Draft_PWS_Hill_AFB_ORC__26Feb2019_(Amendment_1).pdf

PDF 556 KB Posted

Attached to
Optimized Remediation Contract for Hill AFB, UT Federal contract opportunity
Solicitation number
W91238-19-R-0050
Issued by
Department of the Army Corps of Engineers Engineering District Sacramento

About this file

This sources sought synopsis requests capability statements from interested parties for an optimized remediation contract to perform environmental remediation activities at 23 Installation Restoration Program sites and two Military Munitions Response Program sites at Hill Air Force Base in Utah. The resulting ten-year firm-fixed price contract will have an estimated value of $20.5 million. Interested parties must submit responses by March 29th to be considered, with capability statements not to exceed ten pages in length and including details on relevant experience, business size, joint venture information if applicable, and contact information. The Army Corps of Engineers will use the information received to help determine acquisition approach and ensure adequate small business participation for the solicitation planned for release on federalbusinessopportunities.gov.

View the file

Other files for this federal contract opportunity

Other files attached to Optimized Remediation Contract for Hill AFB, UT, newest first.
File Type Posted
SF33 Attachment C-1 Hill AFB_PWS Enclosure 2B GFI List Hill AFB_20200113.xlsx XLSX spreadsheet
W923819R0050 Am 0005.pdf PDF
EPA Comments OU 15 2016-2017 letter work plan.pdf PDF
EPA Comments OU6memotofile.pdf PDF
SF33 Attachment B-1 Hill AFB_Sub-CLIN Structure_20191213.xlsx XLSX spreadsheet
Hill AFB_PWS_REV_20191213.pdf PDF
W9123819R0050 Amendment 0004.pdf PDF
W9123819R0050 Amendment 0003.pdf PDF
Am02 REV SF33 Attachment C-1 Hill AFB_PWS Enclosure 2B GFI List Hill AFB_20191031.xlsx XLSX spreadsheet
W9123819R0050 Amendment 0002 .pdf PDF
Solicitation_Phase_Site_Visit_Attendees_16-17_Oct_2019.pdf PDF
Hill_AFB_ORC_Existing_QandA_(PreRFP)_20191101.pdf PDF
SF33_Attachment_B-1_Hill_AFB_Sub-CLIN_Structure_REV1_20191101.xlsx XLSX spreadsheet
Hill_AFB_PWS_REV_20191101.pdf PDF
W9123819R0050_Hill_ORC_Sol_Amendment_0001.pdf PDF
Hill_AFB_Optimized_Remediation_Site_Visit_Attendees_16-17_October_2019.pdf PDF
Hill_AFB_ORC_Solicitation_Package_W9123819R0050.zip ZIP file
Hill_AFB_PWS_V9_20191016.pdf PDF
SF33_Attachment_L-2_Past_Performance_Quality_Questionaire.docx DOCX document
SF33_Attachment_L-1_Labor_Category_Qualifications_16_Oct_2019.docx DOCX document
Hill_AFB_Sub-CLIN_Structure_20191016.xlsx XLSX spreadsheet
7._QASP_Template_v1_20190913_FINAL.DOCX DOCX document
4._AFGM2019-32-01,_AFFF_Related_Waste_Mgmt_Implementation_Guidance.pdf PDF
6._Interim_Guidance_on_1-4_Dioxane,_Environmental_Restoration_Program.pdf PDF
1._ORC_PMP_Guidance_v1.0_20190920.docx DOCX document
3._Optimization_Benefit_Template_190520_MD_190710.docx DOCX document
5._Ensuring_Chemistry_Data_Fact_Sheet_April_2013.pdf PDF
2._CPSMR_template-_25Aug2019.docx DOCX document
W9123819R0050_Hill_AFB_ORC_DRAFT_Solicitation_SF33.pdf PDF
Hill_AFB_PWS_V8_Updated_20191009.pdf PDF
Itinerary_HAFB_ORC_Pre-Solicitation_Tour_16-17_Oct.pdf PDF
A01.12_Hill_AFB_PWS_V8_20190918.pdf PDF
Hill_ORC_RFIs_w_Responses_20190919.pdf PDF
8560-0006_HillAFB_OU_9_GCA_Bioreactor_OM_Manual_Final_6SEP19.pdf PDF
8560-0006_HillAFB_OU_10_SS109_PMR4_Draft_9MAY19.pdf PDF
Hill_ORC_Docs_10_Sep_2019.zip ZIP file
HillAFB_OU_15_ZZ113_ROD_Draft_2NOV17.pdf PDF
Hill_AFB_ORC_QandA_19_Aug_2019.pdf PDF
Hill_AFB_PWS_20190726.pdf PDF
Sampling_Transition_Table_HillAFB_20190701.docx DOCX document
Hill_AFB_PWS_Enclosure_2.1_List_of_Available_GFI.xlsx XLSX spreadsheet
Hill_AFB__PWS_Enclosure_2.2_List_of_Available_GFI_in_HAFB_Administrative_Record.xlsx XLSX spreadsheet
Hill_AFB_PWS_Enclosure_1_Acronyms_and_Definitions.pdf PDF
Hill_AFB_PWS_Enclosure_3_List_of_Available_GFP.PDF PDF
Hill_AFB_CLIN-SubCLIN_Structure.xlsx XLSX spreadsheet
Hill_AFB_PWS_Enclosure_4_OPSEC_Addendum.pdf PDF
Hill_AFB_PWS_20190603.pdf PDF
Itinerary_HAFB_ORC_Pre-Solicitation_Tour_26-27June.pdf PDF
Bldg383_Directions2019-06-14.pdf PDF
Draft_PWS_for_Hill_AFB_6Mar2019.pdf PDF
Show all 50

Optimized Remediation Contract for Hill AFB, UT has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT (PWS)

FOR

OPTIMIZED REMEDIATION CONTRACT (ORC)

AT

HILL AIR FORCE BASE (AFB), UT

CONTRACT NUMBER:

26 February 2019

1.0 SCOPE

This requirement is for environmental remediation activities to include environmental services, minor construction, and A&E services at Hill AFB. This Performance Work Statement (PWS) defines the scope of Environmental Remediation activities to achieve performance objectives at 23 Installation Restoration Program (IRP) sites and three (3) Military Munitions Response Program (MMRP) sites.

