A07.02_-_Atch_9_-_REVISED_Atch_3_Specification_Section_02_65_00_29_Aug_19.pdf
PDF 73 KB Posted
- Solicitation number
- W91238-19-R-0052
About this file
This specification document outlines requirements for the removal of underground storage tanks at Fresno-Yosemite International Airport in support of the Jet Fuel Complex project. The contractor will be responsible for removing six 25,000 gallon underground steel tanks and associated piping, conducting soil and water testing to identify contamination, disposing of hazardous wastes, and backfilling the excavation site. The contractor must develop plans for work activities, safety, sampling, tank removal and disposal, spill prevention, and closure reporting. The contractor will also be required to characterize and properly dispose of any residual tank contents or hazardous wastes.
Attachment 9
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Jet Fuel Design Update - Fresno 19023
SECTION 02 65 00
UNDERGROUND STORAGE TANK REMOVAL
02/10
PART 1 GENERAL
1.1 UNIT PRICES
Compensation for removal of contaminated soil and pumpable liquids will be paid as a unit cost. This unit cost includes testing, excavation, stockpiling, transportation and disposal of the contaminated soil and backfilling with non-contaminated soil. Payment for all other work is under the base bid for the tank removal and constitutes full payment for all work defined in the contract documents including testing of the contents, excavation and disposal of the tank, and testing of the underlying soil.
Assume, for bidding purposes, that soil bituminous pavement, concrete slabs, and water encountered during the removal of the underground tanks are contaminated with JP-8 fuel oil to be handled as specified herein.
Payment for removal from temporary stockpile and disposal of contaminated soil and furnishing clean soil will be paid for at the contract unit price per cubic yard. Wash bituminous pavement and concrete slabs and dispose of as demolition debris. Collect and store wash water. Disposal of contaminated water will be paid for at the contract unit price per gallon.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN PETROLEUM INSTITUTE (API)
API PUBL 1628 (1996) A Guide to the Assessment and Remediation of Underground Petroleum Releases
API RP 1604 (1996; R 2010) Closure of Underground Petroleum Storage Tanks
API RP 2003 (2008; 7th Ed) Protection Against Ignitions Arising out of Static, Lightning, and Stray Currents
API RP 2219 (2005; R 2012) Safe Operation of Vacuum Trucks in Petroleum Service
API STD 2217A (2009) Guidelines for Safe Work in Inert Confined Spaces in the Petroleum and Petrochemical Industries
API Std 2015 (2014) Safe Entry and Cleaning of Petroleum Storage Tanks
SECTION 02 65 00 Page 1
ASTM INTERNATIONAL (ASTM)
ASTM D1556 (2007) Density and Unit Weight of Soil in Place by the Sand-Cone Method
ASTM D1557 (2012) Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3) (2700 kN-m/m3)
ASTM D2167 (2008) Density and Unit Weight of Soil in Place by the Rubber Balloon Method
ASTM D2487 (2011) Soils for Engineering Purposes (Unified Soil Classification System)
ASTM D4397 (2010) Standard Specification for Polyethylene Sheeting for Construction, Industrial, and Agricultural Applications
ASTM D6938 (2010) Standard Test Method for In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth)
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 1110-1-4006 (1998) Engineering and Design -- Removal of Underground Storage Tanks (USTs)
EM 200-1-1 (1994) Environmental Quality -- Validation of Analytical Chemistry Laboratories
EM 200-1-6 (1997) Environmental Quality -- Chemical Quality Assurance for HTRW Projects
EM 200-1-7 (2001) Environmental Quality - Performance Evaluation (PE) Program
EM 385-1-1 (2014) Safety and Health Requirements Manual
U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)
EPA 530-R-97-007 (1997) Best Management Practices (BMPs) for Soils Treatment Technologies;, Suggested Operational Guidelines to Prevent Cross-Media Transfer of Contaminants During Cleanup Activities
EPA 600/4-79/020 (1983) Methods for Chemical Analysis of Water and Wastes
EPA SW-846 (Third Edition; Update IV) Test Methods for Evaluating Solid Waste:
Physical/Chemical Methods
SECTION 02 65 00 Page 2
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1910 Occupational Safety and Health Standards
40 CFR 261 Identification and Listing of Hazardous Waste
40 CFR 262 Standards Applicable to Generators of Hazardous Waste
40 CFR 264 Standards for Owners and Operators of Hazardous Waste Treatment, Storage, and Disposal Facilities
40 CFR 265 Interim Status Standards for Owners and Operators of Hazardous Waste Treatment, Storage, and Disposal Facilities
40 CFR 266 Standards for the Management of Specific Hazardous Wastes and Specific Types of Hazardous Waste Management Facilities
40 CFR 268 Land Disposal Restrictions
40 CFR 279 Standards for the Management of Used Oil
40 CFR 280 Technical Standards and Corrective Action Requirements for Owners and Operators of Underground Storage Tanks (UST)
1.3 SYSTEM DESCRIPTION
The work consists of removal, decontamination and disposal of 6, 25,000 gallon underground storage tanks and associated piping and ancillary equipment, including but not limited to dewatering (if approved), disposal of contaminated soil, laboratory testing, providing reports which are required by regulatory agencies, and backfilling. The tanks are constructed of steel and are at the location shown on the drawings.
Residue remaining in the tank is considered a hazardous waste. Subsurface conditions are represented in the Geotechnical REport and as indicated on the drawings. Groundwater is not expected to be encountered. Verify the actual conditions prior to submitting a bid. The site is not a hazardous waste site, but due due to the nature of the materials and hazards present, use specified procedures until closure activities are complete.
