ATTACHMENT #1
VOLUME 1 – DIVISION 01 THRU DIVISION 09
VOLUME 2 – DIVISION 01 thru DIVISION 33
RFP NO. TO BE DETERMINED
US ARMY CORPS OF ENGINEERS
Sacramento District
W91238-10-R-0035 Specification Vol 1 xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
August 06, 2010 1 of 739 xxxxxxxx xxxxxxxx
L2EDMGH9
New Stamp
L2CTAGLT
Typewritten Text
XXXXXXXXXXXXXXXXXXXXXX
L2CTAGLT
Typewritten Text
L2CTAGLT
Typewritten Text
L2CTAGLT
Typewritten Text
XXXXXXXXXXXXXXXXXXXXXXX
TABLE OF CONTENTS
VOLUME 1 of 4
BID DOCUMENTS
011 ATTACHMENT:
1 Contractor Prepared As-Builts
012 TECHNICAL SPECIFICATIONS
01 11 10 General Requirements 01 32 01.00 10 Project Schedule 01 33 00 Submittal Procedures 01 42 00 Reference Publications 01 45 02.00 10 Quality Control System (QCS) 01 45 04.00 10 Contractor Quality Control 01 50 02.00 10 Temporary Construction Facilities 01 50 05 General Requirements 01 57 20.00 10 Environment Protection 01 62 35 Recycled/Recovered Materials 01 78 02.00 10 Closeout Submittals
VOLUME 2 THRU 3
August 06, 2010 2 of 739 xxxxxxxx xxxxxxxx
Preparing As-Built Drawings INSP05L0.DOC Effective 09/13/04 Rev 1
Preparing As-Built Drawings
Scope
This instruction covers preparing high-quality As-Built drawings to show changes made to the project during construction. As-Built drawings are an official record of the project at the time of construction completion. The original "as-designed" contract drawings and specifications are modified to show all additions, deletions and other changes made during construction. Accurate as-built drawings are very important for project operation and maintenance, and future modifications, particularly for plumbing and electrical systems, which are hidden from view.
References − CADD/GIS Technology Center Architectural, Engineering, and Construction
(A/E/C) CADD Standards[http://tsc.wes.army.mil/products/standards/aec/intro.asp]
Definitions.
See the Glossary of Engineering Quality System Terms and Acronyms [REFQ10L0], for definitions.
Contractor Markups - Drawings that are marked and annotated to show the project As-Built and constructed by the contractor. They are part of the working as-built set.
As-Built Drawings - The amended "As-designed" drawings revised to show the project as the contractor built and constructed it. The revisions from Contractor Markups and field inspection notes are transferred to the Final as-built set of drawings. The final as-built drawings include modifications during construction, field requested changes, shop drawing modifications, and contractor designs.
As-Constructed Drawings - These are As-Built Drawings for Civil Works Projects. The term As-Built used in these instructions is synonymous.
Working As-Built
The Contractor shall maintain 2 sets of paper drawings and specifications (marked-up prints) to track changes, additions or deletions from the original design during construction. Working as-built drawings shall be kept current on a weekly basis and at least one paper set of as-built drawings shall be available on the jobsite at all times.
Areas of Concern
There are some general items that need some special checking to ensure that the marked-up prints are complete and accurate. The working as-built shall show, but shall not be limited to, the following:
Copyright © Oracle Corporation, 2002. All rights reserved. Content written by USACE, Sacramento District, Engineering Division
W91238-10-R-0035 Specification Vol 1 xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
August 06, 2010 3 of 739
Rev 1
(1) The actual location, kinds and sizes of all of existing and new utility lines, especially underground lines within the construction area. Measurements will be shown for all change of direction points and all surface or underground components such as valves, manholes, drop inlets, clean outs, meters, etc. The descriptions of exterior utilities shall include the actual quantity, size, and material of the utility lines. In order that the location of these lines and appurtenances may be determined in the event the surface openings or indicators become covered over or obscured, the as-built drawings shall show, by offset dimensions to two permanently fixed surface features, the end of each run including each change in direction. Valves, splice boxes and similar appurtenances shall be located by dimensioning along the utility run from a reference point. The average depth below the surface of each run shall also be recorded.
(2) The location and dimensions of any changes within the building structure.
(3) Layout and schematic drawings of electrical circuits and piping.
(4) Correct dimensions and details transferred from shop drawings.
(5) Correct grade, elevations, cross section, or alignment of roads, earthwork, structures or utilities if any changes were made from contract plans.
(6) Actual location of anchors, construction and control joints, etc., in concrete.
(7) Changes in location of equipment and architectural features.
(8) Where contract drawings or specifications present options, only the option selected for construction shall be shown on the final as-built prints. Cross out such words and phrases as "optimal requirement," "or equal," etc., and list specifically the items of material provided.
(9) Unusual or uncharted obstructions that are encountered in the contract work area during construction.
(10) Location, extent, thickness, and size of stone protection particularly where it will be normally submerged by water.
(11) Changes in details of design or additional information obtained from working drawings specified to be prepared and/or furnished by the Contractor; including but not limited to fabrication, erection, installation plans and placing details, pipe sizes, insulation material, dimensions of equipment foundations, etc.
