ARCF WRDA 96 Sites - Phase 2 Remaining Sites Sites R3A and L10 1827
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 73 05
SUPPLEMENTARY CONDITION REQUIREMENTS FOR SITES R3A & L10
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 SUPPLEMENTARY CONDITIONS REQUIREMENTS
1.3.1 SCR-1 Location of Work
1.3.2 SCR-2 Scope of Work
1.3.3 SCR-3 Allowable Time, Schedule Constraints and Time of
Completion
1.3.4 SCR-4 Site Conditions
1.3.5 SCR-5 Lands and Right-of-Way
1.3.6 SCR-6 Access by Government, and Other Jurisdictional Public
Agencies
1.3.7 SCR-7 Contractor's Tools and Equipment
1.3.8 SCR-8 Locking Gates
1.3.9 SCR-9 Water Source for Construction Operations
1.3.10 SCR-10 Cleaning Up
1.3.11 SCR-11 Protection of Existing Improvements
1.3.12 SCR-12 Record Drawings
1.3.13 SCR-13 Flood Emergency
1.3.14 SCR-14 Permits and Approvals
1.3.15 SCR-15 Dust Control
1.3.16 SCR-16 Fire Control
1.3.17 SCR-17 Air Pollution Control
1.3.18 SCR-18 Noise Control
1.3.19 SCR-19 Allowable Work Hours
1.3.20 SCR-20 Archaeological, Paleontological, and Cultural Resources
1.3.21 SCR-21 Protection of Existing Trees
1.3.22 SCR-22 Biological Resources
1.3.23 SCR-23 Raptor and Migratory Birds
1.3.24 SCR-25 Wetlands and Sensitive Habitats
1.3.25 SCR-27 U.S. Fish and Wildlife Service
1.3.26 SCR-28 Central Valley Flood Protection Board
1.3.27 SCR-29 Speed Limit
1.3.28 SCR-30 American River Flood Control District (ARFCD)
Coordination
1.3.29 SCR-31 Provision Regarding Maintaining Minimum Flood
Protection During Construction
1.3.30 SCR-32 Coordination with the Contracting Officer and
Utilities Relocation
1.3.31 SCR-33 Haul Routes
1.3.32 SCR-34 Resource Coordination
1.3.33 SCR-35 Flood Contingency Plan
1.3.34 SCR-36 Utility Provider Response Plan
1.3.35 SCR-37 Stop Work Authority
1.3.36 SCR-38 Floodway Construction Schedule
00 73 05 - 1
1.3.37 SCR-39 High Visibility Fencing, Habitat Preservation and Buffers
1.3.38 SCR-40 General Safety Requirements
1.3.39 SCR-41 Storm Water Pollution Prevention Plan
1.3.40 SCR-42 Grading Permit
1.3.41 SCR-43 Cobbles
1.3.42 SCR-44 Local Jurisdictions Permitting Requirements
1.3.43 SCR-45 Staging Area
1.3.44 SCR-46 Recreation/Community Mitigation - Site L10
1.3.45 SCR-47 City Streets - Site L10
1.3.46 SCR-48 Storage Area - Site L10
1.3.47 SCR-49 City Pump Station Sump 91 - Site L10
1.3.48 SCR-50 Project Signage
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
00 73 05 - 2
SECTION 00 73 05
SUPPLEMENTARY CONDITION REQUIREMENTS FOR SITES R3A & L10
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2008; Errata 1-2010; Changes 1-3 2010;
Changes 4-6 2011; Change 7 2012) Safety and Health Requirements Manual
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation.
The following shall be in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals; G
Permits and Approvals; G
Construction emission/dust control plan; G
Permit, waiver or other documentation with the mapped haul routes from local jurisdictions to repair or compensate for damage; G
Slurry Spill Prevention Plan; G
Flood Contingency Plan; G
Utility Provider Response Plan; G
Storm Water Pollution Prevention Plan; G
Grading Permit; G
1.3 SUPPLEMENTARY CONDITIONS REQUIREMENTS
1.3.1 SCR-1 Location of Work
The Project is located in Sacramento County, California, along portions of the American River levee that protects the City of Sacramento.
1.3.2 SCR-2 Scope of Work
For Site L10, levee improvements will be made on the American River levee on the south side of the American River at Howe Avenue. A soil-cement cutoff wall will be installed under the Howe Avenue bridge, the existing bike trail on the waterside of the levee. The new cutoff wall will be
00 73 05 - 3 installed using jet grouting and will pass under the bridge, then ascend the levee on both sides of the bridge to a terminal point with the existing cutoff.
In addition to that new cutoff wall, a low permeability soil blanket will be installed on the waterside slope and connecting with the new cutoff wall. Finally, the existing riprap slope protection will be removed and replaced after construction on the waterside slope under the bridges to prevent erosion.
An approximately 175-foot section of the existing levee upstream of Howe Avenue will be raised in place to provide required flood protection. The levee raise and resulting side slopes will remain within the existing footprint of the levee.
