SCOPE OF WORK
PROJECT: PL 84-99 Colusa Basin Levee Repairs, Site 0561-41.
AUTHORITY: P.L. 84-99 Flood Control and Coastal Emergencies
SOLICITATION NO: W91238-19-R
DATE: April 16, 2019
DOCUMENTS ENCLOSED: Plans showing location, typical section, specifications, and estimated quantities.
AUTHORIZATION: Public Law 84-99
SCOPE OF WORK: The work will require reconstruction in order to rehabilitate the levee to pre-flood conditions. The Contractor shall provide an estimate based on the level of effort described herein to remediate this site located along the western portion of the Colusa Basin Drain in Colusa County approximately 0.5 mile west of the city of Knights Landing.
BACKGROUND: Due to excessive rain events during the winter of 2016/2017 Sacramento area levees experienced varying forms of erosion. The construction work for this site is remedial in nature, which involves rehabilitating the existing levee that experienced flood damage. In order to construct the adjacent levee, dewatering of the ditch at the landside levee toe may be required. The entire site will initially be cleared, grubbed and stripped of organics, vegetation and all loose, wet or deleterious material. The landside slope will be excavated to facilitate placement of fill on the landside slope and a landside berm. A keyway will be excavated below the location of the new levee toe. Upon completion, the slope will be seeded and the levee crown and toe road will be surfaced with aggregate base.
DESCRIPTION OF WORK AND SERVICES: The contractor shall review and analyze this scope and associated drawings for coordination of materials, and the necessary labor and equipment in order to provide an estimate for the activities described.
Task 1: Mobilize equipment required to rehabilitate the levee per the plans and specifications (P&S), as required by CLIN 0001.
Task 2: Provide labor, equipment, and materials required to reconstruct and reseed the levee as specified in the P&S. Dust control shall be incorporated into the cost of other line items.
Task 3: Meetings and Communication. The contractor shall account for and plan to hold a morning safety meeting, including with representatives of USACE, prior to the commencement of every work day. The morning safety meeting shall be accounted for in the cost of levee reconstruction. In addition the contractor shall plan on holding a general weekly progress meeting in the middle of the week to discuss accomplishment, workload and schedule. The contractor shall be responsible for creating a forward looking schedule for discussion purposes for the weekly meeting(s).
Task 4: Submittals. The contractor shall include with their overall price proposal the cost of providing all construction submittals. The cost of submittals shall be accounted for in the cost of levee reconstruction.
Task 5: Demobilize site and equipment required by CLIN 0001.
PERIOD OF PERFORMANCE: ALL WORK FOR THIS REQUIREMENT SHALL BE COMPLETED WITHIN
338 CALENDAR DAYS TO INCLUDE PRECONSTRUCTION SUBMITTALS, CONSTRUCTION ACTIVITIES, AND CLOSE OUT.