(12) The topography, invert elevations and grades of drainage installed or affected as part of the project construction.
(13) If borrow material for this project is from sources on Government property, or if Government property is used as a spoil area, the Contractor shall furnish a contour map of the final borrow pit/spoil area elevations.
Copyright © Oracle Corporation, 2002. All rights reserved. Content written by USACE, Sacramento District, Engineering Division
W91238-10-R-0035 Specification Vol 1 xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
August 06, 2010 4 of 739
Rev 1
(14) Systems designed or enhanced by the Contractor, such as HVAC controls, fire alarm, fire sprinkler, and irrigation systems
(15) Changes or modifications that result from the final inspection.
Mark-up Guidelines
The following information is provided to improve the quality of the marked-up prints and thereby facilitate preparation of final as-built drawings. The most important guideline is that the marked-up changes on the prints shall be complete and understandable. Visits to the site by the draftsperson, or visits to the draftsperson by the construction superintendent, can be minimized by providing complete and understandable marked-up prints.
(1) Frequently use written explanations on As-Built drawings to describe changes - do not rely totally on graphic means to convey the revision.
(2) Legibility of lettering and digit values shall be precise and clear when marking prints, and clarify ambiguities concerning the nature and application of change involved.
(3) Wherever a revision is made, make changes to affect related section views, details, legend, profiles, plans and elevation views, schedules, notes and call-out designations, and mark accordingly to avoid conflicting data on all other sheets.
(4) When changes are made, cross out all features, data and captions that relate to that revision.
(5) When changes are required on small-scale drawings and in restricted areas, suggest large-scale inserts be drawn or sketched, with leaders to the location where applicable.
(6) Provide a legend if colors other than the "base" colors of red, green, and blue are used.
Be sure descriptive markings conform to legend symbols shown.
(7) Be sure to add and denote in legend, any additional equipment or material facilities, service lines, etc., incorporated under As-Built Revision if not already shown in legend.
(8) When attached prints (or sketches) are provided with marked-up print, indicate whether:
a. Entire drawing shall be added to contract drawings or
b. Whether the contract drawings shall be changed to agree, or
c. For reference only to further details not required for initial design.
(9) Make the comments on the drawing complete without reference to letters, memo's, or materials that are not also a part of the As-Built. Annotating the drawing, “Per Change Order #42,” means nothing when the actual change order states, “added an additional 12 duplex” outlets or similar statements. The same is true when the drawing is marked, Copyright © Oracle Corporation, 2002. All rights reserved. Content written by USACE, Sacramento District, Engineering Division
W91238-10-R-0035 Specification Vol 1 xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
August 06, 2010 5 of 739
Rev 1
“changed per COE instructions.” This office and ultimately the using organizations must know what was changed, how it was changed, where the items(s) were relocated to and how the affected connections were altered. Change Orders usually do not provide information as to how the facility was changed, only what was changed.
(10) The markups shall be accomplished on blue or black line prints of the most current originals.
(11) Shop drawings are to be incorporated into the As-Built drawings. They will be provided in electronic CADD file format and conform to the Sacramento District CADD Standards and the A/E/C CADD Standards. Hand drawn or plotted paper shop drawings will not be accepted as submittals.
The hand drawn or plotted paper shop drawings are not usable as original drawings for several reasons.
a. Deleted
b. The drawings are not of an adequate scale or are drawn to no scale and are not transferable to the CORPS drawings due to lack of information.
c. The limited numbers of reproducible shop drawings that have been received have not been on the Corps of Engineers standard sheets sizes making it difficult to convert these drawings to standard COE drawings.
Any drawing provided by non-COE sources will be drawn in CADD. Sheets shall be drawn at the same scale as similar drawings in the set (example: Fire alarm systems shall be drawn to the same scale as the plumbing or electrical drawings). The drawing shall meet the same standards required for the rest of the drawings set. Sheet number, detail number, etc shall tie details and sketches to existing drawings.
FINAL AS-BUILT DRAWINGS
The contractor will transfer the changes from the working as-built marked prints to the original electronic CADD files. Final as-built drawings shall be prepared after the completion of each definable feature of work as listed in the Contractor Quality Control Plan (Foundations, Utilities, Structural Steel, etc., as appropriate for the project). The Resident Engineer and the Contractor will jointly review the working as-built marked prints, printouts from working as-built CADD file drawings, and final as-built drawings for accuracy and completeness, prior to submission of each monthly pay estimate. Monthly review of working as-built CADD printouts shall at minimum cover all sheets revised since the previous review.
DRAFTING STANDARDS
The Corps requires that standard professional engineering drafting practices be utilized in correcting the original electronic CADD drawings to show as-built conditions. In general, the letter styles, line thickness, and scale will be the same as the original drawings. When shop drawings or other sheets are added, they will be drawn in electronic CADD.
