Attachment 2 - Draft Volume 5B Specifications.pdf
PDF 7 MB Posted
- Attached to
- DVA Livermore Phase E - Engineering and Logistics Building Federal contract opportunity
- Solicitation number
- W9123824B0003
About this file
This document provides specifications for a federal construction project. It details requirements for plumbing systems to be installed at the Department of Veterans Affairs Livermore Phase E Engineering and Logistics Building project in Stockton, California. Specifications cover fire suppression systems, plumbing fixtures, piping, meters, valves, insulation, identification, and commissioning. The solicitation number is provided to procure a contractor to install all plumbing systems in accordance with the specifications by the specified response dates.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 1 Draft Volume 5A Specifications.pdf | ||
| Attachment 3 - Draft Volume_6 Drawings.pdf | ||
| Draft Solicitation - Livermore PHE - ELB.pdf | ||
| Pre-Solicitation Notice.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Construction Documents - CD2 Submittal
Livermore VA Medical Center Realignment and Closure Engineering Logistics Building (ELB) (San Joaquin County) Volume 5B of 6 - Specifications
Stockton, CA
February 8, 2018
Construction Documents - Solicitation Set
December 01, 2023
DRAFT
VA NORTHERN CALIFORNIA HEALTHCARE SYSTEM
VA PROJECT 640-423
Project Location: Stockton (French Camp) San Joaquin County, CA
Project Title: VA Livermore Realignment and Closure, Phase E - Engineering Logistics Building (ELB)
Submission Type: Solicitation Set
Submission Date: 01 December 2023
PROJECT MANUAL (SPECIFICATIONS)
VOLUME 5B – Divisions 21 to 41
HDR Architecture, Inc. CLIENT: Department of Veteran Affairs 201 California Street., Suite 1500 Office of Construction & Facilities Management San Francisco, CA 94111 400 Mare Island Parkway Vallejo, CA 94592
Architecture; Interior Design; Signage; Security;
Medical Equipment;
Telecommunication:
Master Plan/Landscape Arch.
HDR Architecture, Inc.
201 California Street, Suite 1500 San Francisco, CA 94105
Mechanical/Electrical/ Plumbing Gayner Engineers 1133 Post Street San Francisco, CA 94109
Geotechnical:
Allegiance Group 4321 SW Corbett, Suite 200 Portland, OR 97239
Civil Engineering:
Sandis 636 Ninth Street Oakland, CA 94607
Structural Engineering:
Degenkolb Engineers 375 Beale Street, Suite 500 San Francisco, CA 94105
Blast Loading:
Hinman Consulting Engineers One Bush Street, Suite 510 San Francisco, CA 94104
Fire Protection:
Jensen Hughes 2950 Buskirk Avenue, Suite Walnut Creek, CA 94597
Acoustical:
Mei Wu Acoustics 3 Twin Dolphins Dr., Suite Redwood City, CA 94065
Cost Estimating:
AECOM
300 California Street San Francisco, CA 94103
VA LIVERMORE PHASE E - ENGINEERING AND LOGISTICS BUILDING (ELB)
Solicitation Set 00 01 10 - 1 01 DEC 2023
TABLE OF CONTENTS
DIVISION 00 — PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 15 - LIST OF DRAWING SHEETS
DIVISION 01 — GENERAL REQUIREMENTS
01 00 00 - GENERAL REQUIREMENTS
01 11 00 - SUMMARY OF WORK
01 14 00 - WORK RESTRICTIONS
01 20 00 - PRICE AND PAYMENT PROCEDURES
01 30 00 - ADMINISTRATIVE REQUIREMENTS
01 32 01 - PROJECT SCHEDULE
01 33 00 - SUBMITTAL PROCEDURES
01 33 00.1 - ATTACHMENT 1 - SUBMITTAL REGISTER
01 33 29 - SUSTAINABILITY REPORTING
01 33 29a - LEED SCORECARD
01 35 26 - GOVERNMENTAL SAFETY REQUIREMENTS
01 35 26.1 - ATTACHMENT 1
01 42 00 - SOURCES FOR REFERENCE PUBLICATIONS
01 43 39 - MOCK-UPS
01 45 00 - QUALITY CONTROL
01 45 00.15 - RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 45 35 - SPECIAL INSPECTIONS
01 50 00 - TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 50 01 - RESIDENT ENGINEER OFFICE
01 57 19 - TEMPORARY ENVIRONMENTAL CONTROLS
