Revised Spec Sections 01 11 00 and 01 22 00.

View the file

Other files

File Type Posted
Abstract.pdf PDF
W9123819B0021.0002.pdf PDF
Amendment_3.pdf PDF
Pricing_Schedule.Amend3.pdf PDF
W9123819B0021.0001.pdf PDF
W9123819B0021.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICIATION NO. W91238-19-B-0021

1 of 1 Amendment 0003

YUBA RIVER BASIN, CALIFORNIA

MARYSVILLE RING LEVEE PHASE 2C

YUBA COUNTY

AMENDMENT 0003 - SUMMARY:

A) SPECIFICATION 1970

1) Replaced entire Section 01 11 00.

2) Replaced entire Section 01 22 00.

Yuba River Basin, California 1970 Marysville Ring Levee Phase 2C

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 WORK INCLUDED

1.2 TYPE OF CONTRACT

1.3 PROJECT DESCRIPTION

1.3.1 Location

1.3.2 Description

1.3.3 Site Conditions

1.4 EXISTING FACILITIES

1.5 CONTRACTOR'S USE OF THE PREMISES

1.6 WORK TO BE PERFORMED BY THE CONTRACTOR

1.7 SCHEDULE CONSTRAINTS

PART 2 PRODUCTS

PART 3 EXECUTION

-- End of Section Table of Contents --

01 11 00 - 1

AM0003

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 WORK INCLUDED

This Specification section describes the Project location and access, existing facilities, the Contractor's use of the premises, Project occupancy, and the work to be performed by the Contractor. The description of the work to be performed that is provided herein is intended to be a general overview and does not include all the work actually required under the Contract.

1.2 TYPE OF CONTRACT

This Contract consists of Job and Unit Price Schedule Items.

1.3 PROJECT DESCRIPTION

1.3.1 Location

The Project is located in Yuba County, California, along portions of the Marysville Ring Levee which surrounds the City of Marysville.

1.3.2 Description

Phase 2C of the Marysville Ring Levee improvement projects is a seepage mitigation project . The seepage mitigation spans between the east side of the Union Pacific Trestle Bridge and the HWY. 70 Bridge. Phase 2C Levee Improvements primarily include the following:

a. A Soil-Cement-Bentonite (SCB) seepage cutoff wall that spans between the Union Pacific Bridge and the HWY. 70 Bridge. Based upon the levee centerline alignment, the cutoff walls spans between STA 236+74 and STA 247+50 (stationing at degrade/working platform elevation). The SCB cutoff wall will extend through the levee crown to depths varying between approximately 81 feet and 84 below the working platform of a partially degraded levee.

b. Waterside levee geometry corrections between STA 236+65 and STA 247+65 to obtain waterside levee slopes primarily at a 3 horizontal to 1 vertical slope.

c. Removal and Replacement portions of Biz Johnson Drive. Biz Johnson Drive is primarily replaced with a 3.5" Asphalt Concrete (AC) and 6" of Aggregate Base (AB). Removal and replacement of the existing paved levee crown to the west and east of Biz Johnson Drive. The west side will be replaced with 6" AB and extends to the UPRR. The east side will be replaced with 3" AC and 6"AB, and extends to Hwy 70. The east side paved surface tapers away from the levee crown toward the landside due to bridge clearance. The salvage of, and reconstruction of, metal beam guard rail along Biz Johnson Drive.

d. The existing rock slope protection (RSP) between Union Pacific Railroad

01 11 00 - 2

Bridge and HWY 70 should be protected in-place. If existing RSP areas are disturbed the RSP will be removed (stock piled) and replaced in the same area.

e. Prior to construction of the cutoff wall. A temporary pressurized sewer line bypass will need to be installed from a designated point of connection on the landside toe near the Waste Water Treatment Plant (WWTP), to a designated connection point on the waterside. The existing 12" temporary gravity sewer line will then be excavated and removed, and other abandoned pipes that run parallel and across the levee will be removed, as shown on the plans. After construction of the cutoff wall, a permanent pressurized 18" sewer pipe will installed and connected at the designated points. Quality Control (QC) will be conducted by the Contractor, and the City of Marysville Engineering representative will conduct Quality Assurance (QA).

f. Demolition, and removal, and replacement of existing City of Marysville wet and dry utilities associated with cutoff walls, vaults, and appurtenances. Removal and replacement of utility vault structures.

Coordination with a City of Marysville contractor to allow the City's construction of an approximately 18", temporary, sewer effluent force main bypass pipe to allow the Phase 2C contractor to demolish and remove existing utilities in coordination with the City's contractor.

g. Construction of aggregate base levee service (O&M) roads primarily along the toe of the waterside slopes (15' wide), varies, and from the east side of the Union Pacific Bridge east to Biz Johnson Drive.

h. General demolition to include signage, chain link fencing, metal pipe gates, metal barricades, pipe bollards, AC dikes, and other levee features identified within the project footprint. Protect existing rock slope protection located at portions of the toe and face of the waterside slope.

i. Work will include the removal and offsite disposal of unsuitable levee material unearthed during the levee degrade and other excavation associated with new levee features.

j. Work will include the excavation and transport of borrow material to provide suitable material needed to replace unsuitable excavated materials and for the construction of levee embankment.

k. Construction of temporary and permanent storm water pollution features and structures in accordance with the specifications.

l. Install a new gate on the levee crown to the west of Biz Johnson Drive as shown on the plans.

m. Remove and Install/replace new gates as shown on the plans.

n. Remove and re-install pressurized storm drain pipe east of Biz Johnson Drive within the limits of the levee degrade onlyor to the limits shown on drawing CU-108A.

1.3.3 Site Conditions

The work is associated with improvements to the existing Marysville Ring Levee. The portion of the levee that is associated with the Phase 2C project runs in the east-west direction between the existing, and active, 01 11 00 - 3

Union Pacific Railroad Trestle Bridge and the existing HWY.70 Bridge, both of which cross over the Yuba River.

At the Union Pacific Bridge, the levee sharply turns northwest and runs somewhat parallel to the Feather River and up to, and beyond, the 5'TH Street Bridge. From HWY.70, the levee runs east. The Yuba River is offset varying distances from the toe of east-west running levee located between the UPRR Bridge and HWY.70.