Copyright © Oracle Corporation, 2002. All rights reserved. Content written by USACE, Sacramento District, Engineering Division
W91238-10-R-0035 Specification Vol 1 xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
August 06, 2010 6 of 739
Rev 1
CADD Standards: File Naming Convention will be maintained on all existing CADD files and followed for any new files added. The Contractor shall revise CADD files as-built drawing layers, to show the as-built conditions during the prosecution of the project. All as-built “triangle” changes shall be on a separate single layer, using a single color, with an associated medium pen width.
• Name the layer AS-BUILT for AutoCAD files (DWG).
• MicroStation files (DGN) use:
− Level #63 − Level/Layer Name contains: ANNO-REVS − Level/Layer Description: Revisions
The following specific requirements apply to the preparation of as-built drawings:
The Title Sheet (first sheet): The first sheet will be labeled with the word AS-BUILT. The words CONTRACT NUMBER and the actual contract number will be entered as shown on attachment
1. The contract number contains the Fiscal Year, the letter C (for construction), and the sequence number (example: 96-C-0000). No other work need be done on this sheet unless sheets are being added or deleted from the List of Drawings or other actual changes are made on this sheet. (See Attachment 1.)
The second and subsequent sheets: All the sheets following the title sheet will be labeled with the AS-BUILT stamp. (See Attachment 2.)
Signature representation (CADD files only): All signatures that appear on the approved original design drawings need to be represented on all the electronic as-built files. The format for these are /s/Name (i.e. /s/Raymond Dennis). The only name that does not require the /s/ is the District Commander’s name that appears only on the cover sheet (the title sheet). (See Attachments 1 & 2.)
Revisions Block entries: Those sheets, which have no changes, will only be labeled AS-BUILT as described above. Those sheets which have changes shown on them will have REVISED AS-BUILT entered in the first available space. This will be revision one and a number 1 will be entered in the triangle at the beginning of that line. In the event the sheet has already been revised and a number and revision appear in the revision lines the next sequential number will be used. Normally the first entry is made in the first line. The completed originals CADD file drawings will be reviewed for accuracy and initialed by the Contractor. (See Attachments 2 & 3.)
Marking Revisions: Place an equilateral triangle (3/8" per side) near the area revised for all changes. One triangle may be placed near the table or detail title where several items in a table or detail are changed or completely redrawn. This same method may be used for general revisions to floor plans and system plans (plumbing, electrical, a/c, heating); when a major portion of the drawing is changed, the triangle may be placed near the diagram, detail, section or plans title. A triangle will be placed near each item when only a few items are revised, added or
Copyright © Oracle Corporation, 2002. All rights reserved. Content written by USACE, Sacramento District, Engineering Division
W91238-10-R-0035 Specification Vol 1 xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
August 06, 2010 7 of 739
Rev 1 deleted. The triangles will contain the same number as the As-Built revision on that sheet. (See Attachment 4.)
Revision Annotations:
Deletion - to show an item was not installed, cross the item out on the drawing along with any associated devices, connecting lines, ducts, pipes etc., including notes and dimensions.
To show a detail is not being used, box the detail and letter NOT USED across the detail. A box will be drawn on the sheet with an X as shown in Attachment 5. The words NOT USED will be in heavy block lettering a minimum of 5/8" high. Place a triangle and revision number inside the box where notes are indicated as not being used.
Notes - draw a line thru the note or line item in a table in lieu of erasing the line item or note. A triangle and number will be placed near the deleted item.
Additions - show a new or additional item or items and associated connections made if the print indicates such connections. A triangle and number will be placed near the new item.
All lettering will conform to the existing lettering on each sheet.
Relocations - draw the item in the new location and erase it from the old location. All connections will be transferred if applicable, such as wiring, piping, and ducts. Revision triangles with appropriate number will be shown at the new and old location.
Drawing continuity: The applicable drawings shall be marked-up when a change was made, although this will not always be the case. Final responsibility for drawing continuity is with the person doing the As-Built. When one floor plan indicates a wall, room, doors etc., has been changed, the same change shall be made on all other applicable drawings. When the change is applicable to only one discipline such as electrical and does not directly affect other discipline sheets, a note may be added to other discipline sheets such as "See sheet _____ for As-Built Conditions.”
Shop drawings: When shop drawings are added to the original contract drawing set they need to be appropriately labeled with the Sacramento District file number, and discipline and sequence sheet number. The Index of Drawings will also need to be revised to show the additional sheet
(s) with the appropriate sheet title. In the case where the shop drawing are smaller than the Corps standard sheet size (i.e. 8.5"x11" or 11"x17" etc.) the sheets will be cut into a standard Corps sheet size border sheet and appropriately labeled. (For additional information refer to Mark-up Guidelines, Shop drawings above.)
Distribution
Archives Unit
Contractor*
Resident Engineer*
Specification Engineer
Copyright © Oracle Corporation, 2002. All rights reserved. Content written by USACE, Sacramento District, Engineering Division
W91238-10-R-0035 Specification Vol 1 xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
August 06, 2010 8 of 739
Rev 1
Ownership
The Archives Unit [Raymond.E.Dennis@usace.army.mil?Subject=INSP05L0-Preparing As- Built Drawings] is responsible for ensuring that this document is necessary and that it reflects actual practice.
