This is a Questions and Answers document for federal contract solicitation W9123826BQA031 regarding the New Hogan Restroom Replacement project. The Q&A clarifies requirements in the associated Performance Work Statement for a prefabricated concrete restroom/shower building with installation services. No bid bond is required for this Supply with Installation (Service) type contract, and no engineering estimate has been provided.

The project requires a prefabricated concrete restroom building with a 20 feet by 30 feet footprint containing four unisex restroom/shower combinations, each with a minimum of six exhaust fans. The utility/maintenance chase shall not exceed 104 square feet. Key specifications include stainless steel plumbing fixtures throughout, four 2'–4"×10" double-pane windows, and four skylights for natural lighting. The contractor is responsible for selecting and furnishing the building that meets PWS requirements, providing a cast-in-place reinforced concrete foundation, connecting all utilities to the existing footprint, establishing proper site drainage and grading, and managing delivery and crane placement. Construction must be completed between September and March 31st to accommodate the open campground. No temporary facilities, ADA improvements, or bid/performance/payment bonds are required. Permits are the contractor's responsibility if required. The government will provide water and initial electrical access for demolition; the contractor must furnish additional power if needed post-demolition. Product approval for equivalent items occurs after award. Warranty begins the day after final government acceptance and runs for a minimum of one year.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers (Q&A)

New Hogan Restroom Replacement

W9123826BQA031

Question 1 (Q1): Please confirm whether Solicitation W9123826QA031 requires a bid bond with the quote or performance and payment bonds after award. We did not identify a specific bonding requirement in the current solicitation and want to confirm before proceeding with pricing.

Answer 1 (A): The bonding requirement was not included in solicitation because it is not required for this Supply with Installation (Service) type contract.

Q2: Is there an engineers estimate for this project?

A2: There is no engineering estimate to state a contract Magnitude value range statement, because this is a Service contract.

Q3: Prefabricated Restroom Building Please provide the basis-of-design manufacturer/model, floor plan, or approved equivalent for the required prefabricated concrete restroom/shower building. If no specific manufacturer/model is required, please confirm that the Contractor is responsible for selecting and furnishing a building that meets the Performance Work Statement (PWS).

Please also clarify whether the stated 26 ft x 30 ft footprint is an approximate size, maximum size, or required footprint, and whether the minimum of four individual unisex restroom/shower combinations is the exact configuration required for bidding.

A3: Yes, contractor is responsible for selecting and furnishing building that meets PWS requirements. The 20X30 is the required footprint with 4 unisex bathrooms per PWS paragraph

3. Prefabricated Concrete Cast Waterborne Restroom

Q4: Utility / Maintenance Chase Size The PWS states that the building shall contain a utility/maintenance access chase "not to exceed 1,000 square feet." Please confirm whether the 1,000-square-foot limitation applies specifically to the utility chase or whether it was intended to reference the overall building size.

A4: Pipe chase shall not exceed 104 Square Feet. For measurements refer to the attachment titled Referenced Conceptual Drawings and see revised PWS section II. SCOPE OF WORK, paragraph 3. Prefabricated Concrete Cast Waterborne Restroom.

Q5 Exhaust Fan Quantity The PWS states: "Each unisex restroom/shower combo shall have a minimum of six (4) exhaust fans." Please confirm whether the required quantity is four or six, and whether that quantity is required per restroom/shower combination or for the building as a whole.

A5: See PWS Section II paragraph 13. h. iii. Prefabricated Concrete Cast Waterborne Restroom:

Each unisex restroom/shower combo shall have a minimum of six (6) exhaust fans. This is six

(6) per restroom/shower combo.

Q6: New Concrete Foundation / Pad Design Please provide the required design criteria for the approximately 27 ft x 33 ft concrete structural pad/foundation, including slab thickness, concrete compressive strength, reinforcing steel size and spacing, footing or thickened-edge requirements, aggregate base thickness, subgrade preparation, compaction requirements/testing, vapor barrier requirements (if applicable), finished floor elevation, and drainage requirements.

Please confirm whether the Government will provide the foundation design or whether the Contractor/prefabricated building manufacturer is responsible for providing engineered and stamped foundation drawings. The PWS refers to a "prefabricated concrete structural pad."

Please clarify whether the foundation/pad itself is required to be prefabricated, or whether the Contractor may construct a conventional cast-in-place reinforced concrete slab/foundation onsite, provided it is engineered to support the selected prefabricated restroom building and complies with all applicable codes and manufacturer requirements.

If cast-in-place construction is permitted, please confirm that it may be proposed as a cost-saving alternative without affecting technical acceptability.

A6: Contractor shall provide a prefabricated conventional cast-in-place reinforced concrete slab/foundation onsite, that is engineered to support the selected prefabricated restroom building and complies with all applicable codes and manufacturer requirements. See revised PWS section II. SCOPE OF WORK. Paragraph 2. Prefabricated concrete pad.