1.4 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Work Plan; G, RO.
Site safety and health plan; G, RO Excavation and material handling plan; G, RO Field sampling and laboratory testing plan; G, RO
SECTION 02 65 00 Page 3
Tank and piping removal and disposal plan; G, RO Spill and discharge control plan; G, RO Qualifications; G, RO Laboratory Services; G, RO State licensed hazardous waste transporter
SD-06 Test Reports
Laboratory and field testing reports Backfill Material Tank Contents Verification Contaminated Water Disposal Soil Examination, Testing, and Analysis Backfilling; G, RO.
SD-11 Closeout Submittals
Salvage Rights; G, RO Tank Closure Report; G, RO
1.5 QUALITY ASSURANCE
1.5.1 Qualifications
Substantiate a minimum of 2 years of tank removal experience, including subcontractors and personnel employed on the project, and certification by the local authority having jurisdiction for tank removal work. Experience shall include removal, transportation, and disposal of underground tanks and associated piping, in conformance with the following:
a. API RP 1604
b. 40 CFR 280, State and local regulations and procedures.
c. Applicable safety rules and regulations.
d. Use of equipment and procedures for testing and vapor-freeing tanks.
e. Handling and disposal of types of wastes encountered in underground tank and pipe removal including disposal of underground tanks and associated piping.
f. Excavation, testing, and disposal of petroleum contaminated soils, liquids, and sludge.
g. Project titles, dates performed, owner's names, points of contact for each project with current contact phone numbers.
1.5.2 Laboratory Services
Submit documentation for laboratory services in accordance with State of California certification requirements EM 1110-1-4006, EM 200-1-1, EM 200-1-6 and EM 200-1-7.
1.5.3 Support Staff
Identify all staff involved for the various components, including personnel collecting and shipping samples, and detail staff member's qualifications.
SECTION 02 65 00 Page 4
1.5.4 Preconstruction Conference and Work Plan
Prior to the commencement of work, a preconstruction conference will be scheduled by the Contracting Officer. Prepare and submit a comprehensive Work Plan within 30 days of contract award. The work plan shall conform to the requirements of this specification, API RP 1604, API Std 2015, API RP 2003, API STD 2217A and API RP 2219. Allow 30 days in the schedule for the Government's review and approval. No adjustment for time or money will be made for re-submittals required as a result of noncompliance. No work at the site is allowed, with the exception of site inspections and mobilization, until the Work Plan is approved. As a minimum, include the following in the Work Plan:
1.5.4.1 Site Safety and Health Plan
Furnish detailed safety, health, and accident prevention provisions and develop a Site Safety and Health Plan (SSHP). Incorporate the requirements of 29 CFR 1910 and EM 385-1-1 into the SSHP. Include current training certification statement for personnel prior to entry into the work site.
Do not commence work until the SSHP is approved by the Contracting Officer. As a minimum, include the following:
a. Health and safety organization, including discussion of distribution of functions and responsibilities.
b. Organization and components of the SSHP.
c. Physical and chemical site hazard identification.
d. Basic toxicology and toxicity information.
e. Discussion of the EZ and CRZ.
f. Protective clothing.
g. Respiratory protection.
h. Air quality monitoring.
i. Personnel exposure guidelines.
j. Decontamination procedures.
k. Basic first aid review.
l. Emergency response and contingency plan.
m. Site entry and exit procedures.
n. Sampling procedures.
1.5.4.2 Excavation and Material Handling Plan
Describe methods, means, equipment, sequence of operations and schedule to be employed in excavation, transport, handling, borrowing source and stockpiling of soil during underground tank removal. Include shoring requirements. Fifteen days before beginning tank removal work, submit to the Contracting Officer, for approval, a material handling plan that describes phases of dealing with the contaminated soil and water as it
SECTION 02 65 00 Page 5 relates to the proposed tanks and piping removal, including methods of excavating, a material handling plan for the contaminated material, soil testing requirements, and water pumping and collection requirements.
1.5.4.3 Field Sampling and Laboratory Testing Plan
Submit a detailed Sampling and Analysis Plan.
Describe field sampling methods and quality control procedures. Identify laboratory and laboratory methods to be used for contamination testing.
Include sample reports showing sample identification for location, date, time, sample method, contamination level, name of individual sampler, identification of laboratory, and quality control procedures.
1.5.4.4 Tank and Piping Removal and Disposal Plan
Describe methods, means, sequence of operations, and schedule to be employed in the testing, pumping, cleaning, de-vaporizing, inspecting, cutting and removal, and disposal of underground storage tanks and piping.
Include methods to be employed for product, sludge, vapor, and pumpable liquid removal; purging and inerting; and storage methods proposed for control of surface water. Also address the following:
a. Treatment Options
b. Identification of waste, tank and contaminated soil transporters and means of transport.
c. Disposal and alternate facilities, disposal or remediation.
d. Decontamination procedures and coordination with SSHP.
Coordinate decontamination procedures, shoring, and safety measures in accordance with Section 01 35 29.13 HEALTH, SAFETY, AND EMERGENCY RESPONSE
PROCEDURES FOR CONTAMINATED SITES.
1.5.4.5 Spill and Discharge Control Plan
Develop a comprehensive spill and discharge control plan. Consider and provide contingency measures for potential spills and discharges from handling and transportation of contaminated soils and water. A possible source of guidance for assessment and remediation is API PUBL 1628.
