Task Order #1

PERFORMANCE WORK STATEMENT (PWS)

Natomas Basin Mitigation at Novak Revised 4 Oct 2016

Revised 14 Oct 2016

1.0 GENERAL:

1.1 This work under this scope creates mitigation for upland and riparian woodland habitats. The major work elements described herein includes: collecting propagules, propagating seedlings, providing water, installing irrigation systems, installing container plants, grass seeding and soil stabilization, installing browse guards, and maintaining the features and the plants for a five year period of service, which includes a multi-year establishment period. Maintenance and establishment tasks includes: watering, weeding, mowing, spraying, storm water sampling, testing and reporting, replacing dead plants and restoration and cleanup. Design, plan, coordinate, organize, manage, and perform the activities described herein.

1.2 Description of Services/Introduction: The work described herein is mitigation for impacts that occurs at the

Natomas Basin Levee Project, Reaches I, H & D. The mitigation described above is being developed at one site identified as the Novak site.

1.3 Background: The levee work that encircles the Natomas Basin is to remediate seepage issues. As a result of this work impacts to vegetation and habitat will occur. The work scoped herein will mitigate for those impacts.

1.4 Objectives: The objectives of this Task Order are to develop and establish riparian upland vegetation at the

Novak site. Habitat development is based on installing plants on 11.1 acres and maintaining the plants until they have achieved self-sufficiency. Plant self-sufficiency is achieved when the plants roots have reached ground water and are able to live and thrive without artificial watering or maintenance.

1.5 Scope: Services require the Contractor to design, plan, coordinate, organize, manage, and perform the activities described herein. Tasks to be provided are tree removal and transplanting, seedling installation, water well drilling, temporary irrigation system installation, and soil preparation and grass seeding. Maintenance and establishment tasks includes: watering, weeding, mowing, spraying, storm water sampling, testing and reporting, replacing dead plants and restoration and cleanup. The contractor shall accomplish healthy plant growth and maturity.

1.6 Period of Performance: The period of performance shall be for one (1) Base Year of 12 months and four (4)

12-month option years. The Period of Performance reads as follows:

Base Year

Option Year I

Option Year II

Option Year III

Option Year IV

1.7 Place of Performance: The work to be performed under this contract will be performed at the project site known as the Natomas Mitigation site at Novak. This site is located near the intersection of the Garden Hwy and

Powerline Road, in Sacramento County, California.

1.8 Special Qualifications: The contractor is responsible for ensuring the herbicide spray employees possess and maintain current pesticide spraying certification during the execution of this contract. See MATOC PWS for key personnel.

2.0 CONTRACTOR QUALITY CONTROL (CQC):

The contractor shall develop and maintain an effective quality control program to ensure services are performed in accordance with this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor’s quality control program is the means by which he assures himself that his work complies with the requirement of the contract.

2.1 Work Phases: Contractor Quality Control is the means by which the Contractor ensures that the work activities, to include that of subcontractors and suppliers, complies with the requirements of the Contract. Conduct at least three phases of control for each definable feature of work as follows:

2.1.1 Preparatory Phase: Perform this phase prior to beginning work on each definable feature of work, after all required plans/documents/materials are accepted, and after copies are at the work site. This phase includes:

Review of the Contract requirements and drawings.

Examination of the work area to assure that all required preliminary work has been completed and is in compliance with the Contract.

Review of the appropriate activity hazard analysis to assure safety requirements are met.

2.1.2 Workmanship Phase: This phase is accomplished during the performance of each work activity.

Perform daily checks to assure completion of the particular feature of work. Accomplish the following:

Verify adequacy of controls to ensure full Contract compliance. Verify required control inspection and testing.

Establish level of workmanship and verify that it meets minimum acceptable workmanship standards. Compare with required sample panels as appropriate.

Check safety to include compliance with and upgrading of the safety plan and activity hazard analysis. Review the activity analysis with each worker.

2.1.3 Acceptance Phase: Conduct final follow-up checks and correct all deficiencies prior to the start of additional features of work which may be affected by the deficient work.

Pre-final Inspection: The Government will perform the Pre-final inspection to verify that the facility is complete and ready to be turned over to the Government. A Government Pre-final

Punch List may be developed as a result of this inspection. Ensure that all items on this list have been corrected before notifying the Government, so that a Final inspection with the customer can be scheduled. Correct any items.

Final Inspection: The final acceptance inspection will be formally scheduled by the Contracting

Officer based upon results of the Pre-Final inspection. Notify the Contracting Officer at least 14 days prior to the final acceptance inspection and include the Contractor's assurance that all specific items previously identified as being unacceptable, along with all remaining work performed under the Contract, will be complete and acceptable by the date scheduled for the final acceptance inspection.

2.2 Documentation: Maintain current records providing factual evidence that required quality control activities have been performed.

2.3 Notification: Of Noncompliance: The Contracting Officer will notify the Contractor of any detected noncompliance with the foregoing requirements. Take immediate corrective action after receipt of such notice.

Such notice, is deemed sufficient for the purpose of notification when delivered to the Contractor at the work site. If the Contractor fails or refuses to comply promptly, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders will be made the subject of claim for extension of time or for excess costs or damages by the Contractor.