Activity Preface
These tasks are performed whenever changes, additions or deletions from the original "as-designed" contract drawings and specifications are made during construction.
Prior Activity
Creation, Packaging, and Delivery of Project Documents [PROP09L0]
Contractor
1. Print two sets of paper drawings and specifications for working as-built.
The Contractor shall maintain 2 sets of paper drawings and specifications (marked-up prints) to track changes, additions or deletions from the original design during construction.
2. Mark working as-built set to show changes, additions or deletions.
Place an equilateral triangle (3/8" per side) near the area revised for all changes. One triangle may be placed near the table or detail title where several items in a table or detail are changed or completely redrawn. This same method may be used for general revisions to floor plans and system plans (plumbing, electrical, a/c, heating); when a major portion of the drawing is changed, the triangle may be placed near the diagram, detail, section or plans title. A triangle will be placed near each item when only a few items are revised, added or deleted. The triangles will contain the same number as the As-Built revision on that sheet.
(See Attachment 4.)
Changes, additions or deletions will immediately be noted on each of the working as-built set by redline process. No other marks, doodles, notes, or annotations shall be put on these sets of working as-built prints. All changes from the contract plans, which are made in the work, or additional information which might be uncovered in the course of construction will be accurately and neatly recorded as they occur by means of details and notes.
All changes and/or required additions to the paper prints will be clearly identified in color contrasting to black, as follows:
Colors shall be the "base" colors of red, green, and blue. Color code for changes shall be as follows:
(1) Deletions (red) - Deleted graphic items (lines) shall be colored red with red lettering in notes and leaders.
Copyright © Oracle Corporation, 2002. All rights reserved. Content written by USACE, Sacramento District, Engineering Division
W91238-10-R-0035 Specification Vol 1 xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
August 06, 2010 9 of 739
Rev 1
(2) Additions (Green) - Added items shall be drawn in green with green lettering in notes and leaders.
(3) Special (Blue) - Items requiring special information, coordination, or special detailing or detailing notes shall be in blue.
The working as-built sets will be annotated in as much detail as necessary to clarify exactly what construction changes were performed.
3. Transfer the changes from the working as-built marked prints to the "as-designed" electronic CADD files.
The contractor will transfer the changes from the working as-built marked prints to the original electronic CADD files on a monthly basis. Final as-built drawings shall be prepared after the completion of each definable feature of work as listed in the Contractor Quality Control Plan (Foundations, Utilities, Structural Steel, etc., as appropriate for the project).
If Project feature complete, goto task #4. Otherwise, goto task #2.
4. Submit As-Built drawings for review.
The contractor shall submit the Final As-built conditions on a new CD to the Resident Engineer in the customer specified electronic format as a Government, District Office Approval (G, DO) required submittal.
Resident Engineer
5. Review As-Built drawings.
The Resident Engineer and the Contractor will jointly review the working as-built marked prints, printouts from working as-built CADD file drawings, and final as-built drawings for accuracy and completeness, prior to submission of each monthly pay estimate. Monthly review of working as-built CADD printouts shall at minimum cover all sheets revised since the previous review.
If As-built OK, goto task #7. Otherwise, goto task #6.
6. Note required corrections on submittal and return to Contractor.
Goto task #3.
7. Notify Contractor of submittal acceptance.
If Final Submittal, End of activity; Goto Managing As-Built & As-Constructed Drawings [PROQ08L0]. Otherwise, goto task #2.
Copyright © Oracle Corporation, 2002. All rights reserved. Content written by USACE, Sacramento District, Engineering Division
W91238-10-R-0035 Specification Vol 1 xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
August 06, 2010 10 of 739
Rev 1
Flow Chart Preparing As-Built Drawings
PROP09L0
Start
Contractor Print two sets of paper drawings & Specs for working as-built. (1)
Contractor Mark working as-built set to show changes, additions or deletions. (2)
Contractor Transfer changes from working as-built marked prints to "as-designed" electronic CADD files. (3)
Proj feature complete?
Contractor Submit As-Built drawings for review.
(4)
Resident Engr Review As-Built drawings. (5)
As-built OK?
Resident Engr Note required corrections on submittal & return to Contractor. (6)
Resident Engr Notify Contractor of submittal acceptance. (7)
Final Submittal?
End
PROQ08L0
A
B
B
A
Y
N
Y
N
Y
N
Copyright © Oracle Corporation, 2002. All rights reserved. Content written by USACE, Sacramento District, Engineering Division
W91238-10-R-0035 Specification Vol 1 xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
August 06, 2010 11 of 739
August 06, 2010 12 of 739
August 06, 2010 13 of 739
August 06, 2010 14 of 739
August 06, 2010 15 of 739
August 06, 2010 16 of 739
TECHNICAL SPECIFICATIONS
August 06, 2010 17 of 739
SECTION 01 11 10
PROJECT DESCRIPTION/SCOPE OF WORK PERFORMANCE ORIENTED
CONSTRUCTION ACTIVITIES
1. Intent. The intent of this contract is to provide a timely response to the construction, maintenance, repair, or rehabilitation (MRR) needs at Government installations, facilities or municipalities. Typical efforts include, but are not limited to these areas: new construction, maintenance, repair, rehabilitation, energy conservation, environmental, logistical, and operation. The work may include both military and civil works projects. The contractor shall perform all facets of the work such as surveying the problem, recommending a solution, and correction of the problem in a timely manner. Task Orders may be issued for work within the Sacramento District U.S. Army Corps of Engineers’ Military and Civil Works boundaries in the states of California, Nevada and Utah and other locations within the boundaries of the South Pacific Division. Task orders will be primarily issued by the Sacramento District, however, others may be authorized to issue task orders under the proposed contract as designated by the Sacramento District Contracting Officer.