1.5.4.6 Site Safety And Health Officer
Identify an individual to serve as the Site Safety and Health Officer (SSHO) to report problems and concerns regarding health and safety to the Contracting Officer. Provide documentation that the SSHO possesses working knowledge of local and Federal occupational safety and health regulations, and provide training, in accordance with 29 CFR 1910 to Contractor employees in air monitoring practices and techniques. The SSHO shall remain onsite to provide day to day industrial hygiene support, including air monitoring, training, and daily site safety inspections. The SSHO may not be assigned other duties, such as project foreman or quality control manager.
1.5.5 Permits and Licenses
As required or as directed by the Contracting Officer, obtain local, state, or federal permits and licenses that directly impact the Contractor's ability to perform the work prior to commencing removal operations.
SECTION 02 65 00 Page 6 bstrayer Rectangle bstrayer Callout The allowable duties of the SSHO have been clarified
1.5.6 Statutes and Regulations
Perform tank closures, removal, and disposal in accordance with 40 CFR 280, 40 CFR 262, 40 CFR 264, and 40 CFR 265 as well as the applicable local, State of California, and Federal regulations. Transport hazardous material and waste in accordance with Section 02 41 00 DEMOLITION.
1.6 PROJECT/SITE CONDITIONS
Notify the Installation Environmental Coordinator (IEC) and the Contracting Officer 30 days prior to tank removal. The Contractor is responsible for contacting the Implementation Agency (IA) in accordance with the applicable reporting requirements.
PART 2 PRODUCTS
2.1 BACKFILL MATERIAL
Obtain backfill material from offsite. Classify backfill in accordance with ASTM D2487 as GW, GP, GM, GC, SW, SP, SM, SC, MH, CL, or CH and free from roots and other organic matter, trash, debris, snow, ice or frozen materials. Secure and submit soil classification test results, including the chain-of-custody records, prior to bringing offsite materials onsite.
The testing frequency for backfill material is 1 per 1000 cubic yards or a minimum of 1 test. Use non-contaminated material removed from the excavation for backfill in accordance with Paragraph BACKFILLING.
2.2 PLASTIC SHEETING
Provide plastic sheeting conforming to ASTM D4397.
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Furnish labor, materials, necessary permits, laboratory tests, and reports and equipment to remove and dispose of products remaining in the underground tanks; clean and vapor free the underground tanks and connecting piping; excavate, remove underground tanks and associated piping, and backfill to the level of the adjacent ground; sample soil and water to determine if contaminated; dispose of tanks and associated piping, and petroleum contaminated soil and water.
3.1.1 Safety Guidelines
Comply with personnel safety guidelines specified in Section 01 35 29.13
HEALTH, SAFETY, AND EMERGENCY RESPONSE PROCEDURES FOR CONTAMINATED SITES,
and conform to the guidelines as stipulated in the approved SSHP.
3.1.2 Exclusion Zone (EZ) And Contamination Reduction Zone (CRZ)
Do not permit personnel, not directly involved with the project, to enter work zones, called the EZ and CRZ. The EZ is an area around the tank a minimum of 10 feet from the limits of the tank excavation. At the perimeter of the EZ, establish a CRZ. Clean equipment and personnel within the CRZ, as stated in the paragraph titled "Personnel and Equipment Decontamination." Locate the Contractor's site office, parking area, and other support facilities outside the EZ and CRZ. Clearly mark and post boundaries of the EZ and CRZ. Include a site map, outlining the extent of
SECTION 02 65 00 Page 7 work zones and location of support facilities, in the SSHP.
3.1.3 Onsite Training
Prior to starting onsite work, conduct a health and safety training class directed by the SSHO to discuss the implementation of the SSHP. Notify the Contracting Officer 24 hours prior to beginning the training class.
3.1.4 Personnel Protection
Furnish appropriate personal safety equipment and protective clothing to personnel and ensure that safety equipment and protective clothing is kept clean and well maintained. Furnish three clean sets of personal protective equipment and clothing for use by the Contracting Officer or official visitors as required for entry into the EZ.
3.1.5 Respiratory Protection Program
Fully employ respiratory protection program, addressing respirator usage and training, in accordance with 29 CFR 1910 and EM 385-1-1.
3.1.6 Decontamination
Decontaminate or properly dispose of personal protective equipment and clothing worn in contaminated areas at the end of the work day. The SSHO is responsible for ensuring that personal protective clothing and equipment are decontaminated before being reissued.
3.1.7 Emergency Response and First Aid Equipment
a. Prior to commencement of work, thoroughly review emergency response and contingency plan in accordance with 29 CFR 1910. In an emergency, take action to remove or minimize the cause of the emergency, alert the Contracting Officer, and institute necessary measures to prevent repetition of the emergency. Equip site-support vehicles with route maps providing directions to the medical treatment facility.
b. Provide appropriate emergency first aid equipment for treatment of exposure to site physical and chemical hazards. Provide and post a list of emergency phone numbers and points of contact for fire, hospital, police, ambulance, and other necessary contacts. Provide and post a route map detailing the directions to the nearest medical facility.
c. Notify the Contracting Officer of any unforeseen hazard or condition which becomes evident during work.
3.1.8 Burning and Explosives
Use of explosives or burning debris is not allowed. Do not permit ignition sources in the EZ and CRZ.
3.1.9 Protection of Existing Structures and Utilities
Take all necessary precautions to avoid damage to existing structures, their appurtenances, monitoring wells, or utilities that may be affected by work activities. Repair any damage to utilities and monitoring wells resulting from the Contractor's operations at no expense to the Government. Coordinate with the installation to locate underground
SECTION 02 65 00 Page 8 utilities prior to beginning construction. Do not disturb utilities encountered which were not previously shown or otherwise located without approval from the Contracting Officer.