3.0 DEFINITIONS AND ACRONYMS

3.1. Definitions: See MATOC base contract PWS for definition.

3.2. Acronyms: See MATOC base contract PWS for Acronyms.

4.0. GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND SERVICES

4.1. Services: The Government will not provide the Contractor any services.

4.2 Facilities: The Government will not provide the Contractor any facilities. . However, the government will provide an area designated for the Contractor’s use. The Contractor may establish facilities to include, but not limited to covered storage, etc on or in the designated area. Provide all utilities to this area. The Government will not be responsible for any damage to or loss of equipment and supplies stored on the Government’s premises.

Maintain fire extinguishers and other safety equipment responsibly.

4.3 Utilities: There may be electrical power poles at or near the site that the Contractor may use. Other than that, the Government will not provide utilities. The Contractor shall instruct employees in utilities conservation practices.

The contractor shall be responsible for operating under conditions that preclude the waste of utilities, which include turning off the water faucets or valves after using the required amount to accomplish cleaning vehicles and equipment. Electricity and phone service will NOT be furnished by the Government for the Contractor’s work area.

4.4 Equipment: The Government will not provide any equipment.

4.5 Materials: The Government will not provide any materials.

4.6 Data: The Government may provide computer data in the form of AutoCAD files, Microsoft Word Files, Microsoft Excel Files for creation of certain contractor submittals that follow specified formats, templates or development of as-built and as-installed drawings.

5.0. CONTRACTOR FURNISHED ITEMS AND SERVICES:

The Contractor shall furnish all supplies, equipment, facilities and services required to perform work under this contract that are not listed under Section 4.0 of this PWS.

6.0. PERFORMANCE OBJECTIVES:

6.1. Basic Services. The contractor shall provide services for the development of native vegetation habitats. These services include harvesting, propagating and installing plants; designing and installing an irrigation system; creating and erecting plant and site protection features; and maintaining the plants and features until the plants have reached self-sufficiency.

6.2 The work described herein applies to all mitigation sites within this task order, except as noted. Provide the following services and items, including but not limited to:

6.2.1 Post-Award Meeting: The Contractor agrees to attend any post-award meeting convened by the contracting activity or contract administration office in accordance with Federal Acquisition Regulation

Subpart 42.5 – Postaward Orientation. The meeting may be attended via teleconference. The Contractor shall coordinate a Post-Award meeting with the USACE-SPK (Sacramento District) Contracting Office

(CT) Point of Contact (POC), Donald Sumner, Donald.Sumner@usace.army.mil, via email 10 days after award of this task order, and ensure that all Contractor parties, including those having authority to sign on behalf of the Contractor, as well as, all other required parties that will be coordinating the work efforts on a daily basis, are present at the meeting. This meeting may be conducted by telephone conference or in person. If the Contractor attends the meeting in person, travel costs shall be at the Contractor's additional expense. The Contractor shall take meeting minutes during this meeting and submit to the Contracting

POC, no later than seven (7) days after the meeting. The meeting shall occur as soon after task order award as possible.

mailto:Donald.Sumner@usace.army.mil

6.2.2. Preparing and Submitting Plans: Prepare and submit all plans pertinent to the work required herein. Refer to Attachment G-Submittal Register. At a minimum, provide the following:

6.2.2.1 Performance Work Plan: addressing the design approach. Describe all tasks as listed in the Performance Objectives and how each will be performed. Identify who will undertake the tasks, where the work will be done, what will be done, and task duration.

6.2.2.2 Project Schedule: Keep the project schedule up to date and submit every month with the

Contractor’s invoice.

6.2.2.3 Accident Prevention Plan (APP): to be prepared in accordance with Appendix A of EM

385-1-1, US ARMY CORPS OF ENGINEERS SAFETY AND HEALTH REQUIREMENTS

MANUAL. See paragraph 15. SAFETY REQUIREMENTS. Prepare the written site-specific

Accident Prevention Plan (APP) in accordance with the format and requirements of USACE EM

385-1-1 (2014). Cover all paragraph and subparagraph elements in Appendix A of USACE EM

385-1-1 "Minimum Basic Outline for Preparation of Accident Prevention Plan". Append the

Activity Hazard Analyses (AHAs) to the APP. Use the APP for the project because it will present site specific hazards and provide site specific controls. Where a paragraph or subparagraph element is not applicable to the work to be performed indicate "Not Applicable" next to the heading. Address job-specific tasks and any unusual or unique aspects of the project or activity for which it is written. Interface the APP with the Contractor's overall safety and health program

(SHP). Include and make site-specific in the applicable APP element any portions of the

Contractor's overall safety and health program referenced in the APP. The Government considers the Prime Contractor to be the "controlling authority" for all worksite safety and health of the subcontractors. Contractors are responsible for informing their subcontractors of the safety provisions under the terms of the contract and the penalties for noncompliance, coordinating the work to prevent one craft from interfering with or creating hazardous working conditions for other crafts, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out. Sign the APP in accordance with the requirements of EM 385-1-1, Appendix A.

