Amend 1 Attachment 2 - Seed Task Order PWS March 2021_3.10.21 .pdf

PDF 10 MB Posted

Attached to
$50M MEGA MATOC ERS for FUDS Ft. Douglas
Solicitation number
W91238-21-R-0021
Issued by

About this file

This document provides details for a federal contract opportunity issued by the Department of the Army Corps of Engineers Engineering District Sacramento. The solicitation number is W91238-21-R-0021 and seeks responses for a $50 million MEGA MATOC contract vehicle to be used for environmental remediation and restoration services at former Fort Douglas in Utah under the Formerly Used Defense Sites program. The acquisition strategy includes a partial small business set-aside with a target of awarding 3-4 contracts to small businesses out of a total of five planned IDIQ contracts. The initial task order issued against the MATOC will be for restoration work at Fort Douglas. Offerors are directed to monitor the posting for updates and direct any comments or questions to the named USACE contracting officials by the given deadlines. The period of performance and further details of work requirements are provided in the attached Performance Work Statement and in other documents to be distributed to offerors during the solicitation period through the DOD Safe system.

View the file

Other files

File Type Posted
Amend 5 Solicitation W9123821R0021 0005 FUDS MATOC SPK__24Aug2021.pdf PDF
Amend 3 Solicitation W9123821R0021 0003 FUDS MATOC SPK__23Aug2021.pdf PDF
Amend 4 Solicitation W9123821R0021 0003 FUDS MATOC SPK__23Aug2021.pdf PDF
Amend 2 SLast 2 RFI Answers W9123821R0021 FUDS MATOC SPK 26 March 21 -.pdf PDF
Amend 2 Response to RFI_105mm_munition_ as of 23 March 2021.pdf PDF
Amend 2_Attachment 3 - Seed Task Order - Blank Pricing Schedule_ 2_3.16.21_.xlsx XLSX spreadsheet
Amend 2_Attachment 6 - MATOC IDIQ Wage Rates Blank Pricing Schedule__3.16.21_.xlsx XLSX spreadsheet
Amend 2_Attachment 4 - Project Experience Form_Amend 2_3.16.21_.docx DOCX document
Amend 2_Attachment 2 - Seed Task Order PWS March 2021_2_3.16.21.pdf PDF
Amend 2_Attachment 1 - MATOC PWS - Mar2021_3.16.21_.pdf PDF
A07.06 Amend 2_SF33 Solicitation W9123821R0021 0002 FUDS MATOC SPK__3.22.21 .pdf PDF
Amend 2_Attachment 2 - Seed Task Order PWS March 2021_2_3.16.21_trackedChanges.pdf PDF
Amend 2_Attachment 1 - MATOC PWS - Mar2021_2_3.16.21_trackedChanges.pdf PDF
Amend 1 SF33 Solicitation W9123821R0021 0001 FUDS MATOC SPK__3.10.21 .pdf PDF
Amend 1 Attachment 14 - Small Business Participation Proposal 1_3.10.21 .docx DOCX document
Amend 1 Attachment 1 - MATOC PWS - Mar2021_3.10.21.pdf PDF
Amend 1 Attachment 6 - MATOC IDIQ Wage Rates Blank Pricing Schedule_3.10.21 .xlsx XLSX spreadsheet
Amend 1 Attachment 4 - Project Experience Form_3.10.21 .docx DOCX document
Amend 1 Attachment 3 - Seed Task Order - Blank Pricing Schedule_3.10.21 .xlsx XLSX spreadsheet
A07.06 ProjNet Procedures for Solicitation W9123821R0021 FUDS MATOC SPK .pdf PDF
A01.12 PWS Seed (FtDouglas) Task Order_ Jan2021.pdf PDF
A07.06 Seed Task Order Pricing Schedule_2021.01.28.xlsx XLSX spreadsheet
A01.12 PWS 09Dec2020 Task Order Seed MEGA MATOC - Ft Douglas.pdf PDF
A01.12 Eng_Form_6048 Munitions Response .pdf PDF
A07.06 MATOC Wage Rates Blank Pricing Schedule 25Jan21 .xlsx XLSX spreadsheet
A07.06 Small Business Participation Proposal.docx DOCX document
A04.11 Wage Determination - Salt Lake County, UT.pdf PDF
A07.06 Project Experience Form.docx DOCX document
A07.06 8 Approved SF33 Solicitation W9123821R0021 FUDS MATOC SPK 12 Feb 2021.pdf PDF
A07.06 DOD Safe-Directions for Submitting Proposals.pdf PDF
A01.12 PWS 8Dec2020 $50M MEGA MATOC Sacramento.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Performance Work Statement 1 Remedial Investigation / Feasibility Study / Proposed Plan / Decision Document 2

Impact Area Munitions Response Site, Fort Douglas 3 Salt Lake County, Utah 4

FUDS Project No. J08UT110801 5 March 2021 6

(Amendment 0001) 7 Revision: 0 8

Revision Date: N/A 9

1.0 OBJECTIVE: 10

The overall objective of this task order (TO) is to perform a Remedial Investigation (RI), and if required due to 11 existing or potential risk to human health and the environment by the site prepare a Feasibility Study (FS), a 12 Proposed Plan, and a Decision Document in compliance with the Comprehensive Environmental Response, 13 Compensation, and Liability Act (CERCLA), as amended, and in accordance with Department of Defense (DoD), 14

Department of the Army (DA), and United States (US) Army Corps of Engineers (USACE) Regulations and Guidance. 15 The RI shall characterize site conditions of the Impact Area Munitions Response Site (MRS) at former Fort Douglas. 17 to define the nature and extent of Munitions and Explosives of Concern (MEC) and Munitions Constituents (MC) 18 contamination and assess the MEC and MC risk to human health and the environment. The FS, if required, shall 19 develop Remedial Action Objectives (RAOs) specific to the conditions that exist, or can reasonably exist in the 20 future throughout the site, and evaluate remedial alternatives against the nine criteria stated in the National 21 Contingency Plan (40CFR300.430(e)(9)). The proposed remedy shall be presented in the Proposed Plan and 22 selected in a Decision Document. 23 Work under this Performance Work Statement (PWS) falls within the Military Munitions Response Program 25 (MMRP) for the Impact Area (MRS 01), Fort Douglas, a Formerly Used Defense Site (FUDS), Project Number 26

