SECTION 32 12 10
BITUMINOUS TACK AND PRIME COATS
08/08
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
AMERICAN SOCIETY OF TESTING AND MATERIALS (ASTM)
ASTM D 140 (1993) Sampling Bituminous Materials
ASTM D 977 (1991) Emulsified Asphalt
ASTM D 1250 (1980; R 1990) Petroleum Measurement Tables
ASTM D 2027 (1976; R 1992) Cutback Asphalt (Medium-Curing Type)
ASTM D 2397 (1994) Cationic Emulsified Asphalt
ASTM D 2995 (1993) Determining Application Rate of Bituminous Distributors
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01330 SUBMITTAL PROCEDURES:
SD-03 Product Data
Tack Coat; G, RE; Prime Coat; G, RE
Copies of all test results for bituminous materials, within 24 hours of completion of tests. Certified copies of the manufacturer's test reports indicating compliance with applicable specified requirements, not less than 30 days before the material is required in the work.
1.4 PLANT, EQUIPMENT, MACHINES AND TOOLS
1.4.1 General Requirements
Plant, equipment, machines and tools used in the work shall be subject to approval and shall be maintained in a satisfactory working condition at all times.
1.4.2 Bituminous Distributor
The distributor shall have pneumatic tires of such size and number to prevent rutting, shoving or otherwise damaging the base surface or other layers in the pavement structure. The distributor shall be designed and equipped to spray the bituminous material in a uniform coverage at the specified temperature, at readily determined and controlled rates with an allowable variation from the specified rate of not more than plus or minus 5 percent, and at variable widths. Distributor equipment shall include a separate power unit for the bitumen pump, full-circulation spray bars, tachometer, pressure gauges, volume-measuring devices, adequate heaters for heating of materials to the proper application temperature, a thermometer for reading the temperature of tank contents, and a hand hose attachment suitable for applying bituminous material manually to areas inaccessible to the distributor. The distributor shall be equipped to circulate and agitate the bituminous material during the heating process.
1.4.3 Power Brooms and Power Blowers
Power brooms and power blowers shall be suitable for cleaning the surfaces to which the bituminous coat is to be applied.
1.5 WEATHER LIMITATIONS
Bituminous coat shall be applied only when the surface to receive the bituminous coat is dry. Bituminous coat shall be applied only when the atmospheric temperature in the shade is 50 degrees F or above and when the temperature has not been below 35 degrees F for the 12 hours prior to application.
PART 2 PRODUCTS
2.1 TACK COAT
Emulsified asphalt shall conform to ASTM D 977 Grade SS-1. Cationic emulsified asphalt shall conform to ASTM D 2397 Grade CSS-1.
2.2 PRIME COAT
Cutback asphalt shall conform to ASTM D 2027, Grade SC-70.
PART 3 EXECUTION
3.1 PREPARATION OF EMULSION
Bituminous materials for emulsions shall be diluted by adding equal volumes of bituminous material and compatible water. If the bituminous material is to be diluted in the field, first test the mix by placing equal volumes of emulsion and water in a glass quart jar (do not use a metal container, as it could cause the mixture to "break") and mix for one minute. If the mixture "breaks", a different source of water or bituminous material is required.
3.2 PREPARATION OF SURFACE
Immediately before applying the bituminous coat, all loose material, dirt, clay, or other objectionable material shall be removed from the surface to be treated. Power brooms shall be used as needed. The surface shall be dry and clean at the time of treatment.
3.3 APPLICATION RATE
The exact quantities within the range specified, which may be varied to suit field conditions, will be determined by the Contracting Officer.
3.3.1 Tack Coat
Bituminous material for the tack coat shall be applied in quantities of not less than 0.05 gallon nor more than 0.15 gallon per square yard of pavement surface.
3.3.2 Prime Coat
Bituminous material for the prime coat shall be applied in quantities of not less than 0.15 gallon nor more than 0.40 gallon per square yard of pavement surface.
3.4 APPLICATION TEMPERATURE
3.4.1 Viscosity Relationship
Asphalt application temperature shall provide an application viscosity between 10 and 60 seconds, Saybolt Furol, or between 20 and 120 centistokes, kinematic. The temperature viscosity relation shall be furnished to the Contracting Officer.
3.4.2 Temperature Ranges
The viscosity requirements shall determine the application temperature to be used. The following is a normal range of application temperatures:
Emulsions SS-1 70-160 degrees F CSS-1 70-160 degrees F
3.5 APPLICATION
Following preparation and subsequent inspection of the surface, the bituminous coat shall be applied at the specified rate with uniform distribution over the surface to be treated. All areas and spots missed by the distributor shall be properly treated with the hand spray. Until the succeeding layer of pavement is placed, the surface shall be maintained by protecting the surface against damage and by repairing deficient areas at no additional cost to the Government. If required, clean dry sand shall be spread to effectively blot up any excess bituminous material. To obtain uniform application of the prime coat on the surface treated at the junction of previous and subsequent applications, building paper shall be spread on the surface for a sufficient distance back from the ends of each application to start and stop the prime coat on the paper. Immediately after application, the building paper shall be removed and disposed-of.
3.6 CURING PERIOD
Following application of the bituminous material and prior to application of the succeeding layer of pavement, the bituminous coat shall be allowed to cure and to obtain evaporation of any volatiles or moisture. Prime coat shall be allowed to cure without being disturbed for a period of at least 48 hours or longer, as may be necessary to attain penetration into the treated course.
3.7 FIELD QUALITY CONTROL
Samples of the bituminous material used shall be obtained by the Contractor as directed, under the supervision of the Contracting Officer. The sample may be retained and tested by the Government at no cost to the Contractor.
-- End of Section --