Activity Hazard Analysis (AHA) Appendix to the APP. Develop an Activity Hazard

Analysis (AHA) for every operation involving site activities presenting hazards. Format the AHA(s) in accordance with Figure 1-2 of EM 385-1-1. Submit subsequent AHAs as amendments to the APP. Identify the analysis and evaluate hazards and outline the proposed methods and techniques for the safe completion of each phase of work. At a minimum, in the AHA define the activity being performed, sequence of work, specific safety and health hazards anticipated, control measures (to include personal protective equipment) to eliminate or reduce each hazard to acceptable levels, equipment to be used, inspection requirements, training requirements for all involved, and the competent person in charge of that phase of work.

Submit to the COR and the Government Safety Officer, operations using chemicals containing 2,4-D, Sulfometuron, or any other chemicals which have TLVs, PEL standards, or other regulated standards based on known health hazards, a Health Hazard

Control Program. Address the requirements in EM 385-1-1 Section 06.A and be completed by a qualified Industrial Hygienist, or equivalent competent person in

Industrial Hygiene operations in the Health Hazard Control Program. A sampling technician working under the CIH may perform any sampling required to do the work

References. Comply with the most current version of the following referenced documents, at a minimum:

EM 385-1-1, USACE Safety & Health Requirements Manual, 30 November 14

Edition.

http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManua ls/EM_385-1-1.pdfTitle 29 Code of Federal Regulations (CFR) 1910, Occupational Safety and Health Standards.

NIOSH/OSHA/USCG/EPA, Occupational Safety and Health Guidance Manual for Hazardous Waste Activities (October 1985).

American Conference of Governmental Industrial Hygienists (ACGIH®), TLVs® and BELs®, Threshold Limit Values for Chemical Substances and

Physical Agents & Biological Exposure Indices (2016).

Title 8 California Code of Regulations (CCR) Chapter 4 Subchapter 4, Construction Safety Orders.

8 CCR Chapter 4 Subchapter 7, General Industry Safety Orders.

8 CCR Sections 3203 & 1509, Injury and Illness Prevention Program.

OSHA ancillary safety and health regulations governing certain aspects for this contract include:

Respiratory Protection (29 CFR 1910.134/8 CCR Section 5144)

Occupational Noise Exposure (29 CFR 1910.95/8 CCR Sections 5095-5100)

Hazard Communication (29 CFR 1910.1200/29 CFR 1926.59/8 CCR Section

5194)

The Control of Hazardous Energy (Lockout/Tagout) (29 CFR 1910.147)

Proposition 65 (22 CCR Section 12000) Chemicals Know to the State to Cause

Cancer or Reproductive Toxicity

6.2.2.4 Injury and Illness Prevention Program (IIPP) Submit a corporate Injury and Illness

Prevention Program (IIPP) for projects within the State of California. Address all elements of

Title 8 California Code of Regulations (CCR) Section 3203 and Section 1509. Develop the IIPP under the direct supervision of a qualified SHM.

6.2.2.5 Environmental Protection Plan (EPP): to include:

A Temporary Work Facility Plan: showing locations of temporary excavation for roads, ingress/egress, material storage, structures, sanitary facilities, fence locations, signs, etc.

Show proposed activity in each portion of the site and measures for marking the limits of use areas and areas to be preserved. Indicate measures to minimize the amount of mud transported onto paved public roads.

A Spill Control Plan: including procedures, instructions, and reports to be used in the event of an unforeseen spill.

Traffic Control Plan: including advanced notification, warning signs, and physical monitoring and flagging controlling automobile, bike and pedestrian access to work areas. Satisfy all relevant requirements for Traffic Control Plans required by EM 385-1-

1. Append to the Accident Prevention Plan (APP) as required under EM 385-1-1 (2014).

6.2.2.6 Quality Control Plan (QCP): List the projects key design team members along with their functional discipline and state the risks inherent to the project. Include an inspection plan covering all services required by this contact; on-site records of all inspections; and methods for identifying and preventing deficiencies in the quality of service performed. Develop and maintain a complete QCP to assure the requirements of this Contract are provided as specified. The

Contracting Officer will review the QCP and list any needed clarifications, and return to

Contractor for response, if necessary. Include the following in the QCP during performance of

Contract, at a minimum:

An inspection plan covering all services required by this contact. Specify in the inspection plan the areas to be inspected on either a scheduled or unscheduled basis, how often inspections will be accomplished and documented, and specify the title of the individual(s) who will perform the inspections.

Provide on-site records of all inspections conducted noting necessary corrective action taken. The Government reserves the right to request copies of any and/or each inspection.

Incorporation of either active or established internal policy and procedures for updating equipment and procedures that may affect performance of Contract.

On-site records identifying the character, physical capabilities, certifications and ongoing training of each employee performing services under this Contract.

On-site records of any complaints or problems, with procedures taken to allow for corrections and/or elimination before effects caused interruption of performance of

Contract.

6.2.2.7 Weed Control Plan: Provide a weed control plan indicating target schedule for required weed control activities for entire task order. Indicate types of equipment to be used for each mowing and for each herbicide application. Include types of nozzles and application pressures and flow rates. Include types and rates of herbicides and any additives such as dyes, surfactants, penetrating agents, anti-drift agents or other additives. Include personnel to be used and their certifications. Submit the weed control plan with the performance work plan for approval by the

Contracting Officer. The weed control plan does not substitute or replace any environmental submittals or safety submittals related to herbicide use that are required. The weed control plan must be updated regularly, refer to section 6.2.24., Preparing Activity Records.