The new SCB cutoff wall will be located at the center line of the existing levee crown and between the existing and active Union Pacific Railroad Bridge (UPRR) and the HWY. 70 Bridge. Biz Johnson Drive, a 2-lane roadway, runs east-west beneath the UPRR Bridge diagonally up the waterside slope, over the levee crown, and down the landside slope to 1'ST Street, and with access to HWY.70. A road closure will be required at Biz Johnson Drive and an approved detour plan installed and maintained by the Contractor.

The City of Marysville Waste Water Treatment Plant (WWTP) is located adjacent to the westerly portion of the landside slope. The WWTP is accessed from Biz Johnson Drive. Access to the WWTP plant must be maintained at all times.

A dirt levee service road runs along the toe of the slope for the portion of the levee that runs north from the Union Pacific Bridge. The toe of slope service road is accessible to bicyclists and pedestrians to gain access to the paved service road located at the crown of the northerly running levee. At 5'TH Street bridge signage will be required to alert pedestrians and bicyclist that the service road is closed ahead during work associated with the levee, rock slope, and erosion control improvements.

Biz Johnson Drive runs beneath the 5'TH Street Bridge and will require a road closure with an approved detour plan installed and maintained by the Contractor.

A multi-use paved road (service road and bicycle path) runs diagonally across the waterside slope beneath the 5'TH Street Bridge.

A seasonally active soccer field park is located just north of the 5'TH Street Bridge. A picnic area is also located just north of the 5'TH Street Bridge. A Feather River boat ramp and associated parking lot is located just south of the 5'TH Street Bridge and adjacent to the work.

Seasonally active baseball fields are located along Biz Johnson Drive between 5'TH Street Bridge and the UPRR Bridge.

Utilities cross through the levee as identified in the demolition and utility plans and as discussed herein.

1.4 EXISTING FACILITIES

Existing facilities are shown on the Plans to the extent known.

Prior to commencing construction, the Contractor is solely responsible for contacting all utility companies with facilities in the project footprints.

The Contractor is to request field identification of all utilities within the project footprints. The Contractor and its' Subcontractors are required to notify the Underground Service Alert 48 hours in advance of performing any excavation by calling (800) 227-2600.

Unknown utilities may be encountered on site and not shown on the plans.

01 11 00 - 4

The location of existing utilities are shown in an approximate way only and have not been independently verified by the owner or its' representatives.

The Contractor shall determine the exact location of all utilities within the project footprints in vicinity of excavations and/or other contract work that could impact or interfere with a utility or utility operation.

The contract drawings include a "CITY OF MARYSVILLE, Temporary Force Main Bypass PLAN". As indicated in drawings, the Contractor is required to coordinate all utility demolition and removal work with the City of Marysville Public Works Department, its' Representatives, and its' Contractor's. Demolition and removal of utilities shall not commence until written approval is obtained from the City of Marysville and the Contracting Officer.

1.5 CONTRACTOR'S USE OF THE PREMISES

In addition to requirements presented elsewhere on the Plans and in the Specifications, the Contractor shall adhere to the following requirements:

a. The Contractor shall have charge and care of, and bear the risk of damage to, the Project until its completion and final acceptance.

b. The Contractor shall not create or permit the continued existence of any nuisance in or about the job site.

c. The Contractor shall protect and not disturb existing facilities, or access thereto, which are not in the work area or are in the work area and can be avoided.

d. Materials and equipment shall be stored and protected, as recommended by the manufacturer or required by applicable codes and standards, to guarantee preservation of quality, appearance, and suitability for the Project. They shall be stored to facilitate inspection by the Contracting Officer. Materials shall not be stored on the embankment slopes.

e. The Contracting Officer will provide the lands, easements, and rights-of-way, or other right-to-enter and work on lands shown on the Plans. Nothing herein contained and nothing marked on the Plans, shall be interpreted as giving the Contractor exclusive occupancy of the lands, easements, or rights-of-way provided by the USACE.

f. The work areas and the areas for the Contractor's use are shown on the Plans.

g. The Contractor shall be responsible for restoring, at its own expense, all disturbed storage and work areas to a condition similar to those existing prior to construction or improved, except where other surfacing or treatment is required by the Plans or Specifications.

h. Should the contractor elect to use an alternate staging area, they should get in writing that the landowner will hold the Government harmless of any damage caused by the contractor. This written agreement should be submitted to the Contractin Officer.

1.6 WORK TO BE PERFORMED BY THE CONTRACTOR

Construction of the Project consists, in general, of the following activities:

01 11 00 - 5

a. Performing mobilization, demobilization, and Contract administration.

b. Performing erosion and sediment control and storm water pollution prevention, and complying with all environmental controls and requirements related to the Contractor's operations as specified, in Project licenses and permits obtained by the Government, and as specified elsewhere in the Specifications.

c. Performing pre-construction surveying, construction surveying, and construction quality control.

d. Providing all required equipment, personnel, and materials to construct the Project as required by the Plans and Specifications, and to complete the Project in accordance with the Contract schedule.

e. Providing all required temporary facilities, utilities, and offices required to complete the work.

f. Providing water for construction from available sources, including pumping, piping, hauling, and storage that may be required, and paying all fees and costs associated with developing the water supply, including pumping energy costs if wells are used.

g. Coordinate Utility Demolition and Removal with the City of Marysville, its' Representatives and Contractors.

1.7 SCHEDULE CONSTRAINTS

The Contractor shall reference the Contract Documents and Technical Specifications for schedule constraints.

The Contractor shall also reference the Contract Documents and Technical Specifications for information on Contract completion dates and liquidated damages.

