Supplies Service Section SF 1449 - CONTINUATION SHEET
| ITEM NO | SUPPLIES/SERVICES | QUANTITY | UNIT | UNIT PRICE | AMOUNT |
| 0001 | | | | | |
| 12 | Month | | | |
| Washer and Dryer Service | | | | |
| FFP | | | | |
| The Contractor shall furnish all labor, equipment, tools, transportation, supervision and any other items necessary to provide maintenance and repairs of Government owned washers and dryers identified in Technical Exhibit 1 in accordance with the Performance Work Statement and manufacture maintenance guidelines. | | | | |
| FOB: Destination |
| PSC CD: J072 |
| ITEM NO | SUPPLIES/SERVICES | QUANTITY | UNIT | UNIT PRICE | AMOUNT |
| 0002 | | 12 | Months | | |
| Other Direct Costs (ODC) | | | | |
| FFP | | | | |
| Contractor shall provide all supplies and materials necessary to repair/ replace/maintain washer and dryers. The Contractor shall not charge any labor, work tools nor any profit on this CLIN. The Contractor shall NOT separately price the mentioned CLINs. The Contractor shall use the plug figures provided by the Government. The supplies and materials CLIN’s are Cost Reimbursement type CLIN’s and as such the Government will reimburse the contractor for actual costs for all supplies/ materials used in support of the maintenance and repair of washer and dryers IAW the PWS (2.1.11.1.8). This CLIN is Not To Exceed (NTE) | | | | |
$45,000.00.
| FOB: Destination |
| PSC CD: J072 |
| ITEM NO | SUPPLIES/SERVICES | QUANTITY | UNIT | UNIT PRICE | AMOUNT |
| 1001 | | | | | |
| OPTION | | 12 | Months | | | |
| | Washer and Dryer Service | | | | |
| | FFP | | | | |
| | The Contractor shall furnish all labor, equipment, tools, transportation, supervision and any other items necessary to provide maintenance and repairs of Government owned washers and dryers identified in Technical Exhibit 1 in accordance with the Performance Work Statement and manufacture maintenance guidelines. | | | | |
| FOB: Destination | $0.00 |
| PSC CD:J072 | |
| ITEM NO | SUPPLIES/SERVICES | QUANTITY | UNIT | UNIT PRICE | AMOUNT |
| 1002 | | 12 | Months | | |
| Other Direct Costs (ODC) | | | | |
| FFP | | | | |
| Contractor shall provide Engineering Technicians support services to provide | | | | |
Project Definition Code 3 Design with Parametric Estimating Architect-Engineer and Construction Contract Documents for Fort Bragg Directorate of Public Works (DPW) in strict compliance with all specifications, Federal Regulations, NC State Codes, Fort Bragg Installation Design Guide (IDG), terms and conditions, and all other provisions contained herein in accordance with the Performance Work Statement (PWS).
| FOB: Destination |
| PSC CD: J072 |
| ITEM NO | SUPPLIES/SERVICES | QUANTITY | UNIT | UNIT PRICE | AMOUNT |
| 2001 | | | | | |
| 12 | Month | | | |
| Washer and Dryer Service | | | | |
| FFP | | | | |
| The Contractor shall furnish all labor, equipment, tools, transportation, supervision and any other items necessary to provide maintenance and repairs of Government owned washers and dryers identified in Technical Exhibit 1 in accordance with the Performance Work Statement and manufacture maintenance guidelines. | | | | |
| FOB: Destination |
| PSC CD: J072 |
| ITEM NO | SUPPLIES/SERVICES | QUANTITY | UNIT | UNIT PRICE | AMOUNT |
| 2002 | | 12 | Months | | |
| Other Direct Costs (ODC) | | | | |
| FFP | | | | |
| Contractor shall provide all supplies and materials necessary to repair/ replace/maintain washer and dryers. The Contractor shall not charge any labor, work tools nor any profit on this CLIN. The Contractor shall NOT separately price the mentioned CLINs. The Contractor shall use the plug figures provided by the Government. The supplies and materials CLIN’s are Cost Reimbursement type CLIN’s and as such the Government will reimburse the contractor for actual costs for all supplies/ materials used in support of the maintenance and repair of washer and dryers IAW the PWS (2.1.11.1.8). This CLIN is Not To Exceed (NTE) | | | | |
$45,000.00.