6.2.2.8 Irrigation Design Plan (ID): Provide an irrigation design showing all critical components to provide water from the source to each plant. Indicate routing of all buried pressure lines, valve sizes and locations; all non-pressure lines, and all equipment and material used in the execution of water sources and delivery. Provide water to each plant at the rate and frequency specified and for the duration of the Contract and provide as part of the as-built drawings.

6.2.2.9 Storm Water Pollution Prevention Plan (SWPPP): Provide a SWPPP for compliance with the State Water Resources Control Board (SWRCB) Order Number 2010-0014-DWQ

Construction General Stormwater Discharge Permit. See Attachment D, Temporary Storm Water

Pollution Control for more complete SWPPP and permit coverage requirements.

6.2.3. Monitoring for Cultural Resources: Notify the Contracting Officer two weeks prior to flagging site so he/she can notify the Governments Archeologist of upcoming activities. Direct the setup of the fencing locations around known cultural resources. Contact the Corps’ Archeologist to determine whether or not a cultural site exists at that location, if two or more artifacts are found within close proximity to each other. Prepare a daily monitoring log that includes a summary of each day’s activities to include description and photographs of new finds, if any, and coordination efforts. At end of field work submit to the Corps a field summary report of monitoring activities and daily logs. Archeological, historic, and architectural work will be carried out by, or under the direction supervision of a person or persons meeting qualifications set forth in the Secretary of the Interior’s Professional Qualification Standards (36 CFR Part

61). Submit 10 copies of the field summary report and monitoring logs. Refer to Attachment G, Submittal

Register.

6.2.4. Setting-up Site: Identify, mark and establish site boundary lines and infrastructure locations, test soils locations, provide work signs, construct safety fencing, staging areas, wetlands, and cultural sites.

Verify site conditions prior to ground disturbance. Also identify and flag all cultural resource features prior to any vehicular traffic on the site. Thoroughly clean all adjacent public pavements of impacts upon completion of work. Refer to Attachment G, Submittal Register.

6.2.4.1 Verify Site Conditions: Before performing any work, verify site conditions. Provide photographs of all existing access roads for Contracting Officer review prior to commencing work.

These will serve to verify pre-work conditions. Identify existing features and underground obstructions and utilities, including notifying Underground Service Alert (U.S.A.) at 1-800-642-

2444 for all locations in this Contract. Read materials found on OSHA website http://www.dir.cago.

6.2.4.2 Boundary and Infrastructure Layout: Identify and stake property boundary lines. Mark on the ground, showing the extents of where all infrastructures will be located. Include access and http://www.dir.cago/ maintenance roads, water well, and pump locations, electrical hookups and routing, signage, fence and gate locations, staging area location, sensitive resources/habitat (e.g. elderberry habitat) temporary construction limits and locations to all other tasks included in project. Prior to starting work at all sites, obtain approval from the Government. Keep all vehicle traffic to staging area and maintenance roads. Do not drive off of designated project site.

6.2.4.3 Layout Maintenance Roads: Layout access point and maintenance road where shown on drawings. Create all roads 15 feet wide.

6.2.4.4 Soil Testing: Take soil samples from each planting site. Take one sample for each project acre. Round to the closest whole number. Spread sample locations out evenly over the entire site.

Perform an agricultural soil analysis for each sample from a reputable soil testing laboratory.

Include, at minimum, an analysis of soil texture (showing percentage of sand, silt and clay), particle size, organic content, and macro and micro nutrient analysis for chemical properties, pH, nutrient level, and salinity. Include soil analysis results in the 1st yearly report along with a site map identifying each referenced sample location.

6.2.4.5 Staging Area Setup: Include an onsite staging area that contains all appropriate temporary facilities needed to construct and maintain the project, include as necessary, securable storage bins, temporary fencing (encompassing the entire staging area, shade structures, drinking water and sanitation stations. The Contractor is responsible for the security of all stored material and facilities.

6.2.4.6 Protect Existing Native Vegetation: Do not disturb existing native vegetation, unless required herein. Adjust new plant layout around existing woody natives, where they exist. Place safety fences between work areas and existing elderberry shrubs (Sambucus mexicana).

6.2.4.7 Provide Work Signs: Provide work signs at the main entrance at the Novak project site.

Include project identification signs identifying the project name and that it is a Woodland Habitat

Mitigation Project. Include the cooperating agency names, Contractor name, Contractor contact information, State wage rates, EEO and project health information, and safety requirements.

Present signs on 4 feet by 8 feet face, made of exterior plywood or better material, supported by two 4 inch by 4 inch diameter posts.

6.2.4.8 Include the names of the following agencies:

U.S. Army Corps of Engineers

State of California – The Resources Agency

Central Valley Flood Protection Board

U.S. Department of the Interior, Fish and Wildlife Service, Sacramento Fish and Wildlife Office

Sacramento Area Flood Control Agency

See Exhibits for site location drawings.

6.2.5. Providing SWPPP and BMPs: Work under this Contract is anticipated to disturb greater than one acre of land. Obtain coverage under the California State Water Resources Control Board Construction

Activities Storm Water General Permit Order No. 2009-0009-DWQ as amended by 2010-0014-DWQ and

2012-0006-DWQ (CGP). The Contractor is the Legally Responsible Person (LRP) for storm water permits.