Access to the construction sites will be by an existing paved ramp located upstream of Howe Avenue which provides access to a boat ramp and parking area on the river. On the downstream side of Howe Avenue, a new temporary ramp will be built on the landside of the levee starting under the Howe Avenue bridge. Access to these ramps will be from La Riviera Drive using existing curb cuts. Staging areas will be located under the bridges and on the grassed tract east of the Stormwater pump station.
For Site R3A, levee improvements will be made in two locations on the American River North levee on both sides of Business 80 (Capital City Freeway). The improvements will consist of extending the existing cutoff wall by approximately 75-feet on the upstream side of the Capital City Freeway and 67-feet downstream of the expressway. Extension of the existing cutoff wall will be accomplished using jet grouting. All work will be done behind the existing guardrails and there will be no need to enter the existing roadway at these locations.
Access to the construction sites will be by an existing paved ramp located just east of the proposed staging area, and a paved ramp located just west of the Capital City Freeway. The proposed construction work will not impact traffic movement on the Capital City Freeway. Access to the staging area and both construction sites will be from Exposition Boulevard on Tribute Road.
1.3.3 SCR-3 Allowable Time, Schedule Constraints and Time of Completion
The following constraints will apply and must be incorporated into the Contractor's schedule. Site L10 is available from 1 June 2014 through 31 December 2014, but Site R3A is only available from 1 August 2014 through 31 December 2014. Levee construction work shall be completed at both sites by November 2014/.
TIME OF COMPLETION FOR SITE L10
Contracting Officer and Resident Engineer's Office Facility
Installed and ready for occupancy not later than five (5) calendar days prior to start of excavation or not later than fifteen (15) calendar days after Notice to Proceed, whichever occurs first
Complete Pre-Production Cutoff Wall 30 work days (5 calendar weeks)
00 73 05 - 4
Complete waterside blanket 20 work days (4 calendar weeks)
Complete cutoff wall 60 work days (10 calendar weeks)
Complete installation of riprap 6 work days (1 calendar week)
Complete levee crown increase 5 work days (1 calendar week) Complete paving of bike paths 6 work days (1 calendar week) Complete permanent erosion control and site cleanup for all disturbed areas
12 work days (2 calendar weeks)
Copies of Permits Contractor to forward to Contracting Officer within 10 days of receipt
Slurry Spill Prevention Plan Submit to Contracting Officer 30 days prior to commencement of construction activities
TIME OF COMPLETION FOR SITE R3A
Contracting Officer and Resident Engineer's Office Facility
Installed and ready for occupancy not later than five (5) calendar days prior to start of excavation or not later than fifteen (15) calendar days after Notice to Proceed, whichever occurs first
Complete Pre-Production Cutoff Wall 30 work days (5 calendar weeks)
Complete cutoff wall 60 work days (10 calendar weeks)
Complete restoration of bikeway 6 work days (1 calendar week)
Complete permanent erosion control and site cleanup for all disturbed areas
10 work days (2 calendar weeks)
Slurry Spill Prevention Plan Submit to Contracting Officer 30 days prior to commencement of construction activities
1.3.4 SCR-4 Site Conditions
The Contractor shall satisfy himself or herself concerning the nature and location of the work; the general and local conditions, particularly those affecting transportation, disposal, handling and storage facilities;
availability of labor, water, power, communications, roads, climatic conditions and seasons; physical conditions at the job sites and Project areas as a whole; job-site topography and ground conditions; permits, 00 73 05 - 5 equipment, and facilities needed preliminary to, and during, work prosecution; and all other matters which can in any way affect the work, including cost thereof. Failure of the Contractor to become acquainted with all available information regarding any applicable conditions will not relieve the Contractor from the responsibility for properly estimating either the difficulties or the costs of successfully performing the work.
The EA/IS shall be made available upon request by contacting the Contracting Officer.
1.3.5 SCR-5 Lands and Right-of-Way
The right-of-way for the construction work, as shown on the Plans, will be provided by the U.S. Army Corps of Engineers (USACE).
1.3.6 SCR-6 Access by Government, and Other Jurisdictional Public Agencies
American River Flood Control District (ARFCD) is responsible for inspecting and maintaining the existing levee. The Contractor shall conduct the work so that ARFCD personnel and equipment are not prevented from access to the existing levee at all times for normal and emergency purposes. The Central Valley Flood Protection Board, Sacramento Area Flood Control Agency (SAFCA),the U.S. Fish and Wildlife Service, the Army Corps of Engineers, the National Marine Fisheries Service (NMFS), the State Department of Fish and Game, City of Sacramento, and the County of Sacramento have jurisdictional authority over the work as defined in the respective sections, associated permits and/or agreements. The Contractor shall allow these agencies and other jurisdictional public agencies, unrestricted access to the Project site.