1.1 Introduction

Hill AFB (HAFB) is located in northern Utah, approximately 25 miles north of Salt Lake City and about five miles south of Ogden. The Base occupies approximately 6,700 acres in Davis and Weber counties. The base is bounded on the west by Interstate 15 and the Davis-Weber Canal;

and on the east by private property. HAFB and earlier military installations that occupied the Base operated industrial facilities related to military aircraft since the construction of the Ogden Air Depot in 1940. Many different aircraft, missile, and weapons systems have been maintained and tested in the course of continuous operation and expansion of the Base since its inception.

Industrial activities at HAFB have created a number of hazardous waste sites. Contamination from chemicals has impacted the groundwater and formed large plumes, both on and off Base.

Remediation activities at Hill AFB are being conducted pursuant to Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), as amended by the Superfund Amendments and Reauthorization Act (SARA), and National Oil and Hazardous Substances Contingency Plan (NCP) requirements. Regulatory oversight is provided by the US Environmental Protection Agency (EPA) and with Utah Department of Environmental Quality

(UDEQ).

Environmental remediation activities at Little Mountain Test Facility (LMTF) are being conducted pursuant to the CERCLA in accordance with an Integration Agreement (IA) with regulatory oversight provided by UDEQ.

Environmental remediation activities at DB001, OT106, and SS030 are being conducted pursuant to the Toxic Substances Control Act (TSCA) with regulatory oversight provided by EPA and UDEQ.

The installation was placed on the National Priorities List (NPL) in 1987. The installation is being administered under a Federal Facility Agreement (FFA) signed by EPA and UDEQ in 1991.

The Contractor is solely responsible for reviewing all publicly available information and forming their independent, professional conclusions/interpretation of site conditions and requirements to achieve the performance objectives of this contract.

1.2 General ORC Scope and Requirements

FOR OFFICIAL USE ONLY

The Contractor shall perform all the necessary environmental remediation activities required to achieve the performance objectives of this PWS. This PWS and enclosures listed below include general requirements of the project to meet the Air Force (AF) objectives:

• Enclosure 1 – Site List

• Enclosure 2 – Key Documents

• Enclosure 3 – Acronyms and Definitions

• Enclosure 4 – Format For Metadata and .pdf Documents

The AF is required to implement remedies as necessary to enable the mission, protect human health and the environment and comply with laws. The goal of the ORC initiative is to ensure the AF continues to fulfill all facets of its Environmental Restoration Program (ERP) mission, while effectively and efficiently managing the program in a performance-based, results-oriented and cost conscious framework. The AF desires all sites be cleaned up to standards that allow for the current or reasonably anticipated future land use of the property. The intent of the ORC initiative is to advance site cleanup during the Period of Performance (POP) in the most efficient and cost effective manner as supported by a business case analysis that achieves the greatest reduction in life-cycle cost (LCC). The AF is interested in substantial reduction of long-term environmental liabilities and LCCs, through optimization of environmental restoration activities for all sites included in this contract while complying with applicable federal, state, and local laws and regulations; and applicable base-specific orders, agreements, or rules.

The Contractor shall function as an integral team member in support of the Air Force Civil Engineer Center (AFCEC) mission to include the sharing of information with other AFCEC contractors and AF personnel, and cooperation with community stakeholders, regulators, and other Government entities.

Requirements for efficient management of this contract include, but are not limited to, the achievement of accurate, on-time, quality performance objectives and timely identification and solution of impediments to successful project execution. Technical requirements include, but are not limited to, early involvement in the process to allow for the development of the most cost-effective and technically sound approach or solution. AFCEC will rely on the Contractor’s expertise in recognizing and addressing problematic issues and successful execution of this contract. The Contractor shall perform all work in accordance with federal, state, and local statutes and regulations. The Contractor shall also comply with base regulations. Remedies shall conform to environmental permits, decision document requirements, or other legal requirements.

Site specific performance objectives are defined in the Performance Table (Table 1) below.

Descriptions of the different types of performance objectives and deliverables are described in Enclosure 3 and Sections 1.2.1/2.2.2 below.

Table 1: Performance Table

Site Performance Objective Performance Period1

Performance Standard2

N/A Project Management Plan (PMP):

1) Draft Preliminary PMP

2) Final Preliminary PMP

3) Time-phased updates

Draft Preliminary PMP within 60 calendar days from contract award, Final Preliminary PMP within 14 calendar days of receipt of

COR

comments on the draft, and updates at least annually throughout the

POP

Government approval through the Contracting Officer’s Representative (COR) of PMP.

The PMP should maintained with accuracy and completeness based on the current technical approach for each site, management structure, etc.

Updates are required annually at minimum, or more frequently, as appropriate.

N/A Basewide Uniform Federal Policy - Quality Assurance Project Plan (UFP-QAPP)

Draft UFP- QAPP within 60 calendar days from contract award.

Government approval through the COR and Regulatory approval of

UFP-QAPP.

Hill AFB, ST

BP504

(OU 14)

Long Term Management (LTM) in accordance with the approved Record of Decision (ROD)

Through the duration of the

POP

Government approval through the COR and Regulatory approval of LTM documentation (e.g., Land Use Control Inspection Reports).

BP504A

(OU 14)

LTM in accordance with the approved ROD Through the duration of the

POP

Government approval through the COR and Regulatory approval of LTM documentation (e.g., Land Use Control Inspection Reports).

BP504B

(OU 14)

LTM in accordance with the approved ROD Through the duration of the

POP

Government approval through the COR and Regulatory approval of LTM documentation (e.g., Land Use Control Inspection Reports).

DB001 Response Complete (RC)

Upon achievement of RC, continue LTM through the duration of the PoP

Five (5) years Government approval through the COR and Regulatory approval of RC (i.e., Air Force signature on Final Remedial Action Completion Report).

Government approval through the COR and Regulatory approval of LTM documentation (e.g., Land Use Control Inspection Reports).

