Contractor Questions W91213819Q0036 Q1 - Is the contractor to supply all equipment used in the sluicing operation? YES

Q2 - Period of performance states July 1 2019 - June 2020. Can the contractor perform on this job at any point throughout that duration? Is there a specific time for work to be performed in regards to chinook salmon spawning? Gravel must be placed during the period of 15 July – 31 August 2019.