1.3.7 SCR-7 Contractor's Tools and Equipment
The Contractor shall furnish all equipment, materials, tools, supplies, and manufactured articles required for the completion of the work in accordance with the Contract. The Contractor shall take the necessary precautions to secure tools and equipment from theft while on-site. The Government assumes no responsibility for lost, vandalized, or stolen equipment belonging to the Contractor, its subcontractors, or its employees.
1.3.8 SCR-8 Locking Gates
The Contractor shall take care to protect and operate any existing gates that control access to the Project right-of-way, in conformance with the Government, ARFCD, and City of Sacramento requirements. These requirements include preventing passage through the gates of unauthorized persons and equipment during periods of Contractor use of the gates and locking the gates during non-construction periods, if so directed by the Contracting Officer.
1.3.9 SCR-9 Water Source for Construction Operations
Contractor is responsible for identifying, securing, and obtaining all water needed for the project for both potable uses and for construction purposes. Water shall not be pumped from the American River.
Construction water should be reused onsite to the extent practical and disposed of in a manner consistent with the quality of the water after use. Excess water shall not be disposed of into any wetland, stream, river, or storm drainage without permitting.
00 73 05 - 6
Contractor shall be responsible for disposal of all construction water.
1.3.10 SCR-10 Cleaning Up
The Contractor shall dispose of all trash items in closed containers, which shall be removed at least once per day. Vegetative wastes shall be chipped or delivered to waste energy facilities, mulched, composted, or used for firewood.
1.3.11 SCR-11 Protection of Existing Improvements
Except as specified herein or as shown on the Plans, existing structures and utility lines shall not be disturbed, damaged, or undermined by the Contractor, except where in the opinion of the Contracting Officer it is essential to relocate such improvements. If relocation of any facility is required, the Contractor shall relocate the improvements to be at least equal in condition to the original. The Contractor shall take all necessary precautions to prevent any damage to existing facilities.
Should damage or injury occur as a result of the Contractor's operations, the Contractor shall repair or replace such damaged facilities to the Contracting Officer's satisfaction at the Contractor's expense.
The Contractor shall repair any damage to public and private streets resulting from the Contractor's operations, as directed by the Contracting Officer. Repair shall be made per industry standards and conform to local jurisdictional requirements. Repairs shall be made at no additional cost.
1.3.12 SCR-12 Record Drawings
The Contractor shall maintain a neat and accurate marked set of working record drawings in accordance with Specifications. The record drawings shall be subject to the inspection of the Contracting Officer at all times and shall be kept current weekly with all work instructions, change orders, and construction adjustments shown thereon and initiated by inspection. The Contracting Officer reserves the right to withhold progress payments, or portions thereof, if record drawings are not maintained as stated above.
1.3.13 SCR-13 Flood Emergency
In the event of a flood emergency requiring action by the jurisdictional flood control agencies prior to completion of the work, the Contracting Officer shall have the right to suspend the work in accordance with the General Specifications. Such suspension includes the right of the Contracting Officer to take over the Project to conduct flood protection activities.
1.3.14 SCR-14 Permits and Approvals
The Contracting Officer has obtained various permits, agreements, and rights for performance of the work. These permits may be described more fully in other SCRs and these specifications. The Contractor will be required to obtain additional permits or be a signatory on the Contracting Officer obtained permits as noted throughout the specifications. The Contractor shall be responsible for complying with all conditions of the permits and agreements. Any delays to the Project resulting from the Contractor's failure to follow permit requirements will not be the responsibility of the Contracting Officer and the Contractor will not be granted any extension of time for such delays.
00 73 05 - 7
The Contractor is responsible for obtaining all environmental permits or use permits required for easements to land being used for the Contractor's own convenience. Any delays to the Project resulting from the lack of these additional permits or the Contractor's failure to follow permit requirements will not be the responsibility of the Contracting Officer and the Contractor will not be granted any extension of time or additional compensation for such delays. Copies of all permits obtained by the Contractor shall be given to the Contracting Officer within 10 days of receipt of permit.
1.3.15 SCR-15 Dust Control
The Contractor shall comply with the provisions of Section 01 57 20 ENVIRONMENTAL PROTECTION of the General Specifications. The Contractor shall prepare and submit a construction emission/dust control plan to the Contracting Officer and Sacramento Regional Air Quality Management District (SMAQMD) and shall receive approval of the plan before groundbreaking. During the performance of the work, the Contractor shall assume all responsibility for dust control and shall furnish all labor, equipment, and means required, and shall carry out proper and efficient measures wherever and as often as necessary to prevent the construction operations from producing dust in amounts harmful to persons, damaging to property, or causing a nuisance to persons living nearby or occupying buildings in the vicinity of the work, or as directed by the Contracting Officer. Dust control will be strictly enforced with particular emphasis on work areas adjacent to residential and agricultural properties. The curtailment of the construction activities as a result of inadequate dust control measures will not be considered an unavoidable delay. The Contractor shall suspend all grading operations when fugitive dust levels exceed levels specified by SMAQMD regulations or deemed unacceptable by the Contracting Officer.
1.3.16 SCR-16 Fire Control
No burning shall be allowed for any activities associated with this project.