Levee degrade, Demolition and removal of existing 30-inch Sanitary Sewer Effluent pipe near station 238+00 and existing 12-inch chlorine contact pipe, near station 238+40, shall not commence until the contractor has constructed an 18-inch, temporary, bypass, sewer effluent line and until written permission is obtained from the City of Marysville Public Works Department and the Contracting Officer.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

01 11 00 - 6

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 JOB PAYMENT ITEMS

1.1.1 Mobilization and Demobilization (ITEM 0001)

1.1.1.1 Measurement and Payment

1.1.2 Storm Water Pollution Prevention Plan (ITEM 0002)

1.1.2.1 Measurement and Payment

1.1.3 Pre-and-Post Construction Surveys (ITEM 0003)

1.1.3.1 Measurement and Payment

1.1.4 Clearing and Grubbing (ITEM 0004)

1.1.4.1 Measurement and Payment

1.1.5 Topsoil Stripping (ITEM 0005)

1.1.5.1 Measurement

1.1.5.2 Payment

1.1.5.3 Unit of Measurement

1.1.6 Traffic Control (ITEM 0006)

1.1.6.1 Measurement and Payment

1.1.7 Sawcut Pavement (ITEM 0007)

1.1.7.1 Measurement

1.1.7.2 Payment

1.1.7.3 Unit of Measure

1.1.8 Demolition (ITEM 0008)

1.1.8.1 Measurement and Payment

1.1.9 Levee Excavation (Degrade) (ITEM 0009)

1.1.9.1 Measurement

1.1.9.2 Payment

1.1.9.3 Unit of Measure

1.1.10 Cutoff Wall Construction (ITEM 0010)

1.1.10.1 Measurement

1.1.10.2 Payment

1.1.10.3 Unit of Measure

1.1.11 Levee Embankment (Fill Material) (ITEM 0011)

1.1.11.1 Measurement

1.1.11.2 Payment

1.1.11.3 Unit of Measure

1.1.12 Levee Embankment (Impervious Fill) (ITEM 0012)

1.1.12.1 Measurement

1.1.12.2 Payment

1.1.12.3 Unit of Measure

1.1.13 6-inch Aggregate Surface Course(Levee Crown) (0013)

1.1.13.1 Measurement

1.1.13.2 Payment

1.1.13.3 Unit of Measure

1.1.14 6-inch Aggregate Base, Paved Levee Crown (ITEM 0014)

1.1.14.1 Measurement

1.1.14.2 Payment

01 22 00 - 1

1.1.14.3 Unit of Measure

1.1.15 Asphaltic Concrete (Paved Levee Crown) (ITEM 0015)

1.1.15.1 Measurement

1.1.15.2 Payment

1.1.15.3 Unit of Measurement

1.1.16 Temporary WWTP Bypass and Incidental work (ITEM 0016)

1.1.16.1 Measurement and Payment

1.1.17 Permanent Pressurized 18-inch Sewer Pipe and Incidental work

(ITEM 0017)

1.1.17.1 Measurement and Payment

1.1.18 6-Inch Aggregate Base (AB), Biz Johnson Drive (ITEM 0018)

1.1.18.1 Measurement

1.1.18.2 Payment

1.1.18.3 Unit of Measure

1.1.19 Asphaltic Concrete Pavement (AC), Biz Johnson Drive (ITEM 0019)

1.1.19.1 Measurement

1.1.19.2 Payment

1.1.19.3 Unit of Measurement

1.1.20 Asphaltic Concrete (AC) Dike (ITEM 0020)

1.1.20.1 Measurement

1.1.20.2 Payment

1.1.20.3 Unit of Measure

1.1.21 Remove and Reinstall Existing Cal Trans Type A77L1 Guardrail and Supports To The Extent Possible (ITEM 0021)

1.1.21.1 Measurement and Payment

1.1.22 Remove and Reinstall 2 (E) Pipe-Gates and Bollards and

Construct 1 New Pipe-Gate and Bollards (ITEM 0022)

1.1.22.1 Measurement and Payment

1.1.23 Remove and Reuse Signage (ITEM 0023)

1.1.23.1 Measurement and Payment

1.1.24 Pavement Stripping (ITEM 0024)

1.1.24.1 Measurement and Payment

1.1.25 Permanent Erosion Control Seeding (Project Site) (ITEM 0025)

1.1.25.1 Measurement

1.1.25.2 Payment

1.1.25.3 Unit of Measure

1.1.26 Chain Link Fence and Street-End-Barricade (ITEM 0026)

1.1.26.1 Measurement and Payment

1.1.27 Temporary Construction Fence and Rail (ITEM 0027)

1.1.27.1 Measurement and Payment

1.1.28 Excavation, Remove Pipe and Backfill (30" Non-active Sewer

Pipe)(ITEM 0028)

1.1.28.1 Measurement and Payment

1.1.29 Excavation, Remove Pipe and Backfill (12" Active HDPE Pipe)

(ITEM 0029)

1.1.29.1 Measurement and Payment

1.1.30 Excavation, Remove Pipe and Backfill (24" Non-active Sewer

Pipe)(ITEM 0030)

1.1.30.1 Measurement and Payment

1.1.31 Pavement Markers (ITEM 0031)

1.1.31.1 Measurement and Payment

1.1.32 Remove and Re-Use Existing Rock Slope Protection (ITEM 0032)

1.1.32.1 Measurement

1.1.32.2 Payment

1.1.32.3 Unit of Measure

1.1.33 Excavation, Remove Pipe and Backfill (8" Non-active Storm

Water Pipe)(ITEM 0033)

1.1.33.1 Measurement and Payment

1.1.34 Excavation, Remove Pipeline Portion, and Replace (30" Steel

01 22 00 - 2

Active Storm Water Pipe)(ITEM 0034)

1.1.34.1 Measurement and Payment

1.1.35 Imported Impervious Levee Fill (ITEM 1001)

1.1.35.1 Measurement

1.1.35.2 Payment

1.1.35.3 Unit of Measure

1.1.36 Construction Standby (ITEM 1002)

1.1.36.1 Measurement

1.1.36.2 Payment

1.1.36.3 Unit of Measure

PART 2 PRODUCTS

PART 3 EXECUTION

3.1 INVOICE SUBMISSION PROCEDURES

3.1.1 Required Procedure

3.1.2 Required Documents

-- End of Section Table of Contents --

01 22 00 - 3

SECTION 01 22 00

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 JOB PAYMENT ITEMS

Payment items for the work of this contract for which contract job payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, shall be included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

1.1.1 Mobilization and Demobilization (ITEM 0001)

1.1.1.1 Measurement and Payment

Measurement and payment for mobilization, demobilization, staging areas and for all other work covered by this section of the Specifications shall be made at the contract JOB price for item "MOBILIZATION AND DEMOBILIZATION";

which payment shall constitute full compensation for all work covered by Sections 01 71 10 MOBILIZATION AND DEMOBILIZATION and 01 50 02 TEMPORARY CONSTRUCTION FACILITIES of the specifications, as shown in the plans and as specified by the Contracting Officer. The cost loaded should be 60% for mobilization and 40% for demobilization. As a part of the demobilization cost should be 0.5% total award contract for As-built drawings.