01 57 23 - TEMPORARY STORM WATER POLLUTION CONTROL
01 58 00 - PROJECT IDENTIFICATION
01 58 00.1 - ATTACHMENT 1
01 58 00.2 - ATTACHMENT 2
01 64 01 - GOVERNMENT FURNISHED EQUIPMENT
01 64 02 - GOVERNMENT PROVIDED EQUIPMENT
01 64 03 - MEDICAL EQUIPMENT MANUFACTURERS CUT SHEETS
01 74 19 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 78 00 - CLOSEOUT SUBMITTALS
01 78 23 - OPERATION AND MAINTENANCE DATA
01 78 24 - FACILITY DATA REQUIREMENTS
01 83 16 - BLAST RESISTANT FAÇADE SYSTEMS
DIVISION 02 — EXISTING CONDITIONS
02 41 00 - DEMOLITION
DIVISION 03 — CONCRETE
03 30 00 - CAST-IN-PLACE CONCRETE
DIVISION 04 — MASONRY
04 05 13 - MASONRY MORTARING
04 05 16 - MASONRY GROUTING
04 20 00 - UNIT MASONRY
DIVISION 05 — METALS
05 12 00 - STRUCTURAL STEEL FRAMING
05 31 00 - STEEL DECKING
05 36 00 - COMPOSITE METAL DECKING
05 40 00 - COLD-FORMED METAL FRAMING
05 50 00 - METAL FABRICATIONS
Solicitation Set 00 01 10 - 2 01 DEC 2023
DIVISION 06 — WOOD, PLASTICS, AND COMPOSITES
06 10 00 - ROUGH CARPENTRY
06 20 00 - FINISH CARPENTRY
DIVISION 07 — THERMAL AND MOISTURE PROTECTION
07 13 00 - SHEET WATERPROOFING
07 13 52 - MODIFIED BITUMINOUS SHEET WATERPROOFING
07 19 16 - SILANE WATER REPELLENT
07 21 13 - THERMAL INSULATION
07 22 00 - ROOF AND DECK INSULATION
07 27 26 - FLUID-APPLIED MEMBRANE AIR BARRIERS, VAPOR PERMEABLE
07 42 16 - PREFORMED METAL PANELS
07 53 23 - ETHYLENE-PROPYLENE-DIENE-MONOMER ROOFING
07 60 00 - FLASHING AND SHEET METAL
07 71 00 - ROOF SPECIALTIES
07 84 00 - FIRESTOPPING
07 92 00 - JOINT SEALANTS
DIVISION 08 — OPENINGS
08 11 13 - HOLLOW METAL DOORS AND FRAMES
08 14 00 - INTERIOR WOOD DOORS
08 31 13 - ACCESS DOORS AND FRAMES
08 33 00 - COILING DOORS
08 34 53 - SECURITY DOORS AND FRAMES
08 44 13 - GLAZED ALUMINUM CURTAIN WALLS
08 71 00 - DOOR HARDWARE
08 80 00 - GLAZING
DIVISION 09 — FINISHES
09 05 16 - SUBSURFACE PREPARATION FOR FLOOR FINISHES
09 22 16 - NON-STRUCTURAL METAL FRAMING
09 29 00 - GYPSUM BOARD
09 30 13 - CERAMIC-PORCELAIN TILING
09 51 00 - ACOUSTICAL CEILINGS
09 65 13 - RESILIENT BASE AND ACCESSORIES
09 65 16 - RESILIENT SHEET FLOORING
09 65 36 - STATIC DISSIPATIVE RESILIENT TILE FLOORING
09 67 23 - RESINOUS (EPOXY BASE) FLOORING WITH DECORATIVE BROADCAST (RES)
09 67 83 - CONCRETE FLOOR SEALER-HARDENER (CFS-HD)
09 68 00 - CARPET TILE
09 91 00 - PAINTING
DIVISION 10 — SPECIALTIES
10 14 00 - SIGNAGE
10 21 13 - TOILET COMPARTMENTS
10 22 13 - WIRE MESH PARTITIONS
10 26 00 - WALL AND DOOR PROTECTION
10 28 00 - TOILET, BATH, AND LAUNDRY ACCESSORIES
10 44 13 - FIRE EXTINGUISHER CABINETS
10 55 23 - MAIL BOXES
DIVISION 12 — FURNISHINGS
12 32 00 - MANUFACTURED WOOD CASEWORK
12 36 63 - SOLID SURFACE FABRICATIONS (SSF)
12 48 23 - ENTRANCE GRIDS (WOM)
Solicitation Set 00 01 10 - 3 01 DEC 2023
DIVISION 13 — SPECIAL CONSTRUCTION
13 05 41 - SEISMIC RESTRAINT REQUIREMENTS FOR NON-STRUCTURAL COMPONENTS
DIVISION 21 — FIRE SUPPRESSION
21 13 13 - WET-PIPE SPRINKLER SYSTEMS
DIVISION 22 — PLUMBING
22 05 11 - COMMON WORK RESULTS FOR PLUMBING
22 05 19 - METERS AND GAGES FOR PLUMBING PIPING
22 05 23 - GENERAL-DUTY VALVES FOR PLUMBING PIPING
22 07 11 - PLUMBING INSULATION
22 08 00 - COMMISSIONING OF PLUMBING SYSTEMS
22 11 00 - FACILITY WATER DISTRIBUTION
22 13 00 - FACILITY SANITARY AND VENT PIPING
22 14 00 - FACILITY STORM DRAINAGE
22 15 00 - GENERAL SERVICE COMPRESSED-AIR SYSTEMS
22 31 11 - WATER SOFTENERS
22 34 00 - FUEL-FIRED DOMESTIC WATER HEATERS
22 40 00 - PLUMBING FIXTURES
DIVISION 23 — HEATING VENTILATING AND AIR CONDITIONING
23 05 11 - COMMON WORK RESULTS FOR HVAC
23 05 12 - GENERAL MOTOR REQUIREMENTS FOR HVAC AND STEAM GENERATION
EQUIPMENT
23 05 41 - NOISE AND VIBRATION CONTROL FOR HVAC PIPING AND EQUIPMENT
23 05 93 - TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 11 - HVAC AND BOILER PLANT INSULATION