Delivering removed vegetative material to compost or waste-to-energy facilities is encouraged. Land filling of material shall be minimized.
Flammable construction/maintenance materials shall be stored away from Sump 91 and in a manner approved by the City of Sacramento Fire Marshall.
1.3.17 SCR-17 Air Pollution Control
The Contractor shall comply with the air pollution control protocols in the General Specifications. To the extent available, the Contractor shall use existing power sources for the Contractor provided trailers rather than temporary power generators. If existing power sources are unavailable, clean fuel, low-emission on-site stationary generator equipment shall be used. Low-sulfur fuel shall be used for stationary construction equipment. The Contractor shall be responsible for arranging appropriate consultation with the Air Resources Board and the SMAQMD, to determine registration and permitting requirements before operating portable engines or portable engine-driven equipment at the project site.
00 73 05 - 8
1.3.18 SCR-18 Noise Control
The Contractor shall comply with Section 01 57 20 ENVIRONMENTAL PROTECTION of the General Specifications to avoid and minimize noise impacts from the construction activities.
Before construction activity begins within 500 feet of one or more residences, the Contractor shall provide written notification to the potentially affected residents, identifying the type, duration, and frequency of activities. Notification materials shall also identify a mechanism for residents to register complaints with the appropriate jurisdiction if demolition noise levels are overly intrusive.
Before haul truck trips are initiated on roads within 600 feet of one or more residences, the Contractor shall provide written notification at least one day before to the potentially affected residents, identifying the hours and frequency of haul truck trips. Notification materials shall also identify a mechanism for residents to register complaints with the appropriate jurisdiction if haul truck noise levels are overly intrusive or outside exempt daytime hours.
1.3.19 SCR-19 Allowable Work Hours
Monday through Saturday, the Contractor shall limit construction activities to between the following hours on the following days for Site R3A:
Monday through Saturday: 7 AM - 6 PM (as posted in the newspaper or online), whichever is sooner Sunday: 9 AM - 6 PM (as posted in the newspaper or online), whichever is sooner
Monday through Saturday, the Contractor shall limit construction activities to between the following hours on the following days for Site L10:
Monday through Saturday: 7 AM - 4 PM (as posted in the newspaper or online), whichever is sooner Sunday: 9 AM - 4 PM (as posted in the newspaper or online), whichever is sooner
Passive (no operation of heavy machinery) activity off of the levee is restricted to the staging area for one hour after sunset (as posted in the newspaper or online) or 10:00 PM whichever occurs sooner. Only passive activity is allowed on Sundays. No other construction work will be allowed outside the above mentioned hours. Such extended work hours must be reflected in the Contractor's initial approved schedule for the Project.
1.3.20 SCR-20 Archaeological, Paleontological, and Cultural Resources
The Contractor shall comply with protocols in Section 01 57 20, ENVIRONMENTAL PROTECTION, of the General Specifications.
Contractor shall conduct Construction Personnel Training for all on-site employees. If paleontological resources are discovered during construction activities, Contractor shall cease work within 100 feet of the vicinity of the find and immediately contact the archaeologist, 00 73 05 - 9 through the Contracting Officer, and cooperate with all pertinent mitigation procedures.
1.3.21 SCR-21 Protection of Existing Trees
All trees outside the work limits, of any kind, are to be protected.
Contractor shall place protective barrier fencing around sensitive trees adjacent to construction areas as directed by the Contracting Officer. If damaged by the Contractor, damaged trees and landscaping shall be replaced by Contractor or otherwise mitigated as directed by Contracting Officer at the Contractor's expense.
1.3.22 SCR-22 Biological Resources
The Contractor shall comply with the Section 01 57 20, ENVIRONMENTAL PROTECTION, of the General Specifications to avoid and minimize effect upon endangered or sensitive species in the Project area. The Contractor shall schedule activities to comply with the provisions and provide required notice for surveys to be conducted by the Government's Environmental Representative. Construction personnel shall participate in an environmental awareness program, which will be provided by the Contracting Officer at the start of construction. As needed, the Contractor shall provide a translator to allow the training to be conducted in Spanish for Spanish language speakers and other languages as needed or necessary.
1.3.23 SCR-23 Raptor and Migratory Birds
The Contractor shall comply with the provisions of the Construction Contractor Protocols for Avoiding and Minimizing Impacts to Raptors, Special Status, and Other Nesting Birds, which are included in Section 01 57 20, ENVIRONMENTAL PROTECTION, of the General Specifications. If a nesting bird is found injured on the Project site, the Contracting Officer shall be notified immediately so the animal can be relocated to a either a wildlife care facility or a raptor recovery facility.
1.3.24 SCR-25 Wetlands and Sensitive Habitats
The Contractor shall not impact Wetlands and Sensitive Habitats.
1.3.25 SCR-27 U.S. Fish and Wildlife Service
A Biological Opinion has been issued by the U.S. Fish and Wildlife Service. The Contractor shall comply with the terms and conditions and is responsible for implementing all requirements and obligations included in the opinion. A copy of the Biological Opinion is available upon request to the Contracting Officer.