1 The duration in the Performance Period starts from the Obligation Date of the first Sub-CLIN for the site unless otherwise specified.

2 All approvals (both Government and Regulator) per the Performance Standard are required in writing.

Site Performance Objective Performance Period1

Performance Standard2

LF001

(OU 1)

Remedial Action – Operations (RA-O) in accordance with the approved ROD and any post-ROD changes

Through the duration of the

POP

Government approval through the COR and Regulatory approval of RA- O documentation (e.g., Annual Groundwater Monitoring Reports, Monthly O&M Reports, etc.).

LF001

(OU 1)

ROD Amendment, if necessary, based on the cis-1,2-DCE and chlorobenzene evaluation

Two (2) years Government approval through the COR and Regulatory approval of ROD Amendment.

LF011

(OU 4)

Remedial Action – Operations (RA-O) in accordance with the approved ROD

Through the duration of the

POP

Government approval through the COR and Regulatory approval of RA- O documentation (e.g., Annual Groundwater Monitoring Reports, Monthly O&M Reports, etc.).

LF011

(OU 4)

Evaluate effectiveness, efficacy, and adequacy of the existing remedy(ies) across site to include the five enhanced reductive dechlorination (ERD) biobarriers, ERD bioreactor and horizontal drain upgradient system (HUDS), per the current ROD to target the plume (in accordance with (US EPA, 20103; US EPA, 20144), and (ITRC, 20065)).

Evaluation should include usability and expandability of the existing infrastructure. Implement comprehensive performance monitoring of the ERD area and ensure up- /side-/downgradient monitoring of the flux through ERD biobarriers.

Two (2) years Government approval through the COR of the remedy evaluation.

LF012

(OU 4)

ROD Amendment addressing the 2013 Five-Year Review finding

Four (4) years Government approval through the COR and Regulatory approval of ROD Amendment.

LF012

(OU 4)

LTM in accordance with the approved ROD and any post- ROD changes

Through the duration of the

POP

Government approval through the COR and Regulatory approval of LTM documentation (e.g., Land Use Control Inspection Reports).

OT026

(OU 6)

RA-O in accordance with the approved ROD Through the duration of the

POP

Government approval through the COR and Regulatory approval of RA- O documentation (e.g., Annual Groundwater Monitoring Reports, Monthly O&M Reports, etc.).

OT026

(OU 6)

Evaluate effectiveness, efficacy, and adequacy of the existing remedy(ies) and treatability studies, per the current ROD in accordance with US EPA, 2010; US EPA, 2014, and ITRC, 2006. Evaluation should include cost-benefit analyses and usability, expandability, and/or discontinued use of the existing infrastructure.

Two (2) years from the Obligation Date of the Remedy Evaluation Sub-CLIN

(0013AA)

Government approval through the COR of the remedy evaluation.

OT026

(OU 6)

Focused Remedial Investigation (FRI), if necessary, based on the results of remedy evaluation and a comprehensive review of existing data, to ensure the high mass zone is targeted by existing remedy(ies).

Two (2) years from the Obligation Date of the FRI Sub-CLIN

(0013AC)

Government approval through the COR and Regulatory approval of the

FRI.

3 US EPA. (2010). Best Management Practices. Washington DC.

4 US EPA. (2014). Groundwater Remedy Completion Strategy. Washington DC.

5 ITRC. (2006). Performance-Based Management. Washington DC: ITRC.

Site Performance Objective Performance Period1

Performance Standard2

OT026

(OU 6)

Using results from remedy evaluation and FRI, provide recommendations to augment, modify, and/or replace the existing remedy(ies). Support recommendation by conducting treatability/feasibility test as necessary. Update CSM and design of performance model(s) addressing all COCs.

Two (2) years from the Obligation Date of the Remedy Recommendati on Sub-CLIN

(0013AD)

Government approval through the COR of the remedy recommendations.

OT033

(OU 8)

RA-O in accordance with the approved ROD and any post- ROD changes

Through the duration of the

POP

Government approval through the COR and Regulatory approval of RA- O documentation (e.g., Annual Groundwater Monitoring Reports, Monthly O&M Reports, etc.).

OT033

(OU 8)

Replace dry monitoring wells and evaluate Monitored Natural Attenuation (MNA) remedy for on-base plumes

Two (2) Years from the Obligation Date of the Well Replacement and MNA Evaluation Sub-CLIN

(0014AA)

Government approval through the COR and Regulatory approval of MNA evaluation.

OT033

(OU 8)

Supplemental investigation to define all source areas of the on-base deep TCE plume boundaries

Two (2) years from the Obligation Date of the Supplemental Investigation Sub-CLIN

(0014AC)

Government approval through the COR and Regulatory approval of supplemental investigation.

OT033

(OU 8)

Supplemental investigation of the off-base 1,2 DCA plume to delineate the distal toe of plume boundary in the vicinity of existing well U8-130 and to optimize the existing 1,2 DCA extraction system. Based on the results of the investigation, install additional extraction and/or monitoring wells, as needed.

Two (2) years from the Obligation Date of the Remedy Recommendati on Sub-CLIN

(0014AE)

Government approval through the COR and Regulatory approval of supplemental investigation.

OT033

(OU 8)

Soil sampling in the source area in vicinity of Building 265 and prepare a Technical Memo documenting whether TCE soil contamination is below levels that are a risk to leach to groundwater or if additional actions are necessary.

Two (2) years from the Obligation Date of the Soil Sampling Sub-CLIN

(0014AF)

Government approval through the COR and Regulatory approval of technical memo.

OT033

(OU 8)

Evaluate effectiveness, efficacy, and adequacy of the Base Boundary Hydraulic Containment (BBHC) system in accordance with US EPA, 2010; US EPA, 2014, and ITRC, 2006. Evaluation should include exposure risk, cost-benefit analyses, and usability, expandability, and/or discontinued use of the existing infrastructure.

Two (2) years from the Obligation Date of the Remedy Evaluation Sub-CLIN

(0014AG)

Government approval through the COR of remedy evaluation.

Site Performance Objective Performance Period1

Performance Standard2

OT033

(OU 8)

Update ROD to augment/replace existing remedy, if warranted.

