Atch 2 Supl Contract Requ - Richmond Armory.pdf
PDF 15 KB Posted
- Solicitation number
- W91238-10-R-0039
About this file
10R0039 Atch 2 Supplemental Contract Requirements
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Atch 3 CA29_dvb.pdf | ||
| Atch 1 SOW Appendices - Concept Drawings.pdf | ||
| Atch 1 SOW - Richmond Armory.pdf | ||
| 10R0039 Am02.pdf | ||
| Atch 4 TO Pricing Schedule.pdf | ||
| Firms Selected for Phase 2.pdf | ||
| W91238-10-R-0039-0001.pdf | ||
| Volume 2 Specifications.pdf | ||
| 10R0039.pdf | ||
| Volume 1 Specifications.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 2 Sample Task Order
SUPPLEMENTAL CONTRACT REQUIREMENTS
1. Performance Period. The performance period for the work stated above shall be 180 calendar days.
2. Liquidated Damages. Refer to FAR 52.211-12, Liquidated Damages-Construction.
Liquidated damages for this work is $691.00 for each day of delay.
3. Authorities. No person other than the Government Contracting Officer/Administrative Contracting Officer has the authority to make any changes to this contract action that impact cost or schedule. Authority from the Contracting Officer/Administrative Contracting Officer to the contractor to make changes that impact cost or schedule will be in the form of an official, signed modification.
4. Wage Determination. General Decision No. CA100029 dated 09/10/2010, or its most current modification at the time of award is hereby applicable to work performed under this task order. This project is located in Richmond, Contra Costa County, California. The most current decision or its modification can be found at http://www.wdol.gov/wdol/scafiles/davisbacon/CA29.dvb
5. Time Extensions For Unusually Severe Weather. Refer to Default (Fixed-Priced Construction). All weather delay will need to be submitted and approved by the Contracting Officer Representative.
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY
WORK DAYS BASED ON (5) DAY WORK WEEK – RICHMOND, CA
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
(06) (05) (05) (04) (01) (00) (00) (00) (01) (02) (05) (06) http://www.wdol.gov/wdol/scafiles/davisbacon/CA29.dvb�
SUPPLEMENTAL CONTRACT REQUIREMENTS
File details come from the government source that posted it. Updated .