1.3.26 SCR-28 Central Valley Flood Protection Board
The Government has obtained encroachment permits from the Central Valley Flood Protection Board for work on this project. A copy of the permit(s) is available upon request to the Contracting Officer. The Contractor shall comply with the conditions of this permit(s), except where the Technical Specifications specify criteria that are more stringent.
1.3.27 SCR-29 Speed Limit
The speed limit in all Project work areas and along levees shall be 15
00 73 05 - 10 m.p.h., except on county roads and on highways. The Contracting Officer may also require that speed limits on project site be reduced further to ensure vibration limits are not violated. The Contractor shall post, at a minimum, two speed limit signs at each end of the haul route.
1.3.28 SCR-30 American River Flood Control District (ARFCD) Coordination
American River Flood Control District manages the existing levees throughout the project area. The Contractor shall coordinate their work with ARFCD through the Contracting Officer, allowing ARFCD access to its facilities at all times. The Contractor shall maintain access for the ARFCD through the Contracting Officer at all times.
1.3.29 SCR-31 Provision Regarding Maintaining Minimum Flood Protection During Construction
Contractor shall have all levee improvements planned for a construction season completed by the deadlines outlined in Time of Completion requirements as described in paragraph 1.3.3, SCR-3, herein. Contractor shall not disturb the existing levee system beyond the limits of construction. Disturbance includes but is not limited to roadways, ramps, pipes and/or utilities crossings, or excavations within the limits of construction. Stockpiling suitable construction materials is acceptable provided written approval is first obtain from the Contracting Officer.
1.3.30 SCR-32 Coordination with the Contracting Officer and Utilities Relocation
Contractor shall coordinate and cooperate with the Contracting Officer and all utility providers on relocation of any existing overhead and electrical utilities and gas within the limits of construction that may hinder the performance of Contractor's construction activities.
Contractor shall assist in coordination and work with the Contracting Officer such that the utilities are relocated in time not to delay and to allow for completion of improvements in accordance with the Time of Completion schedule.
1.3.31 SCR-33 Haul Routes
All haul and access routes shall be existing public roads and maintenance roads, except for restrictions noted on the drawings. Stockpiling of construction materials, including portable equipment, vehicles, and supplies, shall be restricted to designated construction staging areas.
Movement of heavy equipment to and from the Project site shall be restricted to load limit approved roadways. The Contractor's construction access points shall be limited to those shown on the Plans, defined in the Specifications, or as directed in the field by the Contracting Officer.
Paved areas at these controlled access points shall be swept each day, or more frequently, as required by the Contracting Officer to control dust and clean up material tracked or spilled on said paved areas or roadways.
The Contractor shall conform to all governing codes, laws, and ordinances.
Contractor shall obtain a permit, waiver or other documentation with the mapped haul routes from local jurisdictions to repair or compensate for damage to local roads used in hauling to or from the project site. The permit, waiver or other documentation provided by the local jurisdiction may specify the conditions for repairs to be performed or appropriate compensation to account for the road damage. Contractor shall provide a copy of the permit, waiver or other documentation from local jurisdictions
00 73 05 - 11 with the mapped haul routes to the Contracting Officer and resident engineer prior to commencement of haul operations. All cost associated with permits, haul road repairs, fees shall be incurred by the Contractor and shall not be paid separately from unit prices or lump-sum prices contained in the Bidding Schedule.
1.3.32 SCR-34 Resource Coordination
All contact and coordination with the resource agencies shall occur through the Contracting Officer in coordination with the Government's environmental representative.
1.3.33 SCR-35 Flood Contingency Plan
In the event the water surface elevation of the adjacent river is forecasted by the State-Federal Flood Forecast Center to increase significantly for any reason, the Contracting Officer reserves the right to require the Contractor to stop excavation and to begin continuous operations to complete all partially completed section (s) of the levee embankment and the cutoff wall. At least 15 days prior to any Levee Excavation, the Contractor shall submit a contingency plan outlining the contingency operations in the event that river elevations above the flood stage (as defined by the USACE) are forecasted. The contingency plan shall include the proposed measure to protect the landside areas which have a reduced level of protection due to construction activities. The plan shall include river stage monitoring, river stage at which the plan will be activated, material and equipment to be used in performance of the contingency plan, and location, type and quantity of the stockpiled emergency material. The plan shall also include the length of levee, where stockpiled material will be stored, and the method for monitoring river elevations. The Contractor shall keep any levee degrade material on the project site for the duration of the construction period, protected from inclement weather, for use as emergency backfill as necessary. The Flood Contingency Plan shall be submitted to the Contracting Officer for review.
