Atch_1_SOW_2177_Levee_System_1151.pdf

PDF 86 KB Posted

Attached to
PL 84-99 1151 Levee System Repairs Federal contract opportunity
Solicitation number
W91238-18-R-0028
Issued by
Department of the Army Corps of Engineers Engineering District Sacramento

About this file

Atch 1 SOW 2177

View the file

Other files for this federal contract opportunity

Other files attached to PL 84-99 1151 Levee System Repairs, newest first.
File Type Posted
Sitewalk_Sign-In_Sheet_PL_84-99_1151_Levee_System_Repairs.pdf PDF
Atch_7_PL_84-99_Site_Visit_2177.pdf PDF
SF1442_Final_PL_84-99_1151_Levee_System_Repairs_9JUL2018.pdf PDF
Atch_3_Plans_PL_84-99_Site_1151_Final_Submittal_V12.pdf PDF
Atch_5_PPQ_0_Form.pdf PDF
Atch_4_Pre-Award_Survey_25_APR_2017.pdf PDF
Atch_6_Wage_Determination_6JUL18.pdf PDF
Atch_2_2177_Specifications.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCOPE OF WORK

PROJECT: Levee System 1151 PL 84-99 Levee Repairs, Sites 1151-11, 1151-12, 1151-14, 1151-15, 1151- 16, 1151-17, 1151-18, 1151-19, 1151-22, and 1151-23.

AUTHORITY: PL 84-99 Bank Protection Project; San Joaquin County

SOLICITATION NO: W91238-18-R

DATE: June 8, 2018

DOCUMENTS ENCLOSED: Plans showing location, typical section and estimated quantities.

AUTHORIZATION: Public Law 84-99

SCOPE OF WORK: The work will require reconstruction in order to rehabilitate levees to pre-flood conditions provided in the SITES section below. The Contractor shall provide an estimate based on the level of effort described herein to remediate 10 sites.

SITE: The sites are located along the San Joaquin River in San Joaquin County and are located on the vicinity map provided with the plan set. The specific sites are 1151-11 which is located on the right bank of the San Joaquin River approximately 4 miles southwest of the city of Manteca, California. Site 1151-12 is located on the right bank of the San Joaquin River approximately 4 miles southwest of the city of Manteca, California. Sites 1151-14, 1151-18, and 1151-19 are located on the right bank of the San Joaquin River approximately 4 miles southwest of the city of Manteca, California. Sites 1151-15 and 1151-16 are located on the right bank of the San Joaquin River approximately 4 miles southwest of the city of Manteca, California. Site 1151-17 is located on the right bank of the San Joaquin River approximately 4 miles southwest of the city of Manteca, California. Sites 1151-22 and 1151-23 are located on the right bank of the San Joaquin River approximately 6.5 miles southwest of the town of Ripon, California.

BACKGROUND: Due to excessive rain events during the winter of 2016/2017 Sacramento area levees experienced varying forms of erosion. The construction work is remedial in nature, which involves rehabilitating existing levees that experienced flood damage. The levee repairs necessary require clearing, stripping and grubbing of vegetation, dewatering operations, the removal of eroded or slumped soil, the placement and compaction of levee fill, the placement of rock protection, the placement of Coir fabric, the placement of top soil, the placement and compaction of aggregate base course, and hydroseeding.

DESCRIPTION OF WORK AND SERVICES: The contractor shall review and analyze this scope and associated drawings for coordination of materials, and the necessary labor and equipment in order to provide an estimate for the activities described.

Task 1: Mobilize equipment required to rehabilitate the levee per the plans and specifications (P&S), as required by CLIN 0001.

Task 2: Provide labor, equipment, and materials required to reconstruct and reseed the levee as specified in the P&S. Dust control shall be incorporated into the cost of other line items.

Task 3: Meetings and Communication. The contractor shall account for and plan to hold a morning safety meeting, including with representatives of USACE, prior to the commencement of every work day. The morning safety meeting shall be accounted for in the cost of levee reconstruction. In addition the contractor should plan on holding a general weekly progress meeting in the middle of the week to discuss accomplishment, workload and schedule. The contractor shall be responsible for creating a forward looking schedule for discussion purposes for the weekly meeting(s).

Task 4: Submittals. The contractor shall include with their overall price proposal the cost of providing all construction submittals. The cost of submittals shall be accounted for in the cost of levee reconstruction.

Task 5: Demobilize site and equipment required by CLIN 0001.

PERIOD OF PERFORMANCE: ALL EARTHWORK FOR THIS TASK ORDER SHALL BE COMPLETED BY

NOVEMBER 1, 2018. REMAINING CONSTRUCTION ACTIVITIES AND DEMOBILIZATION MUST BE

COMPLETED BY NOVEMBER 15, 2018. CONTRACT CLOSE-OUT INCLUDING AS-BUILTS AND

RESOLUTION TO MODIFICATIONS SHALL BE COMPLETED BY MARCH 15, 2019.

POINTS OF CONTACT: Gerry Slattery (916) 557-6603; William Doyle (916) 557-7429