replace existing concr

FFP

:Remove and replace existing concrete structures. Work shall include excavations, formwork, reinforcement, aggregate base material, compactions, installing vapor barrier, placing concrete and finishing, asphalt and concrete patching, backfilling, fine grading, topsoil, and seeding. (All reinforcing bars shall be provided as directed by contracting officer).

UNIT UNIT PRICE MAX AMOUNT

0005AA 198 Cubic

0005AA - Stairs with handrail inserts

:Stairs with handrail inserts

UNIT UNIT PRICE MAX AMOUNT

0005AB 119 Cubic

0005AB - Stairs without handrail inserts

:Stairs without handrail inserts

UNIT UNIT PRICE MAX AMOUNT

0005AC 247 Cubic

0005AC - Reinforced slabs up to 6" thick

:Reinforced slabs up to 6" thick

UNIT UNIT PRICE MAX AMOUNT

0005AD 413 Cubic

0005AD - Reinforced slabs 8"-12" thick

:Reinforced slabs 8"-12" thick

UNIT UNIT PRICE MAX AMOUNT

0005AE 8 Each 0005AE - Mailbox pads 4'x4'x4'

FFP

:Mailbox pads 4'x 4'x 4'

UNIT UNIT PRICE MAX AMOUNT

0005AF 163 Cubic

0005AF - Handicap ramps

:Handicap ramps

UNIT UNIT PRICE MAX AMOUNT

0005AG 35 Each 0005AG - curb handicap ramps

FFP

:Curb handicap ramps with raised block exposed aggregate surface (See plate #8).

UNIT UNIT PRICE MAX AMOUNT

0005AH 79 Cubic

0005AH - Headwalls or endwalls

:Headwalls or endwalls

UNIT UNIT PRICE MAX AMOUNT

0006 UNDEFINED

0006 - Construct various types of handra

:Construct various types of handrails in concrete stairs.

UNIT UNIT PRICE MAX AMOUNT

0006AA 158 Linear

0006AA - Pipe railing (see plate #6)

:Pipe railing (See plate #6).

UNIT UNIT PRICE MAX AMOUNT

0006AB 79 Linear

0006AB - Wrought iron railing (See plate

:Wrought iron railing (See plate #7).

UNIT UNIT PRICE MAX AMOUNT

0006AC 40 Linear

0006AC - Aluminum bar railing

:Aluminum bar railing (See plate #7).

UNIT UNIT PRICE MAX AMOUNT

0007 UNDEFINED

0007 - Demo and removal

FFP

:Demolition and removal of existing wood, concrete, and masonry structures.

Work shall include removal of existing wood, concrete, masonry, and aggregate base, backfilling, fine grading, topsoil, and seed.

UNIT UNIT PRICE MAX AMOUNT

0007AA 139 Cubic

0007AA - Reinforced concrete

:Reinforced concrete

UNIT UNIT PRICE MAX AMOUNT

0007AB 1,850 Cubic

0007AB - Plain concrete

:Plain concrete

UNIT UNIT PRICE MAX AMOUNT

0007AC 7,900 Square

0007AC - Demo existing masonry

:Demolish existing masonry building, backfill, and grade to existing conditions, seed, and straw

UNIT UNIT PRICE MAX AMOUNT

0007AD 7,900 Square

0007AD - Demo existing wood bldg

:Demolish existing wood building, backfill and grade to existing conditions, seed, and straw

UNIT UNIT PRICE MAX AMOUNT

0008 1,365 Cubic

0008 - Concrete Work removal

:Concrete Work Removal. Remove existing unsuitable base material, replace with a stabilized aggregate base course, and compact in place.

UNIT UNIT PRICE MAX AMOUNT

0009 3,661 Cubic

0009 - Concrete Work Remove

:Concrete Work Remove unsuitable sub-base. Remove existing unsuitable sub-base material, replace with a stabilized aggregate base course, and compact in place.

UNIT UNIT PRICE MAX AMOUNT

0010 3,408 Cubic

0010 - Concrete - Regrade

:Concrete - Regrade. Regrade the existing landscape to provide the proper drainage.

UNIT UNIT PRICE MAX AMOUNT

0011 2,757 Cubic

0011 - Concrete Work - Backfill

:Concrete Work - Backfill. Backfill area with select material to grade. The material shall be #57, #21A etc. as indicated on the Delivery Order. (Place 2" topsoil and seed at grassy area).

UNIT UNIT PRICE MAX AMOUNT

0012 1,233 Cubic

0012 - concrete Work - Excavate

:Concrete Work - Excavate. Excavate existing surface, including turf, pavement sections, concrete slabs, structures, etc. Backfill with select material to grade.

Place 2" topsoil, fine grade, and seed.

UNIT UNIT PRICE MAX AMOUNT

0013 2,567 Square

0013 - Concrete Work - Sodding

:Concrete Work - Sodding. Provide sodding in lieu of seeding.

UNIT UNIT PRICE MAX AMOUNT

0014 UNDEFINED

0014 - Demo and Removal

FFP

:Demolition and removal of existing concrete slabs. Work shall include removal of concrete and aggregate base, backfilling with select material, fine grading, topsoil, and seed.

UNIT UNIT PRICE MAX AMOUNT

0014AA 7,303 Square

0014AA - Reinforced concrete up to 6"

:Concrete Work - Demolition. Demolition and removal: Reinforced concrete up to 6" thick

UNIT UNIT PRICE MAX AMOUNT

0014AB 23,740 Square

0014AB - Plain concrete up to 6"

:Concrete Work - Demolition. Demolition and removal: Plain concrete up to 6" thick

UNIT UNIT PRICE MAX AMOUNT

0014AC 18,348 Square

0014AC - Reinforced concrete 6"-12"

:Concrete Work - Demolition. Demolition and removal: Reinforced concrete 6" to 12" thick

UNIT UNIT PRICE MAX AMOUNT

0014AD 948 Square

0014AD - Plain concrete 6"-12"

:Concrete Work - Demolition. Demolition and removal: Plain concrete 6" to 12" thick

UNIT UNIT PRICE MAX AMOUNT

0015 395 Square

0015 - Concrete Work - Demo

Concrete Work - Demolition. Demolition and removal of existing deteriorated brick paving. Work shall include excavation, gravel base, concrete base, mortar beds, installing paving bricks with mortar or sand joints, backfilling, topsoil, and seeding of adjacent areas. CLIN 0015 coincides with CLINs 0037-0040. The break out of specific services associated with this CLIN are located on CLINs 0037-0040.