J08UT110801. The Contractor shall perform all work in accordance with the references listed in Attachment 1. 27

2.0 BACKGROUND: 28

Camp Douglas was established as an Army post on October 26, 1862, and the name was changed on December 30, 29

1878, to Fort Douglas. Jurisdiction over 9,190 acres of land was ceded to the U.S. by the Governor of Utah in 1904. 30 The net area of the installation subject to the Findings and Determination is the 7,898.12 acres of Fort Douglas as 31 of 24 December 1941, which included 3,343.31 acres acquired in fee and 4,554.81 acres acquired by transfer. Fort 32 Douglas was established as an Army post and was declared a military installation by an Executive Order on 33

September 3, 1867. Government construction and improvements included 137 buildings, including training, 34 storage and administrative structures, family housing, and miscellaneous support facilities and utilities. In the later 35 1960s, the mission of the facilities was to support active Army and Armed Forces Reserve component training in 36 Utah, Idaho and Montana. Portions of the property were transferred to other entities beginning in 1874. The 37 majority of the area was disposed in the late 1940s and mid-1960s. Portions of Fort Douglas were conveyed to Salt 38 Lake City, the U.S. Department of the Interior, the State of Utah, the University of Utah, the Veterans 39 Administration, the U.S. Navy, the Shriners Hospital for Crippled Children, and the U.S. Department of Agriculture. 40 Currently, the property is owned by various entities, including those aforementioned, and many private 41 individuals. Two areas are still in active use by the Department of Defense and therefore not eligible for the 42 Formerly Used Defense Site program. These areas are a Naval and Marine Corps Reserve Center (approximately 15 43 acres) and an area of the former Fort Douglas occupied by the U.S. Army Reserve 96th Regional Support Command 44 (approximately 51 acres). According to the Preliminary Assessment of Eligibility for the Fort Douglas Toxic Exercise 45

Area (J08UT1103), 3651.22 acres of the original Fort Douglas acreage were found to be eligible as separate FUDS 46 Property. Therefore, the net eligible area under this property is 4,246.9 acres. 47

The 1,459-acre Impact Area MRS is in Salt Lake County, Utah and encompasses the land rising from eastern Salt 1 Lake City onto the front slopes of the Uinta-Wasatch-Cache National Forest. The MRS was used by the Army to 2 train infantry, cavalry, and artillery units between 1862 and the late 1960s. The MRS consists of the artillery 3 impact areas in the mountains. Munitions known or suspected to have been used on the MRS including small arms 4 munitions, grenades, rockets, riot control agents, bombs, illumination signals, and small and large caliber artillery 5 and mortar rounds. No MEC was observed during the Site Inspection (SI) field activities. However, MD including 6 the (inert) fuze assembly for a 3.5- inch diameter rocket, fragments of 37mm projectiles, expended .30 caliber ball 7 munitions, expended .50 caliber ball munitions, and two copper jackets from small arms were observed. MEC/MD 8 have historically been reported at the MRS. Based on the SI qualitative MEC risk evaluation, there is the potential 9 for an explosive safety risk at the MRS. 10

Several explosive ordnance disposal incident reports linked to Fort Douglas have been reported. These include 12 findings which involve 60mm practice mortars, a 12-in HE Stokes mortar, an 81mm mortar, a practice grenade, and 13 a cache of roughly 500 pre-World War II small arms rounds. Most of the area associated with the Impact Area MRS 14 is an uninhabited, national forest and mountainous land controlled primarily by the USDA Forest Service. A small 15 portion of the MRS runs along the eastern side of the University. Access to the MRS is unrestricted. 16

2.1 Additional site-specific information provided on Fort Douglas FUDS includes: 17

▪ Inventory Project Report (INPR) 18

▪ Archives Search Report (ASR) 19

▪ Site Inspection (SI) Report 20

▪ Geographic Information System (GIS) files 21

▪ Results of Systematic Project Planning sessions 1 and 2 (see Attachment 2). 22

2.2 Draft Uniform Federal Policy Quality Assurance Project Plan (UFP-QAPP) Worksheet #10, Conceptual Site 23 Model (CSM), and Worksheet #11, Data Quality Objectives steps 1 through 4 is provided in Attachment 2. 24

The worksheet identifies: 25

▪ RI and FS problem statements as they are currently understood; 26

▪ The goals of the data collection for the RI and FS as they are currently understood; 27

▪ The information inputs that have tentatively been identified to fill data gaps in the preliminary CSM and 28 answer the RI and FS study questions; and 29

▪ The boundaries of the project as they are currently understood. 30

3.0 GENERAL REQUIREMENTS: 31

3.1 Contractor Methods: This is a performance-based task order. The performance objectives and standards 32 included herein are the basis of the task order requirements. The technical approach and level of effort 33 expended to achieve task order objectives and standards are the responsibility of the Contractor. The 34 Government recognizes the contractor’s right to change the technical approach and level of effort from that 35 originally proposed. Any such changes shall be made in accordance with the approved UFP-QAPP; and shall 36 meet all project objectives and gain Government Quality Assurance acceptance in order to receive 37 payment. 38

3.2 Quality monitoring: The contractor will be evaluated periodically during performance of this task order to 39 ensure compliance with the proposed and accepted performance goals, regulations, guidance, and to 40 document that acceptance criteria, performance metrics, delivery schedule, and the overall schedule for 41 completion is being met. This evaluation will be performed according to the Quality Assurance Surveillance 42 Plan (QASP) provided in Attachment 3. Failure to adequately complete any service or product to at least a 43 satisfactory level of quality or timeliness may result in a repeat of the work, and/or a less than satisfactory 44 performance evaluation, or both. 45

3.3 Performance Standards: Performance standards are addressed in each task. 46

3.4 Task Incentives/Disincentives: Satisfactory or greater Contractor Performance Assessment Reporting 1 System (CPARS) rating/ less than satisfactory CPARS rating and re-performance of work at contractor’s 2 expense. 3

3.5 Acceptance Criteria: Task will be considered complete and acceptable once all objectives are achieved, all 4 minimum quality requirements are met, and all task-specific deliverables receive Army approval, through 5 the Contracting Officer’s Representative (COR). 6

3.6 Document review and approval: The USACE COR is the approval authority on all deliverables. The schedule 7 for document reviews shall be in accordance with the deliverable schedule included as Attachment 4. 8