3.1.10 Shoring
Provide shoring in accordance with Section 01 35 29.13 HEALTH, SAFETY, AND
EMERGENCY RESPONSE PROCEDURES FOR CONTAMINATED SITES.
3.2 TANK CONTENTS VERIFICATION
Conduct sampling and analysis in accordance with the approved Sampling and Analysis Plan. Submit reports, including the chain-of-custody records.
3.2.1 Sampling
Sample tank product,pumpable liquids, tank coatings and sludge. If the data is not adequate, additional sampling and analysis to the extent required by the approved permitted treatment, storage or disposal (TSD) facility receiving the material is the responsibility of the Contractor.
Meeting all regulatory requirements, including the preparation of hazardous materials and waste for transportation, is the responsibility of the Contractor.
3.2.2 Analysis
Test tank contents for the parameters listed herein. Include total petroleum hydrocarbons (TPH), benzene, ethylbenzene, toluene and xylene (BETX) and lead in the analysis.
3.2.3 Characterization
Prior to removing any of the tank contents, characterize the contents to determine the type of required disposal: as a hazardous based on local, state, and Federal disposal regulations. Characterize tank product, pumpable liquids, and sludge in accordance with 40 CFR 261 and 40 CFR 279.
Submit the waste contents determination and accompanying test results for each phase present in the tank to the Contracting Officer. The Contractor is responsible for any additional requirements identified by the disposal facility. Do not remove the tank contents until approval is given by the Contracting Officer.
3.3 TOPSOIL
Topsoil shall meet the requirements in Section 31 00 00 EARTHWORK. Strip and stockpile uncontaminated topsoil separately for reuse at a location approved by the Contracting Officer if it meets the requirements of clean fill given in Paragraph BACKFILLING. Obtain additional topsoil in excess of that produced by excavation offsite. Cover with topsoil all areas disturbed by tank removal operations, other than areas to receive pavement or similar surface under this contract.
3.4 PREPARATIONS FOR EXCAVATION
Before excavating, drain product piping back to the tank, remove residual liquids trapped in the product lines and remove all product from the tank.
Purge and vent the tank in accordance with API RP 1604, and as specified herein.
SECTION 02 65 00 Page 9
3.4.1 Removal of Product, Pumpable Liquids, and Sludge
Remove and dispose of tank product, pumpable liquids, and sludge. Use of Government facilities for permanent storage or disposal of the wastes is prohibited. Temporary storage on Government facilities will be allowed only until testing is complete, manifests (if necessary) are complete, and transportation is arranged. The Contractor is responsible for obtaining all required permits. Usable product shall be the property of the Government. Provide approved containers, vehicles, equipment, labor, signs, labels, placards and manifests and associated land disposal restriction notices and notifications, necessary for accomplishment of the work, including materials necessary for cleaning up spills that could occur from tank removal operations.
3.4.2 Contaminated Water Disposal
3.4.2.1 Sampling, Analysis, and Containment
Sample and analyze contaminated water both prior to and after treatment.
Analyze contaminated water produced from excavation operations and tank pumping treated onsite, for pH; benzene, ethylbenzene, toluene, and xylene (BETX); total lead; oil and grease; total petroleum hydrocarbons (TPH).
Perform sampling and analysis prior to disposal for every 25,000 gallons of contaminated water treated. Conform analysis of contaminated water to be taken to an offsite treatment facility to the requirements of the treatment facility, with documentation of all analyses performed furnished to the Contracting Officer in accordance with paragraph RECORDS. Contain, store onsite, and analyze contaminated water prior to transport to the approved treatment, storage and disposal facility and dispose of in accordance with applicable Federal and state disposal regulations. Provide approved containers, vehicles, equipment, labor, signs, labels, placards and manifests and associated land disposal notices and notifications, necessary for accomplishment of the work.
3.4.2.2 Treatment
Treat contaminated water offsite by oil water separation filtering, air stripping and activated carbon, or other means as approved by the Contracting Officer. If contaminated water is to be treated onsite, specify the proposed treatment in the Work Plan and submit for approval, including the chain-of-custody records. Install temporary storage and treatment equipment at a location approved by the Contracting Officer.
Sample and analyze treated effluent and secure approval of results by the Contracting Officer before discharge to the sanitary sewer. Treat and discharge effluent in accordance with the discharge permit.
3.5 PURGING AND INERTING
After the tank and piping contents have been removed, but prior to excavation beyond the top of the tank, disconnect all the piping (except the piping needed to purge or inert the tank). Purge flammable and toxic vapors from the tank or make the tank inert in accordance with API RP 1604, with the exception that filling with water is not permitted and, if dry ice is employed, use a minimum of 3 pounds per 100 gallons of tank volume.
Continuously monitor the tank atmosphere for combustible vapors if the tank is purged, or continuously monitor for oxygen, if the tank is inerted.
SECTION 02 65 00 Page 10
3.6 EXCAVATION
Mark all excavation areas, as well as work near roadways, in accordance with Section 01 35 29.13 HEALTH, SAFETY, AND EMERGENCY RESPONSE PROCEDURES
FOR CONTAMINATED SITES.
3.6.1 Exploratory Trenches
a. Excavate exploratory trenches as necessary to determine the tank location, limits and the location of ancillary equipment. Upon commencing exploratory excavation, utilize organic vapor analyzer/flame ionization device (OVA/FID) equipment to obtain readings for total petroleum hydrocarbons (TPH), and benzene, tolulene, ethylbenzene, and xylene (BTX), and toxicity characteristic leaching procedure (TCLP).
b. To determine soil contamination levels, continuously monitor soil materials excavated to remove tanks with an OVA/FID capable of detecting volatile organic vapors to a minimum of one ppm. Further test contaminated soils with OVA/FID readings of 10 ppm or greater for TPH and BTEX as specified herein. Soils with OVA/FID readings less than 10 ppm may be used as clean backfill. Dispose of contaminated soils in accordance with Federal, State, and local regulations.