UNIT UNIT PRICE MAX AMOUNT

0016 UNDEFINED

0016 - Construct new concrete structures

FFP

:Construct new concrete structures. Work shall include excavation, compacting aggregate base, formwork, installing vapor barrier, placing concrete, finishing, asphalt or concrete patching, backfilling, fine grading, topsoil, and seeding.

UNIT UNIT PRICE MAX AMOUNT

0016AA 790 Linear

0016AA - Standard curb

:Construct new concrete structures. Standard curb (See plate #1).

UNIT UNIT PRICE MAX AMOUNT

0016AB 5,690 Linear

0016AB - Combo curb and gutter

:Construct new concrete structures. Combination curb and gutter (See plate #1).

UNIT UNIT PRICE MAX AMOUNT

0016AC 1,580 Square

0016AC - New channel

:Construct new concrete structures. New channel (See plate #2).

UNIT UNIT PRICE MAX AMOUNT

0016AD 790 Linear

0016AD - Standard gutter

:Construct new concrete structures. Standard gutter (See plate #2).

UNIT UNIT PRICE MAX AMOUNT

0016AE 395 Linear

0016AE - Mountable curb

:Construct new concrete structures. Mountable curb (See plate #2).

UNIT UNIT PRICE MAX AMOUNT

0017 4,024 Square

0017 - Construct new concrete sidewalks

:Construct new concrete sidewalks. Construct new concrete sidewalks and 4" slabs. Work shall include excavation, formwork, compacting, aggregate base, vapor barrier, placing concrete, finishing, backfilling, fine grading, topsoil, and seeding of adjacent areas.

UNIT UNIT PRICE MAX AMOUNT

0018 UNDEFINED

0018 - Construct new drainage structures

FFP

:Construct new drainage structures. New structures shall meet commercial manufacturer's standard. Concrete structures

UNIT UNIT PRICE MAX AMOUNT

0018AA 52 Cubic

0018AA - New drop inlet

:Construct new drainage structures - new drop inlet

UNIT UNIT PRICE MAX AMOUNT

0018AB 87 Cubic

0018AB - New curb drop inlet

:Construct new drainage structures - new curb drop inlet

UNIT UNIT PRICE MAX AMOUNT

0018AC 160 Cubic

0018AC - New manhole

:Construct new drainage structures -new manhole

UNIT UNIT PRICE MAX AMOUNT

0019 UNDEFINED

0019 - Construct new drainage structures

FFP

:Construct new drainage structures. New structures shall meet commercial manufacturer's standard. Concrete structures shall be either precast concrete or cast-in-place. Work includes grates, frames, covers, backfilling, compacting, fine grading, topsoil, and seeding adjacent areas. (To be used in grassy areas).

UNIT UNIT PRICE MAX AMOUNT

0019AA 79 Cubic

0019AA - New drop inlet

:New drop inlet.

UNIT UNIT PRICE MAX AMOUNT

0019AB 79 Cubic

0019AB - New manhole

:New manhole

UNIT UNIT PRICE MAX AMOUNT

0020 UNDEFINED

0020 - Construct new storm drainage pipe

FFP

:Construct new storm drainage pipe under unpaved areas. Work includes excavations, bedding material, compaction, laying pipe, connections to manholes, backfilling, fine grading, topsoil, and seeding.

UNIT UNIT PRICE MAX AMOUNT

0020AA 395 Linear

0020AA - New 12"-18" pipe

:New 12"-18" dia. concrete pipe

UNIT UNIT PRICE MAX AMOUNT

0020AB 198 Linear

0020AB - New 21"-36" pipe

:New 21"-36" dia. concrete pipe

UNIT UNIT PRICE MAX AMOUNT

0020AC 198 Linear

0020AC - New 48" pipe

:New 48" dia. Class III reinforced concrete pipe

UNIT UNIT PRICE MAX AMOUNT

0020AD 198 Linear

0020AD - New 60" Class III pipe

:New 60" dia. Class III reinforced concrete pipe

UNIT UNIT PRICE MAX AMOUNT

0020AE 198 Linear

0020AE - New 72" Class III pipe

:New 72" dia. Class III reinforced concrete pipe

UNIT UNIT PRICE MAX AMOUNT

0020AF 198 Linear

0020AF- New 29"x45" elliptical

:New 29"x 45" elliptical reinforced concrete pipe

UNIT UNIT PRICE MAX AMOUNT

0020AG 198 Linear

0020AG - New 38"x60" elliptical

:New 38"x 60" elliptical reinforced concrete pipe

UNIT UNIT PRICE MAX AMOUNT

0020AH 198 Linear

0020AH - new 48"x76" elliptical

:New 48"x 76" elliptical reinforced concrete pipe

UNIT UNIT PRICE MAX AMOUNT

0020AJ 198 Linear

0020AJ - New 58"x91" elliptical

:New 58"x 91" elliptical reinforced concrete pipe

UNIT UNIT PRICE MAX AMOUNT

0020AK 395 Linear

0020AK - New 24" 16 gauge

:New 24" dia., 16 gauge, corrugated metal pipe (to include collars)

UNIT UNIT PRICE MAX AMOUNT

0020AL 395 Linear

0020AL - New 36" 12 gauage

:New 48" dia., 12 gauge, corrugated metal pipe (to include collars)

UNIT UNIT PRICE MAX AMOUNT

0020AM 395 Linear

0020AM - new 48" 12 gauge

:New 36" dia., 12 gauge, corrugated metal pipe (to include collars)

UNIT UNIT PRICE MAX AMOUNT

0021 9,700 Square

0021 - Construct heavy duty embankment

:Construct heavy duty embankment stabilization fabric

UNIT UNIT PRICE MAX AMOUNT

0022 1,844 Square

0022 - Construct turf reinforcement matt

:Construct turf reinforcement matting

UNIT UNIT PRICE MAX AMOUNT

0023 2,572 Cubic

0023 - Construct new misc concrete pads

:Construct new miscellaneous, reinforced concrete pads, up to 6" thick. Work shall include excavation, formwork, compactions, aggregate base, reinforcing, vapor barrier, concrete placement, finishing, backfill, asphalt and concrete patching, fine grading, topsoil, and seeding. (All reinforcing bars shall be provided as directed by contracting officer).