3.7 Task pricing: A pricing schedule is provided in a separate file. 9

3.8 Contracting Officer Requirements: Only a warranted Contracting Officer (either a Procuring Contracting 10

Officer (PCO) or an Administrative Contracting Officer (ACO)), acting within their delegated limits, has the 11 authority to issue modifications or otherwise change the terms and conditions of this contract. The 12 contractor shall accept directions only from the USACE Contracting Officer (KO) or the duly authorized COR. 13 Requests made directly to the contractor by anyone other than the KO or COR will be immediately brought 14 to the attention of the KO and COR. The KO must authorize any changes to the project scope or other 15 provisions of this PWS in writing. In the event the contractor makes any changes at the direction of any 16 person other than the KO, the change will be considered to have been made without authority and no 17 adjustment will be made in the contract price to cover any increase in costs. 18

3.9 Security Requirements: 19

▪ Pre-screen candidates using E-verify Program. The contractor must pre-screen candidates using the E-20 verify Program http://www.dhs.gov/E-verify website to meet the established employment eligibility 21 requirements. The vendor must ensure the correct information is entered into the E-verify system. An 22 initial list of verified/eligible candidates must be provided to the COR no later than 3 business days after 23 the initial contract award. Update list as candidates are added to the team. 24

3.10 For each project the contractor shall prepare one UFP-QAPP and one remedial investigation report. If a 25 project contains multiple munitions response sites, the contractor shall prepare separate feasibility 26 studies, proposed plans, and decision documents for each one. 27

4.0 Specific Tasks 28

4.1 Task 1, Project Management and Systematic Project Planning (CLIN 0100): This is a Firm Fixed Price task. 29

4.1.1 Objectives: Prepare and execute a Project Management Plan (PMP) and implement Systematic Planning 30 Process (SPP) in order to design a RI and, if required due to existing or potential risk to human health and 31 the environment by the site, prepare a FS. 32

4.1.2 Performance Standards: 33

▪ Prepare the PMP in accordance with Engineer Regulation (ER) 5-1-11 and Engineer Manual (EM) 200-1-34

15. 35

▪ Throughout the lifecycle of the project, manage in accordance with the approved PMP. 36

▪ Contractor plans meetings to effectively meet schedule and to keep Government updated on 37 performance of tasks. 38

▪ Meetings address all requirements per PWS, are conducted professionally, and are productive and 39 necessary. 40

▪ Meeting materials are received by the Government at least 36 hours prior to meeting. (Meetings may be 41 cancelled or rescheduled if meeting materials are delivered late.) 42

▪ Submit meeting minutes within 7 days of meeting and resubmit revisions as requested within 7 days of 43 receiving corrections. 44

▪ All changes in plans are communicated to Government and include safety considerations and risk 45 mitigation. 46

▪ QASP remains up to date and accurate through coordination between the Contractor and the 1 Government. 2

▪ Updates to the QASP recommended to the Government within 30 days of changes to scope, approach or 3 work plan 4

▪ Achieve the objectives of each SPP phase referring to the “Munitions Response-QAPP Toolkit Module 1: 5 Remedial Investigation (RI)/Feasibility Study (FS),” also known as “MR-QAPP”, UFP-QAPP Manual and 6

Worksheets, EPA QA/G-4, EM 200-1-15 and applicable Interim Guidance Documents. 7

▪ Provide monthly progress reports that include the following for each project: updated schedule, 8 explanation of schedule changes and anticipated impact on performance of requirements, status of 9 action items from previous month, summary of any meetings held during previous month, task status 10

(planned, in progress, completed), changes in personnel, safety report, and percent (dollars) complete for 11 contract. Monthly reports shall be provided to the USACE PM (and any additional team members 12 identified by the USACE PM) by the 6th day of the following month. 13

▪ Deliverables are accurate, contain the most current information, meet all requirements of the task per 14 the PWS and are submitted on time as per the deliverables schedule. 15

▪ Assessments, evaluations, analyses, and recommendations are thorough, reliable, clearly presented. 16

4.1.3 Specific Task Requirements: 17

4.1.3.1 Project Management General (CLIN 0101) 18

▪ Prepare for and attend a project kick-off meeting, to be conducted virtually. Meeting shall include, at a 19 minimum, the Contractor’s project manager, project geophysicist, and program geophysicist. 20

▪ Prepare, submit, and gain USACE approval of a PMP that is detailed and comprehensive covering all 21 aspects of the Task Order, including payment milestones. This document is a living document and shall be 22 updated as necessary. 23

▪ Coordinate with the Government on maintaining the Quality Assurance Surveillance Plan since Quality 24

Assurance Surveillance is dependent upon technical approach. Upon Government acceptance of PMP and 25 UFP-QAPP and after scope changes to the TO (such as an option is exercised), propose surveillance 26 methods and procedures (who, what, where, when) for updated tasks. 27

▪ Prepare for and attend in-progress review (IPR) meetings. IPR meetings shall include but are not limited 28 to, regular feedback to the Government, as determined in the PMP, on the progress of its work through 29 email and regularly scheduled telephone conversations. 30

▪ Provide monthly progress reports that include the following for each project: updated schedule, 31 explanation of schedule changes and anticipated impact on performance of requirements, status of 32 action items from previous month, summary of any meetings held during previous month, task status 33 (planned, in progress, completed), changes in personnel, safety report, and percent (dollars) complete for 34 contract. Monthly reports shall be provided to the USACE PM (and any additional team members 35 identified by the USACE PM) by the 6th day of the following month. 36

4.1.3.2 Systematic Project Planning (CLIN 0102) 37

▪ Utilize the SPP process to finalize project-specific DQOs; the MEC and MC CSMs; and all UFP-QAPP 38 worksheets. 39

▪ Plan for meetings to occur in accordance with Figure 9-1 of the MR-QAPP. Planning sessions #1 and #2 40 have been conducted and the draft Worksheet #10 and Worksheet #11 are provided in Attachment 2. 41 Planning sessions #3, #4, #5, and #6 are required to be facilitated by the Contractor. Assume that two 42 meetings will be one-day, in-person meetings, and two will be conducted virtually. The Contractor may 43 propose to deviate from the structure of the MR-QAPP if the basis for deviation is justified and accepted 44 by the Government. 45