1.1.2 Storm Water Pollution Prevention Plan (ITEM 0002)

1.1.2.1 Measurement and Payment

Measurement and payment for Storm Water Pollution Prevention Plan, and for all other work to complete the Storm Water Pollution Prevention Plan including of installing, properly maintaining, and removing temporary BMPs at the end of the job, will be made at the JOB price for item "STORM WATER POLLUTION PREVENTION PLAN" for which payment shall constitute full compensation for all work covered in the specifications and as shown on the drawings.

1.1.3 Pre-and-Post Construction Surveys (ITEM 0003)

1.1.3.1 Measurement and Payment

Measurement and payment for Pre-and-Post Construction Surveys, and for all other work to complete the Pre-and-Post Construction Surveys, will be made at the JOB price for item "PRE-AND-POST CONSTRUCTION SURVEYS" for which payment shall constitute full compensation for all work covered in the specifications, as shown in the plans, and as directed by the Contracting

01 22 00 - 4

Officer.

1.1.4 Clearing and Grubbing (ITEM 0004)

1.1.4.1 Measurement and Payment

CLEARING AND GRUBBING and the disposal of the materials from this operation and for all other work stated in the "CLEARING AND GRUBBING" section of the Specifications shall be measured and paid at the contract JOB PRICE for "CLEARING AND GRUBBING". This price shall constitute full compensation for furnishing all labor, materials and equipment, incidentals, and doing all work necessary to complete the clearing and grubbing, as specified, including disposal or salvage of materials, and restoring all ground surfaces. It Includes storage and replacement of existing sand stockpile near STA 243+50. Clearing and grubbing of the project site, staging areas and borrow sites shall be included in at the contract JOB PRICE for "CLEARING AND GRUBBING". This includes but is not limited to: 1) providing all labor, and equipment to remove levee crown stockpiles, poles, trees, bushes, existing rocks, existing riprap, and debris as indicated in the plans, and as directed by the Contracting Officer.

1.1.5 Topsoil Stripping (ITEM 0005)

1.1.5.1 Measurement

TOPSOIL STRIPPING of the materials from this operation will be measured by Average End Area Methodsquare yard.

1.1.5.2 Payment

Payment for STRIPPING will be made at the contract unit price for "STRIPPING". This price shall constitute full compensation for all equipment, labor, materials and incidentals necessary to complete the work as specified in the Specifications and as shown on the plans. Work includes, but is not limited to, stripping to a depth of 4-inches, hauling, stockpiling, placement, and spreading of topsoil. No separate or direct payment will be made for stockpiling, transportation, loading, unloading, disposal, or dust control of stripped materials. All costs in connection therewith shall be included in the unit price for TOPSOIL STRIPPING.

1.1.5.3 Unit of Measurement

Unit of Measure: CubicSquare Yard (SY).

1.1.6 Traffic Control (ITEM 0006)

1.1.6.1 Measurement and Payment

Measurement and payment for TRAFFIC CONTROL, and for all other work to complete the TRAFFIC CONTROL, will be made at the JOB price for item "TRAFFIC CONTROL" for which payment shall constitute full compensation for all work covered in the specifications which includes but is not limited to traffic control design, traffic control equipment, traffic control signage, and related labor and materials.

01 22 00 - 5

1.1.7 Sawcut Pavement (ITEM 0007)

1.1.7.1 Measurement

The unit of measurement for this item will be based on the number of linear feet of cut made by the specified approved method to the lines delineated on the plans or as directed by the Contracting Officer.

1.1.7.2 Payment

Payment for this item will be based on the contract unit prices per Linear Foot for Sawcut Pavement, completed and approved including all labor, materials, tools, testing, and equipment necessary to complete the work as specified.

1.1.7.3 Unit of Measure

Unit of Measure: Lineal Foot (LF).

1.1.8 Demolition (ITEM 0008)

1.1.8.1 Measurement and Payment

Measurement and payment for DEMOLITION, and for all other work to complete the DEMOLITION, will be made at the JOB price for item "DEMOLITION" for which payment shall constitute full compensation for all work covered in the specifications, as shown in the plans, and as directed by the Contracting Officer. As indicated in the plans demolition will include;

but not be limited to: wet and dry utilities, utility vaults, utility valves and appurtenances, asphaltic concrete pavement and aggregate base, chain link fence, barbed wire fence, asphaltic concrete dikes, and concrete debris removal. Demolition includes the excavation and backfill cost associated with Demolition item. Demolition includes the cost to remove and transport the demolished material to either a legal landfill, recycling center, or to the Marysville Levee District field office.

1.1.9 Levee Excavation (Degrade) (ITEM 0009)

1.1.9.1 Measurement

LEVEE EXCAVATION (DEGRADE) and related work shall be measured by the cubic yard, to the nearest 1.0 cubic yard from the dimensions shown on the plans.

Measurement will be by the Average End Area Method.

1.1.9.2 Payment

Payment for LEVEE EXCAVATION (DEGRADE) will be paid at the contract unit price for "LEVEE DEGRADE". This price shall constitute full compensation for all equipment, labor, materials, waste, hauling excavated materials to and from on-site stockpile locations or other point of use, and all incidentals necessary to complete the work specified.

1.1.9.3 Unit of Measure

Unit of Measure: Embankment Cubic Yard (CY).

