Solicitation W9123824Q0015 Amendment 0001.pdf
PDF 693 KB Posted
- Attached to
- Success Lake Oxidation Ponds Rehabilitation
- Solicitation number
- W9123824Q0015
About this file
This amendment modifies a solicitation for the rehabilitation of Success Lake Oxidation Ponds. The work includes furnishing labor, materials, and equipment to rehabilitate two evaporation ponds, including installing new high-density polyethylene liners with a 10-year warranty. The required response date is extended from January 24, 2024 to January 26, 2024. Offerors must provide pricing, safety plans, and address performance requirements such as coordinating work to minimize impacts to ongoing facility operations. The U.S. Army Corps of Engineers Sacramento District will evaluate proposals and make award.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Responses to submitted questions.pdf | ||
| Solicitation W9123824Q0015.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to:
1. Incorporate an updated Performance Work Statement (PWS)
2. Extend the due date for quotes
No other changes made or implied.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 11
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 17-Jan-2024
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9123824Q0015
X 9B. DATED (SEE ITEM 11)
21-Dec-2023
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
17-Jan-2024
CODE
USACE SACRAMENTO DISTRICT
ATTN: CONTRACTING DIVISION
1325 J STREET
SACRAMENTO CA 95814-2922
W91238 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9123824Q0015
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 1449 - CONTINUATION SHEET
SOLICITATION/CONTRACT FORM
The required response date/time has changed from 24-Jan-2024 11:00 AM to 26-Jan-2024 11:00 AM.
The following have been modified:
PERFORMANCE WORK STATEMENT
Performance Work Statement Rehabilitation of Success Lake Oxidation Ponds
30 August 2023 17 January 2024
1.0 Location: U.S. Army Corps of Engineers, Richard L. Schafer Dam, Success Lake, 29330 Highway 190, Porterville, CA 93257. Site access is off of Highway 190.
2.0 Background: Success Lake has its own self-contained Wastewater Treatment Plant (WWTP) with two side-by-side sewage lagoons/evaporation ponds. These ponds hold the treated effluent water. The existing ponds have been in operation since prior to the 1970s.
The ponds are artificial with very large surface areas designed to efficiently evaporate water by exposure to sunlight and ambient temperatures. There is currently no existing High-Density Polyethylene (HDPE) liner.
3.0 Description: The purpose of this Performance Work Statement (PWS) is to procure contractor services to rehabilitate both evaporation ponds and provide a fully functioning sewage treatment pond system. Evaporation Pond #1 is approximately 200 ft x 205 ft x 8 ft. Evaporation Pond #2 is approximately 150 ft x 200 ft x 8 ft.
3.1 Contractor shall furnish all plant, labor, materials, services, and equipment, etc. to effectuate completion of this project. Material and equipment used shall be rated for the environment in which installed.
a. Contractor is responsible for the test equipment and welding machine(s) needed to install the liners and ensure the evaporative ponds are functioning correctly without any leaks.
b. Inspect/survey site to validate project area and set any required perimeter controls.
3.2 Meet with USACE Contracting Officer Representative (COR) to ascertain a clear understanding of the project guidelines and scope.
a. Prior to commencing work, provide for Government approval a schedule, phased work plan, and or a plan of action on how the project will be executed.
b. Phase Plan: The phase plan should include major milestones i.e., grading, installing underlay, testing, etc. Each phase should be inspected and accepted via signature or email documentation by the COR prior to preceding to the next phase of work.
3.3 Tasks include but are not limited to the following:
a. Pump lagoon water, solids, and effluent from Ponds. Dewater and remove/dispose of sludge from the pond to an offsite location as determined by the contractor. North pond is dry with vegetation. South Pond has effluent in the bottom, but not enough to cover the whole bottom. South pond also has vegetation. There are no reports on the sludge/debris present.
b. Excavate lagoon and grade level. Reshape and compact the pond subgrade and bank slopes with specified materials i.e., concrete, clay, gravel, rock as required by the California Regional Water Quality Control Board (CRWQCB). Embankment layout should stop or minimize the wave action that could erode the banks.
c. Install new underlay liner and 60-millimeter (mm) HDPE top liner. Installed liners shall be smooth, undamaged, and with continuous seam welds.
d. Grade and level traffic areas between the ponds to allow vehicle access for maintenance. A minimum of 10 feet width is required.
e. Coordinate with CRWQCB for permitting requirements.
f. Coordinate with the COR to flood the lagoon immediately after project completion and Government acceptance.
3.4 Provide a Safety Plan and Quality Assurance/Quality Control (QA/QC) Plan for Government review and acceptance. QA/QC plan should address how project performance is implemented to minimize impact to facility operations; and preventative measures to mitigate fugitive dust and noise pollution during operation.