▪ Prepare and submit for acceptance an Abbreviated Accident Prevention Plan (AAPP) if a site visit is 46 planned prior to acceptance of UFP-QAPP. 47

▪ Submit meeting materials at least two weeks in advance (three weeks recommended to allow sufficient 48 time to respond to comments, gain approval, and provide to stakeholders at least one workday before 49 the meeting). Meetings held are organized; accomplish requirements of the SPP process; and are 50 conducted in a professional manner. 51

▪ Organize and coordinate all meetings; involve all stakeholders, upon approval by the Government; and be 1 responsible for the logistics of these meetings to include, but not limited to, providing a facilitator, 2 obtaining meeting location, and sending invitation letters (pending Government review and acceptance). 3

▪ Use the UFP-QAPP Worksheet #9 to document SPP meetings and outcomes. 4

▪ Utilize statistical methods (such as Visual Sample Plan (VSP) software) to support the decision-making 5 processes used to characterize both MEC as well as munitions MC. 6

▪ Include process of considering, incorporating, documenting, and evaluating the benefits of green and 7 sustainable remediation (GSR) practices Pursuant to the DoD Memorandum “Consideration of Green and 8 Sustainable Remediation Practices in the Defense Environmental Restoration Program” (DoD, 2009) and 9 EP 200-1-10, Green Building Technology in Hazardous Waste Cleanup Applications, GSR employs 10 strategies throughout the remedial process that: 11

- Use natural resources and energy efficiently; 12

- Reduce negative impacts on the environment; 13

- Minimize or eliminate pollution at its source; 14

- Protect and benefit the community at large; and 15

- Reduce waste to the greatest extent possible 16

4.1.3.3 Additional In-Person Planning Meeting (CLIN 0103) (OPTIONAL TASK): This is a Firm Fixed Price task. 17

▪ Submit meeting materials at least two weeks in advance and gain approval of meeting materials at 18 least five (5) federal working days prior to the meeting. Meetings held are organized; accomplish 19 requirements and goals set by USACE PM; and are conducted in a professional manner. 20

▪ Organize and coordinate meeting; involve all stakeholders in coordination with and upon approval by 21 the Government; and be responsible for the logistics of these meetings to include, but not limited to, 22 providing a facilitator, obtaining meeting location, sending invitation letters (pending Government 23 review and acceptance), taking meeting minutes and coordinating acceptance of those minutes by all 24 attendees, and providing digital or paper presentations. 25

4.2 Task 2, Project Documents (CLIN 0200): This is a Firm Fixed Price task. 26

4.2.1 Objective: Prepare, submit and gain USACE acceptance of a UFP-QAPP, Accident Prevention Plan 27 (APP)/Site Specific Health Plan (SSHP), and Explosive Site Plan (ESP). 28

4.2.2 Performance Standards: 29

▪ Prepare the UFP-QAPP in accordance with Intergovernmental Data Quality Task Force UFP-QAPP Manual 30 and Worksheets (March 2012) and the MR-QAPP; EM 200-1-15; EM 385-1-1; EM 385-1-97 including 31

Errata Sheets and Changes; General Data Validation Guidelines and the State of Utah regulatory guidance, 32 as appropriate. Contractor shall also enter data into FUDSChem. 33

▪ See Attachment 5 for crosswalk for Optimized UFP-QAPP and MR-QAPP worksheets. 34

▪ UFP-QAPP content related to MC shall meet the requirements of DoD Quality Systems Manual (QSM) for 35

Environmental Laboratories (current version). 36

▪ The APP/SSHP must be approved by the government before field work can commence. 37

▪ Prepare required submission in accordance with DESR 6055.09, Edition 1, EM 385-1-97, and Errata Sheet 38

#3 as a standalone document. 39

▪ Deliverables are accurate, contain the most current information, meet all requirements of the task per 40 the PWS and are submitted on time as per the deliverables schedule. 41

▪ Drafts contain 5 or fewer grammar plus spelling errors. 42

4.2.3 Specific Task Requirements: 43

4.2.3.1 UFP-QAPP (CLIN 0201) 44

▪ Include a phased approach for the MC elements of the UFP-QAPP, address contaminants of interest, 45 sample media (soil/groundwater/sediment/surface water/air), background, and methods that will be 46 utilized to ensure that data generated are of an acceptable quality for its intended use. The contractor 47 shall discuss quantity, quality and the methods used to verify adherence to the precision, accuracy, 48 representativeness, comparability, completeness, and sensitivity (PARCCS) parameters for sample 49 collection, handling, laboratory analysis, verification and validation. 50

▪ For MC, prepare a risk assessment work plan as part of the overall project work plan incorporating 1 implementation of the risk assessment and methodologies per USEPA Risk Assessment Guidance for 2

Superfund (RAGS), State regulatory guidance, and USACE EM 200-1-4, Volumes I and II, as appropriate; 3 and for MEC in accordance with the 7 February 2019 HQUSACE memorandum, “Subject: Trial Period 4 Extension for Risk Management Methodology (RMM) at Formerly Used Defense Sites (FUDS) Military 5 Munitions Response Program (MMRP) Projects.” 6

▪ Provide a firewall plan that assures all seeding information cannot be viewed or otherwise obtained by or 7 made available to any personnel except those inside the firewall. Appropriate personnel shall be 8 identified as part of the SPP process and include communication drivers with stakeholders. 9

▪ Supplement the UFP-QAPP with standard operating procedures (SOPs) associated with the remedial 10 action. Examples: Additional Project Tasks (e.g., Biological and Cultural) & SOP’s not listed in MR-QAPP 11 Module 1, e.g., utility permits (if required), evacuation and establishing controlling exclusion zones, 12 vegetation removal, surface removal of MEC, MD, MPPEH, RRD, reacquisition of anomalies, intrusive 13 investigation of near surface anomalies, blow in place MEC items, and MEC consolidation. SOP’s that 14 would be expected to be included: anomaly avoidance, brush clearing, civil surveying, surface clearance & 15 intrusive operations for near surface anomalies, demolition operations, explosives management. These 16 can be individual SOP’s or combined into single MMRP Field operations SOP. 17

▪ Include a section after the title page that illustrates the changes made to the “black” text from the MR-18

QAPP, module 1, template. The rationale for these changes must be specifically identified, documented, 19 and concurred upon by the project team. 20