Q7: Geotechnical / Soils Information

Is a geotechnical or soils report available for the proposed building location? If no report is available, please provide the required design bearing pressure or confirm the assumptions bidders should use for foundation design and subgrade preparation.

A7: Please refer to CA State Building requirements in Chapter 18 for design and subgrade preparation.

Q8: Existing Building Foundation Demolition Please confirm the limits of demolition for the existing restroom. Specifically, is the entire existing slab and foundation to be removed, including all footings? Please identify whether any existing exterior concrete sidewalks/entrance slabs may remain and whether existing underground utility stubs are intended to remain for reconnection.

A8:The entire existing slab and foundation shall be removed. The sidewalks shall remain in place along with any entrance areas that won’t affect the removal of the old building. Existing underground utility stubs will remain and be used for reconnection; however, the contractor shall notify the COR if reconnection of utilities are identified as needing repair and will be addressed via negotiated modification issued by the Contracting Officer prior to additional work being performed. See revised PWS section II. SCOPE OF WORK, paragraph 3. Prefabricated Concrete Cast Waterborne Restroom.

Q9: Hazardous Materials Has the existing restroom been surveyed or tested for asbestos-containing materials, lead-containing paint, or other hazardous materials? If hazardous materials are encountered during demolition, please confirm whether abatement/remediation will be performed by the Government or treated as additional/change-order work rather than being included in the Contractor's base bid.

A9: No known Hazardous Materials are expected on this site, however the contractor is required to test materials to dispose of properly. If Haz Mat is discovered, the contractor shall notify the COR and this will be addressed via negotiated modification issued by the Contracting Officer prior to additional work being performed. See revised PWS section I. GENERAL, paragraph 11.

Contractor Responsibilities.

Q10: Existing Sewer Connection

Please provide available information regarding the existing sanitary sewer serving the restroom, including pipe size, material, depth, invert elevation, connection location, direction of flow, and available capacity. Please confirm whether the Contractor is expected to reuse the existing sewer connection and whether any sewer improvements beyond the immediate connection to the new building are included in the scope.

A10: Sewer connections are required, as these are waterborne restrooms, with showers and flushable toilets. Sewer connection will be required by Contractor. If connection sites are deemed in need of repair, the Contractor will notify and coordinate with the COR and this will be addressed via negotiated modification issued by the Contracting Officer prior to additional work being performed. See PWS section II. SCOPE OF WORK, paragraph 3. Prefabricated Concrete Cast Waterborne Restroom.

Q11: Existing Domestic Water Service Please provide available information regarding the existing domestic water service, including pipe size, material, depth, connection location, available pressure/flow, and system capacity.

Please confirm whether the existing service has been verified as adequate to serve the new building, including simultaneous use of the required restroom and shower fixtures.

A11: Water lines are able to withstand the system capacity because that is currently what is used now. Pipes size, material, depth, connection location will all be confirmed on site after demolition occurs. See PWS section II. SCOPE OF WORK, paragraph 3. Prefabricated Concrete Cast Waterborne Restroom.

Q12: Existing Electrical Service Please confirm the existing electrical service voltage, phase, amperage, feeder size, service location, and available capacity. The new building is specified to have single-phase 240-volt service with a 200-amp panel, along with two 80-gallon electric water heaters, hand dryers, exhaust fans, lighting, and other electrical loads.

Please confirm whether the existing electrical service has sufficient capacity for the new building. If it does not, please clarify whether the Contractor is responsible for upgrades to the existing feeder, service, transformer, meter, distribution equipment, or other upstream electrical infrastructure.

A12: Voltage is 480 currently that is phased down to 240V. There is sufficient electrical capacity for the new building. See PWS section II. SCOPE OF WORK paragraph h. Electrical/Electrical Service.

Q13: Existing Utility As-Builts Are existing utility drawings or as-built plans available showing water, sewer, and electrical services serving the current restroom? If available, please provide them to bidders.

A13: As-Builts are not available.

Q14: Utility Relocation / Tie-In Limits Please define the Contractor's limits of responsibility for existing utility modifications. Does the base bid include only connecting the new restroom to existing utility stubs within or adjacent to the existing building footprint, or is the Contractor responsible for relocating/extending utilities from whatever location is necessary to serve the new building?

A14:The contractor is responsible for connecting the new restroom and all of it’s utilities to the existing footprint. Contractor will have the responsibility to meet current connection site location. See PWS section II. SCOPE OF WORK

Q15: Exterior ADA Improvements Please define the limits of required exterior ADA work. Please confirm whether the Contractor's scope includes ADA parking stalls, access aisles, accessible pathways, new sidewalks, concrete landings, ramps, curb ramps, site grading, exterior ADA signage, or other modifications necessary to connect the new building to an existing accessible route. If exterior ADA improvements are required, please provide plans or clearly defined limits of work.

A15: There are no ADA improvements required.