01 22 00 - 6

1.1.10 Cutoff Wall Construction (ITEM 0010)

1.1.10.1 Measurement

Payment for Cutoff Wall Construction (Soil Cement Bentonite) shall be made at the contract price per square foot (height of the wall x length of the wall) of bid item. Such price shall include all costs of levee preparation, cutoff wall installation, stockpiling or spoiling materials generated during the cutoff wall installation, and all other items incidental to the construction and completion of the cutoff wall. No separate payment will be made for materials including bentonite, cement, additives, soil, equipment and mixing, handling and cleaning the slurry, and overtime during continuous operations, cleanup, assistance in the collection and maintenance of records and quality control testing, Type G survey monuments for as-constructed cutoff wall location; such items being included in the price of the cutoff wall. Final acceptance of the cutoff wall will be based on meeting all the requirements for the cutoff wall dimensions, bentonite slurry mix, and the 28-day hydraulic conductivity and strength requirements.

1.1.10.2 Payment

The amount to be paid for Cutoff Wall Construction (Soil Cement Bentonite) shall be determined by a unit price and the payment shall include full compensation for equipment usage, labor, transportation, materials, installation, maintenance, removal, restoration of areas disturbed by all construction activities necessary to complete the work specified at the contract unit price.

1.1.10.3 Unit of Measure

Unit of Measure: Square Foot (SF).

1.1.11 Levee Embankment (Fill Material) (ITEM 0011)

1.1.11.1 Measurement

Materials specified for LEVEE EMBANKMENT (FILL MATERIAL) will be measured for payment by the cubic yard, in place, and quantities will be determined by the average end method of in-place volume. Contractor shall account for shrink and swell. The basis for measurement will be cross sections of the areas to be filled taken after levee excavation operations and the actual cross sections of the embankments constructed within the specified tolerance. Cross sections shall be performed at significant breaks in grade except that the maximum distance between cross sections shall not exceed the distance specified in the General Specifications. Embankments not constructed to design grade and section including allowable tolerance as indicated on the Contractor's compliance survey will not be accepted.

1.1.11.2 Payment

Payment will be made for LEVEE EMBANKMENT (FILL MATERIAL) placed as required in levee and ramp embankments as indicated in Section 31 00 00 EARTHWORK and on the Plans at the contract unit price for "LEVEE EMBANKMENT (Fill Material). Payment shall constitute full compensation for furnishing all plant, labor, equipment, material, hauling, and performing all operations necessary for foundation preparation and placing and compacting the material, materials testing, and moisture control, including hauling embankment material from the material source.

01 22 00 - 7

1.1.11.3 Unit of Measure

Unit of Measure: Embankment Cubic Yard (CY).

1.1.12 Levee Embankment (Impervious Fill) (ITEM 0012)

1.1.12.1 Measurement

Select fill material specified for LEVEE EMBANKMENT (IMPERVIOUS FILL) will be measured for payment by the Embankment cubic yard, and quantities will be determined by the average end area method of in-place volume.

Contractor shall account for shrink and swales. The basis for measurement will be cross sections of the areas to be filled taken after clearing, grubbing, and stripping operations and the actual cross sections of the embankments constructed within the specified tolerance. Cross sections shall be performed at significant breaks in grade except that the maximum distance between cross sections shall be less than 500 feet. The levee sections not constructed to design grade and section including allowable tolerance as indicated on the Contractor's compliance survey will not be accepted. Material removed as a result of the clearing, grubbing, and stripping operations will not be included in measurement of fill for payment.

1.1.12.2 Payment

Payment will be made for the LEVEE EMBANKMENT (IMPERVIOUS FILL) material placed as required, as indicated on the Drawings. Payment shall constitute full compensation for furnishing all plant, stockpiling, importing, labor, transportation, hauling,equipment and material, and performing all operations necessary for foundation preparation and placing and compacting the material, materials testing, and moisture control.

1.1.12.3 Unit of Measure

Unit of Measure: Embankment Cubic Yard (CY).

1.1.13 6-inch Aggregate Surface Course(Levee Crown) (0013)

1.1.13.1 Measurement

6-INCH AGGREGATE SURFACE COURSE (LEVEE CROWN) will be measured for payment by the ton (2,000 pounds), to the nearest 1.0 ton. Quantities for payment will be certified by individual truck weight tickets delivered to the Engineer at the time of delivery of each truckload of material. Moisture content not exceeding six percent by weight will be acceptable in determining payment quantities. Deductions will be made from the certified weight for moisture in excess of this amount and for materials in excess of the allowable thickness.

1.1.13.2 Payment

6-INCH AGGREGATE SURFACE COURSE (LEVEE CROWN) will be paid for at the contract unit price under Bid Item "6-INCH AGGREGATE SURFACE COURSE (LEVEE CROWN)". Payment will constitute full compensation for the construction and completion of the Aggregate Base including material, SUBGRADE PREPARATION, and furnishing all labor and incidentals necessary to complete the work required as shown on the Plans, as specified in these Specifications, and as directed by the Contracting Officer.

01 22 00 - 8

1.1.13.3 Unit of Measure

Unit of Measure: Ton.

1.1.14 6-inch Aggregate Base, Paved Levee Crown (ITEM 0014)

1.1.14.1 Measurement

6-INCH AGGREGATE BASE PAVED LEVEE CROWN will be measured for payment by the ton, to the nearest 1.0 ton. Quantities for payment will be certified by individual truck weight tickets delivered to the Engineer at the time of delivery of each truckload of material. Moisture content not exceeding six percent by weight will be acceptable in determining payment quantities.

Deductions will be made from the certified weight for moisture in excess of this amount and for materials in excess of the allowable thickness.

1.1.14.2 Payment

6-INCH AGGREGATE BASE PAVED LEVEE CROWN will be paid for at the contract unit price under Bid Item "6-INCH AGGREGATE BASE PAVED LEVEE CROWN".

Payment will constitute full compensation for the construction and completion of the Aggregate Base including material, SUBGRADE PREPARATION, and furnishing all labor and incidentals necessary to complete the work required as shown on the Plans, as specified in these Specifications, and as directed by the Contracting Officer.