▪ Incorporate all requirements from the Cultural and Biological Resources Work Plan into the UFP-QAPP 21 prior to regulatory review of the Draft Final UFP-QAPP. 22

▪ Attach all approved Cultural and Biological Technical Memorandums to the approved UFP-QAPP. Note: 23 The Contractor must adhere to the Freedom of Information Act and Section 304 of the NHPA so some or 24 all the Cultural Technical Memorandums may be excluded from this requirement as determined by the 25 USACE Archaeologist. 26

▪ The Contractor shall submit the draft UFP-QAPP and subsequent revisions to Army for review and 27 approval, through the USACE PM, until the final UFP-QAPP is accepted. 28

4.2.3.2 Site Safety and Health Plan (SSHP) and Accident Prevention Plan (APP) (CLIN 0202) 29

▪ The contractor will prove with all pertinent provisions of the latest version of the U.S. Army Corps of 30 Engineers Safety and Health Requirements Manual, EM 385-1-1. 31

▪ The level of detail provided in the APP/SSHP shall be tailored to the type of work, complexity of 32 operations to be accomplished, and the hazards anticipated. 33

▪ The contractor shall ensure that its subcontractors, suppliers, and support personnel comply with the 34 approved APP/SSHP at no additional cost to the Government. 35

▪ Ensure that its subcontractors, suppliers, and support personnel comply with the approved APPs/SSHPs at 36 no additional cost to the Government. 37

4.2.3.3 Explosive Site Plan (ESP) (CLIN 0203) 38

▪ Obtain approval of the document from the Environmental and Munitions Center of Expertise (EM CX), 39

U.S. Army Technical Center for Explosives Safety (USATCES), and the Depart of Defense Explosives Safety 40 Board (DDESB). 41

▪ Designate a single individual who shall work directly with the designated Project Lead OESS in order to 42 quickly and smoothly route the document through each of the reviews. This document will be in 43 electronic format only and not staffed through the Project Delivery Team (PDT), except for the designated 44 OESS. It will be reviewed by the Project Lead OESS, EMCX, U. S. Army Technical Center for Explosives 45

Safety (USATCES), and DDESB, with possible comments and changes required numerous times from each 46 reviewer. The designated OESS will orchestrate all the reviews. The document will not be labeled Draft, 47 Draft-Final or Final. 48

▪ Once final approval is obtained, copies of the ESP along with all approvals will be combined into one 49 document and provided to the USACE PM and the ESP shall be added to the QAPP as an appendix. No 50 fieldwork shall begin without an approved ESP. 51

4.3 Task 3, Community Relations Support (CLIN 0300): This task is a Firm Fixed Price task. 52

4.3.1 Objectives: Prepare, submit and gain USACE acceptance of a CRP, also known as a Public Involvement 1 Plan (PIP). Successfully complete public meetings and support the USACE Sacramento District with 2 community relations. 3

4.3.2 Performance Standards: 4

▪ Prepare the CRP in accordance with EP 200-3-1, ER 200-3-1, EP 1110-1-18, guidance provided in the FUDS 5

Public Involvement Toolkit and the DENIX UXO Safety Website, http://denix.osd.mil/uxo/. 6

▪ Conduct community relations in accordance with the accepted CRP. 7

▪ Deliverables are accurate, contain the most current information, meet all requirements of the task per 8 the PWS and are submitted on time as per the deliverables schedule. 9

▪ Drafts contain 5 or fewer grammar plus spelling errors. 10

4.3.3 Specific Task Requirements: 11

▪ Assist in planning and facilitating three (3) public meetings. These meetings are different from and in 12 addition to SPP meetings but should be scheduled at the same time as SPP meetings whenever possible 13 for efficiency. Meetings shall be held near the project site; specific location to be determined as part of 14 the CRP development. Support shall include providing a meeting facilitator, preparation and delivery of 15 briefings, graphics, maps, posters, provide sound equipment as needed, public notification, preparing 16 correspondence, professionally recording the meetings and routing meeting minutes through reviews, 17 and support of question and answer sessions during public meetings. NOTE: If in person meetings are not 18 possible or in the best interest of the government, the Contractor shall host virtual meetings. For 19 proposal purposes assume that one (1) meeting will be held virtually and two (2) meetings will be held in 20 person near Salt Lake City, Utah.Prepare and deliver stakeholder surveys; review and present survey 21 findings; complete of stakeholder interviews.Gain Government approval for all materials prior to them 22 being presented/distributed to the public. 23

4.4 Task 4, Geospatial Data (CLIN 0400): This is a Firm Fixed Price task. 24

4.4.1 Objective: Utilize a GIS in the development of the CSM and maintain and manage all project and 25 geospatial data. 26

4.4.2 Performance Standards: 27

▪ Manage and maintain project data in GIS in accordance with ER 1110-1-8156, EM 1110-1-2909, EM 1110-28

1-1200, and EM 200-1-15. 29

4.4.3 Specific Task Requirements: 30

▪ Develop CSM in GIS. The Geospatial Data Package shall include all forms of data to include raster, vector, 31 tabular and any other form of applicable data to produce a comprehensive CSM. 32

▪ Perform a pre- and post-project RI geospatial data analysis using a GIS. 33

▪ Consolidate all available existing data applicable to the project into the project’s GIS database. Analyze 34 and relay pertinent information to the Project Delivery Team (PDT). 35

▪ Document the information attained through the pre-RI analysis in the QAPP. 36

▪ Document the information attained in the post-RI and FS analysis in the RI and FS reports. 37

▪ Incorporate social, environmental, and economic entities that will be or may be impacted by or affect 38 response-action activities into the pre-RI analysis and represent that data within the GIS. Data examples 39 include census, tax maps, maps of historical sites, soil type maps, hydrologic maps, maps of vegetation 40 cover and vegetation types, transportation maps, etc. 41

▪ Incorporate details of entities impacted by RI/FS activities and impacts of future response action activities 42 (if applicable) in the post-RI and FS analysis and represent the data within the GIS. Data examples include 43 city/county jurisdictions, land parcels, fauna, flora, structures, landowners, homeowners, rental tenants, 44 schools, utilities, roads, businesses, recreational areas, air traffic, water bodies, and industries, etc. 45