6.2.5.1 Preliminary risk calculations indicate the following:

Natomas Novak Site – Risk Level 1

Risk Level 1 sites follow Attachment D, 01 57 23.01 Temporary Storm Water Pollution

Control, Risk Level 1

The site’s risk is influenced by the Contractor’s anticipated dates of disturbance and site stabilization window. The stabilization timeframes may be influenced by seeding schedule requirements in Attachment E, Section 32 92 33 Grass Seeding and Erosion

Control. Re-calculate risk level’s based on the Contractor’s anticipated start dates of work and anticipated date of stabilization.

6.2.5.2 Do not commence work until a WDID number is received from the State Water Board.

6.2.5.3 Collect pre-project photographs of the site.

6.2.5.4 Include, the following minimum BMPs during installation and establishment (regardless of risk level or permit status) and that it is required to be returned to a condition demonstrating no future erosion potential. Minimum BMPs include but are not limited to perimeter protection, stabilized project entrance/exit, stockpile management, project site sediment perimeter controls, waste management, good housekeeping, stockpile management, preservation of existing vegetation, stabilized project entrance/exits, tracking control and wind erosion (dust) control.

6.2.5.5 Prevent dust from leaving the project site by providing dust control during dust generating project activities (including but not limited to work traffic on unpaved roadways and grading).

6.2.5.6 .Follow their manufacturer’s instructions and conform to BMP fact sheets outlined in the

California Storm Water Quality Association (CASQA) BMP Handbook.

6.2.5.7 As construction finishes follow the Notice of Termination (NOT) guidelines outlined in the attachments and terminate coverage. The site must not pose any additional sediment discharge risk than it did prior to the commencement of construction.

6.2.5.8 Temporary Storm Water Permit Related Submittals: Below are the required submittals in relation to temporary storm water pollution control. Separate sets of submittals are required for each site. Digital submittals are preferred over paper copies.

Storm Water Pollution Prevention Plan (SWPPP) - Government Approval Required

Permit Registration Documents (PRDs) - Government Approval Required

BMP Product Data

SWPPP Amendments

Sampling Results

Numeric Action Level (NAL) Exceedance Reports

Rain Event Action Plans (REAPS)

Inspection Reports (Weekly, prior to forecast rain, daily during rain events, and once following rain)

Annual Report

Post Construction Storm Water Management Plan

Final SWPPP

NOT Application – Government Approval Required

See Attachment D1 Temporary Storm Water Protection Control Risk Level 1. See

Attachment F – Submittal Register.

6.2.6 Inspecting/Sampling & Reporting SWPPP Compliance: Comply with all SWPPP requirements;

including performing inspections, taking samples and reporting results until a Notice of Termination has been issued. Successfully prepare and submit Notice of Termination.

6.2.7. Removing Trees: Cut down 41 44 designated trees and leave stumps within 3 feet of the ground surface. Cut up and remove all wood, branches and twigs from site and dispose at an approved offsite disposal facility. Clean up site of all debris and leaves and leave in a neat appearance. Transplant 3 designated trees to the Novak site. Minimum size of tree spade for transplanting must be 100 inches. At the transplant site, construct water basins to 4 feet larger in diameter (2’ larger radius) than the diameter of the rootball and capable of holding 50 gallons of water at one time. Water in the transplants within 6 hours of transplanting. Restore and repair impacts made to the soil, pavement, and fences damaged or impacted during work operations. Coordinate all tree removal with Contracting Officer prior to cutting or transplanting trees. Provide any BMPs necessary to ensure compliance to the SWPPP. Maintain access through the bike trail at all times. Provide traffic control on the bike trail if necessary to maintain safety of the bike trail. Maintain traffic access on Garden Highway. Lane closures are discouraged and closure of lanes shall be subject to approval of the Contracting Officer and any and all authorities with jurisdiction over traffic on the subject road. Obtain all necessary permits for lane closures. Provide all necessary flagging, marking, traffic cones, signage and traffic control in compliance with all applicable state and local rules and regulations. Tree removal and any associated impacts to traffic must be addressed in the Accident Prevention Plan. Access to the tree removal areas must be through the gravel driveway approximately 700 ft southwest of the I5 overpass over the Garden Highway and at the southwest corner of the intersection of the Garden Highway and

Natomas Park Drive.

See Exhibits B1-3 for Tree Removal Site Locations and Exhibit D Novak Row Layout and Planting Plan

6.2.8. Creating Maintenance Road: Provide a maintenance road where shown on exhibits. Removed rocks or other debris and obstructions that will impede a two-wheel drive vehicle; but do not blade or grade the surface. Spray the entire road surface with a contact herbicide to kill all vegetative growth through the life of the contract. Ensure overspray does not occur. Repair erosion that occurs and maintain the road so it is operable and so that is does not become a fire hazard. Regularly water roads to control dust as needed to meet air pollution standards. Street sweep the County road when soil is tracked onto it. See Exhibit C, Novak Site Layout Plan.