23 08 00 - COMMISSIONING OF HVAC SYSTEMS
23 09 23 - DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC
23 11 23 - FACILITY NATURAL-GAS PIPING
23 21 13 - HYDRONIC PIPING
23 21 23 - HYDRONIC PUMPS
23 22 13 - STEAM AND CONDENSATE HEATING PIPING
23 25 00 - HVAC WATER TREATMENT
23 31 00 - HVAC DUCTS AND CASINGS
23 34 00 - HVAC FANS
23 36 00 - AIR TERMINAL UNITS
23 37 00 - AIR OUTLETS AND INLETS
23 40 00 - HVAC AIR CLEANING DEVICES
23 51 00 - BREECHINGS, CHIMNEYS, AND STACKS
23 74 13 - PACKAGED, OUTDOOR, CENTRAL-STATION AIR-HANDLING UNITS
23 82 00 - CONVECTION HEATING AND COOLING UNITS
23 82 16 - AIR COILS
DIVISION 25 — INTEGRATED AUTOMATION
25 10 10 - ADVANCED UTILITY METERING SYSTEM
DIVISION 26 — ELECTRICAL
26 05 11 - REQUIREMENTS FOR ELECTRICAL INSTALLATIONS
26 05 19 - LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
26 05 26 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
26 05 33 - RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS
26 05 73 - OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY
26 08 00 - COMMISSIONING OF ELECTRICAL SYSTEMS
26 09 13 - POWER MONITORING COMMUNICATIONS SYSTEM
26 09 23 - LIGHTING CONTROLS
26 22 00 - LOW-VOLTAGE TRANSFORMERS
Solicitation Set 00 01 10 - 4 01 DEC 2023
26 24 16 - PANELBOARDS
26 25 11 - TRACK BUSWAY AND RECEPTACLE MODULES FOR COMMUNICATION SYSTEMS
26 27 26 - WIRING DEVICES
26 29 11 - MOTOR CONTROLLERS
26 29 21 - ENCLOSED SWITCHES AND CIRCUIT BREAKERS
26 36 23 - AUTOMATIC TRANSFER SWITCHES
26 41 00 - FACILITY LIGHTNING PROTECTION
26 43 13 - SURGE PROTECTIVE DEVICES
26 51 00 - INTERIOR LIGHTING
DIVISION 27 — COMMUNICATIONS
27 05 11 - REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS
27 05 26 - GROUNDING AND BONDING FOR COMMUNICATIONS SYSTEMS
27 05 33 - RACEWAYS AND BOXES FOR COMMUNICATIONS SYSTEMS
27 10 00 - STRUCTURED CABLING
27 11 00 - TELECOMMUNICATIONS ROOM FITTINGS
27 15 00 - COMMUNICATIONS STRUCTURED CABLING
27 41 31 - MASTER ANTENNA TELEVISION EQUIPMENT AND SYSTEMS
27 51 16 - PUBLIC ADDRESS AND MASS NOTIFICATION SYSTEMS
DIVISION 28 — ELECTRONIC SAFETY AND SECURITY
28 05 00 - COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY
28 05 13 - CONDUCTORS AND CABLES FOR ELECTRONIC SAFETY AND SECURITY
28 05 26 - GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY
28 05 28.33 - CONDUITS AND BACKBOXES FOR ELECTRONIC SAFETY AND SECURITY
28 13 00 - PHYSICAL ACCESS CONTROL SYSTEM
28 16 00 - INTRUSION DETECTION SYSTEM
28 23 00 - VIDEO SURVEILLANCE
28 26 00 - ELECTRONIC PERSONAL PROTECTION SYSTEM
28 31 00 - FIRE DETECTION AND ALARM
DIVISION 31 — EARTHWORK
31 20 00 - EARTHWORK
DIVISION 32 — EXTERIOR IMPROVEMENTS
32 05 23 - CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS
32 12 16 - ASPHALT PAVING
32 17 23 - PAVEMENT MARKINGS
32 84 00 - PLANTING IRRIGATION
32 90 00 - PLANTING
DIVISION 41 — MATERIAL PROCESSING AND HANDLING EQUIPMENT
41 22 23 - HOIST
END OF TABLE OF CONTENTS
Solicitation Set 21 13 13 - 1 01 DEC 2023
SECTION 21 13 13
WET-PIPE SPRINKLER SYSTEMS
PART 1 - GENERAL
1.1. DESCRIPTION
A. Design, installation, and testing shall be in accordance with NFPA 13.
B. The design and installation of a hydraulically calculated automatic wet-pipe system complete and ready for operation, for all portions of the new Engineering & Logistics Building (ELB) at the VA San Joaquin site.
C. The automatic sprinkler system drawings represent design criteria only.
The contractor is responsible for all work necessary for a complete, operating system including the preparation of shop drawings, hydraulic calculations, and seismic bracing calculations. Exposed sprinkler piping in unfinished areas shall be painted.
D. The omission of any necessary system component, as required by the authorities having jurisdiction, the specifications, or the drawings shall not relieve the Contractor of the responsibility for providing such necessity, without additional cost. Any case of error, omission, discrepancy, or lack of clarity shall be promptly identified for clarifications prior to the bid due date.
1.2. RELATED WORK
A. Section 01 33 00, SUBMITTAL PROCEDURES
B. Section 07 84 00, FIRESTOPPING
C. Section 09 91 00, PAINTING
D. Section 13 05 41, SEISMIC RESTRAINT REQUIREMENTS FOR NON-STRUCTURAL
COMPONENTS
E. Section 22 05 23, GENERAL-DUTY VALVES FOR PLUMBING PIPING
F. Section 28 31 00, FIRE DETECTION AND ALARM
1.3. DESIGN CRITERIA
A. Design Basis Information: Provide design, materials, equipment, installation, inspection, and testing of the automatic sprinkler system in accordance with the requirements of NFPA 13.
1. Perform hydraulic calculations in accordance with NFPA 13 utilizing the Area/Density method.
2. Sprinkler Protection: Sprinkler hazard classifications shall be in accordance with NFPA 13. The hazard classification examples of uses and conditions identified in the Annex of NFPA 13 shall be mandatory for areas not listed below. Request clarification from the
Solicitation Set 21 13 13 - 2 01 DEC 2023
Government for any hazard classification not identified. To determining spacing and sizing, apply the following coverage classifications:
a. Light Hazard Occupancies: Office areas, patient units, exam rooms, bathrooms, corridors, waiting areas, reception areas and similar areas.
b. Ordinary Hazard Group 1 Occupancies: Mechanical equipment rooms, transformer rooms, electrical switchgear rooms, electric closets, within the Business Occupancy portion of the buildings.
Coordinate with Fire Protection Drawings.
c. Ordinary Hazard Group 1 Occupancies: Throughout the Industrial
Occupancy portion of the building. Coordinate with Fire
Protection Drawings.
d. Extra Hazard Group 1 Occupancies: The Storage Occupancy within the building shall be classified as Extra Hazard Group 1. Utilize a density of 0.30 gpm/square feet over the most remote 2,500 square feet design area. The commodities stored have been classified as Class I and Class II commodities with Group A
Plastics. The Group A plastics are cartoned, expanded, and stored on double-row racks.
3. Hydraulic Calculations: Calculated demand including hose stream requirements shall fall no less than 10 percent below the available water supply curve.
4. Water Supply: Water shall be supplied via a 2000 gpm pump providing
90 psi boost to 40 psi provided to the pump by the city. Design criteria for hydraulic calculations shall be as follows:
STATIC: 125 PSI
RESIDUAL: 125 PSI
FLOW: 2,000 GPM
The source of this design criteria shall be located at the outlet of the pump located in the Central Utility Plant (CUP), see Site
Utilities and Fire Protection drawings for location and configuration of planned pump.
5. Zoning:
a. The following shall apply when zoning is present
b. For each sprinkler zone provide a control valve, flow switch, and a test and drain assembly with pressure gauge.
Solicitation Set 21 13 13 - 3 01 DEC 2023
6. Provide seismic protection in accordance with NFPA 13. Contractor shall submit load calculations for sizing of sway bracing for systems that are required to be protected against damage from earthquakes.
1.4. SUBMITTALS
A. Submit as one package in accordance with Section 01 33 00, SUBMITTAL
PROCEDURES. Prepare detailed working drawings that are signed by a
NICET Level III or Level IV Sprinkler Technician or stamped by a
Registered Professional Engineer licensed in the field of Fire
Protection Engineering. As the VA review is for technical adequacy only, the installer remains responsible for correcting any conflicts with other trades and building construction that arise during installation. Partial submittals will not be accepted. Material submittals shall be approved prior to the purchase or delivery to the job site. Suitably bind submittals in notebooks or binders and provide an index referencing the appropriate specification section. In addition to the hard copies, provide submittal SHOP DRAWINGS, HYDRAULIC
CALCULATIONS, AND PRODUCT DATA electronically in pdf format on a compact disc or as directed by the Contracting Officer’s Technical
Representative (COR). Submittals shall include, but not be limited to, the following:
1. Qualifications:
a. Provide a copy of the installing contractor’s State of California fire sprinkler contractor’s license.
b. Provide a copy of the NICET certification for the NICET Level III or Level IV Sprinkler Technician who prepared and signed the detailed working drawings unless the drawings are stamped by a
Registered Professional Engineer licensed in the field of Fire
Protection Engineering.
c. Provide documentation showing that the installer has been actively and successfully engaged in the installation of commercial automatic sprinkler systems for the past ten years.