Q16: Exterior Concrete Restoration Please clarify what exterior concrete is required following demolition and installation. Should the Contractor replace existing entrance sidewalks, concrete immediately surrounding the building, accessible landings, and concrete disturbed by utility trenching? Please provide required dimensions and limits where applicable.

A16: Contractor to repair what they have damaged during trenching operations. See revised PWS section II. SCOPE OF WORK, paragraph 3. Prefabricated Concrete Cast Waterborne Restroom.

Q17: Site Grading and Drainage Please provide the required finished floor elevation and grading criteria for the new building.

Please confirm whether the Contractor is responsible for importing/exporting soil, establishing positive drainage, constructing swales, installing storm drains or other drainage improvements, and restoring disturbed areas outside the immediate building pad.

A17: Yes, Contractor is responsible for establishing adequate level elevation and grade appropriately for drainage while coordinating the COR in all possible adjustments to the site area. See revise PWS section I. GENERAL paragraph 11. Contractor Responsibilities.

Q18: Permits and Engineered Drawings Please clarify responsibility for obtaining and paying for building, electrical, plumbing, and grading permits; plan review and inspection fees; engineered structural drawings; architectural drawings; and electrical/plumbing design documents. Please also confirm whether the prefabricated building manufacturer is required to provide California-stamped structural and building plans.

A18: Pre-fabricated building is replacing the current building, no permits should need to be pulled. If permits are required, it is the responsibility of the Contractor to do so. See revise PWS section I. GENERAL paragraph 11. Contractor Responsibilities.

Q19: Building Delivery and Crane Access Please confirm that the Contractor is responsible for crane placement of the prefabricated structure and identify any Government restrictions affecting crane setup, delivery truck access, outrigger placement, staging areas, road weight limits, delivery hours, or temporary road/ground protection.

A19: Yes Contractor is responsible for delivery, Crane work, and all other installation. There are no onsite restrictions. Delivery must be done during business hour and coordinated with COR prior to delivery date. See PWS section I. GENERAL paragraph 11. Contractor Responsibilities.

Q20: Stainless Steel Plumbing Fixtures The PWS states that all plumbing fixtures shall be stainless steel. Please confirm whether this requirement includes toilets, lavatories, drinking fountain, shower assemblies, faucets, floor drains, and hose bibs, as applicable.

A20: All plumbing fixtures shall be stainless steel per PWS section II. SCOPE OF WORK, paragraph 3. Prefabricated Concrete Cast Waterborne Restroom.

Q21: Stainless Steel Windows and Weld Plates Please clarify the requirement for "stainless steel windows and weld plates on each unisex restroom/shower combo." Please provide the required window quantity, dimensions, type, location, and specification/detail for the referenced weld plates.

A21: 4 windows, 2’ – 4”X10” Double Pane Windows. Please refer to the Referenced Conceptual Drawings Attachment location and specific details.

Q22: Skylights Please provide the required number, size, and location of skylights. The PWS currently states only that skylights shall provide adequate natural lighting for the interior.

A22: 4 skylights are required. Please refer to the Referenced Conceptual Drawings Attachment for location.

Q23: Existing Restroom Downtime / Temporary Facilities Please confirm whether temporary restroom and/or shower facilities are required while the existing restroom is demolished and the new building is being installed. If temporary facilities are required, please provide the required quantity, ADA accommodations, servicing frequency, duration, and location.

A23: No temporary facilities are needed.

Q24: Campground Operating Restrictions Please confirm whether Acorn Campground will remain open during construction and identify any seasonal restrictions, blackout dates, restrictions on heavy equipment operation or construction traffic, required pedestrian protection/temporary fencing, and noise restrictions.

A24: The Acorn Campground will remain open. The area where the restroom will be replaced will be closed to public traffic. Construction will need to be completed after labor day through March 31st. Contractor will coordinate with the COR. There is no known restrictions to heavy machinery or equipment. Protection of the area shall be marked with general safety cones, but fencing is not needed. See revised PWS section II SCOPE OF WORK.

Q25: Construction Water and Power Will the Contractor be permitted to use the existing Government water and electrical services for construction activities prior to final utility connections? If not, please confirm that temporary power and construction water are Contractor-furnished.

A25: The Government will be able to provide water. Power will be available during demolition but will have to be reassessed once the demolition of the building has taken place. In the event that power is unavailable, Contractor will need to furnish their own power. See revise PWS section I. GENERAL paragraph 11. Contractor Responsibilities.

Q26: Building / Fixture Product Approval Where the PWS permits colors or products that are "similar," please identify the submittal and approval requirements for proposed equivalents. Please confirm whether equivalent products must be approved prior to bid or may be submitted for approval after award.

A26: Yes, submittal and approval will take place after award.

Q27: Warranty Start Date The PWS requires a minimum one-year warranty. Please confirm whether the warranty period begins at building delivery, substantial completion, final Government acceptance, or beneficial occupancy.

A27: Warranty starts day after final Government Acceptance See revised PWS section II.

SCOPE OF WORK, paragraph 4. Warranty.