Two (2) years from the Obligation Date of the ESD or ROD Amendment Sub-CLIN

(0014AH)

Government approval through the COR and Regulatory approval of ESD or ROD Amendment.

OT097

(OU 11)

RA-O in accordance with the approved Decision Document (DD) and the RD/RA Work Plan and Reduce LCC

Through the duration of the

POP

Government approval through the COR and Regulatory approval of RA- O documentation (e.g., Annual Groundwater Monitoring Reports, Monthly O&M Reports, etc.).

OT097

(OU 11)

Evaluate and rehabilitate pump and treat and SVE systems as necessary to achieve the objectives specified in the DD and RD/RA Work Plan.

Two (2) years Government approval through the COR and Regulatory approval of system evaluation and rehabilitation.

OT106 ROD Within the

POP

Government approval through the COR and Regulatory approval of ROD (i.e., Air Force and Regulatory signatures on Final ROD).

SD107

(OU 12)

RA-O in accordance with the approved ROD and Reduce

LCC

Through the duration of the

POP

Government approval through the COR and Regulatory approval of RA- O documentation (e.g., Annual Groundwater Monitoring Reports, Monthly O&M Reports, etc.).

SD107

(OU 12)

Evaluate effectiveness, efficacy, and adequacy of the existing remedy(ies) per the current ROD and potential mid-plume remedy(ies) (in accordance with (US EPA, 2010; US EPA, 2014), and (ITRC, 2006)).

Two (2) years Government approval through the COR of the remedy evaluation.

SS017

(OU 5)

RA-O in accordance with the approved ROD and Reduce LCCs

Through the duration of the

POP

Government approval through the COR and Regulatory approval of RA- O documentation (e.g., Annual Groundwater Monitoring Reports, Monthly O&M Reports, etc.).

SS027

(OU 7)

RA-O in accordance with the approved ROD Through the duration of the

POP

Government approval through the COR and Regulatory approval of RA- O documentation (e.g., Annual Groundwater Monitoring Reports, Monthly O&M Reports, etc.).

SS030 Response Complete (RC)

Upon achievement of RC, continue LTM through the duration of the PoP

Within the

POP

Government approval through the COR and Regulatory approval of RC documentation (e.g., Air Force signature on Final Remedial Action Completion Report).

Government approval through the COR and Regulatory approval of LTM documentation (e.g., Land Use Control Inspection Reports).

SS089

(OU 9)

Site Closeout (SC) Within the

POP

Government approval through the COR and Regulatory approval of SC documentation (e.g., Site Closeout Report and Well Abandonment Confirmation Report).

Site Performance Objective Performance Period1

Performance Standard2

SS090

(OU 9)

Explanation of Significant Differences (ESD) or ROD Amendment

Within the

POP

Government approval through the COR and Regulatory approval of ESD or ROD Amendment.

SS090

(OU 9)

RA-O in accordance with the approved ROD and any post- ROD changes

Through the duration of the

POP

Government approval through the COR and Regulatory approval of RA- O documentation (e.g., Annual Groundwater Monitoring Reports, Monthly O&M Reports, etc.).

SS091

(OU 5)

RA-O in accordance with the approved ROD Through the duration of the

POP

Government approval through the COR and Regulatory approval of RA- O documentation (e.g., Annual Groundwater Monitoring Reports, Monthly O&M Reports, etc.).

SS109

(OU 10)

Explanation of Significant Differences (ESD) or ROD Amendment

Within the

POP

Government approval through the COR and Regulatory approval of ESD or ROD Amendment.

SS109

(OU 10)

RA-O in accordance with the approved ROD and any post- ROD changes

Through the duration of the

POP

Government approval through the COR and Regulatory approval of RA- O documentation (e.g., Annual Groundwater Monitoring Reports, Monthly O&M Reports, etc.).

SS112

(OU 13)

Remedial Design / Remedial Action (RD/RA) Work Plan One (1) year Government approval through the COR and Regulatory approval of RD/RA Work Plan.

ST061 Site Closeout (SC) Within the

POP

Government approval through the COR and Regulatory approval of SC documentation (e.g., Site Closeout Report and Well Abandonment Confirmation Report).

ST071 Site Closeout (SC) Within the

POP

Government approval through the COR and Regulatory approval of SC documentation (e.g., Site Closeout Report and Well Abandonment Confirmation Report).

WP005

(OU 3)

Explanation of Significant Differences (ESD) Within the

POP

Government approval through the COR and Regulatory approval of

ESD.

WP005

(OU 3)

RA-O in accordance with the approved ROD and any post- ROD changes and Reduce LCCs

Through the duration of the

POP

Government approval through the COR and Regulatory approval of RA- O documentation (e.g., Annual Groundwater Monitoring Reports, Monthly O&M Reports, etc.).

WP007

(OU 2)

RA-O in accordance with the approved ROD and any post- ROD changes

Through the duration of the

POP

Government approval through the COR and Regulatory approval of RA- O documentation (e.g., Annual Groundwater Monitoring Reports, Monthly O&M Reports, etc.).

Site Performance Objective Performance Period1

Performance Standard2

WP007

(OU 2)

Evaluate effectiveness, efficacy, and adequacy of the existing remedy(ies) and treatability studies, per the current ROD in accordance with US EPA, 2010; US EPA, 2014, and ITRC, 2006. Evaluation should include exposure risk, cost-benefit analyses, and usability and expandability of the existing infrastructure.

Two (2) years from the Obligation Date of the Remedy Evaluation Sub-CLIN

(0029AA)

Government approval through the COR of the remedy evaluation.

WP007

(OU 2)

Focused Remedial Investigation (FRI), if necessary, to support a revised Remedial Design (RD) based on a comprehensive review of existing data:

• If appropriate, install borings to create detailed model of the site subsurface and to delineate high mass and high flow zones in accordance with ITRC, 2010.

• Based on findings, select appropriate boreholes and convert to monitoring wells, individually screened in the high mass zones.

Three (3) years from the Obligation Date of the FRI Sub-CLIN

(0029AC)

Government approval through the COR and Regulatory approval of FRI.