1.3.34 SCR-36 Utility Provider Response Plan
Contractor shall prepare and submit a Utility Response Plan to the Contracting Officer, SRCSD, and the City of Sacramento. Plan shall detail how utility locations are verified, provide protocol for coordination with Utility Providers, detail process on conducting required worker training for all on-site employees with respect to accidental utility damage, and provide utility provider emergency contact information. Contractor is responsible for coordinating any temporary utility services needs during construction, and shall assume all temporary utility services cost.
1.3.35 SCR-37 Stop Work Authority
The Contracting Officer in cooperation with the Government's Environmental Representative shall have the authority to immediately stop any activity that is not in compliance with the permits, and/or order any reasonable measure to avoid the unauthorized take of an individual of the Covered Species (e.g., giant garter snake, Swainson's hawk, valley elderberry longhorn beetle, Federally- and State-listed fish).
1.3.36 SCR-38 Floodway Construction Schedule
Contractor shall not perform any work within the existing floodway (i.e., waterside) per the date restrictions in Time of Completion requirement
00 73 05 - 12 herein and shall not begin any construction until evaluation of upstream conditions indicate that inundation of these areas is unlikely to occur.
1.3.37 SCR-39 High Visibility Fencing, Habitat Preservation and Buffers
Contractor shall provide high visibility fencing that shall be placed to prevent encroachment of construction personnel and equipment into areas outside of or adjacent to the project footprint that contain sensitive habitats, including at least 20 feet from the dripline of elderberry shrubs and up to 200 feet from the edge of aquatic features that are suitable giant garter snake habitat. K-Rails, if used, shall be used in areas noted on the drawings. The fencing shall be inspected by the Contractor before the start of each work day and shall be maintained until completion of the Project. The Contractor shall not remove the fencing until construction of the Project is completed. No insecticides, herbicides, or other chemicals that might harm the longhorn beetle or its host plant shall be used within 100 feet of the elderberry shrubs.
1.3.38 SCR-40 General Safety Requirements
The Contractor shall conform to all applicable occupational safety and health standards, rules, regulations, and orders established by the State of California or Federal Government. The Contractor shall, upon request, submit to the Contracting Officer a copy of their Injury Illness Prevention Program (IIPP) (including Site Safety Plan and Code of Safe Work Practices) for review. The Contractor is required to fulfill the requirements of these programs during the prosecution of the Work, and comply with conditions set forth in the Specifications. The Contractor shall comply with all regulations set forth in EM 385-1-1 .
1.3.39 SCR-41 Storm Water Pollution Prevention Plan
Coverage under the State Water Resources Control Board (SWRCB) General Permit to Discharge Water Associated with Construction Activity shall be obtained by the Contractor for this Project prior to initiation of any construction activities. The Notice of Intent (NOI) shall comply with the Terms of the General Permit to Discharge Storm Water Associated with Construction Activity (WQ Order No. 99-08-DWQ) and/or (WQ Order No.
2009-0009-DWQ); contingent upon SWRCB direction at the time of filing.
The Contractor shall develop and submit to the Contracting Officer a Storm Water Pollution Prevention Plan (SWPPP) for the work in accordance with the state's guidelines and the Specification 01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL that address the all pertinent SWPPP regulations, including the new regulations that become effective as of July 1, 2010.
The Contractor shall implement the SWPPP prior to the start of soil-disturbing activity, and be responsible for all monitoring and maintenance until permanent erosion control has been established, as determined by the Contracting Officer. The SWPPP shall include Best Management Practices to prevent sediment, runoff from dust control, and oil and other chemicals used in construction from entering areas of wildlife habitat. The Contractor shall use fiber netting and other environmentally sound materials and methods as defined in Specification
01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL.
1.3.40 SCR-42 Grading Permit
Contractor shall obtain a Grading Permit from City of Sacramento prior to initializing work. Copy of work permit shall be given to the Contracting Officer prior to disturbing ground.
00 73 05 - 13
1.3.41 SCR-43 Cobbles
Contractor should be aware that cobbles may exist within the cutoff wall profile. No additional allowances will be allowed for working around cobbles.
1.3.42 SCR-44 Local Jurisdictions Permitting Requirements
Contractor shall obtain a permit, waiver or other documentation with the mapped haul routes from local jurisdictions to repair or compensate for damage to local roads used in hauling to or from the project site. The permit, waiver or other documentation provided by the local jurisdiction may specify the conditions for repairs to be performed or appropriate compensation to account for the road damage. Contractor shall provide a copy of the permit, waiver or other documentation from local jurisdictions with the mapped haul routes to the Contracting Officer and resident engineer prior to commencement of haul operations. All cost associated with permits, haul road repairs, fees shall be incurred by the Contractor and shall not be paid separately from unit prices or lump-sum prices contained in the Bidding Schedule.
1.3.43 SCR-45 Staging Area
Staging areas needed by the Contractor for the project have been identified in the Drawings and permits have been obtained for them by the Government. If additional areas are needed, they will be the responsibility of the Contractor to obtain.
1.3.44 SCR-46 Recreation/Community Mitigation - Site L10
A minimum of two weeks prior to start of work Contractor shall provide written notification to the DPW Representative as well as outreach to the immediate project neighbors advising of the work, duration, the days of the week work is to take place, and the hours to be worked for each day.