3.6.2 Tank Excavation
a. Provide Contracting Officer with written documentation, no later than 30 days before work begins, that proper State or local authorities have been notified. Notify the Contracting Officer at least 48 hours prior to start of tank removal work. Stage operations to minimize the time that tank excavation is open and the time that contaminated soil is exposed to the weather. Provide protection measures around the excavation area to prevent water runoff and to contain the soil within the excavation area.
b. Perform excavation around the perimeter of the tank to limit the amount of potentially petroleum contaminated soil that could be mixed with previously uncontaminated soil. Segregate petroleum contaminated soil in separate stockpiles.
c. Maintain an excavation around the tank of sufficient size to allow workers ample room to complete the work, but also protect the workers from sliding or cave-ins. Install sheeting, bracing, or shoring in the absence of adequate side slopes if there is a need for workers to enter the excavated area. Divert surface water to prevent direct entry into the excavation.
d. Dewatering of the excavation may require a discharge permit by the State and shall be limited to allow adequate access to the tank and piping, to assure a safe excavation, and to ensure that compaction and moisture requirements are met during backfilling. Dewatering may result in the production of petroleum contaminated water and/or free product. Recover free product from the groundwater only as part of necessary dewatering.
e. Collect and test water generated by dewatering during excavation required for removal of tanks or piping, surface water collected in open excavation, or water used for washing equipment or existing concrete or bituminous surfaces, in accordance with EPA 530-R-97-007, EPA 600/4-79/020, EPA SW-846 and state or locally required analyses.
SECTION 02 65 00 Page 11
3.6.3 Temporary Containment of Excavated Soil
Provide temporary containment area near the excavated area. Cover containment area with 30 mil polyethylene sheeting. Place excavated soil on the impervious barrier and cover with 6 mil polyethylene sheeting.
Provide straw bale berm around the outer limits of the containment area and cover with polyethylene sheets. Secure edges of sheets to keep the polyethylene sheeting in place.
3.6.4 Piping Excavation
Perform excavation as necessary to remove tank piping and ancillary equipment in accordance with paragraphs: Shoring, Tank Excavation, and Open Excavations.
3.6.5 Open Excavations
Secure open excavations and stockpile areas while awaiting confirmation test results from the soil beneath the tank. Backfill the excavation as soon as possible after tank and contaminated soil removals have been completed and confirmation samples have been taken. Divert surface water around excavations to prevent water from directly entering into the excavation.
3.6.6 Hidden Structures
During excavation activities, if asphalt pavement, concrete slabs, or other hidden structures are encountered, remove and wash with high pressure water cleaning equipment. Remove and dispose of the pavement, concrete, and other structures as specified in Section 02 41 00 DEMOLITION.
3.6.7 Stockpiles
Uncontaminated excavated soil and petroleum contaminated soil, that is not a state-regulated hazardous waste, shall be stockpiled and used for backfill in the tank excavation prior to using borrow material. Excavated material that is regulated by the state as a hazardous waste which is visibly stained and which has an obvious petroleum odor or as required by the State of California or implementing agency is considered contaminated.
Stockpile material if the site is a RCRA-designated CAMU Place in containers such as drums, roll-offs or dumpsters for sampling in accordance with paragraph Stockpiled Material Sampling. Separately stockpile uncontaminated soil from the contaminated soil, a safe distance away from, but adjacent to, the excavation. Place allowable stockpiles of contaminated soil on an impermeable geomembrane a minimum of 3 layers, each 30 mils thick, covered with a 10 mils sheet of geomembrane as specified.
Place the geomembrane to prevent the stockpiled soil from coming into contact with surface water run-off. Locate the geomembrane cover to prevent rain or surface water from coming into contact with the contaminated soil, as well as limit the escape of the volatile constituents in the container and stockpile.
3.6.8 Acceptable Levels of Contamination
Take further samples and test soils with OVA/FID readings of 10 ppm or greater for TPH and for BTEX in accordance with EPA SW-846 and EPA 600/4-79/020, and for toxicity characteristic leaching procedure (TCLP) for lead if leaded gasoline was stored in or near the underground tank
SECTION 02 65 00 Page 12 being removed. For stockpiled soils, provide a minimum of one test for every 100 cubic yards for TPH, and one test for every 100 cubic yards for BTEX and TCLP. Soils that contain 50 ppm or more TPH, 10 ppm or more BTEX or have TCLP reading of 10 ppm lead or virgin petroleum products are considered contaminated materials. Soils which are less than the above may be used as clean fill. Furnish results to the Contracting Officer within 24 hours after the results are obtained.
3.7 REMOVAL OF PIPING, ANCILLARY EQUIPMENT, AND TANK
3.7.1 Piping and Ancillary Equipment
Disconnect all piping and ancillary equipment from the tank. Remove the piping completely (interior and exterior of the tank)as directed by the Contracting Officer. Cap all tank ancillary equipment and piping connections, except those connections necessary to inert the tank within the excavation zone. Clean the piping exterior and ancillary equipment to remove all soil and inspect for signs of corrosion and leakage. Ensure no spillage of the piping contents occurs, as specified in the Work Plan, and as required in paragraph SPILLS. If the soil under and around the tank pad is contaminated, remove the tank pad and dispose of offsite at an approved hazardous waste facility.
