Yuba River Gravel Removal
Solicitation number
W9123824Q0047
Issued by

About this file

This document contains the Questions and Answers for the Yuba River Gravel Removal solicitation with Solicitation Number W9123824Q0047. The key details are:

The solicitation is for gravel removal from the Yuba River. There is no incumbent contractor currently performing this work. The Performance Work Statement provides a maximum amount of gravel that could be removed, but no specific quantities are listed. No plans, specifications, or site visit are available for this project, but the work has been completed previously, with approximately 1,500 cubic yards of material removed in 2022 and 2023. The channel is required to be widened to 45 feet and deepened to 5 feet, but the current dimensions are unknown. All questions must be submitted in writing to the Department of the Army Corps of Engineers Engineering District Sacramento by July 9, 2024 at 11:00PM (PDT), and no additional questions will be accepted after this date.

View the file

Other files

File Type Posted
Amendment 0001.pdf PDF
B08 - Solicitation.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Yuba River Gravel Removal Questions and Answers

W9123824Q0047

1. Is there an incumbent contractor currently?

No, there not currently an incumbent contractor performing this work.

2. There are no quantities for gravel removal listed. How are we to bid without any quantities?

Please see the revised PWS, it gives a maximum amount of gravel that could be removed.

3. Is there any plans or specifications?

No, there is only a PWS.

4. Is there a site visit for this project?

No there is not a site visit for this project.

5. Has this been done before, if so, how much gravel was removed?

The work has been completed previously. Approximately 1,500 cubic yards of material removed in 2022 and 2023.

6. Widening the Channel, Channel shall be widened to 45 feet (measured from the face of the dam upstream) and deepened to 5 feet (measured from the crest of the dam to the riverbed). How wide and deep the channel is currently?

The requirements were completed last year however we do not have the exact measurements of how full the channel is currently.