UNIT UNIT PRICE MAX AMOUNT

0024 549 Cubic

0024 - Construct new pads 8"-12"

:Construct new miscellaneous, reinforced concrete pads, 8"-12" thick. Work shall include excavation, formwork, compactions, aggregate base, reinforcing, vapor barrier, concrete placement, finishing, backfill, asphalt and concrete patching, fine grading, topsoil, and seeding. (All reinforcing bars shall be provided as directed by contracting officer).

UNIT UNIT PRICE MAX AMOUNT

0025 40 Each 0025 - New curb handicap ramps

FFP

:Construct new curb handicap ramps with exposed aggregate concrete surface.

UNIT UNIT PRICE MAX AMOUNT

0026 386 Cubic

0026 - New concrete structures

:Construct new concrete structures such as stairs, footers, ramps, or retaining walls. All reinforcing bars shall be provided as directed by contracting officer.

UNIT UNIT PRICE MAX AMOUNT

0027 5,331 Square

0027 - New brick paving

:Construct new brick paving on a rigid base. Work shall include brick paving, concrete slabs with edge, and gravel base. Reinforcing bars shall be provided as directed by contracting officer. (See plate #4).

UNIT UNIT PRICE MAX AMOUNT

0028 3,651 Square

0028 - New interlocking brick pavers

:Construct new interlocking brick pavers on a sand base. Work shall include brick paving, compacted backfill sub-base and sand base with imbedded landscaping fabric. Interlocking brick pavers shall be compacted into final seated position. (See plate #9).

UNIT UNIT PRICE MAX AMOUNT

0029 UNDEFINED

0029 - New PVC Pipe

FFP

:Construct new PVC pipe in unpaved areas, to include: excavation, bedding material, pipe placement, connection to manhole, backfill, compaction, fine grading, topsoil, and seeding.

UNIT UNIT PRICE MAX AMOUNT

0029AA 7,900 Linear

0029AA - 4"-6" pipe

:4"-6" diameter Pipe

UNIT UNIT PRICE MAX AMOUNT

0029AB 1,940 Linear

0029AB - 8"-10" pipe

:8"-10" diameter Pipe

UNIT UNIT PRICE MAX AMOUNT

0029AC 790 Linear

0029AC - Remove existing

:Remove existing PVC pipe, and replace with new 4"-6" dia. PVC pipe

UNIT UNIT PRICE MAX AMOUNT

0029AD 158 Linear

0029AD - Remove existing

:Remove existing PVC pipe, and replace with new 8"-10" diameter PVC pipe.

UNIT UNIT PRICE MAX AMOUNT

0030 UNDEFINED

0030 - New PVC pipe

FFP

:Construct new PVC pipe in paved areas such as concrete or asphalt, to include:

excavation, bedding material, pipe placement, connection to manhole, backfill, compaction, patching, and aggregate.

UNIT UNIT PRICE MAX AMOUNT

0030AA 7,960 Linear

0030AA - 4"-6" pipe

:4"-6" diameter Pipe

UNIT UNIT PRICE MAX AMOUNT

0030AB 1,683 Linear

0030AB - 8"-10" pipe

:8"-10" diameter Pipe

UNIT UNIT PRICE MAX AMOUNT

0030AC 790 Linear

0030AC - Remove and replace

:Remove existing PVC pipe, and replace with new 4"-6" dia. PVC pipe

UNIT UNIT PRICE MAX AMOUNT

0030AD 653 Linear

0030AD - Remove and replace

:Remove existing PVC pipe, and replace with new 8"-10" diameter PVC pipe.

UNIT UNIT PRICE MAX AMOUNT

0031 2,370 Linear

0031 - Construct new under drain

:Construct new under drain. Work shall include excavation, bedding material, compaction, pipe placement, connections to outlet pipes and manholes, backfilling, fine grading, patching, topsoil, seeding, etc. (see plate #12).

UNIT UNIT PRICE MAX AMOUNT

0032 UNDEFINED

0032 - Construct new rip rap

:Construct new rip rap

UNIT UNIT PRICE MAX AMOUNT

0032AA 395 Cubic

0032AA - New class I rip rap

:Construct new class I rip rap (50-150 lbs.).

UNIT UNIT PRICE MAX AMOUNT

0032AB 395 Cubic

0032AB - Construct mixture

:Construct mixture of #550 gabion stone (4-30 lbs.) and class I rip rap (50-150 lbs.) in designated wetland area to prevent erosion.

UNIT UNIT PRICE MAX AMOUNT

0033 UNDEFINED

0033 - New pipe bollard

FFP

:Construct new pipe bollard filled with concrete. Work shall include excavation, compaction, backfilling, patching, fine grading, topsoil, seeding, etc. (see plate #11).

UNIT UNIT PRICE MAX AMOUNT

0033AA 206 Each 0033AA - 6" diameter

FFP

:Construct new pipe bollard filled with concrete. Work shall include excavation, compaction, backfilling, patching, fine grading, topsoil, seeding, etc. (see plate #11) - 6" diameter

UNIT UNIT PRICE MAX AMOUNT

0033AB 217 Each 0033AB - 8" diameter

FFP

:Construct new pipe bollard filled with concrete. Work shall include excavation, compaction, backfilling, patching, fine grading, topsoil, seeding, etc. (see plate #11). - 8" diameter

UNIT UNIT PRICE MAX AMOUNT

0034 79 Each 0034 - Concrete jersey barrier

FFP

:Furnish contractor-owned concrete jersey barrier ( 12" long) and remove after work completion, or as directed by the contracting officer

UNIT UNIT PRICE MAX AMOUNT

0035 3,962 Square

0035 - New masonry block and brick wall

:Construct new concrete masonry block and brick wall. The wall shall be constructed of 8" with 4" brick face. Provide the necessary horizontal and vertical reinforcement as directed by the contracting officer.

UNIT UNIT PRICE MAX AMOUNT

0036 21 Each Provide surveying, engineering, permits

FFP

Provide surveying, engineering, and permitting when required.

UNIT UNIT PRICE MAX AMOUNT

0037 4 Each Tree & Stump Removal

FFP

Tree & Stump Removal Up to 6 inch diameter. 0037 coincides with 0015.

