W91247-17-Q-0002_Attachment3Questions_and_Government_Responses.pdf
PDF 49 KB Posted
- Attached to
- Construct Picnic Shed
- Solicitation number
- W91247-17-Q-0002
About this file
Attachment 03 - Government Answers
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W91247-17-Q-0002_Amendment03,_FINAL.pdf | ||
| W91247-17-Q-0002,_Amendment_02.pdf | ||
| W91247-17-Q-0002_Attachment2-SiteMap.pptx | PPTX presentation | |
| W91247-17-Q-0002,_Amendment_01_FINAL.pdf | ||
| W91247-17-Q-0002,_attachment_1-Shelters_OPHD_Viewshed.jpg | JPG image | |
| W91247-17-Q-0002,_FINAL.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Government Responses
1) “Can you tell me if/when the site visit attendee sign‐in sheet will be posted on FBO?”
Government Response: In effort not to broadcast contact information, contractor’s may visit MICC Center – FB and a hard copy will be provided.
2) “Is this solicitation just for disable veterans or for disable veterans and veteran owned businesses?” Government Response: As specified in Section ‘M’ of the solicitation [extract]:
“Award will be made to the lowest price quote who has been determined to be responsible. The quoter shall be a registered in System for Award Management (SAM) certified SDVOSB Small Business Concern whose price and past performance represents the best overall value to the Government.
3) “When will the construction performance meeting be held, couldn’t find it on any documents?”
Government Response: As specified in FAR 52.236‐26, Preconstruction Conference, will be scheduled prior to construction.
4) “Is it possible to come by on my own?” Government Response: The site location is not in a secure area and in open to the public.
5) "All column shall be anchored to concrete footing. Columns can be surface mounted to footings with anchor bolts at or below finish slab elevation or they can be embedded directly into the flooding without base plates is the finished slab already in place?” If not, what will be required?
Government Response: The picnic shed construction limits are located in an asphalt area. The contractor shall saw‐cut the asphalt and place concrete able to support the column members.
All work shall be in strict compliance with local, state, and federal regulations.