Atch_1_SPEC_2268_BID_SCHEDULE_Rev.pdf

PDF 58 KB Posted

Attached to
PL 84-99 Site 1151_15_16_17_22_23 Federal contract opportunity
Solicitation number
W9123819B0013
Issued by
Department of the Army Corps of Engineers Engineering District Sacramento

About this file

BID SCHEDULE

View the file

Other files for this federal contract opportunity

Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Line Item No. Description Quantity Unit of

Measure Unit Price Total Price

0001 Mobilization and Demobilization 1 JOB -$ -$ 0002 SWPPP Development and Implementation 1 JOB -$ -$

SubTotal -$

Site: 1151-15

Line Item No. Description Quantity Unit of

Measure Unit Price Total Price

0003 Clearing, Grubbing, And Stripping 620 SY -$ -$ 0004 Excavation - General 80 CY -$ -$ 0005 Levee Fill 100 CY -$ -$ 0006 Hydro-Seeding 620 SY -$ -$

SubTotal -$

Site: 1151-16

Line Item No. Description Quantity Unit of

Measure Unit Price Total Price

0007 Clearing, Grubbing, And Stripping 460 SY -$ -$ 0008 Excavation - General 70 CY -$ -$ 0009 Levee Fill 270 CY -$ -$ 0010 Hydro-Seeding 460 SY -$ -$

SubTotal -$

Site: 1151-17

Line Item No. Description Quantity Unit of

Measure Unit Price Total Price

0011 Clearing, Grubbing, And Stripping 570 SY -$ -$ 0012 Quarry Stone - Below Water Placement 2,150 TN -$ -$ 0013 Soil-Filled Quarry Stone 560 CY -$ -$ 0014 Coir Fabric 230 SY -$ -$ 0015 Top Soil - Haul and Place 680 SY -$ -$ 0016 Hydro-Seeding 680 SY -$ -$

SubTotal -$

Site: 1151-22

Line Item No. Description Quantity Unit of

Measure Unit Price Total Price

PRICE SCHEDULE

South San Joaquin County Levee Repairs

Specification 2268

0017 Clearing, Grubbing, And Stripping 650 SY -$ -$ 0018 Excavation - General 190 CY -$ -$ 0019 Levee Fill 290 CY -$ -$ 0020 Hydro-Seeding 650 SY -$ -$

SubTotal -$

Site: 1151-23

Line Item No. Description Quantity Unit of

Measure Unit Price Total Price

0021 Clearing, Grubbing, And Stripping 470 SY -$ -$ 0022 Excavation - General 80 CY -$ -$ 0023 Levee Fill 160 CY -$ -$ 0024 Hydro-Seeding 470 SY -$ -$