UNIT UNIT PRICE MAX AMOUNT

0038 4 Each Tree & Stump Removal

FFP

Tree & Stump Removal From 6 inch to 12 inch diameter. 0038 coincides with 0015.

UNIT UNIT PRICE MAX AMOUNT

0039 4 Each Tree & Stump Removal

FFP

Tree & Stump Removal From 12 inch to 24 inch diameter. 0039 coincides with 0015.

UNIT UNIT PRICE MAX AMOUNT

0040 4 Each Tree & Stump Removal

FFP

Tree & Stump Removal Greater than 24 inch diameter. 00340 coincides with 0015.

UNIT UNIT PRICE MAX AMOUNT

1001 UNDEFINED

1001 - Removal

FFP

:Remove and replace deteriorated concrete roadway structures. Work shall include removal, excavation, formwork, compacting sub-base, aggregate base, UNIT UNIT PRICE MAX AMOUNT

1001AA 8,962 Linear

1001AA - Curb (See plate #1)

:Curb (See plate #1)

UNIT UNIT PRICE MAX AMOUNT

1001AB 18,354 Linear

1001AB - Combination Curb and Gutter

:Combination Curb and Gutter

UNIT UNIT PRICE MAX AMOUNT

1001AC 1,659 Square

1001AC - Channel (See plate #3)

:Channel (See plate #3)

UNIT UNIT PRICE MAX AMOUNT

1001AD 415 Linear

1001AD - Gutter (See plate #2)

:Gutter (See plate #2)

UNIT UNIT PRICE MAX AMOUNT

1001AE 852 Square

0001AE - Reinforced 6" driveway pad

:Reinforced 6" driveway pad

UNIT UNIT PRICE MAX AMOUNT

1001AF 1,595 Linear

0001AF - Mountable curb and/or tack coat

:Mountable curb and/or tack coat

UNIT UNIT PRICE MAX AMOUNT

1002 12,516 Square

0002 - Remove existing

:Remove existing deteriorated sidewalks and replace as detailed on plate #4.

Work shall include removal, excavation, formwork, compacting sub-base, aggregate base, installing vapor barrier, concrete and finishing, backfilling, fine grading, topsoil, and seeding of adjacent areas

UNIT UNIT PRICE MAX AMOUNT

1003 UNDEFINED

0003 - Remove and replace

FFP

:Remove and replace existing with new commercial manufacture standards or

UNIT UNIT PRICE MAX AMOUNT

1003AA 41 Cubic

1003AA - Drop inlets

:Remove and replace existing drop inlets in asphalt and concrete roads.

UNIT UNIT PRICE MAX AMOUNT

1003AB 108 Cubic

0003AB - Curb drop inlets

:Remove and replace existing curb drop inlets in asphalt concrete roads.

UNIT UNIT PRICE MAX AMOUNT

1003AC 8 Cubic

0003AC - Manhole

:Remove and replace existing manhole in asphalt and concrete roads.

UNIT UNIT PRICE MAX AMOUNT

1003AD 33 Cubic

0003AD - Drop inlets (grassy areas)

:Remove and replace existing drop inlets. (To be used in grassy areas).

UNIT UNIT PRICE MAX AMOUNT

1003AE 33 Cubic

0003AE - Manhole (grassy areas)

:Remove and replace existing manhole. (To be used in grassy areas).

UNIT UNIT PRICE MAX AMOUNT

1003AF 33 Cubic

0003AF - Provide new commercial

:Provide new commercial manufacturer's standard pre-cast concrete manhole, or cast-in-place concrete manhole. (To be used in grassy areas).

UNIT UNIT PRICE MAX AMOUNT

1004 UNDEFINED

0004 - Remove and replace existing storm

FFP

:Remove and replace existing storm drainage pipe with concrete pipe under unpaved areas. Replacement work includes excavations, bedding material, UNIT UNIT PRICE MAX AMOUNT

1004AA 166 Linear

1004AA - 12" - 18" diameter pipe

:12" to 18" diameter pipe

UNIT UNIT PRICE MAX AMOUNT

1004AB 113 Linear

1004AB - 21" - 36" diameter pipe

:21" to 36" diameter pipe

UNIT UNIT PRICE MAX AMOUNT

1005 UNDEFINED

1005 - Remvoe and replace existing concr

FFP

:Remove and replace existing concrete structures. Work shall include excavations, formwork, reinforcement, aggregate base material, compactions, installing vapor barrier, placing concrete and finishing, asphalt and concrete

UNIT UNIT PRICE MAX AMOUNT

1005AA 207 Cubic

1005AA - Stairs with handrail inserts

:Stairs with handrail inserts

UNIT UNIT PRICE MAX AMOUNT

1005AB 124 Cubic

1005AB - Stairs without handrail inserts

:Stairs without handrail inserts

UNIT UNIT PRICE MAX AMOUNT

1005AC 259 Cubic

1005AC - Reinforced slabs up to 6" thick

:Reinforced slabs up to 6" thick

UNIT UNIT PRICE MAX AMOUNT

1005AD 433 Cubic

1005AD - Reinforced slabs 8"-12" thick

:Reinforced slabs 8"-12" thick

UNIT UNIT PRICE MAX AMOUNT

1005AE 8 Each 1005AE - Mailbox pads 4'x4'x4'

FFP

:Mailbox pads 4'x 4'x 4'

UNIT UNIT PRICE MAX AMOUNT

1005AF 171 Cubic

1005AF - Handicap ramps

:Handicap ramps

UNIT UNIT PRICE MAX AMOUNT

1005AG 37 Each 1005AG - curb handicap ramps

FFP

:Curb handicap ramps with raised block exposed aggregate surface (See plate #8).

UNIT UNIT PRICE MAX AMOUNT

1005AH 83 Cubic

1005AH - Headwalls or endwalls

:Headwalls or endwalls

UNIT UNIT PRICE MAX AMOUNT

1006 UNDEFINED

1006 - Construct various types of handra

UNIT UNIT PRICE MAX AMOUNT

1006AA 166 Linear

1006AA - Pipe railing (see plate #6)

:Pipe railing (See plate #6).

UNIT UNIT PRICE MAX AMOUNT

1006AB 83 Linear

1006AB - Wrought iron railing (See plate

:Wrought iron railing (See plate #7).

UNIT UNIT PRICE MAX AMOUNT

1006AC 41 Linear

1006AC - Aluminum bar railing

:Aluminum bar railing (See plate #7).