6.2.9. Laying Out Planting Rows: Layout planting rows continuously across site as per Exhibit D, Row

Layout Plan and Exhibit F – Plant Layout Curvilinear Row Detail. The polygons identify different planting lists of species and quantities to be installed within each. The curvilinear rows will trail in and out through the different Polygon ID areas. See Attachment C – Plant Schedule.

6.2.10. Seeding Grass: Do not disk or disturb the soil in preparation for grass seeding. Apply grass seed to the entire mitigation site, except for the designated maintenance roads and as noted. Perform grass seeding using the no-till drill seeding method. To meet SWPPP compliance, reseed as necessary to meet

70% SWPPP vegetative coverage compliance by the end of the first year after seeding. Native grass establishment must comply with the performance standards indicated in Attachment E Section 32 92 33

Grass Seeding and Erosion Control requirements. For grass seed mixtures, see Attachment C Plant

Schedule and Exhibit E for seeding locations.

6.2.11. Providing Informational Field Signs: Provide (9) nine informational field signs at the project site.

Field locate sign locations as directed by the Contracting Officer.

Identify on the revegetation signs the following agencies:

U.S. Army Corps of Engineers

U.S. Fish and Wildlife Service

California State Department of Water Resources

Sacramento Area Flood Control Agency

See Exhibit F, Details for sign detail.

6.2.12. Providing Water: Design, provide, deliver, store, operate and maintain all water components, including water source, electrical power, equipment, and materials. Provide and deliver water to all plants using a drip/bubbler type system. Overhead spray and flood irrigation is not permitted. Provide water to meet the amount, frequency and duration as stated in the PWS. Provide, trench and bury a pipeline form the well pump to the project site. Bring electrical power to the water source from the nearest power pole.

Coordinate and pay all utility service costs for well operation for the life of the contract. There is an existing well that may be used as the water source, however, it is unknown of its capabilities. If it is used, determine and upgrade its capabilities to meet the requirements of this project scope indicated herein. If a new well is drilled, the new well location must be within the project boundary. Exact location must be coordinated with and approved by the Contracting Officer.

See Attachment F, Well Installation and Development for specific requirements.

6.2.13. Install Irrigation System

Providing Buried Pressure Irrigation Lines: Bury the main pressure line a maximum of 24” deep. Route, but minimize as appropriate throughout planting area. Provide risers at the surface level where each circuit valve will be located. Mark each riser with a 4 inch x 4 inch diameter top-tapered wood post, roughly 36 inches in height above grade that identifies where the riser and valve boxes are located. Backfill all trenches. Provide circuit valves to control water flow to each water circuit. All other pipe may be above grade as appropriate.

Providing Non-Pressure Irrigation Lines: At each circuit provide PE (polyethylene) drip pipes as non-pressure lateral lines. Align layout to extend each pipe within the proximity of each plant, where an emitter can feed the plant. Coordinate irrigation layout with plant layout and grass maintenance activities, such as mowing. Irrigation PE pipes may be placed above ground or “cut-in” below the soil surface to ensure less damage from rodents or mowing operations.

Providing Tubing & Emitters: At each plant location that is shared by two plants, provide 3 pressure compensating emitters connected to the pipe at each location. If needed, connect one-quarter inch distribution tubing to the PE drip pipes and provide an emitter at the end of the tubing at each plant. Provide the appropriately sized orifice that is capable of supplying the required amount of water at each watering event.

6.2.14. Seedling Delivery: Coordinate all delivery of plant material to the project site with the contractor growing the government supplied plants. Coordinate timing of delivery with the work being done at each of the sites. Provide manifest of nursery seedling delivery, refer to Attachment G, Submittal Register and

Section 7.0., Submittals.

See Attachment C for Planting Schedules.

6.2.15. Laying Out Plant Locations: Prior to planting, layout and flag plant locations on the ground along the curvilinear rows. Space plant locations along each row at 12’ O.C. Place one overstory or midstory plant and one understory plant at each plant location. Place the two plants within each plant location within two feet of each other, both to be watered from one shared emitter. Coordinate and adjust plant locations as per the Contracting Officer and obtain his/her approval prior to installing any plants.

See Exhibit D, Novak Row Layout and Planting Plan. See also Attachment C, Plant Schedule.

6.2.16. Drilling Plant Pits: Drill a plant pit capable of supporting each size of containerized plant where the flag locations have been placed. Dig each planting pit to the depth of the plant’s root ball and twice as wide.

6.2.17. Installing Plants: Provide and install all container plants, at the locations flagged, for the species and at the amounts as indicated within this Contract. Keep woody plants 15 feet from site perimeter and any designated interior maintenance roads. For all woody plants, provide browse guard (1/2 gallon milk carton), gopher cage, stake, geotextile fabric mulch, slow-release commercial grade free-flowing fertilizer appropriate for the plant and soil characteristics. Provide fertilizer product data to Contracting Officer for review prior to work. Place a stake inside the browse guard to keep the guard upright and so that birds can use it to climb out. Water basin are not required, however manipulate soil around plant so that all the water from the emitter is contained and soaks into the soil before it flows away from the root zone of the plant.

Water-in all plants within 12 hours of installation. Refer to Attachment G, Submittal Register for plant installation submittal requirements.

See Attachment C, Plant Schedule for plant container sizes and quantities; and Exhibits D Row Layout Plan for plant locations; and Exhibit F, Details for Plant with Browse Guard Detail.