2. Contract Period and Amount. The contract shall be for a three (3) year period, or until the Not-To-Exceed Amount of $5,000,000 has been reached. Services will be provided on a task order basis. Task orders under this contract shall be Firm-Fixed Price. Task orders may be placed under this contract for construction and/or incidental services. The Government is under no obligation to issue any orders against this contract in excess of the minimum contract obligation. The minimum amount to be paid for the contract is $2,000.00. This minimum guarantee is to be obligated upon award of the contract. The minimum guarantee amount will be satisfied with the issuance of one or more task orders, or funding may be provided from other sources approved by the Contracting Officer.
3. Objective.
a. The primary objective of this contract is to provide site survey, work plan, and maintenance, repair, and rehabilitation services on Government installations, facilities or municipalities. The work shall be of high quality and contracted for at a reasonable price, and performed in a fast manner with a minimum number of change orders. The ability to: survey and identify deficiencies; plan and document the work required to correct deficiencies; provide incidental engineering services; estimate the cost of the work; obtain subcontracts or perform the work with the contractor’s own work forces;
and manage the construction effort while insuring quality and safety are paramount to the success of this contract. It is not critical that the contractor be prepared to execute all the work under this contract with its own workforce, except to the extent necessary for full compliance with FAR 52.219-14. However, the contractor must perform such work in order to manage the work throughout the geographic boundaries of the contract in a cost effective and quality manner while meeting project schedules. The contractor shall be responsible for managing and executing facility or installation deficiency corrections. If the contractor fails to provide a quality product at a reasonable price and on schedule, the contractor may not receive additional task orders under this contract over the minimum specified by the contract.
b. Typical Work Requirements. In order to meet the objectives of this contract, the contractor must provide expertise in certain areas in order to accomplish the required work. Disciplines and related work requirements may include, but are not limited to:
(1) Architectural. Enclosures, shelters, building systems, mobile buildings, chimneys, grout, mortar, concrete, brick, concrete masonry units (CMUs), waterproofing, insulation, caulking and sealants, roofing, gutters, drains, metal decking, joists, siding and exterior surfacing, levelers, docks, ramps, stairs, shelving, windows, doors, painting, finishes, louvers, awnings, shutters, panels, grills, ceilings, acoustical areas, walls, paneling, flooring (conductive and nonconductive), carpeting, tiles, builder’s hardware, signage, metals, woods and plastics, millwork, thermal and moisture protection, playground equipment, fireproofing, equipment systemization layouts, building fixtures and furnishings, and handicap systemization.
(2) Civil. Grading and earthwork, surface and subsurface storm drainage and drainage control structures, storm water management, erosion and sediment control, clearing and grubbing, paving and surfacing for roads, parking areas and sidewalks, parking layout, pavement markings, traffic control and signage, gates and fencing, curbs and gutters, railroads, dewatering, landscaping, seeding and sodding, riprap, geotechnical investigations, slope stabilization, foundations, borings, trenching, piles and caissons, bridges, spill containment, berms, demolition, wetlands delineation, and airfield runway and taxiway.
W91238-10-R-0035 Specification Vol 1 xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
August 06, 2010 18 of 739 xxxxxxxx xxxxxxxx
L2CTAGLT
Typewritten Text $15X
L2CTAGLT
Typewritten Text
L2CTAGLT
Typewritten Text
L2CTAGLT
Typewritten Text
L2CTAGLT
Typewritten Text
(3) Electrical. Electrical distribution and network balancing (aerial and underground), transmission lines, poles (telephone and power), towers, ducts, raceways, conduits, tubing, connectors, wires, cable, cable trays, outlet boxes, cabinets and enclosures, supports, fiber optics cable and equipment, manholes, concrete pads, insulators, lightning arrestors, transformers, capacitors, switches, relays, fuses, grounding, lightning protection, cathodic protection, service entrances, panel boards, circuit breakers, motor control centers, special equipment/systems, targeting systems, resistance heating, starters, uninterrupted power supplies (UPS), beacons, batteries, generators, solar systems, receptacles, lighting fixtures, lamps, ballasts, equipment connections, special outlets, disconnect switches, splices, terminations, control systems, security systems, IDS, utilities monitoring and control systems (UMCS), and similar micro processor environmental control systems, audio and visual communication systems, telephone systems, instrumentation systems, and fire detection and alarm systems.