WP007

(OU 2)

Complete a revised CSM in 3-D to cover the source area and the distant plume for the site based on the FRI.

One (1) year from the Obligation Date of the CSM Sub-

CLIN

(0029AD)

Government approval through the COR and Regulatory approval of revised CSM.

WP007

(OU 2)

Update monitoring program to:

• Evaluate performance monitoring of treatment areas.

• Use appropriate wells to evaluate hydrogeology, plume geometry, horizontal and vertical plume stability, and matrix diffusion across site.

• Validate existing perimeter wells and determine the need for additional boundary wells. Install new wells as needed.

One (1) year from the Obligation Date of the update to monitoring well program Sub-CLIN

(0029AE)

Government approval through the COR and Regulatory approval of RA- O documentation (e.g., Annual Groundwater Monitoring Reports, Monthly O&M Reports, etc.).

WP007

(OU 2)

Based on the results from the remedy evaluation, 3-D CSM, and FRI, provide recommendations to augment, modify, and/or replace the existing remedy. Support recommendation by conducting treatability/feasibility test as necessary.

Update CSM and design of performance model(s) addressing all COCs.

Two (2) years from the Obligation Date of the Remedy Analysis Sub-

CLIN

(0029AF)

Government approval through the COR of the recommended proposed remedial strategy including successful demonstration of the existing or alternate remedy (e.g., through pilot or field test) showing decreasing trends in COCs.

WP007

(OU 2)

Update ROD to augment/replace existing remedy, if warranted.

Two (2) years from the Obligation Date of the ESD or ROD Amendment Sub-CLIN

(0029AG)

Government approval through the COR and Regulatory approval of ESD or ROD Amendment.

WP008

(OU A)

RA-O in accordance with the approved ROD including addressing all 2020 Five Year Review findings

Through the duration of the

POP

Government approval through the COR and Regulatory approval of RA- O documentation (e.g., Annual Groundwater Monitoring Reports, Monthly O&M Reports, etc.).

Site Performance Objective Performance Period1

Performance Standard2

ZZ113

(OU 15)

RA-O in accordance with the approved ROD Through the duration of the

POP

Government approval through the COR and Regulatory approval of RA- O documentation (e.g., Annual Groundwater Monitoring Reports, Monthly O&M Reports, etc.).

1.2.1 Optimized Exit Strategy (OES)

Not Applicable.

1.2.2 Alternate Objectives

Alternate objectives have been identified for selected sites considered to have complex attributes that control progress towards the achievement of RC. These sites are identified in the Table I of the PWS. For Alternate Objective sites, as for all sites in Table 1 of the PWS, the contractor shall maintain compliance with all existing final or interim RODs, any post-ROD changes, or other equivalent remedial decision documents throughout the POP of the contract.

Based on Air Force technical review of the performance of existing remedial strategies/ approaches at selected sites, sites were placed in a category of alternatives objectives if one or more of the following conditions were identified:

1. Achieving RC is expected to require substantially longer than 30 years;

2. Achieving RC is unattainable with standard characterization and/or existing remediation technology due to technical or other limitations related to site conditions; and/or

3. Achieving RC is anticipated to require advanced site characterization technologies to improve the CSM, determine appropriate remedial technology, and/or characterize recently regulated contaminants.

The Air Force will use the data and information obtained by meeting the objectives in this PWS to inform future decisions regarding restoration potential and investment strategies.

Site-specific alternate objectives shall include one or more of the following:

• Advanced Site Characterization – Data are needed to improve the CSM, determine appropriate remedial technology, support remediation design and construction, and/or characterize recently regulated contaminants. Site-specific objectives identified in Table 1 address these data needs and are described further in subsection 1.2.2.1.

• Remedy Recommendation and/or Amendments in Decision Documents – The existing remedial technology has been ineffective; however, RC is achievable with different, but currently available technologies. Site-specific objectives are identified in Table 1 and described further in subsection 1.2.2.2.

1.2.2.1 Advanced Site Characterization

Existing remedial technologies have been ineffective and collecting data to update and refine the CSM is necessary. Site-specific objectives related to advanced site characterization are identified for OT026, OT033, and WP007 in order to support selection and/or optimization of an effective remediation strategy. The Contractor shall implement advanced characterization methods, both established approaches and state-of-science techniques (applied per guidance identified in enclosure X), to attain these objectives.

The Contractor shall identify key site characteristics that may have limited the effectiveness of existing remedial technologies so that optimization (of existing technologies) can be implemented, or provide a basis for selecting an alternative technology. Data collection may include better definition of the geology, hydrogeology, geochemistry, and/or distribution of COCs. Consider the following data needs: (1) Source Definition; (2) Migration pathway, rates, and fluxes in 3-D; (3) Mass distribution; (4) Biogeochemical framework; and (5) Impact of recent and historical remedies on site conditions.

The deliverable from this task will be a report describing data collection efforts, an updated CSM, and a risk evaluation, as appropriate. If a source-strength evaluation has been completed, the Contractor shall evaluate whether additional source control is needed or appropriate. If a plume stability evaluation has been conducted, the Contractor shall evaluate whether the plume, or portions of the plume, are amenable to natural attenuation.

1.2.2.2 Remedy Recommendation and/or Amendments in Decision Documents

As mentioned above, the existing remedial technologies have been ineffective at the sites listed in Table 1. Site-specific objectives are identified for site WP007 related to evaluating and selecting alternative remediation technologies that may not be specified in the existing decision document.

Unless the characterization described in section 1.2.3.1 identifies how the prior technologies can be successfully implemented at the site, the Contractor shall evaluate and select alternative remediation technologies capable of attaining RC within an acceptable timeframe.

Where appropriate to evaluate the proposed technology, the contractor shall conduct pilot and/or full-scale technology demonstrations. The Contractor shall identify appropriate remedial technologies and target zones, design/plan, conduct and evaluate the pilot and/or field scale technology consistent with appropriate Air Force, regulatory and ITRC guidance. The Contractor shall determine performance monitoring criteria, and identify a control sub-site (current state) for comparison and evaluate results.

