This is a Standard Form 30 (SF 30) amendment to a solicitation for the San Jose MEPS Partition Wall Installation project. The amendment was issued on March 18, 2026, by the U.S. Army Corps of Engineers, Fort Knox, Kentucky (W96QM MICC-FT KNOX KO DIRECTORATE OF CONTRACTING). The solicitation number is W9124D26QA078, originally dated March 13, 2026. The amendment does not extend the offer due date and requires offerors to acknowledge receipt of the amendment prior to the deadline through one of three methods: completing items 8 and 15 and returning copies, acknowledging receipt on each copy of the offer submitted, or submitting a separate letter or electronic communication referencing the solicitation and amendment numbers.

The primary change contained in this amendment is the addition of FAR Clause 52.212-4, Terms and Conditions – Commercial Products and Commercial Services (with a deviation), effective February 2026. All other terms and conditions of the Request for Proposal (RTOP) remain unchanged. The amendment also includes the Q&A history, noting that the government will not provide probable cost estimates as doing so would compromise solicitation integrity, site visits will not be conducted (with floor plans and designs available in the Statement of Work), and the bid due date and material delivery schedule are specified in the respective solicitation documents. The contracting officer is John P. Haarala, dated March 19, 2026.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.

If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Block 14 (Description of Amendment/Modification):

San Jose MEPS Partition Wall Installation RTOP List of Changes:

1. Added: Clause FAR 52.212-4 Terms and Conditions - Commercial Products and Commercial Services.

2. All other terms and conditions of this RTOP remain unchanged.

(End of San Jose MEPS Partition Wall Installation RTOP List of Changes)

San Jose MEPS Partition Wall Installation List of Questions Received with Answers:

1. Question: Would it be possible to get the opinion of probable cost for the subject solicitation?

a. Answer: Providing an opinion on a probable cost is not permissible, as it would violate the integrity and fairness of the solicitation.

2. Question: When is your bid due and when is material needed on site?

a. Answer: Please read Block 8-Offer Due Date/Local Time. Please read page 6 Continuation of Deliveries or Performance-Delivery Schedule

3. Question: I am interested in bidding on this project, may you advice on walk through date?

a. Answer: No site visit will be conducted. Please read the Statement of Work (SOW). You will also find the floor plan design and front view within the SOW.

(End of San Jose MEPS Partition Wall Installation List of Questions Received with Answers)

(End of Block 14 Continuation)

Contract Clauses

Additional Information/Notes

The following clauses were added:

FAR Clauses Incorporated by Reference Number Title Effective Date Alternate/

Deviation Variation Effective

W9124D26QA0780001

Date 52.212-4 Terms and Conditions-Commercial Products and Commercial Services. (Deviation) Feb 2026

W9124D26QA0780001

IDCode: J
Page: 1
Pages: 3
AmendNo: 0001
EffDate: 18 MAR 2026
ReqNo:
ProjNo:
IssCode: W9124D
AdmCode:
IssuedBy: W6QM MICC-FT KNOX

KO DIRECTORATE OF CONTRACTIN, BLDG 1109B RM 250

FORT KNOX, KY 40121-5000

UNITED STATES

TARA GLASS, EMAIL: TARA.E.GLASS.CIV@ARMY.MIL TELEPHONE: 502-624-1456

AdminBy:

SCD: PAS:

ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: W9124D26QA078
SolDate: 13 MAR 2026
AwardChg: Off
AwardNo:
AwardDate:
Amended: 1
OffrExt: Off
OffrNoEx: 1
NoCopies: 1
ApprData: SEE CONTINUATION
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: See Schedule
ContNameTitle:
CoNameTitle: JOHN P. HAARALA
ContDate:
CODate: 19 MAR 2026

File details come from the government source that posted it. Updated .