(4) Environmental. Industrial and sanitary sewers, waste treatment facilities, septic tanks with drains, portable toilets wells, water treatment facilities, water distribution systems, potable and fire water supplies (including wells, piping, pumps, valves, sprinklers, water use analyses, leakage analysis, and hazardous waste analyses, and disposal of waste products.
(5) Mechanical. Heating, ventilation and air-conditioning (HVAC) systems and components, chillers, refrigerants, cooling towers, air handling equipment, energy conservation, heat transfer surfaces, furnaces, air distribution, valves, pumps and associated piping and ducts; conveying systems, elevators, dumbwaiters, moving walks, box conveyors, hoists and cranes, lifts, escalators with associated electrical and hydraulic controls; incinerators, boilers, material handling systems, dryers, steam lines, transient tubes, shredders, plumbing fixtures, special equipment/systems, sterilization systems, fuel distribution (i.e. propane, natural gas, and slurries), petroleum oil lubricants (POL), storage tanks for fuel, gas, water, and sewage, piping systems, fire suppression (water, chemical, and gas), fuel use and leak analyses, sterilizers, compressed air production and distribution systems, medical and industrial gas distribution systems, exhaust systems, steam systems, pipe insulation, and plumbing systems involving water, solids, and hazardous waste.
(6) Safety. Life safety, fire protection systems, industrial hygiene, inflammatory gases, medical safety and hygiene, asbestos and/or lead based paint evaluation and removal/encapsulation, blast distances, failure mode and effective analyses (FMEA), Occupational Safety and Hazards Act (OSHA) and American Disability Act (ADA) evaluations.
(7) Structural. Structural design and analysis of building systems and ancillary structures (concrete, masonry, steel, etc.), foundations, underwater structures, reinforced concrete, equipment mounting, shock isolation reinforced masonry, wood, steel joists, steel decks, structural steel frame systems, steel bracing, seismic design and evaluations, steel connections, non-building structures, welding procedures, detailing of structural components and hardened (protective) structures. Non-building structures such as elevated tanks, vertical tanks on ground, horizontal tanks, retaining walls and buried structures. Anchorage and support of mechanical and electrical equipment. Applications of industry building codes and standards.
(8) Systems. Quality control, operations and maintenance (O&M) manuals and procedures both preventative and breakdown, training, human factors engineering, upgrade assessments, equipment inventories and O&M documentation to obtain support, energy system surveys, O&M training efforts to support the MRR, System/equipment and life safety repair and maintenance efforts for existing systems/equipment, logistical support, accreditation surveys.
(9) Other Requirements. Asbestos and/or lead based paint abatement may be required during equipment/systems remediation. On-site inspection and checkout of MRR effort will be required.
Demolition and/or temporary removal and reinstallation of supporting elements in the project related areas might be required. Surveys and assessments of systems/equipment may be required prior to MRR action.
On-site inspection and acceptance services may be required. Ancillary work necessary to support the MRR action project or to restore the work area to the condition prior to the MRR action project may be included.
4. Task Orders. When Fixed Price task orders are required, the Contracting Officer or Contracting Officer’s Representative will issue a request for proposal stating the efforts to be accomplished to complete the work. The task order will be negotiated on a firm fixed lump sum price basis. Current Davis-Bacon (construction) wage rates that apply to the location will be provided with the Request for Proposal for each individual task order. Once the task order is awarded the wage rate will remain in force for the duration of the task order. The only element from the basic contract pricing schedule which will be used as a basis in preparing each request for proposal is the General and Administrative (G&A) rate. To support the proposed price, the contractor’s proposal will include detailed backup cost details. Examples of such detail include, but are not limited to: subcontractor quotations; labor hours and
W91238-10-R-0035 Specification Vol 1 xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
August 06, 2010 19 of 739 associated costs proposed materials and supplies and quotations; equipment costs; extended overhead (field office) costs; performance and payment bond costs; travel costs; overhead and G&A costs; and proposed profit/fee.
5. Definitions. The following is a list of typical work requirements contemplated to be performed under this contract. This list is not all-inclusive. Typical activities to be performed under a task order are listed in paragraph 7.
a. Site Survey/Investigation: An inspection of an installation or facility to evaluate areas which need MRR action.
b. Site Visit: A visit to an installation or facility to obtain specific information pertaining to a proposed MRR action.
c. Work Plan: The minimal documentation required for the Government to monitor the contractor’s efforts with regard to scope, schedule, costs, codes, and standards in order to perform a MRR action to correct a situation. The work plans level of detail will be commensurate with the complexity of the project. Details to be included in a work plan may include, but are not limited to: general methodology for performing the work; single line diagrams; sketches; schedules; manufacturers’ data such as catalog cuts of equipment and installation requirements; and cost estimates. Ultimately, the approved work plan represents the definitized scope of work. The contractor may be requested to prepare a cost proposal for the construction portion of the requirement based on the approved work plan.
d. Facility Rehabilitation Project (FRP): A project undertaken to correct an MRR situation identified by the facility with details taken from a site survey, site visit, feasibility study, or related sources. These projects may involve operation, maintenance, repair, or rehabilitation, as stated in the task order, to remedy the situation. They are activated by a task order based on the facility requirements.