1.1.14.3 Unit of Measure

Unit of Measure: Ton.

1.1.15 Asphaltic Concrete (Paved Levee Crown) (ITEM 0015)

1.1.15.1 Measurement

The quantity of ASPHALTIC CONCRETE (PAVED LEVEE CROWN) completed and accepted as determined by the Contracting Officer shall be measured in tons.

1.1.15.2 Payment

Quantities of ASPHALTIC CONCRETE (PAVED LEVEE CROWN) as measured above, will be paid for at the respective contract unit price under Item "ASPHALTIC CONCRETE (PAVED LEVEE CROWN)". Payment will constitute full compensation for the construction and completion of the bituminous concrete pavement, including material, equipment, and furnishing all labor and incidentals necessary to complete the work required as shown on the Plans, as specified in Section 32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS of these Specifications, and as directed by the Contracting Officer.

1.1.15.3 Unit of Measurement

Unit of Measure: Ton

1.1.16 Temporary WWTP Bypass and Incidental work (ITEM 0016)

1.1.16.1 Measurement and Payment

Measurement and payment for Temporary WWTP Bypass Sewer Line, and for all other work to complete the Temporary WWTP Bypass Sewer Line, will be made

01 22 00 - 9 at the JOB price. Construction of a TEMPORARY WWTP BYPASS AND INCIDENTAL WORK from the landside near the Waste Water Treatment Plant (WWTP) to a designated point on the waterside including the removal of an existing 12-inch gravity sewer line and other abandoned pipes, disposal of the materials from this operation shall be measured and paid at the contract JOB PRICE for "TEMPORARY WWTP BYPASSAND INCIDENTAL WORK". This price shall constitute full compensation for furnishing all labor, materials and equipment, incidentals, and doing all work necessary to complete the TEMPORARY WWTP BYPASS AND INCIDENTAL WORK, for which payment shall constitute full compensation for all related work covered in the specifications and as shown on the drawings.

1.1.17 Permanent Pressurized 18-inch Sewer Pipe and Incidental work (ITEM 0017)

1.1.17.1 Measurement and Payment

Measurement and payment for Permanent Pressurized 18-inch Sewer Pipe, and for all other work to complete the Permanent Pressurized 18-inch Sewer Pipe, will be made at the JOB price. Construction of a PERMANENT PRESSURIZED 18-INCH SEWER PIPE from the landside near the Waste Water Treatment Plant (WWTP) to a designated point on the waterside shall be measured and paid at the contract JOB price for "PERMANENT PRESSURIZED 18-INCH SEWER PIPE AND INCIDENTAL WORK". This price shall constitute full compensation for furnishing all labor, engineering-design, materials and equipment, incidentals, and doing all work necessary to complete the PERMANENT PRESSURIZED 18-INCH SEWER PIPE, for which payment shall constitute full compensation for all work covered in the specifications and as shown on the drawings.

1.1.18 6-Inch Aggregate Base (AB), Biz Johnson Drive (ITEM 0018)

1.1.18.1 Measurement

6-INCH AGGREGATE BASE (AB), BIZ JOHNSON DRIVE will be measured for payment by the ton, to the nearest 1.0 ton. Quantities for payment will be certified by individual truck weight tickets delivered to the Engineer at the time of delivery of each truckload of material. Moisture content not exceeding six percent by weight will be acceptable in determining payment quantities. Deductions will be made from the certified weight for moisture in excess of this amount and for materials in excess of the allowable thickness.

1.1.18.2 Payment

6-INCH AGGREGATE BASE (AB), BIZ JOHNSON DRIVE will be paid for at the contract unit price under Bid Item "6-INCH AGGREGATE BASE (AB), BIZ JOHNSON DRIVE". Payment will constitute full compensation for the construction and completion of the Aggregate Base including material, SUBGRADE PREPARATION, and furnishing all labor and incidentals necessary to complete the work required as shown on the Plans, as specified in these Specifications, and as directed by the Contracting Officer.

1.1.18.3 Unit of Measure

Unit of Measure: Ton.

01 22 00 - 10

1.1.19 Asphaltic Concrete Pavement (AC), Biz Johnson Drive (ITEM 0019)

1.1.19.1 Measurement

The quantity of ASPHALTIC CONCRETE PAVEMENT (AC), BIZ JOHNSON DRIVE completed and accepted as determined by the Contracting Officer shall be measured in tons.

1.1.19.2 Payment

Quantities of ASPHALTIC CONCRETE PAVEMENT (AC), BIZ JOHNSON DRIVE as measured above, will be paid for at the respective contract unit price under Bid Item "ASPHALTIC CONCRETE PAVEMENT (AC), BIZ JOHNSON DRIVE".

Payment will constitute full compensation for the construction and completion of the bituminous concrete pavement, including material, equipment, and furnishing all labor and incidentals necessary to complete the work required as shown on the Plans, as specified in Section 32 12 16 HOT-MIX ASPHALT (HMA)FOR ROAD of these Specifications, and as directed by the Contracting Officer.

1.1.19.3 Unit of Measurement

Unit of Measure: Ton

1.1.20 Asphaltic Concrete (AC) Dike (ITEM 0020)

1.1.20.1 Measurement

The unit of measurement for "Asphaltic Concrete (AC) Dike" will be based on the number of linear feet of cut made by the specified approved method to the lines delineated on the plans or as directed by the Contracting Officer.

1.1.20.2 Payment

Payment for "Asphaltic Concrete (AC) Dike" will be based on the contract unit prices per Linear Foot for AC dike construction, completed and approved including all labor, materials, tools, testing, and equipment necessary to complete the work as specified.

1.1.20.3 Unit of Measure

Unit of Measure: Lineal Foot (LF).

1.1.21 Remove and Reinstall Existing Cal Trans Type A77L1 Guardrail and Supports To The Extendt Possible (ITEM 0021)

1.1.21.1 Measurement and Payment

Construction work for this item will be made at the JOB price for item

"REMOVE AND REINSTALL EXISTING CAL TRANS TYPE A77L1 GUARDRAIL AND SUPPORTS

TO THE EXTENT POSSIBLE" for which payment shall constitute full compensation for all work covered in the specifications, as shown in the plans, and as directed by the Contracting Officer.