USACE and Contractor to provide, via posted signage, a USACE project manager name, contact number and email address as well as a Contractor project manager name, contact number and email address, for residents in the vicinity of the Premises should any concern from the immediate project neighbors arise with regard to noise, traffic, or other such disturbance which directly results from USACE's and/or Contractor's work. The purpose of USACE and Contractor posting their respective contact information is to avoid Construction Inspection and Survey staff having to field telephone calls and other inquiries related to USACE's and Contractor's work.
In addition, signage shall be posted at the entrance to the American River Parkway ("Parkway") and other key access points one month prior to commencement of construction and shall remain in place during the duration of the project. Signage shall provide information on the reduced or closed access to the Parkway and shall direct parkway visitors to alternate access points. Contractor shall maintain a similar path to the bike trail from La Riviera Drive as the existing dirt trail that will be encumbered by the Contractor's use of the Premises. The signs shall include a general description of the type of repairs being constructed; the approximate dates of commencement and completion; information on alternative access points to the Parkway; and the contact name and number of the Contractor's Project Manager. Signs shall be at least 3' x 4' in size and printed on sturdy cardboard stock or plywood. Signage text shall be subject to the
00 73 05 - 14 review and approval of the City's Representative prior to its installation.
Should there be any possibility of interference with public access along the Parkway, Contractor shall be responsible for placing 'Levee Closure Signs' at appropriate points along the levee to discourage public access into the work zone during work hours. If there is, at any time during the effective period of this Agreement, a proposed or unexpected closure of the public access and thoroughfare along the Parkway by Contractor, Contractor shall notify the City's Representative staff immediately to implement safety measures for the general public in and along the immediate vicinity of the work zone in the Parkway.
1.3.45 SCR-47 City Streets - Site L10
The Contractor shall ensure that its construction equipment and hauling operations do not damage City streets. Prior to start of construction, Contractor shall photograph the street along and at the La Riviera Drive entrance to the American River Parkway before construction operations begin. In addition, the Contractor shall use extreme caution when operating under the Howe Avenue overpass. Several abutments for the Howe Avenue overpass are located within Premises. Photographs shall be shared with the City Department of Public Works Representative, Jon Liffring, Supervising Construction Inspector, (the "DPW Representative"), (916) 808-7124, and will be used to compare before and after project conditions at the project's end. Contractor shall immediately contact DPW Representative should any damage or collision occur with respect to these abutments. It is imperative that any trucks driving under the Howe Avenue overpass have an appropriate amount of clearance so as not to come into contact with the underside of the roadway. It is also imperative that the trucks, vehicles, and any other such equipment and/or storage materials not come into contact with any abutment located on the Premises. Any damage to the Premises, including the structural integrity of the Howe Avenue overpass, caused by Contractor's operations must be repaired at Contractor's cost and to City's satisfaction.
The Contractor shall notify and submit truck routes for review to the DPW Representative prior to starting work. Furthermore, the Contractor shall provide the City Representative with a location for a wash out area to wash and clean Contractor's trucks, equipment and tires before they exit onto La Riviera Drive.
At no time shall the Contractor block or impede the use of the sidewalk on the north side of La Riviera Drive. At no time shall Contractor block or impede the use of the parking spaces on the north side of La Riviera Drive. If any portion of the sidewalk or parking spaces will be needed on a temporary basis, an encroachment permit will need to be issued by the DPW Representative to Contractor.
1.3.46 SCR-48 Storage Area - Site L10
Contractor shall erect cyclone fencing a minimum of eight (8) feet tall around the perimeter of its storage area. The fencing shall post signage no smaller than 3' x 3' in size providing the Contractor's company name as well as a name and telephone number for Contractor who may be contacted by the public in general in the event that any issues arise out of the use of the Premises. All material remnants need to be removed from the storage site. If this is difficult to achieve with the types of materials to be stockpiled, a protective barrier between the ground surface and stockpiled materials shall be used. Upon the conclusion of the work, or prior to the
00 73 05 - 15 time period that this Right of Entry shall expire, whichever occurs first, Contractor shall return the site to a condition equal to or better than the condition it was in at the outset of this Right of Entry.
1.3.47 SCR-49 City Pump Station Sump 91 - Site L10
Sump 91 The Contractor shall also ensure that their construction equipment and hauling operations do not damage the access driveway off La Riviera Drive. Prior to start of construction, Contractor shall photograph the access driveway. Copies of the photographs shall be shared with the City Department of Utilities Representative, Pete Millino, Water and Sewer Superintendent, (916) 808-5173 ("DOU Representative"), and will be used to compare before and after project conditions at the project's end. Any damage caused by Contractor's operations must be repaired at Contractor's cost and to City's satisfaction.