UNIT UNIT PRICE MAX AMOUNT

1007 UNDEFINED

1007 - Demo and removal

FFP

:Demolition and removal of existing wood, concrete, and masonry structures.

UNIT UNIT PRICE MAX AMOUNT

1007AA 146 Cubic

1007AA - Reinforced concrete

:Reinforced concrete

UNIT UNIT PRICE MAX AMOUNT

1007AB 1,943 Cubic

1007AB - Plain concrete

:Plain concrete

UNIT UNIT PRICE MAX AMOUNT

1007AC 8,295 Square

1007AC - Demo existing masonry

:Demolish existing masonry building, backfill, and grade to existing conditions, seed, and straw

UNIT UNIT PRICE MAX AMOUNT

1007AD 8,295 Square

1007AD - Demo existing wood bldg

:Demolish existing wood building, backfill and grade to existing conditions, seed, and straw

UNIT UNIT PRICE MAX AMOUNT

1008 1,433 Cubic

1008 - Concrete Work removal

:Concrete Work Removal. Remove existing unsuitable base material, replace with a stabilized aggregate base course, and compact in place.

UNIT UNIT PRICE MAX AMOUNT

1009 3,844 Cubic

1009 - Concrete Work Remove

:Concrete Work Remove unsuitable sub-base. Remove existing unsuitable sub-base material, replace with a stabilized aggregate base course, and compact in place.

UNIT UNIT PRICE MAX AMOUNT

1010 3,578 Cubic

1010 - Concrete - Regrade

:Concrete - Regrade. Regrade the existing landscape to provide the proper drainage.

UNIT UNIT PRICE MAX AMOUNT

1011 2,895 Cubic

1011 - Concrete Work - Backfill

:Concrete Work - Backfill. Backfill area with select material to grade. The material shall be #57, #21A etc. as indicated on the Delivery Order. (Place 2" topsoil and seed at grassy area).

UNIT UNIT PRICE MAX AMOUNT

1012 1,294 Cubic

1012 - concrete Work - Excavate

:Concrete Work - Excavate. Excavate existing surface, including turf, pavement sections, concrete slabs, structures, etc. Backfill with select material to grade.

Place 2" topsoil, fine grade, and seed.

UNIT UNIT PRICE MAX AMOUNT

1013 2,695 Square

1013 - Concrete Work - Sodding

:Concrete Work - Sodding. Provide sodding in lieu of seeding.

UNIT UNIT PRICE MAX AMOUNT

1014 UNDEFINED

1014 - Demo and Removal

FFP

:Demolition and removal of existing concrete slabs. Work shall include removal

UNIT UNIT PRICE MAX AMOUNT

1014AA 7,668 Square

1014AA - Reinforced concrete up to 6"

:Concrete Work - Demolition. Demolition and removal: Reinforced concrete up to 6" thick

UNIT UNIT PRICE MAX AMOUNT

1014AB 24,927 Square

1014AB - Plain concrete up to 6"

:Concrete Work - Demolition. Demolition and removal: Plain concrete up to 6" thick

UNIT UNIT PRICE MAX AMOUNT

1014AC 19,265 Square

1014AC - Reinforced concrete 6"-12"

:Concrete Work - Demolition. Demolition and removal: Reinforced concrete 6" to 12" thick

UNIT UNIT PRICE MAX AMOUNT

1014AD 995 Square

1014AD - Plain concrete 6"-12"

:Concrete Work - Demolition. Demolition and removal: Plain concrete 6" to 12" thick

UNIT UNIT PRICE MAX AMOUNT

1015 415 Square

1015 - Concrete Work - Demo

Concrete Work - Demolition. Demolition and removal of existing deteriorated brick paving. Work shall include excavation, gravel base, concrete base, mortar beds, installing paving bricks with mortar or sand joints, backfilling, topsoil, and seeding of adjacent areas. CLIN 1015 coincides with CLINs 1037-1040. The break out of specific services associated with this CLIN are located on CLINs 1037-1040.

UNIT UNIT PRICE MAX AMOUNT

1016 UNDEFINED

1016 - Construct new concrete structures

FFP

:Construct new concrete structures. Work shall include excavation, compacting aggregate base, formwork, installing vapor barrier, placing concrete, finishing, asphalt or concrete patching, backfilling, fine grading, topsoil, and seeding.

UNIT UNIT PRICE MAX AMOUNT

1016AA 830 Linear

1016AA - Standard curb

:Construct new concrete structures. Standard curb (See plate #1).

UNIT UNIT PRICE MAX AMOUNT

1016AB 5,975 Linear

1016AB - Combo curb and gutter

:Construct new concrete structures. Combination curb and gutter (See plate #1).

UNIT UNIT PRICE MAX AMOUNT

1016AC 1,659 Square

1016AC - New channel

:Construct new concrete structures. New channel (See plate #2).

UNIT UNIT PRICE MAX AMOUNT

1016AD 830 Linear

1016AD - Standard gutter

:Construct new concrete structures. Standard gutter (See plate #2).

UNIT UNIT PRICE MAX AMOUNT

1016AE 415 Linear

1016AE - Mountable curb

:Construct new concrete structures. Mountable curb (See plate #2).

UNIT UNIT PRICE MAX AMOUNT

1017 4,225 Square

1017 - Construct new concrete sidewalks

:Construct new concrete sidewalks. Construct new concrete sidewalks and 4" slabs. Work shall include excavation, formwork, compacting, aggregate base, vapor barrier, placing concrete, finishing, backfilling, fine grading, topsoil, and seeding of adjacent areas.

UNIT UNIT PRICE MAX AMOUNT

1018 UNDEFINED

1018 - Construct new drainage structures

FFP

:Construct new drainage structures. New structures shall meet commercial manufacturer's standard. Concrete structures

UNIT UNIT PRICE MAX AMOUNT

1018AA 54 Cubic

1018AA - New drop inlet

:Construct new drainage structures - new drop inlet

UNIT UNIT PRICE MAX AMOUNT

1018AB 92 Cubic

1016AB - New curb drop inlet

:Construct new drainage structures - new curb drop inlet

UNIT UNIT PRICE MAX AMOUNT

1018AC 167 Cubic

1018AC - New manhole

:Construct new drainage structures -new manhole

UNIT UNIT PRICE MAX AMOUNT

1019 UNDEFINED

1019 - Construct new drainage structures

FFP

:Construct new drainage structures. New structures shall meet commercial manufacturer's standard. Concrete structures shall be either precast concrete or cast-in-place. Work includes grates, frames, covers, backfilling, compacting, fine grading, topsoil, and seeding adjacent areas. (To be used in grassy areas).