Based upon the results of the remedy evaluation and pilot/field tests, the Contractor shall provide one of the final deliverables, as identified for the site in Table 1: (1) Provide a technical memorandum to the Air Force with a recommendation to augment, modify, and/or replace the existing remedy at OT033 and WP007; or (2) Complete an ESD or ROD Amendment at OT033 and WP007.

2.0 APPLICABLE DOCUMENTS

The Contractor shall identify and comply with all applicable federal, state, and local statutes;

DOD and AF instructions, manuals, handbooks, regulations, guidance, and policy letters (including AF policy and guidance for IRP, and MMRP); Executive Orders (EOs); American Society for Testing and Materials (ASTM); American Petroleum Institute (API) Codes; National Association of Corrosions Engineers (NACE); National Fire Protection (NFPA); Steel Structures and Painting Counsel (SSPC); National Electrical Code (NEC); Uniform Fire Code (UFC); and International Building Code (IBC) including all changes and amendments in effect on the date of issuance of this contract. Interim Air Force Guidance On Sampling and Response Actions for 1,4-Dioxane at Operational and BRAC Installations, 15 August 2013. Interim Guidance on Perfluorinated Compounds,” 17 August 2012. It is the Contractor’s responsibility to identify and comply with all applicable requirements. In addition, the Contractor shall refer to the current versions of the Department of Defense (DoD) Policy and Guidelines for Acquisitions Involving Environmental Sampling or Testing and The United States AF Construction Management Implementation Guide. See Attachment 1 for guidance for Alternate Objective Sites.

The Contractor shall identify and comply with all applicable documents for the bases including RODs, ROD Amendments, ESDs, RCRA Permits and subsequent modifications, Risk Evaluation Corrective Action Program (RECAP) documents, the Endangered Species Act, other Decision Documents, Deeds, and conveyance notices. Key base-specific documents are listed in Enclosure 2.

The information provided in this PWS is not intended as a substitute for complete analysis of technical data available, nor is it intended to be a guide on how the Contractor should address achievement of the Performance Objectives.

3.0 GOVERNMENT FURNISHED INFORMATION, EQUIPMENT, AND PROPERTY

(GFI, GFE, GFP)

Government Furnished Information is listed in Enclosure 2, Key Documents. The AF believes that documentation provided with the solicitation represents the most recent and appropriate documentation available for the Installation and sites identified in this contract. However, if there is a conflict between this information and other site documentation (the existing reports), the Contractor is solely responsible for reviewing all available information and forming their own independent, professional conclusions/interpretation of site conditions and requirements to achieve the performance objectives of this contract. Specific documents may be made available following a request to the Contracting Officer (CO), if the documentation can be distributed in a timely manner. Electronic format is not guaranteed.

The Contractor shall properly account for and manage all new and existing GFE and/or GFP procured and utilized at the bases as-is where-is in accordance with the applicable Federal Acquisition Regulation (FAR). Lists of GFE/GFP are provided in Attachment X.

Remediation systems may or may not be listed as GFE and/or GFP. The Contractor is responsible for providing all other supplies and equipment, not already installed and not listed in Attachment X, required to achieve the performance objectives of this contract. All AF owned property (including wells) used for remediation purposes must be maintained by the Contractor in accordance with applicable maintenance requirements and usability for the intended purpose.

The Contractor is responsible for proper return or disposal of excess or unserviceable equipment or materials as required during the duration of this contract. Prior to disposal of excess or unserviceable equipment listed in Attachment X, the Contractor shall coordinate activities with the Contracting Officer (CO) for disposition instructions.

4.0 MANAGEMENT, PLANNING, AND REPORTING REQUIREMENTS

The Contractor shall implement a full range of environmental remediation activities as required to meet objectives of this contract and in accordance with all applicable base, regulatory, and site requirements. The Contractor shall supply all labor, equipment, and materials necessary to accomplish the work. The Contractor shall perform management and planning functions, including performance measurement and fund status reporting.

4.1 Project Management Plan (PMP)

The Contractor shall develop and maintain a detailed PMP. The PMP shall include the Technical Approach, Integrated Master Schedule (IMS), and Milestone Payment Schedule (MPS), prepared as part of the Contractor’s proposal. The IMS and MPS shall be consistent with each other. In addition, the PMP shall specify the resources required for the planning, execution, control, and completion of the stated performance objectives. At a minimum, the PMP shall include the following sections: technical approach, performance objectives in accordance with the PWS, draft Performance Models, organization and integration of the project team, schedule management and project controls, transitional activities, risk management, SubCLIN management, quality management, health and safety management, project communications and stakeholders, procurement management, security management, IMS and MPS. The PMP should identify the project’s resources and project tasks corresponding to the SubCLINs for this contract.

The first draft of the PMP shall be due within sixty (60) calendar days of contract award and subsequent revisions shall be subject to AF review and approval. The revised version of the PMP shall be due within 14 calendar days from receipt of AF comments. The PMP shall be updated as necessary throughout the contract to remain current with the approved execution strategy. The revised versions and all updates of the PMP shall be submitted in an electronic format consistent/compatible with the AFCEC SharePoint website, eDASH.

4.2 Schedule and Planning Requirements – Integrated Master Schedule (IMS)

The Contractor shall prepare and submit an IMS as part of the proposal, with each PMP delivery, and monthly in electronic format that at a minimum will contain the following: (D1)

• Identifies activities and milestone payments at a detailed level, to include installation, site, CLIN/Sub-CLIN, task description, start dates, finish dates, milestone payment amount, percent complete as approved by the COR, designation of regulatory CERCLA phase completions, predecessor and successor relationships associated with activities, and designation of performance objective achievement

• Presents a realistic sequenced events for completion of the performance objectives within the performance period

• Identifies critical path items that may affect ability to meet the schedule

• Identifies all milestone payments consistent with the approved MPS (i.e., descriptions, cost, start/finish dates, and percent complete)

• Sites associated with each milestone/task shall be noted using the EESHO-MIS Site IDs and referencing all site aliases noted in Table 1 of this PWS and SubCLINs.