The following additional conditions shall apply to the Contractor's use of the Premises as it affects the operation of Sump 91. Contractor shall:
a. Provide at least 72 hours' notice prior to access or use of the Premises. Such notice shall be provided to the DOU Representative.
b. Agree that only the work described above is authorized.
c. Agree that the project access area shall be restored to at least the same condition that existed prior to commencement of work.
d. Agree that this Agreement does not relieve Contractor of the responsibility to obtain authorization from all concerned federal, State and local agencies; or to satisfy any California Environmental Quality Act (CEQA) requirements.
e. Assure that the City's property is kept clean and free of debris and litter.
f. Provide the DOU Representative a 24-hour contact list of persons with authority and resources to respond to an unexpected after-hours situation including, but not limited to, an unexpected storm event.
g. Coordinate any planned power outages with the DOU Representative.
h. Assure that the access route from the gate at La Riviera Drive to Sump 91 facility and outfall area is accessible at all times for a dump truck sized vehicle.
i. Monitor the following for damage during each construction season and make repairs, if necessary:
1. Fencing and Gates
2. Pavement within Sump 91 and the entry road from La Riviera Drive.
3. Grading and condition of access road.
1.3.48 SCR-50 Project Signage
The Contractor shall provide all signage for the project. Sign wording, sizes and other parameters shall be coordinated with the Contracting Officer and/or his/her representative.
00 73 05 - 16
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
00 73 05 - 17
| 00 73 05 - SUPPLEMENTARY CONDITION REQUIREMENTS FOR SITES R3A & L10 |
| 00 73 05 - SUPPLEMENTARY CONDITION REQUIREMENTS FOR SITES R3A & L10 |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 SUBMITTALS |
| 1.3 SUPPLEMENTARY CONDITIONS REQUIREMENTS |
| 1.3.1 SCR-1 Location of Work |
| 1.3.2 SCR-2 Scope of Work |
| 1.3.3 SCR-3 Allowable Time, Schedule Constraints and Time of Completion |
| 1.3.4 SCR-4 Site Conditions |
| 1.3.5 SCR-5 Lands and Right-of-Way |
| 1.3.6 SCR-6 Access by Government, and Other Jurisdictional Public Agencies |
| 1.3.7 SCR-7 Contractor's Tools and Equipment |
| 1.3.8 SCR-8 Locking Gates |
| 1.3.9 SCR-9 Water Source for Construction Operations |
| 1.3.10 SCR-10 Cleaning Up |
| 1.3.11 SCR-11 Protection of Existing Improvements |
| 1.3.12 SCR-12 Record Drawings |
| 1.3.13 SCR-13 Flood Emergency |
| 1.3.14 SCR-14 Permits and Approvals |
| 1.3.15 SCR-15 Dust Control |
| 1.3.16 SCR-16 Fire Control |
| 1.3.17 SCR-17 Air Pollution Control |
| 1.3.18 SCR-18 Noise Control |
| 1.3.19 SCR-19 Allowable Work Hours |
| 1.3.20 SCR-20 Archaeological, Paleontological, and Cultural Resources |
| 1.3.21 SCR-21 Protection of Existing Trees |
| 1.3.22 SCR-22 Biological Resources |
| 1.3.23 SCR-23 Raptor and Migratory Birds |
| 1.3.24 SCR-25 Wetlands and Sensitive Habitats |
| 1.3.25 SCR-27 U.S. Fish and Wildlife Service |
| 1.3.26 SCR-28 Central Valley Flood Protection Board |
| 1.3.27 SCR-29 Speed Limit |
| 1.3.28 SCR-30 American River Flood Control District ARFCD Coordination |
| 1.3.29 SCR-31 Provision Regarding Maintaining Minimum Flood Protection |
| 1.3.30 SCR-32 Coordination with the Contracting Officer and Utilities |
| 1.3.31 SCR-33 Haul Routes |
| 1.3.32 SCR-34 Resource Coordination |
| 1.3.33 SCR-35 Flood Contingency Plan |
| 1.3.34 SCR-36 Utility Provider Response Plan |
| 1.3.35 SCR-37 Stop Work Authority |
| 1.3.36 SCR-38 Floodway Construction Schedule |
| 1.3.37 SCR-39 High Visibility Fencing, Habitat Preservation and Buffers |
| 1.3.38 SCR-40 General Safety Requirements |
| 1.3.39 SCR-41 Storm Water Pollution Prevention Plan |
| 1.3.40 SCR-42 Grading Permit |
| 1.3.41 SCR-43 Cobbles |
| 1.3.42 SCR-44 Local Jurisdictions Permitting Requirements |
| 1.3.43 SCR-45 Staging Area |
| 1.3.44 SCR-46 Recreation/Community Mitigation - Site L10 |
| 1.3.45 SCR-47 City Streets - Site L10 |
| 1.3.46 SCR-48 Storage Area - Site L10 |
| 1.3.47 SCR-49 City Pump Station Sump 91 - Site L10 |
| 1.3.48 SCR-50 Project Signage |
| PART 2 PRODUCTS |
| PART 3 EXECUTION |