3.5 The Contractor’s Safety Plan and subsequent activities shall comply with the following referenced documents (most current version, if different than the date referenced), at a minimum:
a. EM 385-1-1, USACE Safety & Health Requirements Manual, EM 385-1-1, 30
November 2014 Edition:
http://www.publications.usace.army.mil/Portals/76/Publications/EngineerMan uals/EM_385-1-1.pdf?ver=2015-04-09-142531-467
b. Title 29 Code of Federal Regulations (CFR) 1910, Occupational Safety and Health Standards.
c. 29 CFR 1926.65/29 CFR1910.120, Hazardous Waste Operations and Emergency Response.
d. USACE, Safety and Occupational Health Document Requirements for Hazardous, Toxic and Radioactive Waste (HTRW) Activities, ER 385-1-92 (1 July 2003).
e. NIOSH/OSHA/USCG/EPA, Occupational Safety and Health Guidance Manual for Hazardous Waste Activities (October 1985).
f. Hazard Communication (29 CFR 1910.1200/29 CFR 1926.59/8 CCR Section 5194)
3.6 Provide a Waste Disposal Plan. Include contact information for landfill and/or recycle center.
3.7 Facility will remain fully operational during the project work period. Coordinate work activities with the Government to minimize conflicts, downtime, and interference with the daily facility operations. Work hours are Monday through Friday 7:00 am until 4:30 pm. Modifications to the designated work hours must be approved by the COR.
3.8 Coordinate any shutdown with the COR. Provide a minimum of five-days’ notice before any utility or program system is shutdown or de-energized. Prior to starting restoration repairs, tag out equipment affected by a specific task or work area.
3.9 Warranty: The HDPE, 60 mm liner shall have a minimum 10-year, ultra-violet weathering warranty. Underlay liner shall have a 10-year warranty.
3.10 Liner and Underlay Installation:
a. Contractor shall not cover underlay liner until inspected and accepted by the
COR.
Install all liners (geotextile underlay and HDPE) per the manufacturer’s recommendations and industry standards.
3.11 Testing: Contractor shall pressure test i.e., air, water, etc., commission, and certify the new HDPE of any leaks. Note: Contractor shall be responsible for all tests, any fees associated with third party testing, and inspections performed by the state of California and any other entity.
a. Perform QA testing for all seam welds per ASTM D 6392. Provide third party QA testing for test weld samples.
b. Contractor shall certify in writing that the evaporative pond can support the load of the new coverings, as well as the weight of the coverings and aluminum extrusions used to fasten down the rigid coverings.
3.12 During the course of the project performance period, if the Contractor encounters an unusual situation, Contractor shall document the discovery via pictures and immediately notify the COR before proceeding.
a. Contractor shall keep a photo journal of all work performed during the project performance period. Unless otherwise requested by the Government, provide at a minimum, weekly reports inclusive of photographs with captions that document work progress.
b. Photo journal and logs shall be surrendered to the Government during project closeout.
c. Maintain log of the following:
1. Speed and temperature during installation.
2. Trial weld testing.
3. Destructive or non-destructive testing conducted, location, and results.
4. Labeled panels and location for the as-built record.
5. Leak field air, vacuum and/or water tests after installation and any repairs are complete. Identify and document locations of all leaks for future reference.
3.13 Place/install compacted fill material to trench the liner rather than using the rock as shown in the diagram attached…roughly two feet in all directions. Reference Attachment 4, “Typical Sewer Lagoon Edge Anchor Trench Detail.” Adjust trench layout as required to ensure liner is properly anchored. As reasonably as possible, provide fill material from one source. Detail shown on Pg. 10 is an example only.
Contractor shall ensure the edge of the liner is protected and will not allow wind and uplift under the liner attached. Contractor shall submit details on their proposed solution for Government review and acceptance.
3.14 Additions, alterations, renovations, or repairs to any sewer/piping system shall conform to that required for a new piping system without requiring the existing plumbing system to comply with all the requirements of the code. Additions, alterations, or repairs shall not cause an existing system to become unsafe. All new work attached to existing infrastructure will be in accordance with codes and will not impede the operation of existing infrastructure. All new work shall be inspected by the COR.
3.15 All work shall be performed in accordance with the requirements of the California
Regional Water Quality Control Board (CRWQCB). Contractor shall certify that all material, equipment, and appurtenances were installed per the manufacturer’s recommendations and industry standards, are functioning as designed, and are code compliant.