▪ Detail the fieldwork strategies, areas of concern, survey requirements, environmental concerns, 46 milestones and/or other factors that affect product delivery and future action planning in the pre- and 47 post-RI and FS analyses. 48

▪ Provide the Government and Stakeholders internet access to the GIS database. The database shall be 49 accessible by USACE at all times and be a living repository that is refined throughout the life of the 50 project. 51 http://denix.osd.mil/uxo/

▪ Include data layers that identify site discoveries. Data types include: locations of subsurface anomalies, 1 identified by sensor type; MEC; munitions debris (MD); other debris; advanced geophysical classification 2

(AGC) source parameters; sampling locations; areas of unique or specific MEC risk determination; areas of 3 unique or specific MC risk determination; cultural resources; environmental, biological, and socio-4 economic information. 5

▪ Include all archeological data in the GIS Database, but ensure it is not released to the public without 6 written permission from USACE. 7

▪ Include all GIS metadata, geodatabases, layers etc. created, developed or modified under this task order 8 in original format in Final GIS deliverable. This deliverable shall meet QA acceptance prior to payment of 9 final invoice. 10

▪ Maintain a geo-referenced permanent record of the investigation during the fieldwork and deliver as part 11 of the RI report. MEC and MD items shall be individual data points, including information regarding depth 12 to geometric center, type, and orientation. 13

4.5 Task 5, Right-of-Entry Support (CLIN 0500): This is a Firm Fixed Price task. 14

4.6.1 Objective: Assist the District in obtaining property Right of Entry (ROE). 15

4.6.2 Performance Standards: 16

Maintain and update property GIS data for all landowners within the project boundaries. 17

4.6.3 Specific Task Requirements: 18

Preserve property owner privacy. Property owner names shall not be disseminated in any 19 documents. 20

Contact property owners, as needed by mail, phone, or in person, in order to assist USACE in 21 obtaining and maintaining ROEs. The Contractor must clearly identify themselves as a Contractor 22 employee. 23 Assist with creating, printing and mailing 2nd and 3rd letters to landowners, calling landowners, and 24 maintaining database of landowner information and status of ROEs. Assume for proposal purposes: 25 50 landowners per mailing. 26

4.6 Task 6, RI/FS Field Activities (CLIN 0600): This is a Firm Fixed Price task. 27

4.6.1 Objective: Conduct a RI in accordance with CERCLA, as amended, and Department of Defense (DoD), 28 Department of Army (DA) and the United States (US) Army Corps of Engineers (USACE) Regulations and 29

Guidance characterizing the nature and extent of MEC and MC and identify and estimate costs and/or 30 negative impacts associated with biological and cultural resource management for each remediation 31 alternative at Impact Area Munitions Response Site (MRS) at former Fort Douglas. 32

4.6.2 Performance Standards: 33

▪ Demonstrate that the work was performed in accordance with the accepted Biological and Cultural Work 34

Plans, UFP-QAPP and approved Field Change Requests stemming from planning sessions that occur during 35 the project lifecycle, and in accordance with all applicable laws, regulations, and guidance documents and 36 that all DQOs were achieved. 37

▪ Demonstrate that biological and cultural data from the RI is sufficient to develop detailed cost estimates 38 to perform resources management for each remedial alternative. 39

▪ Demonstrate that biological and cultural data from the RI is sufficient to analyze impacts to biological and 40 cultural resources for each remedial alternative. 41

▪ TO requirements met with little rework/re-performance required and with few minor and no significant 42 problems encountered 43

▪ Performance meets all technical and functional requirements, and the Contractor is highly responsive to 44 changes in technical direction and/or the technical support environment. 45

▪ Deliverables are accurate, contain the most current information, meet all requirements of the task per 46 the PWS and are submitted on time as per the deliverables schedule. 47

▪ Drafts contain 5 or fewer grammar plus spelling errors. 48

4.6.3 Specific Task Requirements: 49

4.6.3.1 MEC and MC Characterization (CLIN 0601) 1

4.6.3.1.1 General 2

▪ Provide all assumed quantities in the proposal, based on the draft Worksheet #11, DQOs, provided by the 3

Government. 4

▪ Update the CSM to describe the predicted horizontal and vertical distributions of MEC necessary to assess 5

MEC risk and estimate alternative costs in the FS. 6

▪ Distinguish between Low Use Areas (LUAs) and No Evidence of Use (NEU) areas in accordance with the 7 criteria outlined in the UFP-QAPP. 8

▪ Demonstrate that data inputs from the RI will be sufficient to develop detailed cost estimates for 9 remedial alternatives. The work and reporting shall estimate the anomaly densities across identified MEC 10 contaminated areas as well as other remediation cost drivers such as vegetation type and density, terrain 11 conditions, soil type, exclusion zone evacuation costs, etc. 12

▪ Provide a data delivery system (SharePoint, external hard drives, etc.) to deliver all interim and final 13 electronic data. All detection data collection shall be at risk to the contractor without concurrence on the 14

Instrument Verification Strip (IVS) Memorandum results by USACE. 15

▪ Restore all areas to their original condition; all access/excavation/detonation holes shall be backfilled. 16

4.6.3.1.2 Geophysical 17

▪ To the maximum extent practicable, conduct the field investigation by gathering AGC data in addition to 18 data that is digitally recorded and geo-referenced (geo-referencing need be no more accurate than is 19 needed for the use of the data). If AGC is not proposed for any areas within the MRS, the contractor’s 20 proposal must include rationale as to why other technologies are selected and how they will achieve all 21 project DQOs. 22

▪ Ensure the Contractor, or Subcontractor in charge of performing the ACG work, is accredited in 23 accordance with the DoD Advanced Geophysical Classification Accreditation Program (DAGCAP). DAGCAP 24 accreditation and AGC requirements shall be in compliance with the Office of the Secretary of Defense 25 (OSD) Policy Memo dated 11 April 2016 and the FUDS AGC Policy Memo dated 6 January 2017. The 26

DAGCAP accreditation must be current at the time of signing the final QAPP and throughout all fieldwork, 27 analysis, data usability assessment, and reporting. In accordance with DAGCAP, all data to include 28 detection surveys and intrusive investigation will fall under the DAGCAP accredited organization. 29