3.7.2 Tank
Remove the tank from the excavation and clean the exterior to remove all soil and inspect for signs of corrosion, structural damage, or leakage.
Use only non-sparking type materials or equipment which comes into contact with the tank, or in the vicinity of the excavation such as shovels, slings and tools. After removal from the excavation, place the tank on a level surface at an approved location and secure it with wood blocks to prevent movement.
3.7.3 Contaminated Soil, Tank and Piping Excavation Examination
a. After the tank has been removed from the ground, examine and test the adjacent and underlying soil for any evidence of leakage. Visually inspect the soil for staining after removal of all obviously contaminated soil, then screen for the presence of volatile and/or semi-volatile contamination using a real time vapor monitoring instrument.
b. If tank is 20 feet or less in length, take two samples. Take each sample 2 feet from each end of the tank and 2 feet below the bottom of the excavation.
c. If the tank is greater than 20 feet, take three samples. Take two samples 2 feet from each end of the tank and 2 feet below the bottom of the excavation. Take a third sample from the middle of the tank area and 2 feet below the bottom of the excavation.
d. Analyze samples for TPH, BTEX, and TCLP. Perform sampling and analysis conforming to standards specified above for stockpiled soils. Soils that contain 50 ppm or more TPH, 10 ppm or more BTEX, or have TCLP reading of 10 ppm of lead or virgin petroleum products are considered contaminated materials. Soils which are less than the above may be used as clean fill. Furnish results to the Contracting Officer within 24 hours after the results are obtained. Along with the results furnish a sketch showing underground tank, sampling location, and
SECTION 02 65 00 Page 13 extent of excavations.
e. Stockpile onsite in accordance with paragraph Stockpiles uncontaminated soil or petroleum contaminated soil not regulated by the state as hazardous waste. Stockpile contaminated soil or suspected contaminated soil, or, if the site is a RCRA-designated CAMU, containerized until further disposition.
f. The Contracting Officer will determine the extent of the contaminated soil to be removed from each site, not to exceed 2000 cubic yards per site. Report any evidence indicating that the amount of contaminated soil may exceed the individual site limit specified, to the Contracting Officer the same day it is discovered. If minimal additional excavation is required, the Contracting Officer may allow the Contractor to proceed. If extensive contamination is encountered, sample the excavation and backfill in accordance with paragraph
BACKFILLING.
g. After the known contaminated soil is removed, sample and analyze the excavation.
3.7.4 Testing Along Piping
For every 25 linear feet of product delivery piping, for every change in direction, and at every mechanical joint take one soil sample and analyze for TPH, BTEX, and TCLP. Conform sampling and analysis of soil materials to EPA standards specified above.
3.8 TANK CLEANING
Provide additional requirements for cleaning and vapor freeing tank as specified in Section 33 65 00 CLEANING PETROLEUM STORAGE TANKS.
b. Fuel Removal: All possible fuel will be pumped or otherwise removed from the tank by the Government. Consider remaining fuel contaminated or waste fuel; pump into 55 gallon drums or other suitable containers for disposal in accordance with approved procedures meeting local, State, and Federal regulations. Dispose of remaining fuel emulsions in accordance with applicable local, State, and Federal regulations.
Drums or tanks used for containerizing waste fuel will be furnished by the Contractor .
c. Identification of Tanks With Hazardous Waste Sludge and Residue
The existing tanks are known or suspected to contain hazardous wastes such as sludge, sandblast residue, and contaminated/contact water.
3.8.1 Exterior
Remove soil from the exterior of the tank, piping, and associated equipment to eliminate soil deposition on roadways during transportation to a temporary storage area, ensure markings will adhere to the surfaces, and simplify tank cutting. Use non-sparking tools to remove soil. Recover removed uncontaminated soil and soil not regulated by the state as a hazardous waste and use them as backfill in the former tank excavation.
Remove and containerize soil believed to be contaminated, or if the site is a RCRA designated CAMU, collect it on 3 layers of 30 mil impermeable geomembrane and stockpile it with other contaminated soil removed from the
SECTION 02 65 00 Page 14 excavation.
3.8.2 Temporary Storage
If the tank is stored after the tank exterior is cleaned and ancillary equipment is removed, and prior to being cut into sections, label the tank as directed in API RP 1604, place it on blocks, and temporarily store it at the location indicated by the Contracting Officer. Prior to cleaning the tank interior, monitor the tank atmosphere for combustible vapors and purge or inert it if combustible vapors are detected. Provide warning labels as follows:
"TANK HAS CONTAINED JET FUEL
NOT VAPOR FREE
NOT SUITABLE FOR STORAGE OF FOOD OR LIQUIDS
INTENDED FOR HUMAN OR ANIMAL CONSUMPTION
DATE OF REMOVAL: MONTH/DAY/YEAR"
Make tank unusable for future use, then transport and dispose of tank in accordance with Federal, State, and local regulations.
3.8.3 Interior
Clean tank interior using a high pressure (greater than 500 psi), low volume (less than 2 gpm) water spray or Steam clean tank interior until all loose scale and sludge is removed, and contamination, in the form of a sheen, is no longer visible in the effluent stream. Also clean the interior surfaces of piping, to the extent possible, using the same method used for cleaning the tank. Contaminated water generated from interior cleaning operations (of both piping and tank) shall not exceed the following quantities for each UST cleaned:
UST VOLUME (GALLONS) PERCENT OF UST VOLUME
1,000 or less 5
10,000 or less 5 or 100 gal., whichever is less
20,000 or less 1 or 150 gal., whichever is less greater than 20,000 1 or 250 gal., whichever is less
Handle in accordance with paragraph Contaminated Water Disposal all contaminated water resulting from cleaning operations. Clean so as to eliminate, to the greatest extent possible, the need for personnel to enter the tank. Use specially designed tank cleaning equipment which allows the tank to be cleaned prior to cutting into sections without requiring personnel to enter the tank or, if less specialized equipment is used, the tank shall be partially dissected to overcome confined space entry hazards. Accomplish this work in accordance with Section 01 35 29.13
HEALTH, SAFETY, AND EMERGENCY RESPONSE PROCEDURES FOR CONTAMINATED SITES.