3.16 Contractor shall be responsible for coordinating with CRWQCB and obtaining an updated operating permit.
3.17 Contractor is responsible for locating existing utilities at the site prior to digging.
Contractor shall contact “811” or similar entity to mark and identify buried utilities in the project area. Contractor will assume all responsibility if damage occurs resulting from failure to properly identify and protect site utilities or equipment in the designated work zone. Damaged utilities whether above or below grade, or equipment shall be repaired by the Contractor at no cost to the Government.
Contractor shall not leave any open trench overnight.
3.18 Contractor shall be responsible for any damages caused during execution of work at no cost to the Government. Areas shall be repaired to the original condition or better as required by the COR.
a. Grade and level traffic areas between the ponds to allow vehicle access for maintenance. A minimum of 10 feet width is required.
3.19 Provide from one source any fill material required to regrade disturbed or excavated areas.
3.20 Contractor shall pull all applicable permits prior to the start of on-site work performance. The contractor shall adhere to the latest editions of national codes and regulations, and federal, state, and local laws including, but not limited to, the following:
International Building, Plumbing and Mechanical Codes National Fire Protection Code (NFPA) National Standard Plumbing Code National Electrical Code (NEC) National Life Safety Code OSHA Regulations Environmental Protection Agency (EPA) California Regional Water Quality Control Board
4.0 Other Requirements: All work outside of the mentioned days and hours shall be approved by the COR in writing prior to entering the facility.
4.1 All vehicles entering the facility shall have proper insurance and registration.
4.2 Roads and surfaces shall be protected from damage. If damaged, roads and surfaces shall be restored to their original or suitable condition as denoted by the COR including removing excessive dirt or compacted mud from paved roads. All repairs and/or clean up are the responsibility of the Contractor.
4.3 Contractor shall always keep driveways and entrances serving the facility clear and available to USACE facility employees and emergency vehicles. Smoking shall only be permitted in an area designated by the Government. Do not use these areas i.e., driveways, entrances, smoking areas, etc. for parking or storing materials.
4.4 Contractor shall be responsible for the care and storage of material and equipment.
Material and equipment shall be stored in a suitable manner to protect them from the elements or any other damage. Damage to or loss of contractor equipment or material is at the expense of the contractor. All work, and material storage shall be kept within the limits of the areas assigned.
a. Schedule deliveries to minimize the storage of materials and equipment on-site. Contractor is responsible for all stored materials on site. Coordinate with the COR for a preapproved on-site storage location.
b. Contractor is responsible for scheduling, receiving, and off-loading all deliveries.
4.5 Contractor shall be responsible for disposal of all solids within ponds. Contractor shall remove all debris and equipment from site after the final inspection and prior to submission of final invoice.
4.6 The contractor warrants that work performed under this contract conforms to the contract requirements and is free of any defect in equipment, material or workmanship performed by the contractor or any subcontractor or supplier at any tier.
4.7 The contractor shall remedy at the contractor's expense any failure or any defect of equipment, material, workmanship furnished.
4.8 The contractor shall provide and maintain portable toilets. Coordinate with the COR for placement.
4.9 At all times, the plant and work areas shall be kept in a safe condition for workers and base employees. Waste or surplus materials shall not accumulate in the designated work areas. Maintain all debris in covered containers. Clean the project site of excessive dirt and all debris. Contractor shall remove at their expense all debris from the site. Clean dust/mud covered roads impacted during work. Restore area(s) to the same level of clean or better prior to the start of work.
4.10 Utilize methodologies to minimize airborne particles or fugitive dust.
4.11 Maintain noise pollution at 85 decibels or below per OSHA 1910.95. If contractor believes noise pollution will become a problem, coordinate with the OPM for resolution.
5.0 Project Facility Right-of-Way: The Contractor will be assigned working areas or working right-of-way limits for use during the execution of work under this contract.
6.0 Payment and Invoices: Invoices for payment shall be submitted upon completion of tasks as outlined in the pricing/payment schedule. Invoices shall include all necessary information, including any necessary supporting documentation required as part of this Performance Work Statement. All invoices must reflect the contract number W91238-XX-X-XXXX, see Block 2 of the Standard Form 1449. The final invoice must be marked “FINAL.” Copies of all invoices shall be provided to the following:
6.1 An original invoice WITHOUT additional information or supporting documentation shall be mailed to:
USAED, Finance Center
Attn: CEFC-FP 5722 Integrity Dr.
Millington, TN 38054-5005 CEFC-Payments@usace.army.mil
6.2 A copy each of invoice WITH all necessary supporting documentation as required by this Performance Work Statement shall be mailed to the following individuals:
U.S. Army Corps of Engineers
Attn: Contracting Officer’s Representative Email to be provided at time of award.