▪ Collect geophysical data along transects spaced no more than 100 meters apart in order to demonstrate 30 that all areas with elevated anomaly density that have the potential to be High Use Area (HUA) are 31 traversed at the completion of fieldwork and that there is a 100% chance of detecting these areas 32 according to the VSP analysis. 33

▪ Demonstrate that the boundaries of all identified HUAs have been defined to within +/- 250 feet, or as 34 otherwise specified in the UFP-QAPP. 35

4.6.3.1.3 Material Potentially Presenting an Explosive Hazard (MPPEH) Handling/Waste Disposal 36

▪ Process and dispose of MEC and MD encountered in accordance with approved plan(s). 37

▪ Inspect all MPPEH in accordance with DODI 4140.62, DESR 6055.09, EM 385-1-97 and applicable Errata 38

Sheets. 39

▪ Maintain a detailed accounting of all MEC and MD and range-related debris (RRD) encountered. This 40 accounting shall include: amounts of MEC and MD; nomenclature; location and depth of MEC; location of 41 MD and RRD; and final disposition. The accounting system shall also account for all demolition materials 42 utilized on site. Digital photographs of MEC and examples of MD found during the investigation are to be 43 taken. 44

▪ Dispose of any waste or hazardous waste created during the investigation in accordance with all 45 applicable DoD, DA, USACE regulations and guidance and Federal and State laws, regulation and guidance 46 rules and regulations. This includes properly containerized, staged, secured, labeled, sampled and 47 analyzed (if required) in accordance with the accepted UFP-QAPP. The Contractor shall perform disposal 48 actions for all waste items meeting all applicable regulations and dispose of all waste items in a timely 49 manner. Disposal facilities shall be identified by the contractor and submitted for acceptance by the 50 government. 51

4.6.3.1.4 MC Sampling and Analysis 1

▪ Perform MC analyses as required, in accordance with the requirements of the DoD QSM (current version) 2 and the approved project specific UFP-QAPP. Data shall be entered into FUDSChem, as appropriate (see 3 Attachment 6). Validation shall be performed in accordance with Environmental Data Quality Workgroup 4 General Data Validation Guidelines, dated 9 February 2018. 5

▪ Utilize laboratories that are DoD Environmental Laboratory Accreditation Program (DoD ELAP) 6 accredited, that conform to the most recent version QSM, and utilizes the most recent version of the SW-7 846 EPA Analytical Methods. Use of an analytical laboratory that is National Environmental Laboratory 8 Accreditation Program (NELAP) certified under the required fields of testing it is encouraged. NELAP relies 9 on consensus standards representing the best professional practices in the industry to establish the 10 requirements for this program, which is then implemented by state agencies recognized by The NELAC 11 Institute (TNI) as Accreditation Bodies. Errors such as inadequate methodologies in the laboratory 12 processing may reflect on the contractor’s rating. All inadequacies shall be addressed prior to the 13 acceptance of the UFP-QAPP. If they cannot be addressed to the satisfaction of the KO, the contractor 14 shall find a laboratory that can successfully perform the requirements of the project at no additional cost 15 to the government. The Contractor shall notify the USACE Project Manager for laboratory failure to meet 16 certification criteria in accordance with the requirements of their accreditation for analyses that are 17 conducted as part of this task order. If, for any reason, the laboratory responsible has their accreditation 18 suspended or revoked, the contractor shall identify an alternate laboratory to complete the task order at 19 no extra cost to the Government. Work shall be in accordance with DoD QSM (current version). 20

▪ Propose and perform the stated quantity, quality and the methods used to verify adherence to the 21 PARCCS parameters for sample collection, handling, laboratory analysis, verification and validation. 22

▪ Ensure that data generated are of an acceptable quality for its intended use, address contaminants of 23 interest and sample media. 24

▪ Submit field and laboratory data in a format compatible with USACE FUDSChem requirements. 25

▪ Use a DOD ELAP-certified laboratory for all the laboratory methods to be performed: 26 http://www.denix.osd.mil/edqw/Accreditation/index.cfm. 27

▪ Submit field sampling Standard Operating Procedures (SOPs) and laboratory preparation methods for any 28 analyses without published ISM Preparation Methods to government chemist review. 29

4.6.3.2 Cultural and Biological Resource Management (CLIN 0602) 31

4.6.3.2.1 General and Work Plan 32

▪ Demonstrate that data from the RI will be sufficient to develop detailed cost estimates for remedial 33 alternatives. The work and reporting shall estimate all biological and cultural cost drivers such as 34 vegetation type and density, terrain conditions, soil type, biological resources, archaeological 35 resources, etc. 36

▪ Prepare and gain approval for a Biological and Cultural Resources Work Plan (Work Plan). A pre-draft, 37 draft, final Work Plan shall be submitted to USACE; the Work Plan must be accepted by USACE prior to 38 mobilization of RI field work. The Work Plan will become an attachment to the MR-QAPP. The Work 39 Plan shall include records research, survey protocols, general survey schedule, monitoring protocols, 40 detailed schedule for transects, qualifications for those performing the monitoring, and safety and 41 compliance services including training and awareness programs. The plan will also address vegetation 42 trimming and/or clearance. The Contractor shall mulch in place or haul for offsite disposal in 43 accordance with this work plan. 44

▪ Amend the Work Plan to include an attachment detailing the change(s) made to the Final Work Plan. 45

All changes shall be coordinated and approved by USACE. These changes should also be discussed in 46 the survey reports. 47

▪ As an appendix to the Work Plan the Contractor shall prepare draft correspondence for the USACE to 48 modify for coordination with interested Tribes and the Utah State Historic Preservation Officer 49 regarding identification of historic properties. The USACE district archaeologist will provide examples 50 of sample correspondence, if requested. 51

▪ Conduct Biological and Cultural records and research searches and summarize available literature and 1 reports in the Work Plan. 2

▪ Coordinate with stakeholder archaeologists and biologists (through USACE) to understand the 3 resources present within the RI Area of Potential Effects (APE), defined as the FUDS RI geophysical 4 investigation footprint, access, and any staging required for the geophysical investigations and include 5 these in the Work Plan. 6

▪ Perform background research for previous archaeological and historic inventories and evaluations 7 work performed within a ¼-mile radius of the RI APE and include in the Work Plan. 8

▪ Provide the completed records search to the USACE archaeologist for review prior to incorporating 9 into the Work Plan (assume review time of 10 workdays). 10

