J14 Bldg. 51424 Floor Plan.pdf
PDF 334 KB Posted
- Attached to
- Renovation BLDGs. 51424 and 51428
- Solicitation number
- W9124A23R0018
About this file
This document outlines renovation requirements for Building 51424 at Fort Huachuca and the related federal contract opportunity. The building renovation priorities include installing new VCT tiles, making the server room habitable with CRAC unit and conduit access, installing mini-split AC units, power pedestals, drop ceilings, LED lighting, data and communication lines, security lights, painting interior and exterior, lightning protection system, replacing exterior doors, repairing walls, replacing window panels with block and blast resistant glass, cleaning and applying epoxy to concrete floors, and renovating the latrine. The related federal contract opportunity is solicitation number W9124A23R0018 from the Department of the Army Materiel Command Army Contracting Command Aberdeen Proving Ground for the renovation of Buildings 51424 and 51428 at Fort Huachuca.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Ft. Huachuca – Bldg. 51424
Priorities:
Floors need new VCT Tiles in all rooms besides the vehicle bay and mech room.
Server room needs to be made habitable and conduit access to C2 vehicle and nodes.
Server room needs Computer Room Air Conditioning (CRAC) Unit.
Install Mini-Split AC units for Rm 1, Rm 2, & Rm 3.
Power Pedestals needed for all bays.
Install need drop ceiling tiles & LED lighting in Rm1 & Rm 2.
Rm 1, Rm 2 & Rm 3 each require 4 data and 4 comm lines.
Server Rm & Equipment Rm require 2 data and 2 comm lines each.
Install security lights on the exterior of the building.
Paint entire building (interior and exterior).
Install lightning protection/grounding system.
Replace exterior doors.
Repair/patch walls as needed to support remove of the mold.
Remove top three rows of window panels and replace w/ block. Replace bottom three rows w/blast resistant glass panels
Office Rm 1
Office Rm 2
Office Rm 3
Clean all concrete floors and apply epoxy paint.
Renovate latrine as indicated in the above drawing.
Install new wall with door as indicated in the above drawing.
File details come from the government source that posted it. Updated .