6.2.18. Watering: Water all container plants, including transplants, within 6 hours following planting, including all woody and herbaceous plants installed from containers for the duration of the Contract. Water as necessary during the IP so that there is continuous soil moisture around each plant. Water more often during very dry, windy conditions to keep plants in good condition. Maintain and repair the irrigation system, as necessary, so that it delivers water to each plant at the frequency and rate specified. For each EP of the Contract provide the following:

EP1 Watering: For container plant basins apply 10 gallons per plant twice a week for a total of 35 weekly events (70 events total) between 1 March and 31 October. For tree transplants, apply 50 gallons per plant weekly for a total of 35 weekly events between 1 March and 31 October.

EP2 Watering: For container plant basins apply 30 gallons per plant weekly for a total of 35 weekly events between 1 March and 31 October. For tree transplants, apply 50 gallons per plant weekly for a total of 35 weekly events between 1 March and 31 October.

EP3 Watering: For container plant basins apply 40 gallons per plant weekly for a total of 35 weekly events between 1 March and 31 October. For tree transplants, apply 50 gallons per plant weekly for a total of 35 weekly events between 1 March and 31 October.

EP4 Watering: For container plant basins apply 40 gallons per plant every other week for a total of

14 events between 1 March and 31 August. For tree transplants, apply 50 gallons per plant weekly for a total of 35 weekly events between 1 March and 31 October.

6.2.19. Weeding: Weed within 18 inch radius of each plant so that weeds do not compete for soil moisture with the plant. Weeding is to occur and generally timed following the latest rains that generate growth.

For each Establishment Period year (EP) provide the following:

EP1 Weeding: 2 times, around April and July.

EP2 Weeding: 2 times, around April and July.

EP3 Weeding: 2 times, around April and July.

6.2.20. Mowing: Mow all herbaceous growth so that the site is kept in a fire safe condition. Keep a fire suppressor water system, such as a trailered water tank with a motor-generated water hose, onsite and near the work area wherever mowing and other hazardous activities are being performed. Provide the following:

IP Mowing: 3 times, timed and spaced to capture growth throughout the season. Mow entire project site.

EP1 Mowing: 3 times, timed and spaced to capture growth throughout the season. Mow entire project site.

EP2 Mowing: 3 times, timed and spaced to capture growth throughout the season. Mow entire project site.

EP3 Mowing: 3 times, timed and spaced to capture growth throughout the season. Mow entire project site.

EP4 Mowing: 2 times, timed and spaced to capture growth throughout the season. Mow entire project site.

6.2.21. Herbicide Application: The herbicide application program is designed to manage and foster native grass throughout the project site. All application of herbicide must follow the approved Weed Control

Plan. Prevent herbicide overspray and wind drift into non-target and planted areas. Do not spray when wind will carry spray to non-target areas. Do not spray when warm weather can volatilize herbicide and cause damage to non-target areas. Utilize low pressure drift resistant spray nozzles, anti-drift agents, spray shields and any other means necessary to ensure non-target areas are not damaged by overspray and wind drift. To accomplish this, the efforts required herein are to reduce and eliminate the non-native exotic grass and broadleaf herbaceous vegetation and accompanying seed banks while enhancing native grass establishment. Select the appropriate herbicide designed to kill all non-native grasses and undesirable exotic growth, including all vegetative growth that occurs onsite, on the maintenance road, and within the staging area and site edges. Prevent annual grasses from setting viable seed, keep broadleaf weeds under

6” in height. When the staging area is removed and no longer in use, seed its entire area and establish native grass prior to leaving. All spraying must be performed by a certified applicator for the type of herbicide used. Place proper notifications at adjacent public roads/trails two days prior to spraying operations. Provide herbicide product and equipment data to COR for review prior to work. Refer to

Attachment G, Submittal Register and Section 6.2.2.7 of the PWS. Spray applications are defined as follows:

6.2.21.1 “Grass Treatment Herbicide Spraying” is defined as the initial IP site spraying during the installation period that is designed to kill and reduce the existing non-native exotic grass competition in areas where they predominate, and to preserve and foster growth in the existing native grasses areas where they predominate. Leave all vegetation that has been killed on the ground to serve as a BMP to protect the soil as an erosion control BMP. The designated treatment areas are identified in Exhibit E, Novak Grass Treatment Plan.

6.2.21.2 Existing Grass Areas: These areas have abundant amounts of desirable existing native grass that are to remain. The goal is to retain the existing native grass and manage those areas to control exotic grasses and broadleaf weeds. Treat by applying a selective broadleaf herbicides and pre-emergent herbicides. Take care to preserve as much existing native grass as possible. Pre-emergent herbicide use will be discontinued a minimum of 6 months prior to grass seeding.

6.2.21.3 Incorporate the grass treatment areas into the overall herbicide spraying program for row, middles, spot spraying, and pre-emergent spraying after the container plants have been installed and the new grasses have been seeded.

“Rows” are defined herein as the container plant alignments where all herbaceous vegetation 2-3’ out from both sides of the center line are sprayed and killed. This effectively leaves a 4-6’ wide strip “row’ that is void of herbaceous vegetation. Spray all rows with a non-selective herbicide to completely kill all herbaceous vegetation.