2. Drawings: Submit scaled detailed working drawings conforming to the
Plans and Calculations chapter of NFPA 13. Drawings shall include graphical scales that allow the user to determine lengths when the drawings are reduced in size. Include a site plan showing the piping to the water supply connection to the city water.
Solicitation Set 21 13 13 - 4 01 DEC 2023
3. Manufacturer’s Data Sheets: Provide data sheets for all materials and equipment proposed for use on the system. Include listing information and installation instructions in data sheets. Where data sheets describe items in addition to those proposed to be used for the system, clearly identify the proposed items on the sheet.
4. Calculation Sheets:
a. Submit hydraulic calculation sheets in tabular form conforming to the requirements and recommendations of the Plans and
Calculations chapter of NFPA 13.
b. Submit calculations of loads for sizing of sway bracing in accordance with NFPA 13.
5. Valve Charts: Provide a valve chart that identifies the location of each control valve. Coordinate nomenclature and identification of control valves with COR. Where existing nomenclature does not exist, the chart shall include no less than the following: Tag ID
No., Valve Size, Service (control valve, main drain, aux. drain, inspectors test valve, etc.), and Location.
6. Final Document Submittals: Provide as-built drawings and testing and maintenance instructions in accordance with the requirements in
Section 01 33 00, SUBMITTAL PROCEDURES. In addition, submittals shall include, but not be limited to, the following:
a. A complete set of as-built drawings showing the installed system with the specific interconnections between the fire sprinkler system and the fire alarm equipment. Provide a complete set in the formats as follows. Submit items 2 and 3 below on a compact disc or as directed by the COR.
1) One full size (or size as directed by the COR) printed copy.
2) One complete set in electronic pdf format.
3) One complete set in AutoCAD format or a format as directed by the COR.
b. Material and Testing Certificate: Upon completion of the sprinkler system installation or any partial section of the system, including testing and flushing, provide a copy of a completed Material and Testing Certificate as indicated in NFPA
13. Certificates shall be provided to document all parts of the installation.
c. Operations and Maintenance Manuals that include step-by-step procedures required for system startup, operation, shutdown, and
Solicitation Set 21 13 13 - 5 01 DEC 2023 routine maintenance and testing. The manuals shall include the manufacturer's name, model number, parts list, and tools that should be kept in stock by the owner for routine maintenance, including the name of a local supplier, troubleshooting guide, and recommended service organization, including address and telephone number, for each item of equipment.
d. One paper copy of the Material and Testing Certificates and the
Operations and Maintenance Manuals above shall be provided in a binder. In addition, these materials shall be provided in pdf format on a compact disc or as directed by the COR.
e. Provide one additional copy of the Operations and Maintenance
Manual covering the system in a flexible protective cover and mount in an accessible location adjacent to the riser or as directed by the COR.
1.5. QUALITY ASSURANCE
A. Installer Reliability: The installer shall possess a valid State of
California fire sprinkler contractor's license. The installer shall have been actively and successfully engaged in the installation of commercial automatic sprinkler systems for the past ten years.
B. Materials and Equipment: All equipment and devices shall be of a make and type listed by UL or approved by FM, or other nationally recognized testing laboratory for the specific purpose for which it is used. All materials, devices, and equipment shall be approved by the VA. All materials and equipment shall be free from defect. All materials and equipment shall be new unless specifically indicated otherwise on the contract drawings.
1.6. APPLICABLE PUBLICATIONS
A. The publications listed below form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only.
B. National Fire Protection Association (NFPA):
NFPA 13-13..............Installation of Sprinkler Systems
NFPA 101-12.............Life Safety Code
C. Underwriters Laboratories, Inc. (UL):
Fire Protection Equipment Directory (2011)
D. Factory Mutual Engineering Corporation (FM):
Approval Guide
Solicitation Set 21 13 13 - 6 01 DEC 2023
PART 2 - PRODUCTS
2.1. GENERAL
A. All components not referenced by NFPA 13 shall be UL listed and/or FM approved for use in fire protection systems. All components shall be new and used in accordance with the manufacturer's recommendations and its UL listing and/or FM approval.
B. The naming of manufacturers in the specifications shall not be construed as eliminating the materials, products, or services of other manufacturers and suppliers providing approved equivalent items.
C. The substitutions of materials or products other than those named in the specifications are subject to proper approval of the Owner and
Engineer granted in writing.
2.2. PIPING & FITTINGS
A. Piping and fittings for private underground water mains shall be in accordance with NFPA 13.
1. Pipe and fittings from inside face of building 300 mm (12 in.) above finished floor to a distance of approximately 1500 mm (5 ft.)
outside building: Ductile Iron, flanged fittings, and 316 stainless steel bolting.
B. Piping and fittings for sprinkler systems shall be in accordance with
NFPA 13.
1. Plain-end pipe fittings with locking lugs or shear bolts are not permitted.
2. Piping sizes 50 mm (2 inches) and smaller shall be black steel
Schedule 40 with threaded end connections.
3. Piping sizes 65 mm (2 ½ inches) and larger shall be black steel
Schedule 10 with grooved connections. Grooves in Schedule 10 piping shall be rolled grooved only.
4. Use nonferrous piping in MRI Scanning Rooms.
5. Plastic piping shall not be permitted.
6. Standard Flexible sprinkler connections are permitted to be used where suspended ceilings with t-bar and stud framing are used.
Where used, the entire listed assembly shall be provided.
Connection shall be to a standard screwed fitting on the branch line, press fittings shall not be used.
2.3. VALVES
A. General:
1. Valves shall be in accordance with NFPA 13.
Solicitation Set 21 13 13 - 7 01 DEC 2023
2. Do not use quarter turn ball valves for 50 mm (2 inch) or larger drain valves.
B. Control Valve: The control valves shall be a listed indicating type.
Control valves shall be UL Listed or FM Approved for fire protection installations. System control valve shall be rated for normal system pressure but in no case less than 175 PSI.
C. Check Valve: Shall be of the swing type with a flanged cast iron body and flanged inspection plate.
D. Automatic Ball Drips: Cast brass 20 mm (3/4 inch) in-line automatic ball drip with both ends threaded with iron pipe threads.
E. Backflow Preventer: Provide backflow preventer in accordance with
Section 22 05 23, GENERAL-DUTY VALVES FOR PLUMBING PIPING. Provide means to forward flow test the backflow preventer in accordance with
NFPA 13. Coordinate with civil drawings.