SECTION 02 65 00 Page 15
3.9 SOIL EXAMINATION, TESTING, AND ANALYSIS
3.9.1 Tank Excavation Sampling Procedures
After soil known to be contaminated has been removed or after soil excavation is complete, sample the excavation with procedures, number, location, and methodology as specified and in accordance with state regulations.
3.9.2 Stockpiled Material Sampling
Stockpiled contaminated soil shall be sampled and preserved in accordance with the approved Sampling and Analysis Plan. Sampling locations, number and specific procedures are as required by the State of California and the disposal facility.
3.9.3 Analysis
Test soil samples from the excavation and stockpiled material in accordance with the approved Sampling and Analysis Plan, for the following parameters:
total petroleum hydrocarbon (TPH), benzene, ethylbenzene, toluene, xylene (BETX), toxicity characteristic leaching procedure (TCLP). Submit copies of all test results, including the chain-of-custody records,.to the Contracting Officer.
3.10 BACKFILLING
a. Backfill the tank area and any other excavations as soon as possible after tank and contaminated soil removals have been completed and confirmation samples have been taken. Complete contaminated soil removal after approval by the Contracting Officer.
b. Dewater the excavation if necessary. Use stockpiled material, subjected to chemical confirmation testing as backfill, if it is found to conform to the requirements of clean fill in accordance with appropriate state, local regulations. Place clean backfill in layers with a maximum loose thickness of 8 inches, compacted to 90 percent maximum density for cohesive soils and 95 percent maximum density for cohesionless soils.
Perform density tests using an approved commercial testing laboratory or by facilities furnished by the Contractor. Attach test results to Contractor's Quality Control Report; submit 2 copies of the report for each UST site opened, prepared in a standard 3-ring binder, within 14 days of completing work at each site. Label each binder with contract number, project name, location and tank number; each binder shall be indexed. Furnish a copy of the report to the Installation Environmental Coordinator. Perform a minimum of 1 density test on each lift. Determine laboratory tests for moisture density relations in accordance with ASTM D1557, Method B, C, or D, or ASTM D6938. A mechanical tamper may be used, provided that the results are correlated with those obtained by the hand tamper. Determine field in-place density shall be in accordance with ASTM D1556, ASTM D6938, or ASTM D2167.
3.11 DISPOSAL REQUIREMENTS
3.11.1 Treatment, Disposal, and Recycling
Perform disposal of hazardous wastes in accordance with all local, State, and Federal solid and hazardous waste laws and regulations; the RCRA;
SECTION 02 65 00 Page 16
Section 02 41 00 DEMOLITION; and conditions specified herein. This work includes all necessary personnel, labor, transportation, packaging, detailed analyses (if required for disposal, manifesting or completing waste profile sheets), equipment, and reports. Recycle product and pumpable liquids removed from the tank to the greatest extent practicable.
Dispose of the tanks removed at a state approved facility. Provide manifest for each tank disposed of in this manner as required by the State of California to document delivery and acceptance at the disposal facility.
3.11.2 Tank and Ancillary Equipment Disposal
After the tank, piping, and ancillary equipment have been removed from the excavation and the tank cleaned, cut the tank into sections with no dimension greater than 5 feet. Recycle or Dispose of tank and piping sections in a State approved or offsite disposal facility or in a salvage yard. Perform tank cutting prior to being taken from the tank removal site.
Do not sell the tank intact. Recycle or Dispose of ancillary equipment at an approved offsite disposal facility or a salvage yard. Piping shall be disconnected from the tank and removed unless otherwise indicated.
3.11.3 Transportation of Wastes
Provide transportation in accordance with Department of Transportation (DOT) Hazardous Material Regulations and State and local requirements, including obtaining all necessary permits, licenses, and approvals. Submit evidence that a State licensed hazardous waste transporter is being used.
3.11.4 Salvage Rights
The Contractor retains the rights to salvage value of recycled or reclaimed product and metal not turned in to the DRMO or otherwise identified, so long as the requirements of 40 CFR 266 and 40 CFR 279, or the applicable State requirements are met. At the end of the contract, provide documentation on the disposition of salvaged materials.
3.11.5 Manifest Records
Maintain records of all waste determinations, including appropriate results of analyses performed, substances and sample location, the time of collection, and other pertinent data as required by 40 CFR 280, Section 74 and 40 CFR 262 Subpart D. Also record transportation, treatment, disposal methods and dates, the quantities of waste, the names and addresses of each transporter and the disposal or reclamation facility, shall and available for inspection, as well as copies of the following documents:
a. Manifests.
b. Waste analyses or waste profile sheets.
c. Certifications of final treatment/disposal signed by the responsible disposal facility official.
d. Land disposal notification records required under 40 CFR 268for hazardous wastes.
Provide records in accordance with Section 01 35 29.13 HEALTH, SAFETY, AND EMERGENCY RESPONSE PROCEDURES FOR CONTAMINATED SITES. Upon contract close out, the records will become the property of the Government.