The schedule shall be provided in initial hardcopy and subsequently in electronic format consistent/compatible with AF software, currently Microsoft Project and in Adobe Acrobat portable document file (.pdf) [cite any other formats required such as Microsoft Excel].

Updates to the IMS must be completed monthly. The updated and revised schedules shall be submitted electronically to the AFCEC SharePoint website, eDASH, with monthly status reports with changes clearly identified by the Contractor.

4.3 Milestone Payment Schedule (MPS)

Milestone payments shall be based on the completion of definable and measurable steps which are considered integral and necessary to the achievement of the stated performance objectives.

Completion of milestones shall demonstrate payment is appropriate and warranted. AF approval of the documentation supporting the completion of the milestone is required for payment.

Examples include AF approval of Draft Remedial Investigation report, AF acceptance that annual and final performance goals per approved performance models have been achieved.

Where regulatory acceptance/concurrence is required for this documentation, AF acceptance of the milestone will occur following regulatory acceptance/concurrence of the documentation (e.g., EPA approval of Draft Record of Decision). For milestones where regulatory acceptance/ concurrence is required and regulatory acceptance/concurrence cannot be obtained, the AF will evaluate the Contractor’s documents to determine if they are legally and technically acceptable to warrant payment for achieving that milestone.

The Contractor’s proposed MPS may require restructure of Contract Line Item Number (CLIN)/SubCLINs, if necessary, to align with projected available funding prior to award;

however, the MPS is not final with award of the contract. Changes made to the MPS prior to award are used to finalize the SubCLINs description and amount. Award of the contract does not equate to final acceptance of the MPS. The MPS shall be included as part of the PMP. The MPS will be negotiated during development of the PMP and may require additional changes.

The Contractor shall submit the MPS in an electronic format consistent/compatible with the AFCEC SharePoint website, eDASH. Final decisions regarding the adequacy of milestone and deliverable completion resides solely with the Contracting Officer’s Representative (COR). The COR will take into consideration the appropriate acceptance and/or concurrence of necessary site remediation documentation by regulators, consistent with applicable regulatory drivers of this

PWS. (D2)

Management and overhead type costs (e.g., program/project management, monthly reporting, mobilization costs, etc.) do not provide measureable program advancement and are not appropriate milestone payments. These costs/expenses should be allocated into site, site grouping, or Operable Unit (OU)-related milestone payments that provide demonstrable value to the program. Milestones shall not represent a “progress” payment or a monthly payment for level of effort expended. Completing site mobilization/demobilization (unless exempted by CO), accomplishment of field activities, or submittal of a monthly status or Operations and Maintenance (O&M) reports are examples of unacceptable milestone payments.

The first deliverable milestones required in the MPS are the PMP and Basewide UFP-QAPP.

There shall be one initial PMP deliverable milestone for the contract and one Basewide UFP- QAPP deliverable milestone per installation. The Contractor shall not allocate costs to specific sites or include indirect costs associated with sites. PMPs shall be updated as necessary to remain current with the approved execution strategy but will not have a milestone payment associated with it. Site specific UFP-QAPPs shall be specified as separate payment milestones under the site-specific SubCLIN(s), as appropriate.

The number of milestone payments per site should be limited to a reasonable amount based on the scope and anticipated duration to achieve the performance objective at the site. The final SubCLIN milestone may include a combination of the AF approved draft-final and Regulator approved final version which must be a minimum of 20% of the total SubCLIN cost. The Contractor is limited to one invoice submitted to AFCEC per month. The invoice must itemize the milestone payments for each site or grouping associated with the invoice.

If the Contractor anticipates working beyond the performance objective date to achieve a final milestone (applies to SubCLIN dates only), the Contractor shall submit a period of performance extension request to the CO at least 60 days prior to the expiration date of the SubCLIN.

The contractor shall not plan or perform work after 1 July of the funds cancellation year. The Contractor shall invoice NLT 1 August in the cancellation of funds year. The Contractor will not receive payment until milestones are achieved in accordance with the MPS.

4.4 ORC Document Repository

The Contractor shall maintain a document repository for all ORC documents to include, but not limited to: information on meetings, documents submitted, SubCLIN details, milestone status as agreed to in the PMP, contract and any modifications; current topics associated with the ORC, basic ORC statistics and objectives, stakeholder Point of Contact (POC) information; calendar of events/meetings/milestones; laboratory results and reports, 3D conceptual models; groundwater reports, analysis, studies; links to administrative records/information repository records and to associated appropriate reference documents- state and federal policy guidance.

The repository is intended to be a single access point repository for all ORC documentation. It shall be accessible to stakeholders during the life of the ORC. The Contractor shall provide notifications to the COR, CO, and Base POC at the time data is included in the repository. At close-out, all repository documents will be transferred to DVD media and delivered to the AF.

The Contractor shall create and maintain a Master Document List (MDL) that includes all documents, whether the document is a deliverable or not, prepared during the course of this contract. The Contractor shall maintain the project documents for the duration of this contract and transfer custody to the AF within 90 calendar days prior to POP expiration. Refer to Enclosure 4, “Format for Meta Data and .pdf Documents” for format guidance when providing documents.

4.5 Cost and Status Reporting

The Contractor shall prepare and submit a monthly Contractor’s Progress, Status, and Management Report (CPSMR). The CPSMR shall be used to review and evaluate the overall progress of the project, along with any existing or potential problem areas. The report shall be prepared in an electronic format consistent/compatible with the AFCEC SharePoint website, eDASH. The CPSMR shall also be used to indicate whether efforts for each site are on target for meeting the performance objective. The Contractor shall submit an updated IMS each month with the CPSMR. (D3)

The CPSMR shall include a summary of the events that occurred during the reporting period, discussion of performance, identification of risks, problems, proposed solutions, corrective actions taken, outstanding issues, and payments made toward the MPS to date.

4.6 Meeting and Conference Requirements

4.6.1 Meeting/Teleconference Support

The Contractor shall participate in post-award meetings and Project Management Review (PMR) meetings and teleconferences with the AF as necessary to achieve the performance objectives in this PWS. The Contractor shall coordinate meetings, provide logistical support (e.g., facilities, audio/visual), present materials, and lead technical discussions. The Contractor shall prepare and submit for Air Force review and concurrence any presentation materials and agendas for meetings no less than one working day prior to the event. The Contractor shall prepare minutes for all meetings attended within 14 calendar days following the event.