2.4. FIRE DEPARTMENT SUPPLY CONNECTION
A. Brass exterior fire department connection with brass escutcheon plate, and a minimum of two 65 mm (2-1/2 inch) connections threaded to match those on the local fire protection service, with polished brass caps and chains. Provide escutcheon with integral raised letters "AUTOSPKR" or "AUTOSPKR AND STANDPIPE" as appropriate. Install an automatic ball drip between fire department connection and check valve with drain piping routed to the exterior of the building or a floor drain.
2.5. SPRINKLERS
A. All sprinklers shall be UL Listed or FM approved quick response except where specifically prohibited by their listing.
B. Temperature Ratings: In accordance with NFPA 13 except that sprinklers in elevator shafts and elevator machine rooms shall be no less than intermediate temperature rated and sprinklers in generator rooms shall be no less than high temperature rated.
C. Provide sprinkler guards in accordance with NFPA 13 and when the elevation of the sprinkler is less than 7 feet 6 inches above finished floor. The sprinkler guard shall be UL listed or FM approved for use with the corresponding sprinkler.
D. Contractor is responsible for reviewing the drawings and field conditions and providing and installing the actual number of sprinklers required under the referenced codes, standards, and these specifications.
Solicitation Set 21 13 13 - 8 01 DEC 2023
2.6. SPRINKLER CABINET
A. Provide sprinkler cabinet with the required number of sprinklers of all ratings and types installed, and a sprinkler wrench for each type of sprinkler in accordance with NFPA 13. Locate adjacent to the riser.
B. Provide a list of sprinklers installed in the property in the cabinet.
The list shall include the following:
1. Manufacturer, model, orifice, deflector type, thermal sensitivity, and pressure for each type of sprinkler in the cabinet.
2. General description of where each sprinkler is used.
3. Quantity of each type present in the cabinet.
4. Issue or revision date of list.
2.7. SPRINKLER SYSTEM SIGNAGE
A. Provide signs where required by NFPA 13.
B. Rigid plastic, steel or aluminum signs with white lettering on a red background with holes for easy attachment. Sprinkler system signage shall be attached to the valve or piping with chain.
C. Valve signs shall indicate purpose and system of each control, test trim, and drain valve. Hydraulic information sign shall meet requirements of NFPA 13.
2.8. SWITCHES
A. OS&Y Valve Supervisory Switches shall be in a weatherproof die cast/red baked enamel, oil resistant, aluminum housing with tamper resistant screws, 13 mm (1/2 inch) conduit entrance and necessary facilities for attachment to the valves. Provide two SPDT switches rated at 2.5 amps at 24 VDC.
B. Water flow Alarm Switches shall be mechanical, non-coded, non-accumulative retard and adjustable from 0 to 60 seconds. Set flow switches at an initial setting between 20 and 30 seconds. Waterflow alarm switch shall be installed before the system has been hydrostatically tested. Activation of waterflow alarm switch shall cause an alarm on the fire alarm system control unit.
C. Valve Supervisory Switches for Ball and Butterfly Valves: May be integral with the valve.
2.9. GAUGES
A. Provide gauges as required by NFPA 13. The gauges shall be liquid filled. Provide gauges where the normal pressure of the system is at the midrange of the gauge.
Solicitation Set 21 13 13 - 9 01 DEC 2023
2.10. PIPE HANGERS, SUPPORTS AND RESTRAINT OF SYSTEM PIPING
A. Pipe hangers, supports, and restraint of system piping shall be in accordance with NFPA 13.
2.11. WALL, FLOOR, AND CEILING PLATES
A. Provide chrome plated steel escutcheon plates for all exposed penetrations through walls, floors, and ceilings.
2.12. VALVE TAGS
A. Engraved black filled numbers and letters not less than 15 mm (1/2 inch) high for number designation, and not less than 8 mm (1/4 inch) for service designation on 19 gauge, 40 mm (1-1/2 inches) round brass disc, attached with brass "S" hook or brass chain.
PART 3 - EXECUTION
3.1. INSTALLATION
A. Installation shall be accomplished by the licensed contractor. Provide a qualified technician, experienced in the installation and operation of the type of system being installed, to supervise the installation and testing of the system.
B. Installation of Piping: Accurately cut pipe to measurements established by the installer and work into place without springing or forcing.
Concealed piping in spaces that have finished ceilings. Where ceiling mounted equipment exists, such as in operating and radiology rooms, install sprinklers so as not to obstruct the movement or operation of the equipment. Sidewall heads may need to be utilized. In stairways, locate piping as near to the ceiling as possible to prevent tampering by unauthorized personnel and to provide a minimum headroom clearance of 2250 mm (seven feet six inches). Piping shall not obstruct the minimum means of egress clearances required by NFPA 101. Pipe hangers, supports, and restraint of system piping, and seismic bracing shall be installed accordance with NFPA 13.
C. Welding: Conform to the requirements and recommendations of NFPA 13.
D. Drains: Provide drips and drains, including low point drains, in accordance with NFPA 13. Pipe drains to discharge indirectly into sanitary risers connected to the sanitary sewer. Discharge to the exterior is not permitted. Drains shall be of adequate size to readily carry the full flow from each drain under maximum pressure and coordinated with the plumbing drawings. The drain piping shall not be restricted or reduced and shall be of the same diameter as the drain collector.
Solicitation Set 21 13 13 - 10 01 DEC 2023
E. Valve Supervisory Switches: Provide supervisory switches for sprinkler control valves.
F. Waterflow Alarm Switches: Install waterflow alarm switches and valves in stairwells or other easily accessible locations.
G. Inspector's Test Connection: Install and supply in accordance with NFPA
13, locate in a secured area.
H. Affix cutout disks, which are created by cutting holes in the walls of pipe for flow switches and non-threaded pipe connections to the respective waterflow switch or pipe connection near to the pipe from where they were cut.
I. Clearances: For systems requiring seismic protection, piping that passes through floors or walls shall have penetrations sized 50 mm (2 inches) nominally larger than the penetrating pipe for pipe sizes 25 mm
(1 inch) to 90 mm (3 ½ inches) and 100 mm (4 inches) nominally larger for penetrating pipe sizes 100 mm (4 inches) and larger.
J. Sleeves: Provide for pipes passing through masonry or concrete. Provide space between the pipe and the sleeve in accordance with NFPA 13. Seal this space with a UL Listed through penetration fire stop material in accordance with Section 07 84 00, FIRESTOPPING. Where core drilling is used in lieu of sleeves, also seal space. Seal penetrations of walls, floors and ceilings of other types of construction, in accordance with
Section 07 84 00, FIRESTOPPING.