01 22 00 - 11

1.1.22 Remove and Reinstall 2 (E) Pipe-Gates and Bollards and Construct 1 New Pipe-Gate and Bollards (ITEM 0022)

1.1.22.1 Measurement and Payment

Measurement and payment for REMOVE AND REINSTALL 2 (E)PIPE GATES AND BOLLARDS AND CONSTRUCT 1 NEW PIPE-GATE AND BOLLARDS, and for all other work to complete the installation and construction of the task "REMOVE AND

REINSTALL 2 (E)PIPE GATES AND BOLLARDS AND CONSTRUCT 1 NEW PIPE-GATE AND

BOLLARDS", will be made at the JOB price for item for which payment shall constitute full compensation for all work covered in the specifications, as shown in the plans, and as directed by the Contracting Officer.

1.1.23 Remove and Reuse Signage (ITEM 0023)

1.1.23.1 Measurement and Payment

Measurement and payment for REMOVE AND REUSE SIGNAGE and for all other work to complete the installation and construction of the REMOVE AND REUSE SIGNAGE, will be made at the JOB price for item "REMOVE AND REUSE SIGNAGE" for which payment shall constitute full compensation for all SIGNAGE work covered in the specifications and as shown in the drawings.

1.1.24 Pavement Stripping (ITEM 0024)

1.1.24.1 Measurement and Payment

Measurement and payment for PAVEMENT STRIPING and for all other work to complete the installation and construction of the PAVEMENT STRIPING, will be made at the JOB price for item "PAVEMENT STRIPING" for which payment shall constitute full compensation for all PAVEMENT STRIPING work covered in the specifications and as shown in the drawings.

1.1.25 Permanent Erosion Control Seeding (Project Site) (ITEM 0025)

1.1.25.1 Measurement

PERMANENT EROSION CONTROL SEEDING (PROJECT SITE) as shown on the plans, and as described in these specifications Section 32 92 33 GRASS SEEDING AND EROSION CONTROL, will be made at the JOB price for item "PERMANENT EROSION CONTROL SEEDING(PROJECT SITE)" for which payment shall constitute full compensation for all work covered in the specifications, as shown in the plans, and as directed by the Contracting Officer.

1.1.25.2 Payment

PERMANENT EROSION CONTROL SEEDING (PROJECT SITE) as shown on the plans, and as described in these specifications, will be paid for at the JOB price for PERMANENT EROSION CONTROL SEEDING(PROJECT SITE); which shall include installation, watering, labor, equipment and material, and performing all operations to establish Permanent Erosion Control. Permanent Erosion Control measures, which are required to be repeated due to the Contractor's negligence, carelessness, neglect, failure to install or maintain Permanent Erosion Control properly, will be performed by the Contractor at no expense to the Government.

1.1.25.3 Unit of Measure

Unit of Measure: Job.

01 22 00 - 12

1.1.26 Chain Link Fence and Street-End-Barricade (ITEM 0026)

1.1.26.1 Measurement and Payment

Measurement and payment for Chain Link Fence and Street Barricade and for all other work to complete the CHAIN LINK FENCE AND STREET-END-BARRICADE installation, will be made at the contract JOB price for item "CHAIN LINK FENCE AND STREET-END-BARRICADE"; which payment must constitute full compensation for all work covered in Section 01 50 02 TEMPORARY CONSTRUCTION FACILITIES of the specifications. Payment also includes removal once approved by the Contracting Officer. Removal and post footing restoration must be included in the JOB price and will not be paid separately.

1.1.27 Temporary Construction Fence and Rail (ITEM 0027)

1.1.27.1 Measurement and Payment

Measurement and payment for Temporary Construction Fence and Rail and for all other work to complete the installation and construction of the Temporary Construction Fence and Rail, will be made at the JOB price for item "TEMPORARY CONSTRUCTION FENCE AND RAIL" for which payment shall constitute full compensation for all TEMPORARY CONSTRUCTION FENCE AND RAIL work covered in the specifications and as shown in the drawings.

1.1.28 Excavation, Remove Pipe and Backfill (30" Non-active Sewer Pipe)(ITEM 0028)

1.1.28.1 Measurement and Payment

Measurement and payment for Excavate, Remove Pipe and Backfill (30" Non-active Sewer Pipe), and for all other work to complete the task "Excavate, Remove Pipe and Backfill (30" Non-active Sewer Pipe)", will be made at the JOB price for item "Excavate, Remove Pipe and Backfill (30" Non-active Sewer Pipe)for which payment shall constitute full compensation for all equipment, labor, materials, waste, hauling excavated materials to and from on-site stockpile locations or other point of use, all incidentals necessary to complete the work specified and as shown in the plans, and as directed by the Contracting Officer. Measurement will be by the Average End Area Method to compute excvation and backfill volumes. Also backfill levee to elevation 81 feet to provide cutoff wall working platform.

1.1.29 Excavation, Remove Pipe and Backfill (12" Active HDPE Pipe) (ITEM 0029)

1.1.29.1 Measurement and Payment

Measurement and payment for Excavate, Remove Pipe and Backfill (12" Active HDPE Pipe), and for all other work to complete the task "Excavate, Remove Pipe and Backfill (12" Active HDPE Pipe)", will be made at the JOB price for item "Excavate, Remove Pipe and Backfill (12" Active HDPE Pipe)for which payment shall constitute full compensation for all equipment, labor, materials, waste, hauling excavated materials to and from on-site stockpile locations or other point of use, all incidentals necessary to complete the work specified and as shown in the plans, and as directed by the Contracting Officer. Measurement will be by the Average End Area Method to compute excvation and backfill volumes. Also backfill levee to elevation 81 feet to provide cutoff wall working platform.