Continue this spraying after the grass has been seeded in the Middles and the Grasslands.

Weed growth in the rows shall be kept under 6” in height.

“Middles” are defined herein as the entire area between the rows and includes all areas that are not roads, or rows. Use broadleaf selective and pre-emergent herbicides to control broadleaf herbaceous vegetation and exotic annual grass vegetation in this area, so that the desirable native grasses prevail.

“Spot Spraying” is defined herein as spraying and killing targeted undesirable broadleaf vegetation or non-native exotic grasses. Prior to spot spraying, coordinate the goals with the Contracting Officer. Spray all targeted undesirable vegetation with a non-selective herbicide designed to completely kill the targeted existing vegetation or a selective herbicide to target specific weed and non-native grass species.

“Pre-seed Herbicide Treatment/Spraying” is applied to the Middle areas with an herbicide designed to completely kill undesirable herbaceous vegetation.

“Pre-emergent Spraying” is applied to the entire grass area. Spray with a pre-emergent herbicide designed to kill undesirable weeds. The EP2 spraying must be based on the evaluation and impacts it would have on the creeping wildrye seed. Both establishment year sprayings are to occur after the first fall rains, which is expected to be Nov-Dec.

6.2.21.4 The application quantities for spraying are as follows:

IP Grass Treatment Spraying: : 2 times; time spraying to capture weed growth over entire site

EP1 Spraying: timed and spaced to capture growth.

o Rows: 4 times o Middles: 2 times o Pre-seeding spraying: 1 time

EP2 Spraying: timed and spaced to capture growth.

o Rows: 3 times o Middles: 3 times o Spot Spraying: 1 time o Pre-emergent spraying: 1 time

EP3 Spraying: timed and spaced to capture growth.

o Rows: 2 times o Middles: 3 times o Spot Spraying: 1 time o Pre-emergent spraying: 1 time

EP4 Spraying: timed and spaced to capture growth.

o Rows: 1 time o Middles: 2 times o Pre-emergent spraying: 1 time

6.2.22. Surveying Plants: In the fall of each of the Contract years following plant installation, perform plant surveys to access plant survival and mortality. Surveys must include woody plant survival and vigor assessment, native grass cover percentage, and overall grass cover percentage. Provide a separate survey for each of the areas in N1, S1, S2, and tree transplants identified on the drawings. Include survival rates for each species planted, based on original number planted. Present the results in each of the subsequent annual reports. See Attachment G, Submittal Register and section 6.2.25 for details.

6.2.23. Replacing Dead Plants: At the end of the first and second year establishment periods replace all dead plants using new browse guards, fertilizer, and mulch of like material, size and type as was originally installed. Coordinate species with the Contracting Officer prior to ordering plant material. Since some species are not always readily available at a local nursery, anticipate in advance those species that may need to be replaced and pre-grow the plants so they are at the required container size and ready when needed. Due to unavailability or poor species performance, adjustments to replacement species may be desirable and accepted, provided coordination has been performed with the Contracting Officer in advance and a written approval of species substitutions has been issued.

6.2.24. Preparing Activity Records: Prepare activity records, which include monthly records of work performed during each month of the contract, as-built drawings of all installation work, and a weed control plan for each year of the contract.

Prepare monthly activity records, one for each month of the Contract. Submit the monthly activity record with each invoice, addressing specific tasks billed. Include activities of all installation and maintenance work that is performed throughout each preceding month of the contract. Submit record along with each monthly invoice, within 7 working days following the end of each month.

Each monthly record must not be longer than one page on 8-1/2”x11” format. The monthly record must address a statement of general plant health and site conditions; and specific activities performed of the following: irrigation operations, weed control & types of chemicals sprayed, mowing performed, weeding performed, infrastructure maintenance. During the IP, state all tasks performed and progress made. Include all the monthly records in the annual reports for each year of the contract. Prepare as-built drawings of all tasks performed.

Prepare as-built drawings of project site features. Keep as-builts current and available to the government upon request, and submit with each annual report. Provide hard copies and electronic files of the original site drawings upon request. Accurately and neatly record all information that is uncovered during the course of planting by means of drawings, sketches, details, and notes.

Mark-up and correct using red ink changes. Document the location of the plantings by marking-up a copy of the contract drawings. The exact location of each plant does not need to be indicated on the drawing. However, the exact number of each species planted and replanted must be recorded.

Prepare quarterly update of the Weed Control Plan. Update the weed control plan on a quarterly basis. Determine the starting date of the weed control season, updates must be submitted quarterly starting with the start date of the weed control season. Quarters must be evenly spaced throughout the weed control season. The Update must account for seasonal weather, long term weather forecasts and weed growth rates. Each update must adjust the timing of required weed control activities for the quarter the update is submitted and subsequent quarters. Timing must be adjusted for optimal results from the required weed control activities. In each update, include a discussion of current and anticipated weather conditions and impact of weather on timing of weed control activities for the quarter the update is submitted.

6.2.25. Preparing Annual Reports: Prepare annual reports, one for each year of the Contract. Submit as drafts and receive the Government’s direction and approval prior to printing and submitting the final reports. Document activities and installation, maintenance, plant and site conditions throughout the previous year.