K. Where dry pendent sprinklers are used for freezers or similar spaces and they are connected to the wet pipe system, provide an EPDM boot around the dry pendent sprinkler on the heated side and securely seal to the pipe and freezer to prevent condensation from entering the freezer.
L. Provide pressure gauges at each water flow alarm switch location and at each main drain connection.
M. Firestopping shall be provided for all penetrations of fire resistance rated construction. Firestopping shall comply with Section 07 84 00, FIRESTOPPING.
N. Painting of Pipe: In finished areas where walls and ceilings have been painted, paint primed surfaces with two coats of paint to match adjacent surfaces, except paint valves and operating accessories with two coats of gloss red enamel. In unfinished areas all piping shall be painted Fire Safety Red. Exercise care to avoid painting sprinklers.
Any painted sprinkler shall be replaced with a new sprinkler. Painting
Solicitation Set 21 13 13 - 11 01 DEC 2023 is not required in areas above suspended ceilings and in crawl spaces is not required. Painting shall comply with Section 09 91 00, PAINTING or by the COR.
O. Sprinkler System Signage: Provide rigid sprinkler system signage in accordance with NFPA 13 and NFPA 25. Sprinkler system signage shall include, but not limited to, the following:
1. Identification Signs:
a. Provide signage for each control valve, drain valve, sprinkler cabinet, and inspector’s test.
b. Provide valve tags for each operable valve. Coordinate nomenclature and identification of operable valves with COR.
Where existing nomenclature does not exist, the Tag
Identification shall include no less than the following: (FP-B-
F/SZ-#) Fire Protection, Building Number, Floor Number/Smoke Zone
(if applicable), and Valve Number. (E.g., FP-500-1E-001) Fire
Protection, Building 500, First Floor East, Number 001.
2. Instruction/Information Signs:
a. Provide signage for each control valve to indicate valve function and to indicate what system is being controlled.
b. Provide signage indicating the number and location of low point drains.
3. Hydraulic Placards:
a. Provide signage indicating hydraulic design information. The placard shall include location of the design area, discharge densities, required flow and residual pressure at the base of riser, occupancy classification, hose stream allowance, flow test information, and installing contractor. Locate hydraulic placard information signs at each sprinkler system riser.
P. Repairs: Repair damage to the building or equipment resulting from the installation of the sprinkler system by the installer at no additional expense to the Government.
3.2. INSPECTION AND TEST
A. Preliminary Testing: Flush newly installed systems prior to performing hydrostatic tests in order to remove any debris which may have been left as well as ensuring piping is unobstructed. Hydrostatically test system, including the fire department connections, as specified in NFPA
13, in the presence of the COR or his designated representative. Test
Solicitation Set 21 13 13 - 12 01 DEC 2023 and flush underground water line prior to performing these hydrostatic tests.
B. Final Inspection and Testing: Subject system to tests in accordance with NFPA 13, and when all necessary corrections have been accomplished, advise COR to schedule a final inspection and test.
Connection to the fire alarm system shall have been in service for at least ten days prior to the final inspection, with adjustments made to prevent false alarms. Furnish all instruments, labor, and materials required for the tests and provide the services of the installation foreman or other competent representative of the installer to perform the tests. Correct deficiencies and retest system as necessary, prior to the final acceptance. Include the operation of all features of the systems under normal operations in test
C. Contractor to complete and sign a Contractor’s Material and Test
Certificate. Use form provided in NFPA 13.
3.3. INSTRUCTIONS
Furnish the services of a competent instructor for not less than two hours for instructing personnel in the operation and maintenance of the system, on the dates requested by the COR.
- - - E N D - - -
Solicitation Set 22 05 11 - 1 01 DEC 2023
SECTION 22 05 11
COMMON WORK RESULTS FOR PLUMBING
PART 1 - GENERAL
1.1 DESCRIPTION
A. The requirements of this Section shall apply to all sections of
Division 22.
B. Definitions:
1. Exposed: Piping and equipment exposed to view in finished rooms.
C. Abbreviations/Acronyms:
1. AC: Alternating Current
2. ACR: Air Conditioning and Refrigeration
3. AI: Analog Input
4. AISI: American Iron and Steel Institute
5. AO: Analog Output
6. AWG: American Wire Gauge
7. BACnet: Building Automation and Control Network
8. BAg: Silver-Copper-Zinc Brazing Alloy
9. BAS: Building Automation System
10. BCuP: Silver-Copper-Phosphorus Brazing Alloy
11. BSG: Borosilicate Glass Pipe
12. CDA: Copper Development Association
13. C: Celsius
14. CLR: Color
15. CO: Carbon Monoxide
16. COR: Contracting Officer’s Representative
17. CPVC: Chlorinated Polyvinyl Chloride
18. CR: Chloroprene
19. CRS: Corrosion Resistant Steel
20. CWP: Cold Working Pressure
21. CxA: Commissioning Agent
22. db(A): Decibels (A weighted)