e. Maintenance, Repair, and/or Rehabilitation Action: The construction action taken to correct a MRR situation. It results from the implementation of a work plan or other documents provided.
f. Submittals: Documents required to be submitted by the contractor to support or record the actions being taken under the task order requirements. Each task order will specify what submittals are required. Examples are: site investigation/survey reports; work plans; site safety and health plan; quality control Program; work schedules; as-built/progress and final drawings; equipment warranties; O&M manuals; correspondence records.
g. Task Order: Contractual Directive issued to the contractor that delineates the requirements for work to be performed. The tasks are the individual efforts to be performed by the contractor and are contained in the task order.
h. Quality Assurance (QA): The procedure by which the Government fulfills its responsibility to be certain that the contractor’s quality control is functioning and the specified service is realized.
i. Quality Control (QC): The contractor’s system to manage, control, and document its activities to comply with the contract requirements.
6. Work to be Performed.
a. General. The contractor shall, commencing upon issuance of a task order, furnish all materials, equipment, transportation, and supervision to safely and efficiently perform the required work. All tasks to be completed under this contract shall be performed in accordance with applicable provision of the US Army Corps of Engineers Safety and Health Requirements Manual, EM 385-11 and the Architectural and Engineering Instructions (AEI) Design Criteria, unless other criteria is provided by the Contracting Officer.
b. Contractor's Representative. The contractor shall execute all work under the direction of a Project Manager. The Project Manager shall have adequate experience to oversee task accomplishment, administer all instructions, and answer all questions from the Contracting Officer or his/her designated representative pertaining the specific requirements of each task order. Additionally, the Project Manager shall be responsible for complete coordination of all work under the task order. All work shall be accomplished with adequate internal controls and review procedures that will eliminate conflicts, errors, and omissions and ensure the technical adequacy of all output. The Project Manager will be identified, in writing, to the Contracting Officer, prior to commencement of work under each task order. Should there be a need to change Project Managers during task order performance, the contractor will notify the Contracting Officer in writing.
c. Overall Responsibility. The contractor shall be responsible for all site surveys, site investigations, site visits, feasibility studies, work plans, MRR action, equipment startup and testing and/or repair, warranty, and training required to implement the task order requirements, including, but not limited to, equipment, materials, software, applicable engineering documentation, and other necessary services and/or products required to correct, implement, test and to provide a complete and fully operational facility, unless otherwise indicated in the task order or as directed by the Contracting Officer.
d. Codes and Standards. The site surveys, site visits, work plans, studies, corrective actions, equipment repair, startup and testing and/or related work shall conform to the requirements of this contract and task order. The contractor shall adhere to
W91238-10-R-0035 Specification Vol 1 xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
August 06, 2010 20 of 739 codes and standards as specified therein. All codes and standard requirements shall be based on the latest edition of applicable codes. All work shall comply with local, state, national, and/or installation codes, whichever are the most stringent.
e. Professional Certification. Registered professional engineers, architects, and industrial hygienists shall certify with their signature and stamp all task order efforts involving life safety and/or fire protection situations as well as certifying proper usage of codes and standards. See contract clause entitled FAR 52.236-25, Requirements for Registration of Designers (section 00700) for additional requirements.
f. Permits. The contractor is responsible for identifying and obtaining all permits from Federal, state, local or installation agencies. See contract clause FAR 52.236-7, "Permits and Responsibilities" located in section 00700.
g. Labor Requirements. The contractor must possess or have access to a variety of skills in order to perform certain task order efforts. Representative vocations and related knowledge include, but are not limited to:
(1) Safety Engineer, Project Superintendent, Quality Control Manager, Health Officer, and Contract Administrator:
Experience in MRR projects.
(2) Architectural, Engineering, Training and Engineering Support Professionals: Experience in design, design review and engineering service for MRR projects. May include architects, senior engineers (except safety), training specialists, and technical writers.
(3) Project Engineer/Architect: Requires a recognized 4 or 5 year degree in engineering or architecture, or 10 years equivalent experience in the construction field; Experience in engineering or construction management, design in MRR projects.
(4) Program and Project Managers: Should have a recognized four year college degree in engineering or related technical field or business/management or 10 years equivalent experience in the construction field. Experience managing and supervising engineering and facility MRR.
(5) Technical Personnel: Experience in the specific technical skills needed to accomplish specific task order requirements. Examples of vocations may be: light truck drivers; unskilled laborers; equipment operators; heavy truck drivers; painters; secretaries; word processors; shipping/receiving clerks; and carpenters. Other vocations that required specific certifications to practice their trade and be conversant with various codes and standards may include: electricians, electronics instrumentation; fire alarm; air conditioning mechanics; sheet metal workers;
plumbers; pipe fitters; welders; masons, and documentation preparation clerks.
h. Documentation. The contractor shall implement, maintain, and control a system for identification, preparation, reproduction, distribution, and maintenance of all documentation, dates and information necessary for its internal management as well as Government management of the individual projects and the total program.
i. Presentations and Meetings. Time and locations of presentations and meetings shall be identified in each task order.
j. Price Proposals. Prior to issuance of any task order, the Government shall request a proposal from the contractor for the requested work. Each price proposal shall be in sufficient detail as required by paragraph 4 above entitled "Task Orders".
k. Safety and Health Program. Site activities in conjunction with the tasks performed under this contract may pose safety hazards that require specialized expertise to effectively address and eliminate. The contractor shall be responsible for preparing and implementing an effective safety and health program. Upon issuance of the first task order for construction work under this contract, the contractor shall submit a generic site safety and health plan within the time limits specified in the task order. The plan shall be capable of being adapted to the sites specified on subsequent task orders. A designated individual shall have direct responsibility for the overall safety and health program. Each task order shall have a designated individual responsible for the site safety.