UNIT UNIT PRICE MAX AMOUNT

1019AA 83 Cubic

1019AA - New drop inlet

:New drop inlet.

UNIT UNIT PRICE MAX AMOUNT

1019AB 83 Cubic

1019AB - New manhole

:New manhole

UNIT UNIT PRICE MAX AMOUNT

1020 UNDEFINED

1020 - Construct new storm drainage pipe

FFP

:Construct new storm drainage pipe under unpaved areas. Work includes excavations, bedding material, compaction, laying pipe, connections to manholes, backfilling, fine grading, topsoil, and seeding.

UNIT UNIT PRICE MAX AMOUNT

1020AA 415 Linear

1020AA - New 12"-18" pipe

:New 12"-18" dia. concrete pipe

UNIT UNIT PRICE MAX AMOUNT

1020AB 207 Linear

1020AB - New 21"-36" pipe

:New 21"-36" dia. concrete pipe

UNIT UNIT PRICE MAX AMOUNT

1020AC 207 Linear

1020AC - New 48" pipe

:New 48" dia. Class III reinforced concrete pipe

UNIT UNIT PRICE MAX AMOUNT

1020AD 207 Linear

1020AD - New 60" Class III pipe

:New 60" dia. Class III reinforced concrete pipe

UNIT UNIT PRICE MAX AMOUNT

1020AE 207 Linear

1020AE - New 72" Class III pipe

:New 72" dia. Class III reinforced concrete pipe

UNIT UNIT PRICE MAX AMOUNT

1020AF 207 Linear

1020AF- New 29"x45" elliptical

:New 29"x 45" elliptical reinforced concrete pipe

UNIT UNIT PRICE MAX AMOUNT

1020AG 207 Linear

1020AG - New 38"x60" elliptical

:New 38"x 60" elliptical reinforced concrete pipe

UNIT UNIT PRICE MAX AMOUNT

1020AH 207 Linear

1020AH - new 48"x76" elliptical

:New 48"x 76" elliptical reinforced concrete pipe

UNIT UNIT PRICE MAX AMOUNT

1020AJ 207 Linear

1020AJ - New 58"x91" elliptical

:New 58"x 91" elliptical reinforced concrete pipe

UNIT UNIT PRICE MAX AMOUNT

1020AK 415 Linear

1020AK - New 24" 16 gauge

:New 24" dia., 16 gauge, corrugated metal pipe (to include collars)

UNIT UNIT PRICE MAX AMOUNT

1020AL 415 Linear

1020AL - new 36" 12 gauge

:New 36" dia., 12 gauge, corrugated metal pipe (to include collars)

UNIT UNIT PRICE MAX AMOUNT

1020AM 415 Linear

1020AM - New 48" 12 gauage

:New 48" dia., 12 gauge, corrugated metal pipe (to include collars)

UNIT UNIT PRICE MAX AMOUNT

1021 10,185 Square

1021 - Construct heavy duty embankment

:Construct heavy duty embankment stabilization fabric

UNIT UNIT PRICE MAX AMOUNT

1022 1,936 Square

1022 - Construct turf reinforcement matt

:Construct turf reinforcement matting

UNIT UNIT PRICE MAX AMOUNT

1023 2,701 Cubic

0023 - Construct new misc concrete pads

:Construct new miscellaneous, reinforced concrete pads, up to 6" thick. Work shall include excavation, formwork, compactions, aggregate base, reinforcing, vapor barrier, concrete placement, finishing, backfill, asphalt and concrete patching, fine grading, topsoil, and seeding. (All reinforcing bars shall be provided as directed by contracting officer).

UNIT UNIT PRICE MAX AMOUNT

1024 576 Cubic

1024 - Construct new pads 8"-12"

:Construct new miscellaneous, reinforced concrete pads, 8"-12" thick. Work shall include excavation, formwork, compactions, aggregate base, reinforcing, vapor barrier, concrete placement, finishing, backfill, asphalt and concrete patching, fine grading, topsoil, and seeding. (All reinforcing bars shall be provided as directed by contracting officer).

UNIT UNIT PRICE MAX AMOUNT

1025 41 Each 1025 - New curb handicap ramps

FFP

:Construct new curb handicap ramps with exposed aggregate concrete surface.

UNIT UNIT PRICE MAX AMOUNT

1026 405 Cubic

1026 - New concrete structures

:Construct new concrete structures such as stairs, footers, ramps, or retaining walls. All reinforcing bars shall be provided as directed by contracting officer.

UNIT UNIT PRICE MAX AMOUNT

1027 5,598 Square

1027 - New brick paving

:Construct new brick paving on a rigid base. Work shall include brick paving, concrete slabs with edge, and gravel base. Reinforcing bars shall be provided as directed by contracting officer. (See plate #4).

UNIT UNIT PRICE MAX AMOUNT

1028 3,834 Square

1028 - New interlocking brick pavers

:Construct new interlocking brick pavers on a sand base. Work shall include brick paving, compacted backfill sub-base and sand base with imbedded landscaping fabric. Interlocking brick pavers shall be compacted into final seated position. (See plate #9).

UNIT UNIT PRICE MAX AMOUNT

1029 UNDEFINED

1029 - New PVC Pipe

FFP

:Construct new PVC pipe in unpaved areas, to include: excavation, bedding material, pipe placement, connection to manhole, backfill, compaction, fine grading, topsoil, and seeding.

UNIT UNIT PRICE MAX AMOUNT

1029AA 8,295 Linear

1029AA - 4"-6" pipe

:4"-6" diameter Pipe

UNIT UNIT PRICE MAX AMOUNT

1029AB 2,037 Linear

1029AB - 8"-10" pipe

:8"-10" diameter Pipe

UNIT UNIT PRICE MAX AMOUNT

1029AC 830 Linear

1029AC - Remove existing

:Remove existing PVC pipe, and replace with new 4"-6" dia. PVC pipe

UNIT UNIT PRICE MAX AMOUNT

1029AD 166 Linear

1029AD - Remove existing

:Remove existing PVC pipe, and replace with new 8"-10" diameter PVC pipe.