23. DDC: Direct Digital Control
24. DI: Digital Input
25. DISS: Diameter Index Safety System
26. DO: Digital Output
27. DVD: Digital Video Disc
28. DN: Diameter Nominal
Solicitation Set 22 05 11 - 2 01 DEC 2023
29. DWV: Drainage, Waste and Vent
30. ECC: Engineering Control Center
31. EPDM: Ethylene Propylene Diene Monomer
32. EPT: Ethylene Propylene Terpolymer
33. ETO: Ethylene Oxide
34. F: Fahrenheit
35. FAR: Federal Acquisition Regulations
36. FD: Floor Drain
37. FED: Federal
38. FG: Fiberglass
39. FNPT: Female National Pipe Thread
40. FPM: Fluoroelastomer Polymer
41. GPM: Gallons Per Minute
42. HDPE: High Density Polyethylene
43. Hg: Mercury
44. HOA: Hands-Off-Automatic
45. HP: Horsepower
46. HVE: High Volume Evacuation
47. ID: Inside Diameter
48. IPS: Iron Pipe Size
49. Kg: Kilogram
50. kPa: Kilopascal
51. lb: Pound
52. L/s: Liters Per Second
53. L/min: Liters Per Minute
54. MAWP: Maximum Allowable Working Pressure
55. MAX: Maximum
56. MED: Medical
57. m: Meter
58. MFG: Manufacturer
59. mg: Milligram
60. mg/L: Milligrams per Liter
61. ml: Milliliter
62. mm: Millimeter
63. MIN: Minimum
64. NF: Oil Free Dry (Nitrogen)
65. NPTF: National Pipe Thread Female
66. NPS: Nominal Pipe Size
Solicitation Set 22 05 11 - 3 01 DEC 2023
67. NPT: Nominal Pipe Thread
68. OD: Outside Diameter
69. OSD: Open Sight Drain
70. OS&Y: Outside Stem and Yoke
71. OXY: Oxygen
72. PBPU: Prefabricated Bedside Patient Units
73. PH: Power of Hydrogen
74. PLC: Programmable Logic Controllers
75. PP: Polypropylene
76. PPM: Parts per Million
77. PSIG: Pounds per Square Inch
78. PTFE: Polytetrafluoroethylene
79. RAD: Radians
80. RO: Reverse Osmosis
81. RPM: Revolutions Per Minute
82. RTRP: Reinforced Thermosetting Resin Pipe
83. SCFM: Standard Cubic Feet Per Minute
84. SDI: Silt Density Index
85. SPEC: Specification
86. SPS: Sterile Processing Services
87. STD: Standard
88. SUS: Saybolt Universal Second
89. SWP: Steam Working Pressure
90. TEFC: Totally Enclosed Fan-Cooled
91. TFE: Tetrafluoroethylene
92. THHN: Thermoplastic High-Heat Resistant Nylon Coated Wire
93. THWN: Thermoplastic Heat & Water Resistant Nylon Coated Wire
94. T/P: Temperature and Pressure
95. USDA: U.S. Department of Agriculture
96. V: Volt
97. VAC: Vacuum
98. VA: Veterans Administration
99. VAMC: Veterans Administration Medical Center
100. VAC: Voltage in Alternating Current
101. WAGD: Waste Anesthesia Gas Disposal
102. WOG: Water, Oil, Gas
1.2 RELATED WORK
A. Section 01 00 00, GENERAL REQUIREMENTS.
Solicitation Set 22 05 11 - 4 01 DEC 2023
B. Section 01 33 00, SUBMITTAL PROCEDURES.
C. Section 01 33 29, SUSTAINABILITY REQUIREMENTS.
D. Section 01 74 19, CONSTRUCTION WASTE MANAGEMENT.
E. Section 01 91 00, GENERAL COMMISSIONING REQUIREMENTS.
F. Section 03 30 00, CAST-IN-PLACE CONCRETE: Concrete and Grout.
G. Section 05 31 00, STEEL DECKING: Building Components for Attachment of
Hangers.
H. Section 05 36 00, COMPOSITE METAL DECKING: Building Components for
Attachment of Hangers.
I. Section 05 50 00, METAL FABRICATIONS.
J. Section 07 60 00, FLASHING AND SHEET METAL: Flashing for Wall and Roof
Penetrations.
K. Section 07 84 00, FIRESTOPPING.
L. Section 07 92 00, JOINT SEALANTS.
M. Section 09 91 00, PAINTING.
N. Section 13 05 41, SEISMIC RESTRAINT REQUIREMENTS FOR NON-STRUCTURAL
COMPONENTS.
O. Section 22 07 11, PLUMBING INSULATION.
P. Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.
Q. Section 23 09 23, DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC.
R. Section 23 11 23, FACILITY NATURAL GAS PIPING.
S. Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS.
T. Section 26 05 19, LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES.
U. Section 26 29 11, MOTOR CONTROLLERS.
V. Section 31 20 00, EARTH MOVING: Excavation and Backfill.
1.3 APPLICABLE PUBLICATIONS
A. The publications listed below shall form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only.
B. American Society of Mechanical Engineers (ASME):
ASME Boiler and Pressure Vessel Code -
BPVC Section IX-2013....Welding, Brazing, and Fusing Qualifications
B31.1-2012..............Power Piping
C. American Society for Testing and Materials (ASTM):
A36/A36M-2012...........Standard Specification for Carbon Structural
Steel
A575-96(R2013)e1........Standard Specification for Steel Bars, Carbon, Merchant Quality, M-Grades
Solicitation Set 22 05 11 - 5 01 DEC 2023
E84-2013a...............Standard Test Method for Surface Burning
Characteristics of Building Materials
E119-2012a..............Standard Test Methods for Fire Tests of
Building Construction and Materials
D. International Code Council, (ICC):
IBC-2012................International Building Code
IPC-2012................International Plumbing Code
E. Manufacturers Standardization Society (MSS) of the Valve and Fittings
Industry, Inc:
SP-58-2009..............Pipe Hangers and Supports - Materials, Design, Manufacture, Selection, Application and
Installation
SP-69-2003..............Pipe Hangers and Supports - Selection and
Application
F. Military Specifications (MIL):
P-21035B................Paint High Zinc Dust Content, Galvanizing
Repair (Metric)
G. National Electrical Manufacturers Association (NEMA):
MG 1-2011...............Motors and Generators
H. National Fire Protection Association (NFPA):
51B-2014................Standard for Fire Prevention During Welding, Cutting and Other Hot Work
54-2012.................National Fuel Gas Code
70-2014.................National Electrical Code (NEC)
I. NSF International (NSF):
5-2012..................Water Heaters, Hot Water Supply Boilers, and
Heat Recovery Equipment
14-2012.................Plastic Piping System Components and Related
Materials
61-2012.................Drinking Water System Components – Health
Effects
372-2011................Drinking Water System Components – Lead Content
J. Department of Veterans Affairs (VA):
PG-18-10................Plumbing Design Manual
PG-18-13-2011...........Barrier Free Design Guide
1.4 SUBMITTALS
A. Submittals, including number of required copies, shall be submitted in accordance with Section 01 33 00, SUBMITTAL PROCEDURES.
Solicitation Set 22 05 11 - 6 01 DEC 2023
B. SD-02 Shop Drawings
C. Information and material submitted under this section shall be marked
"SUBMITTED UNDER SECTION 22 05 11, COMMON WORK RESULTS FOR PLUMBING",
with applicable paragraph identification.
D. Contractor shall make all necessary field measurements and investigations to assure that the equipment and assemblies will meet contract requirements and will fit the space available.
E. If equipment is submitted which differs in arrangement from that shown, provide drawings that show the rearrangement of all associated systems.
Approval will be given only if all features of the equipment and associated systems, including accessibility, are equivalent to that required by the contract.
F. Prior to submitting shop drawings for approval, contractor shall certify in writing that manufacturers of all major items of equipment have each reviewed drawings and specifications, and have jointly coordinated and properly integrated their equipment and controls to provide a complete and efficient installation.
G. Installing Contractor shall provide lists of previous installations for selected items of equipment. Contact persons who will serve as references, with telephone numbers and e-mail addresses shall be submitted with the references.
H. Manufacturer's Literature and Data: Manufacturer’s literature shall be submitted under the pertinent section rather than under this section.