| FOB: Destination |
| PSC CD: J072 |
| ITEM NO | SUPPLIES/SERVICES | QUANTITY | UNIT | UNIT PRICE | AMOUNT |
| 3001 | | | | | |
| OPTION | | 12 | Months | | | |
| | Washer and Dryer Service | | | | |
| | FFP | | | | |
| | The Contractor shall furnish all labor, equipment, tools, transportation, supervision and any other items necessary to provide maintenance and repairs of Government owned washers and dryers identified in Technical Exhibit 1 in accordance with the Performance Work Statement and manufacture maintenance guidelines. | | | | |
| FOB: Destination | $0.00 |
| PSC CD:J072 | |
| ITEM NO | SUPPLIES/SERVICES | QUANTITY | UNIT | UNIT PRICE | AMOUNT |
| 3002 | | 12 | Months | | |
| Other Direct Costs (ODC) | | | | |
| FFP | | | | |
| Contractor shall provide Engineering Technicians support services to provide | | | | |
Project Definition Code 3 Design with Parametric Estimating Architect-Engineer and Construction Contract Documents for Fort Bragg Directorate of Public Works (DPW) in strict compliance with all specifications, Federal Regulations, NC State Codes, Fort Bragg Installation Design Guide (IDG), terms and conditions, and all other provisions contained herein in accordance with the Performance Work Statement (PWS).
| FOB: Destination |
| PSC CD: J072 |
| ITEM NO | SUPPLIES/SERVICES | QUANTITY | UNIT | UNIT PRICE | AMOUNT |
| 4001 | | | | | |
| OPTION | | 12 | Months | | | |
| | Washer and Dryer Service | | | | |
| | FFP | | | | |
| | The Contractor shall furnish all labor, equipment, tools, transportation, supervision and any other items necessary to provide maintenance and repairs of Government owned washers and dryers identified in Technical Exhibit 1 in accordance with the Performance Work Statement and manufacture maintenance guidelines. | | | | |
| FOB: Destination | $0.00 |
| PSC CD:J072 | |
| ITEM NO | SUPPLIES/SERVICES | QUANTITY | UNIT | UNIT PRICE | AMOUNT |
| 4002 | | 12 | Months | | |
| Other Direct Costs (ODC) | | | | |
| FFP | | | | |
| Contractor shall provide Engineering Technicians support services to provide | | | | |
Project Definition Code 3 Design with Parametric Estimating Architect-Engineer and Construction Contract Documents for Fort Bragg Directorate of Public Works (DPW) in strict compliance with all specifications, Federal Regulations, NC State Codes, Fort Bragg Installation Design Guide (IDG), terms and conditions, and all other provisions contained herein in accordance with the Performance Work Statement (PWS).
| FOB: Destination |
| PSC CD: J072 |
Roll Up Direct Labor Rate and Total Price - Base Year Fringe % OH % G&A % Fee 11/01/2022 thru 10/31/2023
| Pos # | E/NE | CLIN | | Position | Labor Category | SCA Code | Prod Hours | Salary Rate | 0.00% | 0.00% | 0.00% | 0.00% | FFP Rate | FTE | Hours | Total Labor Price | Total Price |
| 1 | | 0001 | Ft Bragg | | | | | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | | | $0.00 | $0.00 |
| 2 | | 0001 | Ft Bragg | | | | | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | | | $0.00 | |
| 3 | | 0001 | Ft Bragg | | | | | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | | | $0.00 | |
| 4 | | 0001 | Ft Bragg | | | | | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | | | $0.00 | |
| 5 | | 0001 | Ft Bragg | | | | | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | | | $0.00 | |
| Total Salary | Total Fringe | Total OH | Total G&A | Total Fee | Total Labor Price | |
| $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $0.00 | |
| | | | | | ODC |
Direct Labor Rate and Total Price - Option Period I Fringe % OH % G&A % Fee 11/01/2023 thru 10/31/2024
| Pos # | E/NE | CLIN | | Position | Labor Category | SCA Code | Prod Hours | Salary Rate | 0.00% | 0.00% | 0.00% | 0.00% | FFP Rate | FTE | Hours | Total Labor Price | Total Price |
| 1 | 0 | 1001 | Ft Bragg | 0 | 0 | 0 | 0 | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | 0.00 | | $0.00 | $0.00 |
| 2 | 0 | 1001 | Ft Bragg | 0 | 0 | 0 | 0 | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | 0.00 | | $0.00 | |