▪ For biological resources work, obtain a current list of endangered species and critical habitat that may 11 occur within the project area from the National Marine Fisheries Service (NMFS), and/or the USFWS. 12 The Contractor shall identify any listed, proposed species (and candidate or species of concern, if 13 appropriate), and designated or proposed critical habitat, that are known or have the potential to 14 occur on site or in the vicinity of the project area. All data from this requirement shall be summarized 15 sufficiently in the Work Plan. 16

▪ Perform appropriate level pre-project environmental surveys to determine whether special status 17 species or their suitable habitat is present in the work area. 18

• Include surveys for rare plants in accordance with the procedures of applicable Utah protocols; 19

• For the purposes of these surveys, no specimens of potentially special status plants shall be 20 collected. 21

• Include surveys for Migratory Bird Treaty Act protected species, their habitats, and nests; 22

• Include surveys to determine the location and extent of wetlands and any features regulated 23 under the Clean Water Act, if any are present. 24

• Include surveys to determine if project may be inhabited by the following Federally protected 25 species: Yellow-billed cuckoo (Coccyzus americanus), Canada Lynx (Lynx canadensis), and Ute 26

Ladies’ tresses (Spiranthes diluvialis). 27

▪ Include protocols for Surveying and Evaluating Impacts to Special Status Native Plant Population and 28 Sensitive Natural Communities in the Work Plan. 29

▪ Conduct Environmental Awareness Training prior to commencement of field work. The Contractor’s 30 biological monitor will deliver worker environmental awareness training to all personnel who will work 31 on site. Additional training shall be conducted for new personnel and any time site conditions change. 32 The training must be detailed enough to prevent violations of any protective measures. 33

▪ Instruct all personnel to recognize signs of prehistoric use, and to report any such finds (or suspected 34 finds) immediately, so damage to such resources may be prevented. 35

▪ Develop and execute an Invasive Plant Control Program. All equipment and vehicles will be cleaned of 36 all attached mud, dirt, and plant materials prior to arriving on-site to prevent the introduction and 37 spread of invasive plant species in accordance with Executive Order 13751, Safeguarding the Nation 38 from the Impacts of Invasive Species. 39

▪ This work is being done under CERCLA and is therefore exempt from obtaining permits, however 40 substantive requirements must be followed. 41

4.6.3.2.2 Cultural Resource Monitoring 42

▪ Assume that if monitors are present for all non-intrusive work (such as transects) no survey is needed 43 prior to non-intrusive fieldwork. Monitors shall be provided for non-intrusive transect geophysical 44 work, for MC sampling, and as determined by the Cultural Survey within the high-density area per the 45 Cultural Technical Memorandum. 46

▪ Provide qualifications of the Secretary of Interior Qualified (SOI) archaeologists performing the 47 monitoring to USACE Archaeologist for approval. The SOI-qualified archaeologist may be supported by 48 archaeological technicians during cultural resource management fieldwork tasks. 49

▪ Have an approved Archaeological Monitor present to monitor all non-intrusive fieldwork (transects) 50 completed on foot. (NOTE: If surveys are completed for transects then monitors may only be needed 51 for identified areas for transect work.) The monitor shall work with the geophysical investigators and 1 UXO safety team to help navigate and avoid all archaeological finds identified during RI geophysical 2 transects. Any finds will be reported to the USACE archaeologist in the daily monitoring logs. 3

▪ Have an approved Archaeological Monitor provide pre-work orientation for the Contractor’s 4 employees. All personnel involved in RI geophysical investigation activities will undergo an orientation 5 from the Contractor’s Archaeological Monitor regarding recognition of historical and archaeological 6 objects that could be discovered during project activities, and steps to be taken if objects are found. 7 The orientation will take place prior to the initiation of RI geophysical investigation work. Should any 8 new personnel be brought in after the initial training, it is the responsibility of the Contractor’s 9 Archaeological Monitor to provide the training within a week of that person(s) starting work. 10

▪ Complete intrusive fieldwork in accordance with Cultural Technical Memorandum (which states when 11 Archaeological Monitors must be present). 12

▪ Ensure proper implementation of protective measures. The purpose of the Contractor’s Archaeological 13 Monitor is to inspect soil and other material as work proceeds to make a determination if potentially 14

NRHP-eligible cultural resources or human remains are present. If potentially significant resources are 15 discovered, the subsequent work shall be moved in order to avoid damage. 16

▪ Have an approved Archaeological Monitor complete and maintain daily monitoring logs. These logs 17 shall include, at minimum, written descriptions of the areas monitored, project activities in those 18 areas, Contractor’s compliance/noncompliance with avoidance measures and report incidents of non-19 compliance, and photographs, as appropriate. Include descriptions of any find(s) and the response to 20 the find(s). Submit the daily monitoring logs electronically on a weekly basis to the Contracting Officer 21 and USACE Archaeologist, no later than the Friday following each work week. 22

▪ Record all new archaeological sites and isolated items encountered during monitoring and update site 23 forms for previously recorded sites using the Utah State DPR forms. Each site shall be evaluated for the 24 National Register of Historic Places and eligibility recommendations shall be provided with the 25 monitoring report. 26

▪ Document any archaeological sites and/or artifacts with digital photographs. Photo logs shall be kept 27 indicating GPS points, the site number, the subject of the photograph, and the cardinal direction of the 28 photograph. 29

▪ Submit all GPS data as exportable GPS files in GIS format. Coordinates must be Utah UTM Zone 12, 30 NAD-83 datum, and in meters. Horizontal accuracy must be +/-3 meters. In the event uncorrected GPS 31 positions do not meet this requirement, the Contractor must differentially correct positions to within 32 +/- 3 meters accuracy. The Contractor’s Archaeologist shall capture all previously and newly recorded 33 sites, features and concentrations (locus) utilizing GPS/GIS. The Contractor shall deliver GIS data to 34 include all electronic survey data either in ESRI Shapefile format or in an ESRI Personal or File 35 geodatabase. Each site and concentration (locus) shall require a brief description. Existing feature and 36 concentration labels shall be retained. In instances where site was recorded and cannot be relocated, 37 the site shall be included as part of the mapping effort. However, data fields need to be included for 38 the site 1) clearly indicate the site no longer exists, and 2) when the site was originally recorded. 39

▪ Ensure that no…