SECTION 02 65 00 Page 17
3.11.6 Hazardous/Special Waste Manifests
Provide manifesting conforming to the requirements specified in Section
01 35 29.13 HEALTH, SAFETY, AND EMERGENCY RESPONSE PROCEDURES FOR
CONTAMINATED SITES.
3.11.7 Documentation of Treatment or Disposal
Take wastes, other than recyclable or reclaimable product or metal, to a treatment, storage, or disposal facility which has EPA or appropriate state permits and hazardous waste identification numbers and complies with the provisions of the disposal regulations. Furnish the original return copy of the hazardous waste manifest, signed by the owner or operator of a facility legally permitted to treat or dispose of those materials shall be furnished to the Contracting Officer not later than 5 working days following the delivery of those materials to the facility; and include a copy in the Tank Closure Report. Furnish a statement of agreement from the proposed treatment, storage or disposal facility and certified transporters to accept hazardous wastes in the Work Plan to the Contracting Officer not less than 14 days before transporting any wastes. If the Contractor selects a different facility than is identified in the Work Plan, provide documentation for approval to certify that the facility is authorized and meets the standards specified in 40 CFR 264.
3.12 SPILLS
Use appropriate vehicles and operating practices to prevent spillage or leakage of contaminated materials from occurring during operations.
Inspect vehicles leaving the area of contamination to ensure that no contaminated materials adhere to the wheels or undercarriage. Take immediate containment actions as necessary to minimize effect of any spill or leak. Cleanup in accordance with applicable Federal, State, local laws and regulations, and district policy at no additional cost to the Government. Refer to Section 02 41 00 DEMOLITION for spill response and reporting requirements.
3.13 INSPECTIONS
Arrange for and perform required inspections. Provide copies of inspections to Contracting Officer.
3.14 TANK CLOSURE REPORT
Submit a Site Assessment/Tank Closure Report in a single binder notebook containing a collection of reports, records, starting and ending dates of reporting period, inspections, documentation, and data as follows:
a. Complete UST Notification Form (within 30 days of closure).
b. Description of work, including removal procedures, number of tanks removed, identification of tanks removed and disposed of (include site map showing location of tank and piping), cubic yards of excavated soil, location of disposal sites, and dates of excavation.
c. Site plan, including location of tanks and piping, limits of excavation, sampling points, results of excavation, and depths.
d. Laboratory and field testing reports, copies of data and test results from testing laboratory and the chain-of-custody records.
SECTION 02 65 00 Page 18
e. Tank disposal paperwork (2 copies of UST Notification Form and method of conditioning tank for disposal), contaminated soil disposal paperwork (include laboratory testing reports), and contaminated water disposal paperwork (include laboratory testing reports).
f. Certifications required by implementing agency.
g. Building permit, inspection permits, and other permitsrequired for underground tank removal, notifications, and inspection reports.
h. Cumulative quantities of soil excavated, beginning with start date for each tank and associated piping.
Include in Tank Closure Reports the following information as a minimum:
a. A cover letter signed by a Professional Engineer registered in the State of California certifying that all services involved have been performed in accordance with the terms and conditions of this specification.
b. A narrative report describing what was encountered at each site, including:
(1) condition of the UST.
(2) any visible evidence of leaks or stained soils.
(3) results of vapor monitoring readings.
(4) actions taken including quantities of materials treated or removed.
(5) reasons for selecting sample locations.
(6) sample locations.
(7) collection data such as time of collection and method of preservation.
(8) reasons for backfilling site.
(9) whether or not groundwater was encountered.
c. Copies of all analyses performed for disposal.
d. Copies of all waste analyses or waste profile sheets.
e. Copies of all certifications of final disposal signed by the responsible disposal installation official.
f. Information on who sampled, analyzed, transported, and accepted all wastes encountered, including copies of manifests, waste profile sheets, land disposal restriction, notification and certification forms, certificates of disposal, and other pertinent documentation.
g. Copies of all analyses performed for confirmation that underlying soil is not contaminated, with copies of chain-of-custody for each sample.
Analyses shall give the identification number of the sample used.
SECTION 02 65 00 Page 19
Sample identification numbers shall correspond to those provided on the one-line drawings.
h. Scaled one-line drawings showing tank locations, limits of excavation, limits of contamination, underground utilities within 50 feet, sample locations, and sample identification numbers.
i. Progress Photographs. Take a minimum of 4 views of the site showing such things as the location of each tank, entrance/exit road, and any other notable site condition before work begins. After work has been started at the site, photographically record activities at each work location daily. Photographs shall be 3-1/2 x 5 inches and shall include:
(1) Soil removal, handling, and sampling.
(2) Unanticipated events such as discovery of additional contaminated areas.
(3) Soil stockpile area.
(4) Tank.
(5) Site or task-specific employee respiratory and personal protection.
(6) Fill placement and grading.
(7) Post-construction photographs. After completion of work at each site, take a minimum of four (4) views of the site. Prints shall illustrate the condition and location of work and the state of progress. The photographs shall be mounted and enclosed back-to-back in a double face plastic sleeve punched to fit standard three ring binders. Each color print shall show an information box, 1-1/2 x 3-1/2 inches. The information box for the 3-1/2 x 5 inch photographs shall be scaled down accordingly, or taped to the bottom of the photo. The box shall be typewritten and arranged as follows:
Project No. Contract No.
Location
Contractor/Photographer
Photograph No. Date/Time:
Description
Direction of View
j. Two copies of the report for each UST site opened, prepared in a standard 3-ring binder, within 14 days of completing work at each site. Label each binder with contract number, project name, location and tank number; each binder shall be indexed. Furnish a copy of the report to the Installation Environmental Coordinator.