(1) Site Safety and Health Plan (SSHP). The SSHP shall be prepared in accordance with the following requirements and shall comply with all federal, state and local health and safety requirements, e.g. the Occupational Safety and Health Administration (OSHA) requirements (29 CFR 1910 and 1926) and the US Army Corps of Engineers Safety and Health Requirements Manual (EM 385-1-1). The SSHP shall address those elements which are specific to the site and has potential for negative effects of the safety and health of workers and other personnel on site. Where a specific element is not applicable, the contractor shall make a negative declaration in the plan to establish that adequate consideration was given to the topic, and a brief justification for its omission shall be given. This SSHP shall also cover asbestos and/or lead-based paint removal. It will not cover hazardous material or environmental remediation.
W91238-10-R-0035 Specification Vol 1 xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
August 06, 2010 21 of 739
(2) Staff Organization, Qualifications and Responsibilities. A fully trained and experienced site safety and health officer (SSHO), responsible to the contractor may be delegated to implement the on-site elements of the SSHP. The SSHP shall be in a form usable by authorized Government representatives and other authorized visitors to the site during site operations. The operational and health and safety responsibilities of each key person shall be discussed. The organizational structure, with lines of authority for safety and health and overall responsibilities of the contractor and all subcontractors shall be provided. Each person assigned specific safety and health responsibilities shall be identified in writing to the Contracting Officer.
(3) Accident Prevention. The SSHP may serve as the Accident Prevention Plan provided it addresses all content requirements of both 29 CFR 1910 and EM 385-1-1. All Accident Prevention Plan elements required by EM 385-1- 1, but not specifically covered by these elements shall be addressed in this section of the SSHP. Daily safety and health inspections shall be conducted to determine if site operations are conducted in accordance with the approved SSHP and contract and task order requirements.
(4) Personal Protective Equipment. A Personal Protective Equipment (PPE) program shall be provided in the SSHP if necessary. Minimum levels of protection necessary for each task/operation to be performed shall be based on the hazard assessment/risk analysis.
(5) Medical Surveillance. All personnel requiring respiratory protection shall have an annual medical examination to ensure they are physically qualified to wear respiratory protection. Those requiring respiratory protection shall be fit tested in accordance with appropriate regulations. On-site conditions and exposures shall determine any other medical surveillance requirements.
(6) Noise Control. The contractor shall monitor for hazardous noise conditions. If warranted, a hearing conservation program and noise abatement program shall be implemented.
(7) Standard Operating Procedures, Engineering Controls and Work Practices. The contractor shall develop Standard Operating Procedures for minimizing hazards and taking action to correct hazards where necessary. Site rules and safe work practices shall be discussed and shall include such topics as use of the buddy system, smoking restrictions, material handling procedures, confined space entry, excavation safety, physiological and meteorological monitoring for heat/cold stress, illumination, sanitation, and daily safety inspections, etc. This list of topics is not intended to be all inclusive.
(8) Logs, Reports and Record Keeping. Record keeping procedures for training logs, safety inspection logs, employee/visitor registers, medical surveillance records and certifications, air monitoring results and personal exposure records shall be described. All personnel exposure and medical monitoring records shall be maintained in accordance with applicable OSHA standards, CFR 1910 and 1926. All recordable accidents/injuries/illnesses shall be reported to the Contracting Officer or authorized representative immediately. A completed ENG 3394, Accident Investigation Report, shall be submitted promptly and in accordance with AR 385-40 and USACE Supplement 1 to that regulation.
l. Quality Control Program. The contractor shall be responsible for preparing and implementing an effective quality control program. Upon issuance of the first task order under this contract, the contractor shall submit a generic quality control plan within the time limits specified in the task order. The plan shall be capable of being adapted to the sites specified on subsequent task orders. A designated individual shall have direct responsibility for the overall quality control program. Each task order shall have a designated individual responsible for quality control.
(1) General. The contractor's quality control program shall ensure that all work required under a task order conforms to the requirements whether or not the work is performed by the contractor or by subcontractors or suppliers. The contractor shall be responsible for performing all necessary inspections and tests to assure conformance to drawings, specifications, or other task order requirements unless the required inspection and/or test is specifically designated in the task order to be performed by the Government.
(2) Content of Quality Control Plan. The plan shall address, as a minimum, the following to cover all aspects of construction, including all work by subcontractors, fabricators, and suppliers; description of the quality control organization, showing lines of authority and acknowledgment that the staff shall implement…