PERIOD OF PERFORMANCE
Design Package Name: South San Joaquin Levee Repairs
(Contract Package Name: Levee System 1151 PL 84-99 Levee Repairs)
Sites - 1151-15, 1151-16, 1151-17, 1151-22, and 1151-23
Assumption: This contract is planned to be awarded in 31 May, 2019 and have the contractor begin in-channel work on 23 July, 2019.
3 Phases from Time from Award:
Phase 1 – Submittals: 53 days Phase 2 – Construction: 100 days Phase 3 – Demobilization, As-Builts, Resolution to Modifications: 90 days
Total Period of Performance: 243 days
"ALL EARTHWORK FOR THIS PROJECT SHALL BE COMPLETED BY NOVEMBER 1, 2019."