The Contractor also shall attend and/or support meetings and teleconferences to discuss technical or regulatory issues and project progress and status with the AF and regulatory agency representatives as required, including applicable meetings such as an internal kick-off meeting with the Air Force within 30 days upon contract award, an external kick-off meeting with the Air Force and regulators within 60 days from contract award, Restoration Advisory Board (RAB) meetings, Tier 1/Tier II partnering meetings and teleconferences. Monthly teleconferences shall also be required to discuss in detail progress and any technical or management issues. Also, other periodic meetings/teleconferences shall be required, as necessary. However, the frequency of meetings may change based on the status of the environmental restoration program. The AF will be present for all technical and public meetings with the regulatory agencies [IF

CONTRACTOR WILL PROVIDE LOGISTICAL SUPPORT KEEP FOLLOWING

LANGUAGE, IF NOT DELETE]; however, the Contractor shall coordinate the meetings, provide logistical support (e.g., facilities, audio/visual), present materials, and lead technical discussions. The Contractor shall clearly identify themselves as “Contractors” in all situations involving stakeholders. The Contractor shall prepare, and submit for AF review and concurrence, any presentation materials and agendas for meetings. [IF CONTRACTOR WILL

PROVIDE LOGISTICAL SUPPORT KEEP FOLLOWING LANGUAGE, IF NOT DELETE:]

The Contractor shall prepare minutes for all meetings attended within 14 calendar days following the event. Travel to/from the Base and to other CONUS locations for such purposes as meeting attendance, briefings, and/or presentations may be required in support of this remedial action.

These activities are considered incidental to the effort required and shall not be included for separate milestone payments. (D4 and D5)

The Contractor shall not contact any regulatory agency without prior notification and approval by the AF (Installation).

4.6.2 Public Meetings and Hearings

The Contractor shall support all community involvement requirements to meet CERCLA, RCRA, and other regulatory requirements including public meetings, public notices, RAB meetings, Technical Working Group, Community Advisory Group meetings, public comment periods, and responsiveness summary preparation. Hill AFB Restoration has a very active Community Involvement program which includes an existing Public Affairs (PA) support contract which provides specific requirements such as providing logistical support for RAB meetings and public coordination. Hill AFB has a RAB that is currently meeting quarterly.

However, the frequency of meetings may change based on the status of the environmental restoration program.

The Contractor shall coordinate and attend teleconferences as necessary with the assigned Public Affairs Officer (PAO) to ensure the PAO is fully aware of all ongoing activities, public outreach status, compliance with applicable regulations, and possible issues that might impact the AF and its public image in accordance with Clause H029, Implementation of Disclosure of Information.

The Contractor shall notify the Base POC before any contact with the PAO.

Examples of types of Public Affairs requirements include the presentation of technical information and logistical support (e.g., advertising, audio-visual, handouts, report(s), recordings, verbatim transcripts, poster boards, slides, synopses, etc.) for events and/or meetings in support of the Government’s position. All reports and other information generated under this contract shall become the property of the Government, and distribution to any other source by the Contractor is prohibited unless authorized by the COR.

The Contractor shall use staff trained in public affairs to complement the technical staff on the project. These trained staff must attend all meetings with the public along with the appropriate technical staff. The credentials of the trained staff must be submitted to and approved by the AFCEC COR in advance of any meeting with the public. The trained staff shall demonstrate effective public communications experience and experience in building relationships with the stakeholders involved in cleanup activities or similar efforts.

The Contractor shall research, coordinate, and provide responses for short-notice internal and external requests for information such as congressional inquiries and media requests as requested by the PAO or other applicable action officers. These inquiries require the Contractor to provide the AF factual and responsive information within two (2) hours of request unless a longer timeframe is stipulated.

4.7 Spatial Data (Map) Requirements

The Contractor shall NOT establish new Geographic Information System (GIS) systems.

In furtherance of the environmental construction or restoration effort, the Contractor shall provide geospatial data and map(s) of installation features (historical, existing, or planned) altered or constructed as required to achieve the performance objectives of this contract.

Source data and product data remain the property of the United States Government. The Contractor shall protect all geospatial data, including geometry, attributes, metadata, topologies, and relational database schemas and operations used in association with this PWS. Further information about security and nondisclosure requirements should be obtained from the installation Geospatial Integration Office (GIO).

The Contractor shall provide data to update the GIS and/or computer-aided design and drafting (CADD) files as required to achieve the performance objectives of this contract. Source data and product data remain the property of the United States Government.

The Contractor shall also ensure that GIS data is submitted in a format compatible with the AF GeoBase program, as outlined in the AF GeoBase Strategic Plan. The Contractor shall consult with each Base POC and/or installation GIO office to ensure CADD and GIS data is compatible with each installation’s requirements. (D6)

4.8 Notification Requirements

The Contractor shall notify the CO, COR, and Base POC of critical issues that may affect the contract performance and/or human health and the environment. The types of issues that require notification include, but are not limited to, health risks, spills, Notices of Violation (NOVs) (received or anticipated), changes in critical personnel, and finding unanticipated unexploded ordnance (UXO) or chemical warfare materiel (CWM). If unanticipated UXO were discovered during field activities, the Contractor shall immediately stop work, report the discovery to the Base POC, CO and COR, and implement the appropriate safety precautions. Field activities shall not continue until clearance is received from the CO. On critical issues, verbal notification shall be made immediately, followed by written notification as soon as practical.

4.9 Permits

The Contractor shall develop, coordinate, apply, comply with, and/or modify all federal, state, local, and other applicable environmental permits, access agreements, easements, licenses, and certificates required to achieve the performance objectives of this contract as detailed in Sections

4.9.1 and 4.9.2. Generally, the AF will sign all easement agreements and modifications and/or renewals of new or existing permits, licenses, and certificates required under this contract [except SITE XX where the Contractor will sign the right of access agreement].