01 22 00 - 13

1.1.30 Excavation, Remove Pipe and Backfill (24" Non-active Sewer Pipe)(ITEM 0030)

1.1.30.1 Measurement and Payment

Measurement and payment for Excavate, Remove Pipe and Backfill (24" Non-active Sewer Pipe), and for all other work to complete the task "Excavate, Remove Pipe and Backfill (24" Non-active Sewer Pipe)", will be made at the JOB price for item "Excavate, Remove Pipe and Backfill (24" Non-active Sewer Pipe)for which payment shall constitute full compensation for all equipment, labor, materials, waste, hauling excavated materials to and from on-site stockpile locations or other point of use, all incidentals necessary to complete the work specified and as shown in the plans, and as directed by the Contracting Officer. Measurement will be by the Average End Area Method to compute excavation and backfill volumes. Also backfill levee to elevation 81 feet to provide cutoff wall working platform..

1.1.31 Pavement Markers (ITEM 0031)

1.1.31.1 Measurement and Payment

Measurement and payment for PAVEMENT MARKERS and for all other work to complete the installation and construction of the PAVEMENT MARKERS, will be made at the JOB price for item "PAVEMENT MARKERS" for which payment shall constitute full compensation for all PAVEMENT MARKERS work covered in the specifications and as shown in the drawings.

1.1.32 Remove and Re-Use Existing Rock Slope Protection (ITEM 0032)

1.1.32.1 Measurement

REMOVE AND RE-USE EXISTING ROCK SLOPE PROTECTION will be measured for payment by the cubic yard (CY). Computed by the area disturbed as shown on the drawings and multiplied by and average depth of 18 inches.

1.1.32.2 Payment

REMOVE AND RE-USE EXISTING ROCK SLOPE PROTECTION will be paid at the contract unit price under item "REMOVE AND RE-USE EXISTING ROCK SLOPE PROTECTION". Payment will constitute full compensation for all equipment, labor, materials, waste, hauling RSP materials to and from on-site stockpile location, and incidentals necessary to complete the work specified.

1.1.32.3 Unit of Measure

Unit if Measure: Cubic yard (CY).

1.1.33 Excavation, Remove Pipe and Backfill (8" Non-active Storm Water Pipe)(ITEM 0033)

1.1.33.1 Measurement and Payment

Measurement and payment for Excavate, Remove Pipe and Backfill (8" Non-active Storm Water Pipe), and for all other work to complete the task "Excavate, Remove Pipe and Backfill (8" Non-active Storm Water Pipe)", will be made at the JOB price for item "Excavate, Remove Pipe and Backfill (8" Non-active Storm Water Pipe)for which payment shall constitute full

01 22 00 - 14 compensation for all equipment, labor, materials, waste, hauling excavated materials to and from on-site stockpile locations or other point of use, all incidentals necessary to complete the work specified and as shown in the plans, and as directed by the Contracting Officer. Measurement will be by the Average End Area Method to compute excvation and backfill volumes.

Also backfill levee to elevation 81 feet to provide cutoff wall working platform.

1.1.34 Excavation, Remove Pipeline Portion, and Replace (30" Steel Active Storm Water Pipe)(ITEM 0034)

1.1.34.1 Measurement and Payment

Measurement and payment for Excavate, Remove Pipeline Portion, and Replace (30" Steel Active Storm Water Pipe), and for all other work to complete the task "Excavate, Remove Pipeline Portion, and Replace (30" Steel Active Storm Water Pipe)", will be made at the JOB price for item "Excavate, Remove Pipeline Portion, and Replace (30" Steel Active Storm Water Pipe)" for which payment shall constitute full compensation for all equipment (including temporary storm drain pump to accommodate local drainage), labor, materials, waste, hauling excavated materials to and from on-site stockpile locations or other point of use, all incidentals necessary to complete the work specified and as shown in the drawing, see CU-108A, and as directed by the Contracting Officer. Measurement will be by the Average End Area Method to compute excavation and backfill volumes. Also backfill levee to elevation 81 feet to provide cutoff wall working platform.

1.1.35 Imported Impervious Levee Fill (ITEM 1001)

1.1.35.1 Measurement

Select fill material specified for "IMPORTED IMPERVIOUS LEVEE FILL" will be measured for payment by the cubic yard (CY),which is placed and compacted,and quantities will be computed by the average end method from cross sections taken before and after the embankment fill placement operations when the materials are acceptably placed and compacted as herein specified. Contractor must account for shrinkage and swell. Cross sections must be taken in sufficient numbers to account for geometric changes in the cross sections but not great than 75-foot increments measured along the levee alignment. The levee sections not constructed to design grade and section exceeding allowable tolerances as indicated on the Contractor's compliance survey will not be accepted.

1.1.35.2 Payment

Payment will be made for the "IMPORTED IMPERVIOUS LEVEE FILL" material placed as required, as indicated on the drawings. Payment must constitute full compensation for furnishing all plant, stockpiling, importing, labor,transportation, hauling, equipment and material, and performing all operations necessary for foundation preparation and placing and compacting the material, materials testing, and moisture control as specified in Section 31 00 00 EARTHWORK.

1.1.35.3 Unit of Measure

Unit of Measure: Cubic yard (CY).

01 22 00 - 15

1.1.36 Construction Standby (ITEM 1002)

1.1.36.1 Measurement

Measure CONSTRUCTION STANDBY by the day. Each day will be measured per 24 hour period where the Contractor must stop work as directed by the Contracting Officer.

1.1.36.2 Payment

Payment will be made for costs associated with operations necessary for CONSTRUCTION STANDBY. The work must include furnishing the related labor, equipment, and materials. Include all associated costs in the bid item for "CONSTRUCTION STANDBY"; which payment constitutes full compensation for all Work involved in CONSTRUCTION STANDBY as defined in the Contract Documents or as directed by the Contracting Officer.

1.1.36.3 Unit of Measure

Unit of Measure: Day.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.1 INVOICE SUBMISSION PROCEDURES

References include USACE QMS, FAR 52.232-5, Payments under Fixed-Price Construction Contracts, and FAR 52.232-27, Prompt Payment for Construction Contracts.

3.1.1 Required Procedure

a. The payment request process must begin with the scheduling meeting.

Section 01 32 01 PROJECT SCHEDULE states: "Use the schedule as the basis for determining contract earnings during each update period and therefore the amount of each progress payment." The QA Representative or Project Engineer will meet…