| 3 | 0 | 1001 | Ft Bragg | 0 | 0 | 0 | 0 | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | 0.00 | | $0.00 | |
| 4 | 0 | 1001 | Ft Bragg | 0 | 0 | 0 | 0 | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | 0.00 | | $0.00 | |
| 5 | 0 | 1001 | Ft Bragg | 0 | 0 | 0 | 0 | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | 0.00 | | $0.00 | |
| Total Salary | Total Fringe | Total OH | Total G&A | Total Fee | Total Labor Price | |
| $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $0.00 | |
| | | | | | ODC |
Direct Labor Rate and Total Price - Option Period II Fringe % OH % G&A % Fee 11/01/2024 thru 10/31/2025
| Pos # | E/NE | CLIN | | Position | Labor Category | SCA Code | Prod Hours | Salary Rate | 0.00% | 0.00% | 0.00% | 0.00% | FFP Rate | FTE | Hours | Total Labor Price | Total Price |
| 1 | 0 | 2001 | Ft Bragg | 0 | 0 | 0 | 0 | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | 0.00 | | $0.00 | $0.00 |
| 2 | 0 | 2001 | Ft Bragg | 0 | 0 | 0 | 0 | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | 0.00 | | $0.00 | |
| 3 | 0 | 2001 | Ft Bragg | 0 | 0 | 0 | 0 | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | 0.00 | | $0.00 | |
| 4 | 0 | 2001 | Ft Bragg | 0 | 0 | 0 | 0 | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | 0.00 | | $0.00 | |
| 5 | 0 | 2001 | Ft Bragg | 0 | 0 | 0 | 0 | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | 0.00 | | $0.00 | |
| Total Salary | Total Fringe | Total OH | Total G&A | Total Fee | Total Labor Price | |
| $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $0.00 | |
| | | | | | ODC |
Direct Labor Rate and Total Price - Option Period III Fringe % OH % G&A % Fee 11/01/2025 thru 10/31/2026
| Pos # | E/NE | CLIN | | Position | Labor Category | SCA Code | Prod Hours | Salary Rate | 0.00% | 0.00% | 0.00% | 0.00% | FFP Rate | FTE | Hours | Total Labor Price | Total Price |
| 1 | 0 | 3001 | Ft Bragg | 0 | 0 | 0 | 0 | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | 0.00 | 1,864 | $0.00 | $0.00 |
| 2 | 0 | 3001 | Ft Bragg | 0 | 0 | 0 | 0 | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | 0.00 | 1,864 | $0.00 | |
| 3 | 0 | 3001 | Ft Bragg | 0 | 0 | 0 | 0 | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | 0.00 | 1,864 | $0.00 | |
| 4 | 0 | 3001 | Ft Bragg | 0 | 0 | 0 | 0 | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | 0.00 | 1,864 | $0.00 | |
| 5 | 0 | 3001 | Ft Bragg | 0 | 0 | 0 | 0 | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | 0.00 | 1,864 | $0.00 | |
| Total Salary | Total Fringe | Total OH | Total G&A | Total Fee | Total Labor Price | |
| $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $0.00 | |
| | | | | | ODC |
Direct Labor Rate and Total Price - Option Period IV Fringe % OH % G&A % Fee 11/01/2025 thru 10/31/2026
| Pos # | E/NE | CLIN | | Position | Labor Category | SCA Code | Prod Hours | Salary Rate | 0.00% | 0.00% | 0.00% | 0.00% | FFP Rate | FTE | Hours | Total Labor Price | Total Price |
| 1 | 0 | 4001 | Ft Bragg | 0 | 0 | 0 | 0 | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | 0.00 | 1,864 | $0.00 | ERROR:#VALUE! |
| 2 | E/NE | 4001 | 0 | 0 | Labor Category | SCA Code | Prod Hours | | $0.00 | $0.00 | $0.00 | $0.00 | FFP Rate | FTE | 1,864 | ERROR:#VALUE! | |
| 3 | 0 | 4001 | Ft Bragg | 0 | 0 | 0 | 0 | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | 0.00 | 1,864 | $0.00 | |
| 4 | 0 | 4001 | Ft Bragg | 0 | 0 | 0 | 0 | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | 0.00 | 1,864 | $0.00 | |
| 5 | 0 | 4001 | Ft Bragg | 0 | 0 | 0 | 0 | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | 0.00 | 1,864 | $0.00 | |
| Total Salary | Total Fringe | Total OH | Total G&A | Total Fee | Total Labor Price | |
| $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $0.00 | |
| | | | | | ODC |
| Firm Name | |
| Inflation | 0.00% |
| Productive Man Year | 0 |
| H&W | $4.22 |
| Exempt Healthcare | $0.00 |
| Exempt Retirement | 0.00% |
| SUTA | $0.00 |
| Workman's Comp | 0.00% |
| Firm Overhead Rate | 0.00% |
| Frim G&A Rate | 0.00% |
| Firm Fee | 0.00% |