6.3 The Government shall pay the Contractor upon submission of proper invoices for the services delivered and accepted or for the portion of work actually performed under the contract. Payment shall be made as indicated in the contract’s Payment Schedule.
Deliverables as defined in the Payment Schedule of the contract must be accepted by the Government before payment will be made.
6.4 The Contractor shall be paid at the completion of services for the amount of work accomplished. Failure to complete any of the required items defined in the contract specifications for a particular service shall be cause for that service to be considered incomplete in its entirety. Incomplete services are not billable by the Contractor. As per the Performance Work Statement, if work accomplished is unsatisfactory and does not meet the contract specifications, the Contractor shall be subject to the parameters set forth in the Performance Work Statement and may be held liable for any costs to the Government to correct the problem. The COR shall verify invoices before payment will be authorized.
6.5 The Contractor shall submit an invoice for payment, verifying that all units, quantities, and amounts are true and correct. Invoices shall be received at the respective offices no later than close of business on the tenth business day following performed services. Invoices may also be emailed in either Microsoft Word, Excel or in a PDF format to the COR. An invoice number, the billing period services performed, and itemized line-item charges shall be indicated on the invoice. Hours performed shall be submitted separately with each invoice on a Safety Exposure Report (CESPD Form 94- R). Invoices will not be processed without the Safety Exposure Report.
6.6 The final payment will be authorized when all Government issued equipment has been returned and all reporting requirements have been met.
7. Quality Assurance Surveillance Plan (QASP):
7.1 Monitoring Performance. During the evaluation period, the COR will track Contractor performance. Interim (mid-term) evaluations may be provided to identify strengths and weaknesses in the Contractor's performance during the period being evaluated. At the end of the period, the COR will assess the Contractor's performance in accordance with the Quality Assurance Surveillance Plan (QASP) and report to the Contracting Officer.
7.2 Contractor Self-Assessment. Following each evaluation period, the Contractor may provide a written self-assessment of its performance to the COR to be considered in its report to the Contracting Officer. The self-assessment shall be submitted not later than 5 working days after the end of each evaluation period. The self-evaluation shall not exceed 1 page per PRS element. The self-assessment shall address both the strengths and weaknesses of the Contractor's performance during the evaluation period. Where deficiencies in performance are noted, the Contractor shall describe the actions planned or taken to correct such deficiencies and avoid their recurrence. The self-assessment itself will NOT be the basis for the payment re-calculation determination. The Contractor shall respond to any complaints and/or ratings of poor performance within five (5) calendar days, after receipt of the report.
7.3 COR Recommendation. The COR will consider all evaluations and any other pertinent information, including Contractor self-assessment, and will prepare a report to the Contracting Officer with findings and recommendations. The Contractor will be provided a copy of the draft findings and recommendations of the COR and will be afforded the opportunity to identify factual errors. The COR's draft recommendation is not subject to negotiation and the COR will not engage in discussions with the Contractor. Any errors identified by the Contractor will be addressed by the COR in its final report. The Contractor will be provided a copy of the final COR report at the same time the report is submitted to the Contracting Officer.
7.4 Payment Determination. The Contracting Officer may meet with the COR to discuss the COR's report. The Contracting Officer will make a final determination in writing as to the percentage of work successfully completed, and the resulting payment to be made. A copy of the determination will be provided to the Contractor no later than 45 calendar days after the end of the period being evaluated. All Contracting Officer decisions regarding payment re-calculations are unilateral decisions made solely at the discretion of the Government.
7.5 Payment Re-Calculations. Notwithstanding any other clause of this contract, payment re-calculations will be made within the later of 60 days after the end of the evaluation period or 30 days after receipt of an approved invoice.
7.6 The Quality Assurance Surveillance Plan is one evaluation method the government uses to conduct surveillance performance and to determine whether the Contractor meets the standards of performance as defined in the PWS. The absence of a QASP for any contract requirement, however, shall not detract from its enforceability or limit the rights or remedies of the government under any other provision of the contract in determining the quality of the Contractor performance.
Performance Standard Acceptable Quality Level (AQL)
Method and Frequency of Inspection
Obtain acceptance from the Contracting Officer’s Representative on all Pre-Work
Submittals and attend the pre-work meeting, as outlined in the PWS.
100% Completion
Scheduled Inspection. Upon completion of submittals and pre-work meeting, but not later than 10 days after award.
The Contractor shall complete all tasks as outlined in section 3 in the
PWS.
100% required
100% inspection of deliverables associated with objective
Detail Photo: “Typical Sewer Lagoon Edge Anchor Trench Detail.”
(End of Summary of Changes)