UNIT UNIT PRICE MAX AMOUNT

1030 UNDEFINED

1030 - New PVC pipe

FFP

:Construct new PVC pipe in paved areas such as concrete or asphalt, to include:

excavation, bedding material, pipe placement, connection to manhole, backfill, compaction, patching, and aggregate.

UNIT UNIT PRICE MAX AMOUNT

1030AA 8,358 Linear

1030AA - 4"-6" pipe

:4"-6" diameter Pipe

UNIT UNIT PRICE MAX AMOUNT

1030AB 1,767 Linear

1030AB - 8"-10" pipe

:8"-10" diameter Pipe

UNIT UNIT PRICE MAX AMOUNT

1030AC 830 Linear

1030AC - Remove and replace

:Remove existing PVC pipe, and replace with new 4"-6" dia. PVC pipe

UNIT UNIT PRICE MAX AMOUNT

1030AD 685 Linear

1030AD - Remove and replace

:Remove existing PVC pipe, and replace with new 8"-10" diameter PVC pipe.

UNIT UNIT PRICE MAX AMOUNT

1031 2,489 Linear

1031 - Construct new under drain

:Construct new under drain. Work shall include excavation, bedding material, compaction, pipe placement, connections to outlet pipes and manholes, backfilling, fine grading, patching, topsoil, seeding, etc. (see plate #12).

UNIT UNIT PRICE MAX AMOUNT

1032 UNDEFINED

1032 - Construct new rip rap

:Construct new rip rap

UNIT UNIT PRICE MAX AMOUNT

1032AA 415 Cubic

1032AA - New class I rip rap

:Construct new class I rip rap (50-150 lbs.).

UNIT UNIT PRICE MAX AMOUNT

1032AB 415 Cubic

1032AB - Construct mixture

:Construct mixture of #550 gabion stone (4-30 lbs.) and class I rip rap (50-150 lbs.) in designated wetland area to prevent erosion.

UNIT UNIT PRICE MAX AMOUNT

1033 UNDEFINED

1033 - New pipe bollard

FFP

:Construct new pipe bollard filled with concrete. Work shall include excavation, compaction, backfilling, patching, fine grading, topsoil, seeding, etc. (see plate #11).

UNIT UNIT PRICE MAX AMOUNT

1033AA 216 Each 1033AA - 6" diameter

FFP

:Construct new pipe bollard filled with concrete. Work shall include excavation, compaction, backfilling, patching, fine grading, topsoil, seeding, etc. (see plate #11) - 6" diameter

UNIT UNIT PRICE MAX AMOUNT

1033AB 228 Each 1033AB - 8" diameter

FFP

:Construct new pipe bollard filled with concrete. Work shall include excavation, compaction, backfilling, patching, fine grading, topsoil, seeding, etc. (see plate #11). - 8" diameter

UNIT UNIT PRICE MAX AMOUNT

1034 83 Each 1034 - Concrete jersey barrier

FFP

:Furnish contractor-owned concrete jersey barrier ( 12" long) and remove after work completion, or as directed by the contracting officer

UNIT UNIT PRICE MAX AMOUNT

1035 4,160 Square

1035 - New masonry block and brick wall

:Construct new concrete masonry block and brick wall. The wall shall be constructed of 8" with 4" brick face. Provide the necessary horizontal and vertical reinforcement as directed by the contracting officer.

UNIT UNIT PRICE MAX AMOUNT

1036 22 Each 1036 - Provide surveying, engineering, a

FFP

:Provide surveying, engineering, and permitting when required

UNIT UNIT PRICE MAX AMOUNT

1037 4 Each Tree & Stump Removal

FFP

Tree & Stump Removal Up to 6 inch diameter. Line 1037 coincides with line 1015.

UNIT UNIT PRICE MAX AMOUNT

1038 4 Each Tree & Stump Removal

FFP

Tree & Stump Removal From 6 inch to 12 diameter. Line 1038 coincides with line 1015.

UNIT UNIT PRICE MAX AMOUNT

1039 4 Each Tree & Stump Removal

FFP

Tree & Stump Removal From 12 inch to 24 inch diameter. Line 1039 coincides with line 1015.

UNIT UNIT PRICE MAX AMOUNT

1040 4 Each Tree & Stump Removal

FFP

Tree & Stump Removal Greater than 24inch diameter. Line 1040 coincides with line 1015.

UNIT UNIT PRICE MAX AMOUNT

2001 UNDEFINED

2001 - Removal

FFP

:Remove and replace deteriorated concrete roadway structures. Work shall include removal, excavation, formwork, compacting sub-base, aggregate base, UNIT UNIT PRICE MAX AMOUNT

2001AA 9,126 Linear

2001AA - Curb (See plate #1)

:Curb (See plate #1)

UNIT UNIT PRICE MAX AMOUNT

2001AB 19,272 Linear

2001AB - Combination Curb and Gutter

:Combination Curb and Gutter

UNIT UNIT PRICE MAX AMOUNT

2001AC 1,742 Square

2001AC - Channel (See plate #3)

:Channel (See plate #3)

UNIT UNIT PRICE MAX AMOUNT

2001AD 435 Linear

2001AD - Gutter (See plate #2)

:Gutter (See plate #2)

UNIT UNIT PRICE MAX AMOUNT

2001AE 895 Square

2001AE - Reinforced 6" driveway pad

:Reinforced 6" driveway pad

UNIT UNIT PRICE MAX AMOUNT

2001AF 1,675 Linear

2001AF - Mountable curb and/or tack coat

:Mountable curb and/or tack coat

UNIT UNIT PRICE MAX AMOUNT

2002 13,141 Square

2002 - Remove existing

:Remove existing deteriorated sidewalks and replace as detailed on plate #4.

Work shall include removal, excavation, formwork, compacting sub-base, aggregate base, installing vapor barrier, concrete and finishing, backfilling, fine grading, topsoil, and seeding of adjacent areas

UNIT UNIT PRICE MAX AMOUNT

2003 UNDEFINED

2003 - Remove and replace

FFP

:Remove and replace existing with new commercial manufacture standards or

UNIT UNIT PRICE MAX AMOUNT

2003AA 44 Cubic

2003AA - Drop inlets

:Remove and replace existing drop inlets in asphalt and concrete roads.