1. Electric motor data and variable speed drive data shall be submitted with the driven equipment.
2. Equipment and materials identification.
3. Firestopping materials.
4. Hangers, inserts, supports and bracing. Provide load calculations for variable spring and constant support hangers.
5. Wall, floor, and ceiling plates.
I. Submittals and shop drawings for interdependent items, containing applicable descriptive information, shall be furnished together and complete in a group. Coordinate and properly integrate materials and equipment in each group to provide a completely compatible and efficient installation. Final review and approvals will be made only by groups.
J. Coordination Drawings: Complete consolidated and coordinated layout drawings shall be submitted for all new systems, and for existing
Solicitation Set 22 05 11 - 7 01 DEC 2023 systems that are in the same areas. The drawings shall include plan views, elevations and sections of all systems and shall be on a scale of not less than 1:32 (3/8 inch equal to one foot). Clearly identify and dimension the proposed locations of the principal items of equipment. The drawings shall clearly show the proposed location and adequate clearance for all equipment, controls, piping, pumps, valves and other items. All valves, trap primer valves, water hammer arrestors, strainers, and equipment requiring service shall be provided with an access door sized for the complete removal of plumbing device, component, or equipment. Equipment foundations shall not be installed until equipment or piping layout drawings have been approved. Detailed layout drawings shall be provided for all piping systems. In addition, details of the following shall be provided.
1. Mechanical equipment rooms.
2. Hangers, inserts, supports, and bracing.
3. Pipe sleeves.
4. Equipment penetrations of floors, walls, ceilings, or roofs.
K. Maintenance Data and Operating Instructions:
1. Maintenance and operating manuals in accordance with Section 01 00
00, GENERAL REQUIREMENTS, Article, INSTRUCTIONS, for systems and equipment. Include complete list indicating all components of the systems with diagrams of the internal wiring for each item of equipment.
2. Include listing of recommended replacement parts for keeping in stock supply, including sources of supply, for equipment shall be provided. The listing shall include belts for equipment: Belt manufacturer, model number, size and style, and distinguished whether of multiple belt sets.
L. Completed System Readiness Checklist provided by the Commissioning
Agent and completed by the contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS and
Section 22 08 00 COMMISSIONING OF PLUMBING SYSTEMS.
M. Submit training plans, trainer qualifications and instructor qualifications in accordance with the requirements of Section 22 08 00
COMMISSIONING OF PLUMBING SYSTEMS.
1.5 QUALITY ASSURANCE
A. Products Criteria:
Solicitation Set 22 05 11 - 8 01 DEC 2023
1. Standard Products: Material and equipment shall be the standard products of a manufacturer regularly engaged in the manufacture, supply and servicing of the specified products for at least 5 years.
However, digital electronics devices, software and systems such as controls, instruments, computer work station, shall be the current generation of technology and basic design that has a proven satisfactory service record of at least 5 years.
2. Equipment Service: There shall be permanent service organizations, authorized and trained by manufacturers of the equipment supplied, located within 160 km (100 miles) of the project. These organizations shall come to the site and provide acceptable service to restore operations within four hours of receipt of notification by phone, e-mail or fax in event of an emergency, such as the shut-down of equipment; or within 24 hours in a non-emergency. Names, mail and e-mail addresses and phone numbers of service organizations providing service under these conditions for (as applicable to the project): pumps, compressors, water heaters, critical instrumentation, computer workstation and programming shall be submitted for project record and inserted into the operations and maintenance manual.
3. All items furnished shall be free from defects that would adversely affect the performance, maintainability and appearance of individual components and overall assembly.
4. The products and execution of work specified in Division 22 shall conform to the referenced codes and standards as required by the specifications. Local codes and amendments enforced by the local code official shall be enforced, if required by local authorities such as the natural gas supplier. If the local codes are more stringent, then the local code shall apply. Any conflicts shall be brought to the attention of the Contracting Officers Representative
(COR).
5. Multiple Units: When two or more units of materials or equipment of the same type or class are required, these units shall be products of one manufacturer.
6. Assembled Units: Manufacturers of equipment assemblies, which use components made by others, assume complete responsibility for the final assembled product.
Solicitation Set 22 05 11 - 9 01 DEC 2023
7. Nameplates: Nameplate bearing manufacturer's name or identifiable trademark shall be securely affixed in a conspicuous place on equipment, or name or trademark cast integrally with equipment, stamped or otherwise permanently marked on each item of equipment.
8. Asbestos products or equipment or materials containing asbestos shall not be used.
9. Bio-Based Materials: For products designated by the USDA’s Bio-
Preferred Program, provide products that meet or exceed USDA recommendations for bio-based content, so long as products meet all performance requirements in this specifications section. For more information regarding the product categories covered by the Bio-
Preferred Program, visit http://www.biopreferred.gov.
B. SD-07 Certificates
C. Welding: Before any welding is performed, contractor shall submit a certificate certifying that welders comply with the following requirements:
1. Qualify welding processes and operators for piping according to ASME
"Boiler and Pressure Vessel Code", Section IX, "Welding and Brazing
Qualifications".
2. Comply with provisions of ASME B31 series "Code for Pressure
Piping".
3. Certify that each welder and welding operator has passed American
Welding Society (AWS) qualification tests for the welding processes involved, and that certification is current.
4. All welds shall be stamped according to the provisions of the
American Welding Society.
D. Manufacturer's Recommendations: Where installation procedures or any part thereof are required to be in accordance with the recommendations of the manufacturer of the material being installed, printed copies of these recommendations shall be furnished to the COR prior to installation. Installation of the item will not be allowed to proceed until the recommendations are received. Failure to furnish these recommendations can be cause for rejection of the material.
E. Execution (Installation, Construction) Quality:
1. All items shall be applied and installed in accordance with manufacturer's written instructions. Conflicts between the manufacturer's instructions and the contract documents shall be referred to the COR for resolution. Printed copies or electronic http://www.biopreferred.gov/
Solicitation Set 22 05 11 - 10 01 DEC 2023 files of manufacturer’s installation instructions shall be provided to the COR at least 10 working days prior to commencing installation of any item.
2. All items that require access, such as for operating, cleaning, servicing, maintenance, and calibration, shall be easily and safely accessible by persons standing at floor level, or standing on permanent platforms, without the use of portable ladders. Examples of these items include, but are not limited to: all types of valves, filters and strainers, transmitters, and control devices. Prior to commencing installation work, refer conflicts between this requirement and contract documents to COR for resolution.
3. Complete layout drawings shall be required by Paragraph, SUBMITTALS.
Construction work shall not start on any system until the layout drawings have been approved by VA.
4. Installer Qualifications: Installer…