UNIT UNIT PRICE MAX AMOUNT

2003AB 114 Cubic

2003AB - Curb drop inlets

:Remove and replace existing curb drop inlets in asphalt concrete roads.

UNIT UNIT PRICE MAX AMOUNT

2003AC 9 Cubic

2003AC - Manhole

:Remove and replace existing manhole in asphalt and concrete roads.

UNIT UNIT PRICE MAX AMOUNT

2003AD 35 Cubic

2003AD - Drop inlets (grassy areas)

:Remove and replace existing drop inlets. (To be used in grassy areas).

UNIT UNIT PRICE MAX AMOUNT

2003AE 35 Cubic

2003AE - Manhole (grassy areas)

:Remove and replace existing manhole. (To be used in grassy areas).

UNIT UNIT PRICE MAX AMOUNT

2003AF 35 Cubic

2003AF - Provide new commercial

:Provide new commercial manufacturer's standard pre-cast concrete manhole, or cast-in-place concrete manhole. (To be used in grassy areas).

UNIT UNIT PRICE MAX AMOUNT

2004 UNDEFINED

2004 - Remove and replace existing storm

FFP

:Remove and replace existing storm drainage pipe with concrete pipe under unpaved areas. Replacement work includes excavations, bedding material, UNIT UNIT PRICE MAX AMOUNT

2004AA 174 Linear

2004AA - 12" - 18" diameter pipe

:12" to 18" diameter pipe

UNIT UNIT PRICE MAX AMOUNT

2004AB 119 Linear

2004AB - 21" - 36" diameter pipe

:21" to 36" diameter pipe

UNIT UNIT PRICE MAX AMOUNT

2005 UNDEFINED

2005 - Remove and replace existing concr

FFP

:Remove and replace existing concrete structures. Work shall include excavations, formwork, reinforcement, aggregate base material, compactions, installing vapor barrier, placing concrete and finishing, asphalt and concrete

UNIT UNIT PRICE MAX AMOUNT

2005AA 218 Cubic

2005AA - Stairs with handrail inserts

:Stairs with handrail inserts

UNIT UNIT PRICE MAX AMOUNT

2005AB 131 Cubic

2005AB - Stairs without handrail inserts

:Stairs without handrail inserts

UNIT UNIT PRICE MAX AMOUNT

2005AC 272 Cubic

2005AC - Reinforced slabs up to 6" thick

:Reinforced slabs up to 6" thick

UNIT UNIT PRICE MAX AMOUNT

2005AD 455 Cubic

2005AD - Reinforced slabs 8"-12" thick

:Reinforced slabs 8"-12" thick

UNIT UNIT PRICE MAX AMOUNT

2005AE 9 Each 2005AE - Mailbox pads 4'x4'x4'

FFP

:Mailbox pads 4'x 4'x 4'

UNIT UNIT PRICE MAX AMOUNT

2005AF 179 Cubic

2005AF - Handicap ramps

:Handicap ramps

UNIT UNIT PRICE MAX AMOUNT

2005AG 39 Each 2005AG - curb handicap ramps

FFP

:Curb handicap ramps with raised block exposed aggregate surface (See plate #8).

UNIT UNIT PRICE MAX AMOUNT

2005AH 87 Cubic

2005AH - Headwalls or endwalls

:Headwalls or endwalls

UNIT UNIT PRICE MAX AMOUNT

2006 UNDEFINED

2006 - Construct various types of handra

UNIT UNIT PRICE MAX AMOUNT

2006AA 174 Linear

2006AA - Pipe railing (see plate #6)

:Pipe railing (See plate #6).

UNIT UNIT PRICE MAX AMOUNT

2006AB 87 Linear

2006AB - Wrought iron railing (See plate

:Wrought iron railing (See plate #7).

UNIT UNIT PRICE MAX AMOUNT

2006AC 44 Linear

2006AC - Aluminum bar railing

:Aluminum bar railing (See plate #7).

UNIT UNIT PRICE MAX AMOUNT

2007 UNDEFINED

2007 - Demo and removal

FFP

:Demolition and removal of existing wood, concrete, and masonry structures.

UNIT UNIT PRICE MAX AMOUNT

2007AA 153 Cubic

2007AA - Reinforced concrete

:Reinforced concrete

UNIT UNIT PRICE MAX AMOUNT

2007AB 2,040 Cubic

2007AB - Plain concrete

:Plain concrete

UNIT UNIT PRICE MAX AMOUNT

2007AC 8,710 Square

2007AC - Demo existing masonry

:Demolish existing masonry building, backfill, and grade to existing conditions, seed, and straw

UNIT UNIT PRICE MAX AMOUNT

2007AD 8,710 Square

2007AD - Demo existing wood bldg

:Demolish existing wood building, backfill and grade to existing conditions, seed, and straw

UNIT UNIT PRICE MAX AMOUNT

2008 1,505 Cubic

2008 - Concrete Work removal

:Concrete Work Removal. Remove existing unsuitable base material, replace with a stabilized aggregate base course, and compact in place.

UNIT UNIT PRICE MAX AMOUNT

2009 4,036 Cubic

2009 - Concrete Work Remove

:Concrete Work Remove unsuitable sub-base. Remove existing unsuitable sub-base material, replace with a stabilized aggregate base course, and compact in place.

UNIT UNIT PRICE MAX AMOUNT

2010 3,757 Cubic

2010 - Concrete - Regrade

:Concrete - Regrade. Regrade the existing landscape to provide the proper drainage.

UNIT UNIT PRICE MAX AMOUNT

2011 3,040 Cubic

2011 - Concrete Work - Backfill

:Concrete Work - Backfill. Backfill area with select material to grade. The material shall be #57, #21A etc. as indicated on the Delivery Order. (Place 2" topsoil and seed at grassy area).

UNIT UNIT PRICE MAX AMOUNT

2012 1,359 Cubic

2012 - concrete Work - Excavate

:Concrete Work - Excavate. Excavate existing surface, including turf, pavement sections, concrete slabs, structures, etc. Backfill with select material to grade.

Place 2" topsoil, fine grade, and seed.

UNIT UNIT PRICE MAX AMOUNT

2013 2,830 Square

2013 - Concrete Work - Sodding

:Concrete Work - Sodding. Provide sodding in lieu of seeding.

UNIT UNIT PRICE MAX AMOUNT

2014 UNDEFINED

2014 - Demo and Removal

FFP

:Demolition and…